amended scoping report - royal haskoningdhv scoping report.pdf · amended environmental scoping...
TRANSCRIPT
AMENDED ENVIRONMENTAL SCOPING REPORT AND ENVIRONMENTAL PLAN OF
STUDY FOR THE PROPOSED CONSTRUCTION OF THE 132/11KV SUB-TRANSMISSION
LINE FROM HILLTOP TO THE REST IN NELPSRUIT, MPUMALANGA PROVINCE
DEA REF NO: 12/12/20/1725
ESKOM DISTRIBUTION NORTHERN REGION
27 AUGUST 2010
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 2 of 2
DOCUMENT DESCRIPTION
Client: Eskom Distribution Northern Region
Report name: Amended Environmental Scoping Report And Environmental
Plan Of Study For The Proposed Construction Of The
132/11kV Sub-Transmission Line From Hilltop To The Rest
In Nelpsruit, Mpumalanga Province
Report type: Environmental Scoping Report
Project name: Hilltop to The Rest 132kV Sub-Transmission line
Bohlweki Project number: E02.JNB.000540
Document number: 01
Authority Reference: 12/12/20/1725
Version: 02
Compiled by:
Author (s) Date / location Signature
Sibongile Gumbi June
Reviewer
Nomathemba Mhlanga July
Approval
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 3 of 3
TABLE OF CONTENTS
1 INTRODUCTION 7
1.1. Project Description 7
1.2. Location of the Study Area 7
1.3. Environmental Authorisation Requirements 9
1.4. Structure of this Report 9
2 PARTICULARS OF THE EAP AND PROJECT TEAM 10
3 TECHNICAL DETAILS OF THE PROPOSED PROJECT 11
3.1. 132/11kV Substation 11
3.2. 132kV Towers Servitudes 12
3.3. Communication Tower 12
3.4. Clearance of 132kV Sub-Transmission Lines 13
3.5. Foundations 13
3.6. Insulators 13
3.7. Access 13
3.8. Conductor 13
3.9. Stringing of Conductors 13
4 ALTERNATIVES 15
4.1. Substation Location Alternatives 15
4.2. Sub-Transmission Line Route Alternatives 15
4.3. The No go Option 15
5 LEGAL REQUIREMENTS 17
6 SCOPE OF ENVIRONMENTAL INVESTIGATIONS 21
6.1. Approach to Undertaking the Study 21
6.2 Authority Consultation 21
6.3. Environmental Scoping Study 21
7 DESCRIPTION OF THE POTENTIAL ENVIRONMENTAL ISSUES 22
7.1. Climate 22
7.2. Topography 22
7.3. Specialists Studies 24
7.4. Avifauna 24
7.4.1 Description of Impacts of the powerlines on birds 24
7.5 Biodiversity 26
7.5.1 Direct Impacts 26
7.5.2 Indirect Impacts 27
7.5.3. Cumulative Impacts 28
7.6. Herpetofauna 29
7.7. Heritage 30
7.8. Social 33
8 PUBLIC PARTICIPATION PROCESS FOR THE ENVIRONMENTAL
SCOPING STUDY
37
8.1. Advertising 37
8.2. Identification of Key Stakeholders 37
8.3. Briefing Paper 37
8.4. Consultation and Public Involvement 38
8.5. Social Issues Trail 38
8.6. Public Review of the Draft Environmental Scoping Report 38
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 4 of 4
LIST OF FIGURES
LIST OF TABLES
9 CONCLUSIONS AND RECOMMENDATIONS 39
10 PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT 40
10.1 Process Phases 40
10.2. Particulars of the Applicant 40
10.3. Environmental Consultants 40
10.4. Approach to undertaking the project 42
10.5. Public Participation Process for the EIA Phase 47
10.6. Compilation of the Environmental Impact Report 47
10.7. Review of the Environmental Impacts Assessment Report 48
10.8. Environmental Authorisation 48
10.9. Work Programme 49
Figure 1.1. Locality Map for the Proposed Transmission Line and Substation 8
Figure 3.1. 132kV Hilltop Substation 11
Figure 3.2. 132kV Towers 12
Figure 3.3. Depicts a Communication Tower 12
Figure 4.1. Locality Map with Alternatives 16
Figure 7.1. Distribution of ridges and general topography of the study area 23
Figure 7.2. Single stone wall on rock face of modern times 30
Figure 7.3. Long Iron Age stone wall 31
Figure 7.4. Overview of the study area from a Provincial perspective 32
Table 1.1. Report Structure 9
Table 5.1. Legal Consideration 17
Table 5.2. Listed Activities 18
Table 7.1. Specialists Team 24
Table 7.2. Overview of the Expected Geographical Change Processes and Potential
Impacts
33
Table 7.3. Overview of the Expected Demographical Change Processes and
Potential Impacts
33
Table 7.4. Overview of the Expected Economical Change Processes and Potential
Impacts
34
Table 7.5. Overview of the Expected Institutional and Legal Processes and Potential
Impacts
35
Table 7.6 Overview of the Expected Social and Cultural Processes and Potential
Impacts
36
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 5 of 5
GLOSSARY OF TERMS
Alternatives: Different means of meeting the general purpose and requirements of the
activity, which may include site or location alternatives; alternatives to the
type of activity being undertaken; the design or layout of the activity; the
technology to be used in the activity and the operational aspects of the
activity.
Cumulative
impact:
The impact of an activity that in itself may not be significant but may become
significant when added to the existing and potential impacts eventuating from
similar or diverse activities or undertakings in the area.
Do-nothing
alternative:
The ‘do-nothing’ alternative is the option of not undertaking the proposed
activity.
Environmental
Impact
Assessment (EIA)
In relation to an application to which scoping must be applied, means the
process of collecting, organising, analysing, interpreting and communicating
information that is relevant to the consideration of that application as defined
in NEMA.
Interested and
Affected Party
(I&AP)
Any person, group of persons or organisation interested in or affected by an
activity; and any organ of state that may have jurisdiction over any aspect of
the activity.
Plan of Study for
Environmental
Impact
Assessment:
A document which forms part of a scoping report and sets out how an
environmental impact assessment must be conducted.
Public
Participation
Process
A process in which potential interested and affected parties are given an
opportunity to comment on, or raise issues relevant to, specific matters.
Red Data Species Species listed in terms of the International Union for Conservation of Nature
and Natural Resources (IUCN) Red List of Threatened Species, and/or in
terms of the South African Red Data List. In terms of the South African Red
Data List, species are categorised as being extinct, endangered, vulnerable,
rare, indeterminate, insufficiently known or not threatened.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 6 of 6
ACRONYMS
• DEA - Department of Environmental Affairs
• EAP- Environmental Assessment Practitioner
• EIA - Environmental Impact Assessment
• EMF - Electromagnetic Frequency
• EMP - Environmental Management Plan
• ESS - Environmental Scoping Study
• GN - Government Notice
• I&AP - Interested and Affected Parties
• kV - Kilovolts
• MBCP - Mpumalanga Biodiversity Conservation Plan
• MDARDLA- Mpumalanga Department of Agriculture Rural Development and Land
Administration
• NEMA - National Environmental Management Act
• NGO - Non Governmental Organisation
• PPP - Public Participation Process
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 7 of 7
1 INTRODUCTION
Eskom Distribution Northern Region, a division of Eskom Holdings (Pty) Ltd, is proposing to
construct the 132kV Powerline line from the existing Hilltop Substation to the new The Rest
Substation in Nelspruit. The development will also include a communication tower that is
approximately 18m in height. The proposed The Rest Substation is to supply a new
development, The Rest Eco Estate as well as to provide firm supply to the adjacent areas. The
total load required will be supplied to the area via one overheard 132kV feeder supplying a
common bus-bar and 11kV reticulation feeders. The study area consists mainly of residential
load and it is expected that this load composition will increase in future as new houses and
estates are developed.
1.1 Project Description
The proposed development will entail the following:
• The building a new 132kV feeder line of approximately 6 km from Hilltop substation to The
Rest substation;
• Build a new The Rest 132/11kV Substation; and
• An 18 m high communication tower.
1.2 Location of the Study Area
The broader study area is situated in Nelspruit within the jurisdiction of Mbombela municipality
in the Mpumalanga Province. The line extends from the existing Hilltop Substation located on
the Farm Hilltop 458 adjacent to the R40 Road in a north-easterly direction towards the Farm
The Rest 454 Figure 1.1.below depicts the location of the project
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 8 of 8
Figure 1-1: Locality Map for the Proposed Transmission Line and Substation
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 9 of 9
1.3 Environmental Authorisation Requirements
According to the Environmental Impact Assessment (EIA) Regulations of 2006 promulgated
under Section 24D of the National Environmental Management Act (NEMA), 1998 (Act No. 107
of 1998), the construction of a new 132/11kV substation and power line is activity which may
have a detrimental impact on the environment. According to Section 24 C of the NEMA, as
Eskom Distribution is a parastatal, an environmental authorisation from the National Department
of Environmental Affairs (DEA) for undertaking the proposed project is required. Inputs from
Mpumalanga Department of Agriculture, Rural Development and Land Administration
(MDARDLA), a commenting authority, will be taken into account in the granting of environmental
authorisation.
This environmental authorisation process involves lodging an application with the Competent
Authority and this was submitted to DEA on 21st of November 2009 and acknowledged on 04
December 2009. The Scoping Phase of the environmental assessment then commenced and
the findings thereof are included in this Report.
The environmental authorisation process requires the appointment of an independent
Environmental Assessment Practitioner (EAP) as per Regulation 385 subsections 17(1) and 18
(a). Accordingly, Bohlweki-SSI Environmental has been appointed to undertake this process.
This environmental assessment process will be divided into two phases: the Environmental
Scoping Phase and the Environmental Impact Assessment (EIA) Phase. An Environmental
Management Plan (EMP), providing mitigation and management measures for the construction
and operation of the proposed project, will be compiled based on the findings of the
Environmental Impact Assessment Report.
1.4. Structure of this Report.
Table 1-1 Report Structure
Chapter Content
Chapter 1 Introduction to project and approach to the
Environmental Scoping Study
Chapter 2 Particulars of the EAP and project team and their
credentials
Chapter 3 Technical description of the project and associated
infrastructure
Chapter 4 Project Alternatives, consideration of sites, route
alignments and no go option for the project
Chapter 5 Legal requirements, brief scoping of national
legislations and guidelines.
Chapter 6 Scope of environmental investigations, includes
approach to undertake the scoping study.
Chapter 7 Description of potential environmental impacts (
biophysical and social environments)
Chapter 8 Overview of the public participation undertaken for the
project.
Chapter 9 Conclusion and recommendations of the
Environmental Scoping study
Chapter 10 Plan of Study for EIA includes specialists study
required for the EIA phase of the project.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 10 of 10
2 PARTICULARS OF EAP AND THE PROJECT TEAM
Below are the particulars of the project team and fields of their specialization.
Malcolm Roods is a Principal Associate within SSI specializing in Environmental Impact
Assessments (EIA) for linear infrastructure such as power lines and roads (generation,
transmission and distribution) as well as residential developments and water management
projects. His past experiences include 6 years in public service within the Gauteng Department
of Agriculture, Conservation and Environmental Affairs (GDACE) where he was involved in
policy development, environmental law reform and EIA reviews. He has more than 2 years of
environmental consulting experience. Malcolm Roods is the Project Manager for this
application for environmental authorization.
Sibongile Gumbi is an Environmental Consultant with four years experience in the
environmental field. She will be responsible for the compilation of all EIA documentation and
authority consultation. She is experienced in Environmental Impact Assessments (EIA’s),
environmental monitoring, auditing and training. She has conducted several 132kV and 400kV
applications on behalf of Eskom Holdings. Sibongile is registered with South African Council for
Natural Scientific Professions.
Sibongile Hlomuka is a Social Development and Public Participation Consultant with 7 years of
working experience assisting the project team with Public Involvement Process of the project.
She provides technical and administration assistance in public participation for projects in the
environmental management field. She facilitates public participation for various projects which
include water use licensing and Mining Right Applications.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
Bohlweki-SSI Environmental
3 TECHNICAL DETAILS OF THE PROPOSED PROJECT
In South Africa, thousands of kilometres of high voltage Transmission lines (i.e. 765 kV, 400 kV
or 275 kV Transmission lines) transmit electricity generated at power stations to Eskom’s major
substations. At these major substations, the voltage is reduced, and the electricity is distributed
to smaller substations all over the country through Sub-Transmission lines (i.e. 132 kV, 88 kV or
66 kV lines). At the smaller, substations the voltage is further reduced and the power is
distributed to local users via numerous smaller power lines (i.e. 22 kV and 11 kV lines) referred
to as Reticulation lines. The power generated by Eskom can only be utilised from those points
of supply, which transform the power into a usable voltage.
The size of the footprint depends on the type of pole, i.e. whether it is a single monopole, guyed
suspension or an angle strain pole structure. The size of the footprint ranges from 0,6 m x 0,6 m
to 1,5 m x 1,5 m, with the larger footprint associated with the guyed suspension and angle strain
pole used as bend / strain structures. The average span between two towers is 200 m, but can
vary between 250 m and 375 m depending on the ground profile and the terrain to be spanned.
The single monopole structure (suspension pole) is typically used along the straight sections of
the power line, while the guyed intermediate or guyed suspension and angle strain structures
are used where there is a bend in the power line alignment, the type of structures to be used
depends on the terrain.
A technical description of the proposed project is provided below.
3.1 132/11kV Substation
An area of approximately 73,600 m2 is usually required for the construction of the proposed The
Rest Substation.
Figure 3-1: 132kV Hilltop Substation
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
Bohlweki-SSI Environmental
3.2. 132kV Towers Servitudes
The servitude required for the 132kV power line is 31m wide (15,5m on either side of the centre
line). This width may increase to 36m at bends to accommodate anchor cables. A building
restriction specification is required from the powerline.
Figure 3-2: 132kv Towers (Source: www.nccpowerprojects.com )
3.3. Communication Tower
Figure 3-2: Picture Depicting a Communication Tower (source: www.infotech.com)
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 13 of 13
3.4. Clearances of 132 kV Sub-Transmission Lines
On receipt of an approval of the final corridor by the environmental authorities and after
negotiations with landowners, the final definition of the centre line for the Sub-Transmission line
and co-ordinates of each bend in the line will be determined. Optimal tower sizes and positions
will be identified and verified using a ground survey in terms of the Environmental Management
Plan (EMP) requirements and then clearance for the ground will take place. .
3.5. Foundations
The choice of foundation is influenced by the type of terrain encountered and the underlying
geotechnical conditions. The actual size and type of foundation to be installed will depend on
the soil bearing capacity (actual sub-soil conditions). Strain structures require more extensive
foundations for support than in-line suspension structures, which contribute to the cost of the
construction of the powerline.
3.6. Insulators
Composite insulators are used to connect the conductors to the towers.
Glass and porcelain have previously been used to connect the conductors for many years, and
is the most common. These products are, however, heavy and susceptible to breakage by
vandals, as well as contamination by pollution. Composite insulators have a glass-fibre core
with silicon sheds for insulation. Composite insulators are lightweight and resistant to both
vandalism and pollution.
Composite (Long rod type) insulators with silicone based weathershed material will be used for
strain assemblies. Composite horizontal line post insulators will be used for the intermediate
structures and on the jumper supports.
3.7. Access
In order to reduce potential impacts associated with the construction of new access roads,
existing dirt roads will be used as far as possible for the project. All access points and roads will
be negotiated with landowners, and are to be established during the construction phase.
3.8. Conductors
The conductors are made of aluminium with a steel core for strength. Power transfer is
determined by the area of aluminium in the conductors. Conductors are used singularly, in pairs,
or in bundles of three, four or six. The choice is determined by factors such as audible noise,
corona, and electro-magnetic field (EMF) mitigation.
Many sizes of conductor are available, the choice being based on the initial and life-cycle costs
of different combinations of size and bundles, as well as the required load to be transmitted.
3.9. Stringing of Conductors
A guide wire is used to string the conductors between towers. This can be undertaken
mechanically or by hand. The line is generally strung in sections (from bend to bend). Cable
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 14 of 14
drums are usually placed at 2 km intervals (depending on the length of the conductor) during
this stringing process. In order to minimise any potential negative impacts on the surrounding
area, these cable drums are placed within the servitude.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 15 of 15
4 ALTERNATIVES
In terms of the EIA Regulations, feasible alternatives are required to be considered within the
Environmental Scoping Study. All identified, feasible alternatives are required to be evaluated in
terms of social, biophysical, economic and technical factors.
4.1 Substation Location Alternatives
Two substation sites will be investigated further in the EIA Phase for the proposed project
namely:
• Site A is situated in the northern portion of The Rest farm 454 JT (refer to Figure 4.1 Below)
• Site B is situated in the north easterly portion of The Rest farm 454 JT (refer to Figure 4.1
Below).
Site A is the preferred location for the substation for the applicant as it is the most direct route.
In terms of topographical constraints and possible environmental impacts, it is also the most
favourable location for the substation.
4.2 Sub-Transmission Line Route Alternatives
Three transmission line route alternatives have been considered for this project. However, they
traverse two main corridors as is illustrated in Figure 4.1 below. As mentioned above, the
preferred corridor is alignment 1 which is the most direct and avoids steep terrain towards the
north eastern portion of the Farm The Rest 454 JT.
4.3 The No go Option
If the proposed project were not to proceed, the likelihood of the existing network meeting
demand for The Rest Eco Estate and other future developments in the area is low. The status
quo option is, therefore, not considered to be a feasible option.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 16 of 16
Figure 4-1: Locality Map with Alternatives
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 17 of 17
5 LEGAL REQUIREMENTS
A preliminary review of the relevant legislation was undertaken in order to identify any legal
issues related to the proposed project. Below is an applicable environmental legislation, which
must be considered by Eskom during the implementation of the proposed project.
Table 5-1: Legal Consideration
Legislation Sections Relates to
The Constitution (Act No
108 of 1996)
Chapter 2 Bill of Rights.
Section 24 Environmental right
Section 25 Rights in property.
National Environmental
Management Act (No 107
of 1998)
Section 2 Defines the strategic
environmental management goals
and objectives of the government.
Applies throughout the Republic to
the actions of all organs of state
that may significantly affect the
environment.
Section 24(a) &(d)
&24(5)
Listed activities and Regulations
Section 28 The developer has a general duty
to care for the environment and to
institute such measures as may
be needed to demonstrate such
care.
Environment Conservation
Act (No 73 of 1989)
Section 2 General policy.
Section 16 Provides for the setting aside of
Protected Natural Environments
(PNEs). Any construction activities
within the PNE require the
consent of the PNE management
advisory committee and the
Premier of the relevant province.
Sections 19 and 19A Prevention of littering by
employees and subcontractors
during construction and the
maintenance phases of the
proposed project.
The Conservation of
Agricultural Resources Act
(No 43 of 1983)
Section 6 Implementation of control
measures for alien and invasive
plant species.
National Heritage
Resources Act (No 25 of
1999)
Provides general principles for
governing heritage resources
management throughout South
Africa including national and
provincial heritage sites, burial
grounds and graves;
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 18 of 18
archaeological and
palaeontological sites, and public
monuments and memorials
National Environmental
Management: Air Quality
Act (No 39 of 2004)
Sections 26-27 Control of fuels.
Section 32 Control of dust.
Occupational Health and
Safety Act (No 85 of 1993)
Section 8 General duties of employers to their
employees.
Section 9 General duties of employers and
self employed persons to persons
other than their employees.
Fertilisers, Farm Feeds,
Agricultural Remedies and
Stock Remedies Act (No 36
of 1947)
Sections 3 to 10 Control of the use of registered
pesticides, herbicides (weed killers)
and fertilisers. Special precautions
must be taken to prevent workers
from being exposed to chemical
substances in this regard.
Nature Conservation
Ordinance (Transvaal) (No
12 of 1983)
Section 98 Identification of any specially
protected or rare and endangered
species. If these are to be affected
by the proposed project, a permit
from the Director General, Nature
Conservation should be obtained
prior to removal.
Schedule 11 Prohibits the picking of all
indigenous plants on public roads
and nature reserves without a
permit.
All relevant Provincial
regulations, Municipal
bylaws and ordinances
and internal Eskom laws
Expropriation Act (No 63 of
1975)
The Act requires the determination
based of compensation based on
the principle of market value.
Public access to
information Act ( No 2 of
2000)
In terms of Regulations R.385 to R.387 of the National Environmental Management Act (NEMA
No 107 of 1998) the following listed activities are applicable, which may have an impact on the
environment:
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 19 of 19
Table 5-2: Listed Activities
Indicate the number and
date of the relevant notice
Activity No (s) (in
terms of the relevant
or notice)
Describe each listed activity
Government Notice R 387 –
21 April 2006
1(I) The construction of facilities or
infrastructure, including
associated structures or
infrastructure for the transmission
and distribution of the above
ground electricity with a capacity
of 120 kilovolts or more.
2 Any development activity,
including associated structures
and infrastructures, where the
total area of the developed area
is, or is intended to be 20 hectares
or more.
Government Notice R 386 –
21 April 2006
7 The above ground storage of
dangerous good, including petrol ,
diesel, liquid petroleum gas or
paraffin in containers with a
combined capacity of more than
30 cubic meters but less than
1000 cubic metes at any location
or site.
Government Notice R 386 –
21 April 2006
12 The transformation or removal of
indigenous vegetation of 3
hectares or more or of any size
where the transformation or
removal would occur within a
critically endangered or an
endangered ecosystem listed in
terms of section 52 of the National
Environmental Management:
Biodiversity Act, 2004 (Act No. 10
of 2004).
Government Notice R 386 –
21 April 2006
14 The construction of masts of any
material or type and of any height,
including those used for
telecommunication broadcasting
and radio transmission, but
excluding-
(a) masts of 15 meters and lower
exclusively used (i) by radio
amateurs; or
(ii) for lightning purposes
(b) flag poles; and
(c) lightning conductor poles.
Government Notice R 386 –
21 April 2006
15 The construction of a road that is
wider than 4 metres or that has a
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 20 of 20
reserve wider than 6 metres,
excluding roads that fall within the
ambit of another listed activity or
which are access roads of less
than 30 metres long.
Government Notice R 386 –
21 April 2006
16 The transformation of
undeveloped, vacant or derelict
land to-
(a) (a) establish infill development
covering an area of 5 hectares; or
(b) residential, mixed, retail,
commercial, industrial or
institutional use where such
development does not constitute
infill and where the total area to be
transformed is bigger than 1
hectare.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 21 of 21
6 SCOPE OF ENVIRONMENTAL INVESTIGATIONS
6.1 Approach to Undertaking the Study
Issues based Environmental Scoping Study (ESS) for the proposed new 132/11kV Hilltop to
The Rest Powerline line and Substation has been undertaken in accordance with the
Environmental Impact Assessment (EIA) Regulations published in Government Notice R385 to
R387 of 21 April 2006 in terms of the National Environmental Management Act (NEMA; No 107
of 1998).
6.2 Authority Consultation
The relevant authorities, that are required to provide input to the proposed project, were
consulted from the outset of this study, and will be engaged throughout the project process. The
required application form was submitted to DEA on the 21st November 2009 and was
acknowledged on 4th December 2009. The Competent Authority that needs to provide a
decision regarding the proposed project is the Department of Environmental Affairs (DEA) and
Mpumalanga Department of Agriculture, Rural Development and Land administration
(MDARDLA) is a provincial commenting authority.
6.3 Environmental Scoping Study
The Environmental Scoping Study aimed to address the following:
• Identification of potential positive and negative environmental impacts (biophysical and
social).
• Identification of “hotspots” which should be avoided where possible due to potentially
significant impacts or sensitive environments;
• Description of loop-inline requirements;
• Description of Substation site alternatives that was identified;
• Evaluation of the identified feasible alternatives and the nomination of a preferred
alternative;
• Optimisation of positive impacts to the benefit of the local environment and community;
• To enable I&APs to verify that their contributions have been captured, understood and
interpreted; and
• To afford I&APs an opportunity to raise more issues if there are any.
Impacts on, inter alia, climate, topography, vegetation , avifauna, sites of archaeological,
cultural and historical interest, as well as the social environment were identified by means of a
site inspection, desk-top and field studies, consultation with specialists and key stakeholders, a
review of existing information and relevant literature.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 22 of 22
7 DESCRIPTION OF THE POTENTIAL ENVIRONMENTAL ISSUES
The Environmental Scoping Study (ESS) aims to identify the potential positive and negative
environmental (biophysical and social) impacts for the construction of the proposed new 132/11
kV Sub-Transmission power lines from the existing Hilltop Substation to the proposed New The
Rest Substation. A number of issues for consideration have been identified by the
environmental team to date. This section of the report serves to evaluate these potential
environmental impacts associated with the proposed project at the proposed Substation site
and for each route alignment prior to the implementation of mitigation measures (i.e. measures
to reduce or avoid impacts). The issues identified and potential environmental impacts
associated with the route alignment and the associated Substation sites, will be considered in
selecting the most suitable route alignment for the establishment of the proposed 132/11kV
Sub-Transmission lines as well as the Substation site.
7.1 Climate
Temperature
The mean daily maximum temperature is approximately 24.0°C in January and 15.0°C in July,
but the maximum temperatures in these months may rise to extremes of up to 29.4°C and 23.6
°C, respectively. Mean daily minimum temperatures range from approximately 18.7°C in
January to 6.4°C in July. Extremes of 4.2°C have been recorded.
Rainfall
Based on information recorded at the Nelspruit weather station, the average annual rainfall for
the Nelspruit area is approximately 762.7 mm which occurs as showers and thunderstorms and
falls mainly in the summer months, from October to March, with a peak in December (ISCW,
2006). Falls of over 100 mm can occur in a single day. Rainstorms are often violent with
severe lightning and strong westerly or easterly winds and sometimes accompanied by hail.
The winter months of June, July and August are dry and their combined rainfall comprises
approximately 3.8% of the total annual precipitation.
Wind
The wind direction in the area frequently moves towards the north-east at an average speed of
4.65 m/s. No extreme wind speed cases have been recorded in the area.
7.2. Topography
Significant ridge areas are present in the region of the proposed project. The proposed project
is likely to affect significant areas of high slopes. The general topography of the region is
described as Low Mountains.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 23 of 23
Figure 7-1: Distribution of ridges and general topography of the study area
Proposed SS 1
Proposed SS 2
Route 3
Route 2
Hilltop SS
Route 1
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 24 of 24
7.3. Specialists Studies
As part of the Scoping Study, Bohlweki-SSI Environmental was assisted by a team of
Specialists who conducted their studies making use of existing information and site visits to
identify the potentially significant impacts associated with the proposed project. Table 7.1 below
indicates the Specialists and their fields of specialisation.
Table 7-1 Specialists Team
Specialists Study Name & Organisation
Avifauna Luke Strugnell from Endangered Wild life Trust
Biodiversity Riaan Robbeson from Bathusi Environmental
Consulting
Heritage Udo Kussel from African Heritage Consulting
Herpetology Luke Verburgt from Enviro-insight
Social Nonka Byker from MasterQ Research
7.4. Avifauna
7.4.1. Description of impacts of power lines on birds
Because of its’ size and prominence, electrical infrastructure constitutes an important interface
between wildlife and man. Negative interactions between wildlife and electricity structures take
many forms, but two common problems in southern Africa are electrocution of birds (and other
animals) and birds colliding with power lines. (Ledger & Annegarn 1981; Ledger 1983; Ledger
1984; Hobbs & Ledger 1986a; Hobbs & Ledger 1986b; Ledger, Hobbs & Smith, 1992; Verdoorn
1996; Kruger & Van Rooyen 1998; Van Rooyen 1998; Kruger 1999; Van Rooyen 1999; Van
Rooyen 2000). Other problems are electrical faults caused by bird excreta when roosting or
breeding on electricity infrastructure, (Van Rooyen & Taylor 1999) and disturbance and habitat
destruction during construction and maintenance activities.
• Electrocutions
Electrocution of birds on overhead lines is an important cause of unnatural mortality of raptors
and storks. It has attracted plenty of attention in Europe, USA and South Africa (APLIC 1994;
van Rooyen & Ledger 1999). Electrocution refers to the scenario where a bird is perched or
attempts to perch on the electrical structure and causes an electrical short circuit by physically
bridging the air gap between live components and/or live and earthed components (van Rooyen
2004).
• Collisions
Collisions are the biggest single threat posed by transmission lines to birds in southern Africa
(van Rooyen 2004). Most heavily impacted upon are bustards, storks, cranes and various
species of water birds. These species are mostly heavy-bodied birds with limited
manoeuvrability, which makes it difficult for them to take the necessary evasive action to avoid
colliding with power lines (van Rooyen 2004, Anderson 2001).
Unfortunately, many of the collision sensitive species are considered threatened in southern
Africa. The Red Data species vulnerable to power line collisions are generally long living, slow
reproducing species under natural conditions. Some require very specific conditions for
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 25 of 25
breeding, resulting in very few successful breeding attempts, or breeding might be restricted to
very small areas. These species have not evolved to cope with high adult mortality, with the
results that consistent high adult mortality over an extensive period could have a serious effect
on a population’s ability to sustain itself in the long or even medium term. Many of the
anthropogenic threats to these species are non-discriminatory as far as age is concerned (e.g.
habitat destruction, disturbance and power lines) and therefore contribute to adult mortality, and
it is not known what the cumulative effect of these impacts could be over the long term.
Collision of certain bird species, particularly at river crossings, is anticipated to be an impact of
the proposed power line and should be prevented as far as possible.
• Habitat destruction
During the construction phase and maintenance of power lines and substations, some habitat
destruction and alteration inevitably takes place. This happens with the construction of access
roads, the clearing of servitudes and the levelling of substation yards. Servitudes have to be
cleared of excess vegetation at regular intervals in order to allow access to the line for
maintenance, to prevent vegetation from intruding into the legally prescribed clearance gap
between the ground and the conductors and to minimize the risk of fire under the line which can
result in electrical flashovers. These activities have an impact on birds breeding, foraging and
roosting in or in close proximity of the servitude through modification of habitat.
Habitat destruction could be an impact in the grassland and wetland areas, where natural
vegetation is still relatively intact. However, the amount of habitat destroyed for a line of this
type, or the new substation site is relatively small. This has been assessed in more detail below.
• Disturbance
Similarly, the above mentioned construction and maintenance activities impact on bird through
disturbance, particularly during breeding activities.
• Electrical faulting
Birds are able to cause electrical faults (short circuits) on power lines through their faeces,
whilst perched or roosting on pylons or towers.
ON THE PROPOSED POWER LINE THIS IS UNLIKELY, FAULTING HAS NOT BEEN
REPORTED TO EWT ON 132KV POWER LINES BEFORE, AND THE CLEARANCES AND
POLE DESIGN ON THE PROPOSED STRUCTURE SHOULD BE SUFFICIENT TO AVOID
THIS.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 26 of 26
7.5. Biodiversity
Potential impacts include the following, but are not necessarily limited to:
• Direct impacts:
o Destruction of threatened flora & fauna species & associated habitat;
o Direct impacts on common fauna species;
o Destruction of sensitive/ pristine regional habitat types;
• Indirect Impacts:
o Faunal interactions with structures, servitudes and personnel;
o Impacts on surrounding habitat/ species;
• Cumulative Impacts:
o Impacts on local and national conservation obligations & targets;
o Increase in local and regional fragmentation/ isolation of habitat; and
o Increase in environmental degradation.
7.5.1. Direct Impacts
• Destruction of Threatened Flora & Fauna Species & Associated Habitat
The loss of Red Data or Threatened species or areas that are suitable for these species is a
significant impact on the biodiversity of a region. Threatened species, in most cases, do not
contribute significantly to the biodiversity of an area in terms of sheer numbers as there are
generally few of them, but a high ecological value is placed on the presence of such species in
an area as they are frequently an indication of pristine habitat conditions. Conversely, the
presence of pristine habitat conditions can frequently be accepted as an indication of the
potential presence of species of conservation importance.
Red Data species are particularly sensitive to changes in their environment, having adapted to a
narrow range of specific habitat requirements. Habitat changes, mostly a result of human
interferences and activities, are one of the greatest reasons for these species having a
threatened status. Surface transformation activities within habitat types that are occupied by
flora species of conservation importance will definitely result in significant and permanent
impacts on these species and their population dynamics. Effects of this impact are usually
permanent and recovery or mitigation is generally not perceived as possible.
One of the greatest drawbacks in terms of limiting this particular impact is that extremely little
information is available in terms of the presence, distribution patterns, population dynamics and
habitat requirements of Red Data flora species in the study area. In order to assess this impact
an approach it is therefore necessary to assess the presence/ distribution of habitats frequently
associated with these species. Furthermore, by applying ecosystem conservation principles to
this impact assessment and subsequent planning and development phases, resultant impacts
will be limited to a large extent.
Direct threats to threatened fauna species is regarded low in probability, mainly as a result of
the ability of fauna species to migrate away from areas where impacts occur. Probably the only
exception to this statement will be in the event where extremely localised habitat that are
occupied by threatened fauna species are impacted by construction and operational activities to
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 27 of 27
the extent that the habitat no longer satisfy the habitat requirements of the particular species. It
should also be noted that threatened fauna species potentially occurring in the study area have
relatively wide habitat preferences and ample suitable habitat is presently available throughout
the study area. To place this aspect into context it is estimated that habitat loss and
transformation resulting from non-invasive and often overlooked impacts, such as overgrazing,
infestation by invasive shrubs and selective hunting probably contributes more to impacts on
certain threatened fauna species than powerline developments ever will.
• Direct Impacts on Common Flora & Fauna Species
The likelihood of this impact affecting common fauna species is relatively low as a result of the
ability of animal species to migrate away from direct impacts. The tolerance levels of common
animal species occurring in the study area is of such a nature that surrounding areas will suffice
in habitat requirements of species forced to move from areas of impact.
Likely, common flora species are widespread and occur abundantly in other, adjacent habitat.
The possibility of this proposed powerline affecting common flora species to the extent that their
conservation status might change is regarded highly unlikely.
• Destruction of Sensitive/ Pristine Regional Habitat Types
The loss of pristine natural regional habitat represents loss of habitat and biodiversity on a
regional scale. Sensitive habitat types include ridges, koppies, wetlands, rivers, streams and
localised habitat types of significant physiognomic variation and unique species composition.
These areas represent centres of atypical habitat and contain biological attributes that are not
frequently encountered in the greater surrounds. A high conservation value is attributed to the
floristic communities and faunal assemblages of these areas as they contribute significantly to
the biodiversity of a region. Furthermore, these habitat types are generally isolated and are
frequently linear in nature, such as rivers and ridges. Any impact that disrupts this continuous
linear nature will risk fragmentation and isolation of existing ecological units, affecting the
migration potential of some fauna species adversely, pollinator species in particular.
The importance of regional habitat types is based on the conservation status ascribed to
vegetation types. However, the actual impact of the construction and operation of powerlines in
grassland habitat is generally low since extremely little impacts result on the structure of the
vegetation. Impacts within grassland habitat are mostly restricted to the footprint areas of the
pole structures, which is extremely small. Visual observations within existing servitudes
revealed very little variation in the species composition between areas in- and outside the
powerline servitude.
7.5.2. Indirect Impacts
• Faunal Interactions with Structures, Servitudes & Personnel
It should be noted that animals generally avoid contact with human structures, but do grow
accustomed to structures after a period. While the structures are usually visible as a result of
clearance around tower footprints, injuries and death of animals do occur sporadically as a
result of accidental contact. Large mammals are mostly prone to this type of impact. In
particular, primate species such as baboons and monkeys are known to climb pole structures.
Alteration of habitat conditions within the servitudes does not necessarily imply a decrease in
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 28 of 28
faunal habitation. These areas are frequently preferred by certain fauna species. The
establishment of a dominant grass layer generally results in increased presence of grazer
species, which might lead to an unlikely, but similar increase in predation within these areas.
The presence of personnel within the servitude during construction and maintenance periods
will inevitably result in contact with animals. While most of the larger animal species are likely to
move away from human contact, dangerous encounters with snakes, scorpions and possibly
larger predators always remain likely. Similarly, the presence of humans within areas of natural
habitat could potentially result in killing of animals by means of snaring, poaching, road kills,
poisoning, trapping, etc.
• Impacts on Surrounding Habitat/ Species
Surrounding areas and species present in the direct vicinity of the study area could be affected
by indirect impacts resulting from construction and operation activities. These impacts could
include all of the above impacts, depending on the sensitivity and status of surrounding habitat
and species as well as the extent of impact activities. This impact also includes the floristic
species changes that could potentially occur as a result of the alteration of habitat physiognomy,
particularly in woodland areas.
7.5.3. Cumulative Impacts
• Impacts on Local and National Conservation Obligations & Targets
This impact is regarded a cumulative impact since it affects the status of conservation strategies
and targets on a local as well as national level and is viewed in conjunction with other types of
local and regional impacts that affects conservation areas. Impacts that could potentially affect
the status of protected areas are regarded unacceptable and should be avoided at all costs.
Also, aligning the servitudes in proximity to conservation areas as a mitigation measure against
impacting on the conservation areas is not always a good solution as it places a limitation on
the future expansion of conservation areas. This will only be a solution in selected cases where
extensive transformed habitat is available for the use of servitudes. Natural habitat in the
general surrounds of conservation areas do act as a buffer for these areas, also as a potential
source of genetic variability, particularly in the case of relative small conservation areas.
• Increase in Local & Regional Fragmentation/ Isolation of Habitat
Uninterrupted habitat is a precious commodity for biological attributes in modern times,
particularly in areas that are characterised by moderate and high levels of transformation. The
loss of natural habitat, even small areas, implies that biological attributes have permanently lost
that ability of occupying that space, effectively meaning that a higher premium is placed on
available food, water and habitat resources in the immediate surrounds. This, in some
instances might mean that the viable population of plants or animals in a region will decrease
proportionally with the loss of habitat, eventually decreasing beyond a viable population size.
The danger in this type of cumulative impact is that effects are not known, or is not visible; with
immediate effect and normally when these effects become visible they are beyond repair.
Lineare types of developments affect the migratory success of animals in particular.
An important mitigation measure in this regard is to utilise existing causal factors of habitat
fragmentation. One factor that will be taken into consideration is the presence of existing
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 29 of 29
powerlines in the study area. Habitat fragmentation will not be increased significantly when new
powerlines are placed adjacent to existing lines or other types of linear structures, such as
roads. In contrast, constructing new powerlines through areas of unfragmented habitat, the
adverse effects of habitat fragmentation and isolation will be maximised. Therefore, where
potential servitudes are presented with similar sensitivities, a potential alignment with an
existing servitude might result in one being more suitable for the proposed development than an
option affecting an area of largely untransformed habitat. Unfortunately this is not always a
clear-cut case as it is heavily dependent on the local and regional sensitivity of the existing line,
which might be located in areas of high sensitivity, while a line going through untransformed
habitat might represent impacts of lower significance in terms of other types of impacts.
• Increase in Environmental Degradation
Impacts associated with this type of development that will lead to initial, incremental or
augmentation of existing types of environmental degradation include impacts on the air, soil and
water present within available habitat. Pollution of these elements might not always be
immediately visible or readily quantifiable, but incremental or fractional increases might rise to
levels where biological attributes could be affected adversely on a local or regional scale. In
most cases are these effects are not bound and is dispersed, or diluted over an area that is
much larger than the actual footprint of the causal factor.
Similarly, developments in untransformed and pristine areas are usually not characterised by
visibly significant environmental degradation and these impacts are usually most prevalent in
areas where continuous and long-term impacts have been experienced.
7.6. Herpetofauna
• Direct Impacts
Impacts of transmission lines and the substation are likely to be limited to disturbance and
displacement of herpetofauna during the construction phase. During construction the direct
impacts expected are from habitat destruction/alteration from clearance of vegetation and
foundation construction for the substation, the erection of pylons and the creation of servitudes
as well as disturbance and possible mortality from these activities.
• Indirect Impacts
Impacts of transmission lines, such as the interaction of herpetofauna with the structures,
servitudes and personnel need to be considered. Because of the terrestrial nature of
herpetofauna, limited negative interactions with the structures are expected. Some species such
as dwarf gecko’s (Lygodactylus spp.) benefit from the metal pylons as these structures retain
heat and allow for extended foraging periods (Verburgt, unpublished). Furthermore, many
rupiculous (rock-living) skinks and certain snakes take up residence in the concrete and rock
base of the pylons where cracks or holes in the concrete create suitable refuges. This positive
indirect impact leads to the negative indirect impact of herpetofauna interactions with personnel.
Potentially dangerous snakes (venomous species) may take up residence or hunt for prey
around the base of pylons and interact with personnel inspecting/repairing the transmission line.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
Bohlweki-SSI Environmental
• The Negative Indirect
Impact of transmission line servitudes is of medium- to long-term concern. Once the direct
impact from the construction of servitude has taken place the vehicle traffic on the servitude
represents a potentially large threat to the herpetofauna community since many herpetofauna
species are killed by vehicles while crossing roads. Of particular concern is the annual migration
of adult amphibians towards a suitable breeding site (dam, stream) in spring and then the
migration of both adults and juveniles away from the breeding site in mid-summer and autumn.
Servitudes may also impair dispersal and cause habitat fragmentation for example; compacted
roads may represent a dispersion barrier for strictly fossorial (ground-living) species.
A negative indirect impact of substations is the attraction of potentially dangerous snakes which
may interact with personnel due to the production of heat and the creation of suitable refuges by
a substation. This impact may be enhanced by the presence of improperly stored construction
material on or adjacent to the substation that provide suitable refuges for snakes and attract
certain prey species (e.g. rodents). Furthermore, the presence of powerful lights at night attracts
many insects which cluster around the lights and fall to the ground below. This in turn may
attract amphibians which may attract potentially dangerous snakes that feed on amphibians
(e.g. Naja mossambica).
7.7. Heritage
During the site visit a single stone wall and long Iron Age stone wall on a rock face were found
dating late Iron Age see figures 7.9 and 7.10.below.
Figure 0-2: Single stone wall on rock face, of modern times
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
Bohlweki-SSI Environmental
Figure 0-3: Long Iron Age stone wall
7.8. Social
All of the infrastructure development associated with the proposed project is located within the
Mbombela Local Municipality, which in turn forms part of the Ehlanzeni District Municipality of
the Mpumalanga Province. An indication of the location of the study area within the
Mpumalanga Province is reflected in figure 7.4 below. Mpumalanga means “place where the
sun rises”. The province is located to the north eastern part of South Africa, and is bordered by
Mozambique to the east and the Kingdom of Swaziland to the south and east. On its western
border is the province of Gauteng, with the Free State to the south west and KwaZulu-Natal to
the south east. Mpumalanga has a land surface area of approximate 79 511.5km2, which
represents approximately 6.5% of South Africa’s total land surface. According to Community
Survey 2007, the province is home to approximately 3,643,435 people, which represents a
population growth of approximately 7.6% (or 277,550 people) over the 6-year period between
2001 (when the last census was conducted) and 2007. The population in Mpumalanga accounts
for 7.5% of South Africa’s total population of 48,502, 063 people as of 2007. The province
appears to be largely rural in nature, which is evident in the fairly low population density of 45.8
persons per km2.
According to the Mpumalanga Province’s Growth and Development Strategy (MPGDS), the
economic growth within the province averaged around 2.5% between 1996 and 2001,
increasing to an average of around 4.3% between 2004 and 2007. This places the province
more or less on par with the country’s Geographic Domestic Product (GDP) growth. In 2004 the
main economic sectors in the province were the mining, energy, and manufacturing industries
that, collectively, comprised approximately 60% of the province’s Gross Value Addition. Despite
these industries being the largest, they only provided employment to around 20% of the
province’s population. During 2005 the energy sector was replaced by community services as a
key industry, contributing approximately 20% to the province’s employment rate. The main aim
of the province’s GDS (2004-2014) is to improve the local inhabitants’ quality of life by
promoting sustainable development. It is believed that sustainable development in turn will
create a stable investment climate that will aid in creating employment opportunities, which will
then create income generating capabilities for those individuals involved.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
Bohlweki-SSI Environmental
Figure 0-4 Overview of the Study area from a Provincial perspective
The processes in which the potential social impacts are identified are listed below.
• Geographic processes: land use patterns;
• Demographic processes: the composition of the local community;
• Economic processes: the way in which people make a living and the economic activities in
a society;
• Institutional and Legal processes: the role and efficiency of the local authority and other
service providers in the area in terms of their capacity to deliver services to the local area;
and
• Socio-cultural processes: The way, in which humans behave, interact and relate to each
other, their environment, and the belief and value systems that guide these interactions.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 33 of 33
Table 7-2. Overview of the Expected Geographical Change Processes and Potential Impacts
GEOGRAPHICAL PROCESSES
Summary of Baseline Profile Change Process and Expected Impacts
Large segments of the project area appear to
be utilised for either agricultural purposes or
forestry. A number of scattered households
have also been identified throughout the study
area.
A 31m-wide servitude is required for the sub-transmission power line, which implies a temporary and/or
permanent loss of agricultural/forestry land, which in turn can have an economic impact on the landowner in
question.
At this stage it is assumed that large segments
of the study area are privately owned. At the
time of the study it was unclear whether any
parts of the study area was tribal land or
whether land claims existed on any of the
affected portions.
Private landowners and commercial farmers will be affected by the servitude acquisition process as outlined
above.
Detailed information on future infrastructural
developments was not available at the time of
the study.
The presence of the substation and sub-transmission power line can alter development layout plans to ensure
the safe operation of these installations. Conversely, development cannot take place if there is a lack of
sufficient service such as electricity.
Table 7-3. Overview of the Expected Demographical Change Processes and Potential Impacts
DEMOGRAPHICAL PROCESSES
Summary of Baseline Profile Change Process and Expected Impacts
The current total population within the affected area
is just over 527,000 people with a population density
of 154.5 people per km2. However, it is not expected
that the population density would be as dense in
rural areas as might be the case with urban areas.
The proposed development will lead to an increase of a certain section of the population, i.e. an influx of
migratory workers in the form of the construction team. A change in the number and composition of the
local area can lead to economic, health, safety and social-wellbeing impacts. The impact is expected to be
mostly confined to the construction phase. It should also be noted that a construction team consisting of
486 construction workers will not yield a significant impact on a total population of 527,000 as it represents
an average increase of 0.09% on the population size. The impact is further expected to significantly
decrease during the operation and maintenance phase as the size of the maintenance team will be
considerably smaller than that of the construction team.
The current baseline profile indicated that a total
number of just more than 50,000 people entered the
area since 2001, presumably due to increased
The presence of the construction team and the prospect of employment might intensify the influx of people,
e.g. an influx of unemployed work seekers might be expected. It is difficult to predict what the impact would
be as a result of this, as it is coupled to the number of people who enter the area. This can range from a
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 34 of 34
employment opportunities. handful of people to literally hundreds of people. The influx of unemployed work seekers is an uncontrolled
process and therefore the size of this group is near impossible to predict. .
There are a number of households and/or structures
within each of the route corridor alternatives.
The proposed development might necessitate the relocation of households along the various route corridor
alternatives, depending on the flexibility of the route alignment. It is not expected that the relocation of
households would affect the size and composition of the local population as relocation normally takes place
within the same area. However, the relocation of households impacts on the affected households’ way of
life – but this is to a large degree influenced by the affected family’s level of attachment to their
environment, which in turn is influenced by the family history, years spent in the area, etc.
At this stage the need for relocation is not foreseen at any of the substation sites. However, both sites are
located in close proximity to scattered households
Table 7-4. Overview of the Expected Economical Change Processes and Potential Impacts
ECONOMICAL PROCESSES
Summary of Baseline Profile Change Process and Expected Impacts
The affected area is to a large extent
characterised by a fairly high employment rate
(just over three quarters of the economically
active population is formally employed).
Despite this high employment rate, the area is
still characterised by low household income
levels – in 2001 just over a quarter of all
households earned an income above the
acceptable minimum standard of ≥ R 20,000
per annum.
The proposed development can enhance economic opportunities for vulnerable communities by creating and
affording job opportunities to local community members. However, it is not foreseen that such opportunities would
be sustainable as most of the jobs will be restricted to the construction phase. It is furthermore unlikely that vast
numbers from the local community will find employment during the construction phase due to the skills levels
required and the sensitivity of the construction material used (e.g. in the past temporary staff from local
communities were responsible for copper theft, which resulted in time delays and cost implications for Eskom).
Even if local community members are not utilised as part of the construction team, it is important to note that 486
positions will still be created, which means that there will still be 486 employment opportunities available on a
national level. These individuals will still gain financially from employment on the project, whether they are local or
not. The proposed project can furthermore lead to a boost in the local formal and informal trade market as it is
likely that some local services can be utilised, albeit on a temporary basis.
Large segments of the route corridors span
across cultivated farmland, as discussed
under geographical change processes.
Depending on the size of the area affected and how it affects the surrounding land use (e.g. whether farming
activities can continue mostly unhindered or not), the property value can be affected due to the presence of a
power line that will visually intrude on the farm. Where land loss occurs, this can also bear an economic impact on
the affected farmer.
The baseline municipal profile (as discussed
in detail in the following section) suggests that
The expansion of the municipal services network can take place if more electricity becomes available. This means
that more households can be connected to the electricity grid, which would enhance their quality of life. In
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 35 of 35
municipal services are lacking in the area. It
can be expected that a lack of such services
would hinder economic growth.
addition, the expansion of the electricity grid could stimulate economic growth in the area, which in turn would
have a positive economic impact on the area as more jobs become available.
Table 7-5. Overview of the Expected Institutional and Legal Processes and Potential Impacts
INSTITUTIONAL & LEGAL PROCESSES
Summary of Baseline Profile Change Process and Expected Impacts
The existing baseline municipal profile
suggests that these services are inadequate
in the area with many households that do not
have access to basic services such as
electricity, municipal refuse removal, or
sanitation and water services on par with RDP
standards.
Additional demand on municipal services, such as water, sewerage and roads could impact on health and safety
if such services are not available.
The baseline municipal profile further
suggests that all households do not have
equal access to municipal services – usually it
is the outlying areas and informal settlements
that mostly lack these services.
It is foreseen that the proposed development could enhance the equal access of households to at least some
basic services such as electricity as a result of the broadening of the local network. The availability of additional
services in turn can lead to economic growth.
According to the Mbombela IDP (2009/10),
approximately 82% of the municipal area is
taken up by informal settlements, especially in
the so-called Eastern Development Corridor.
The current housing backlog in the municipal
area is estimated to be around 39,482 units.
Construction workers will require housing. In the past large segments of this group was housed successfully
within the local community to avoid the use of a residential construction village as the presence of such a village
brings with it its own set of socio-cultural change processes and resultant impacts. The need for housing is
normally addressed by the contractor(s).
An influx of unemployed job seekers can lead to the expansion of the informal settlement. This can impact on
health (as services are not provided or further taxed) and safety (an increase in crime is possible as people do not
find employment and become frustrated with their living conditions).
The area appears to be lacking sufficient
infrastructure and services. This is evident in
the fact that the entire area is serviced by two
district hospitals (of which only one is located
in nearby Nelspruit). Although the area is
The influx of job seekers might lead to an increase in opportunistic crime. The health and emergency services in
the area might not be able to cope with accidents and emergencies, which will have obvious health impacts.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 36 of 36
INSTITUTIONAL & LEGAL PROCESSES
serviced by five police stations, these stations
are wide-spread throughout the area.
Table 7-6. Overview of the Expected Social Cultural Processes and Potential Impacts
SOCIO-CULTURAL PROCESSES
Summary of Baseline Profile Change Process and Expected Impacts
At the time of the study information was not
available on the cultural dynamics of the
affected local area.
It is possible that construction workers and job seekers have a different cultural background and dissimilar social
practices than local residents, which can lead to the development of conflict situations that impact on community
cohesion and social well-being.
At the time of the study the level of place
attachment that local residents have to the
area was not known.
The substation and sub-transmission power line might affect people’s relationship with their environment (their
sense of place) as the presence of such infrastructure changes the landscape from unspoilt to ‘spoilt’.
Negative
The family structure and how families from the
area function and the roles ascribed to each
family member was not known.
Although it is not foreseen that the development per se will alter family cohesiveness and the traditional role
played by families, the introduction of strangers to the area might have this affect. This can happen when social
integration is hindered (through conflict) and also because migratory workers have a certain legacy when it comes
to establishing relationships that can increase the risk of spreading HIV and other contagious infections. Apart
from the obvious health implications, HIV infection in particular also has an economic impact.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 37 of 37
8. PUBLIC PARTICIPATION PROCESS FOR THE ENVIRONMENTAL SCOPING STUDY
The primary aims of the public participation process during the Environmental Scoping Study
were:
• to inform Interested and Affected Parties (I&APs) of the proposed project;
• to identify issues, comments and concerns as raised by I&APs;
• to promote transparency and an understanding of the project and its consequences;
• to serve as a structure for liaison and communication with I&APs; and
• to provide local knowledge and input in identifying potential environmental (biophysical and
social) impacts and “hotspots” associated with the proposed development.
8.1. Advertising
In terms of the EIA Regulations, as published in 2006, the commencement of the EIA process
for the project was advertised in the Mpumalanga News, on 25 February 2010 respectively, at
the inception of the project. This advertisement requested I&APs to register, and to become
involved in the project. A copy of the advertisement tear sheet will be attached in the final
scoping report. The primary aim of this advert was to ensure that the widest possible group of
I&APs were informed of the project, and to elicit comments from the public regarding the
proposed project.
8.2. Identification of Key Stakeholders
The first step in the public participation process was to identify key stakeholders, including:
• Central and Provincial Government Representatives;
• Local authorities (i.e. Mbombela Municipality);
• Affected and surrounding landowners.
• Environmental NGOs; and
• Community based organisations.
All I&AP information (including contact details), together with dates and details of consultations
and a record of all issues raised will be recorded within a comprehensive project database. This
database will be updated on an on-going basis throughout the project, and will act as a record
of the communication/public involvement process.
8.3. Briefing Paper
A briefing paper for the project has been compiled and the aim of this document is to provide a
brief outline of the proposed project, provide preliminary details regarding the EIA process, and
explain how I&APs could become involved in the project. The briefing paper, together with a
comment sheet and relevant map, will be distributed to all identified stakeholders and I&APs
inviting them to register for the proposed project and submit details of any issues and concerns
that they may have.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 38 of 38
8.4. Consultation and Public Involvement
Through consultations with I&APs and Stakeholders, issues for inclusion within the
Environmental Scoping Report will be identified and recorded. Consultations will take the form
of telephonic interviews with key I&APs and stakeholders to inform them of the proposed project
and to record their comments. In addition, a Local Authority Focus Group Meeting was held on
the 10 March 2010 at the Nelspruit Public Library. Minutes of this consultation will be included
within the Final Environmental Scoping Report.
A public meeting was held on 11 March 2010 at the Nelspruit Public Library during the review
period of the draft Environmental Scoping Report. In accordance with the requirements of the EIA
Regulations, this meeting was advertised 10 days prior to the event. The primary aim of this
meeting was to:
• disseminate background information regarding the proposed project to I&APs,
• supply more information regarding the EIA process and the findings of the specialist studies
undertaken;
• answer questions regarding the project and the EIA process;
• obtain feedback from I&APs with respect to the proposed project; and
• receive input regarding the public participation process.
These minutes will be included within the Final Scoping Report. Networking with I&APs, will
continue throughout the duration of the project.
8.5. Social Issues Trail
Issues and concerns raised during the public participation process will be compiled into an
Issues Trail. This information will be incorporated within the final Environmental Scoping Report.
8.6. Public Review of Draft Environmental Scoping Report
The draft Environmental Scoping Report was made available for review at the following public
locations within the study area, which were identified as readily accessible to I&APs:
• Nelspruit Public Library -
• Mbombela Municipality Offices -
• Bohlweki Environmental Offices - 21 Woodlands Drive, Woodmead, Johannesburg
The availability of this draft report was advertised in the newspapers. A 30-day period is allowed
for this review process, from 25 February 2010 to 25 March 2010. I&APs registered on the
project database were notified of the availability of this report.
Through the first phase of the report review which occurred between February and March 2010
there was a request from the Interested and Affected Parties that additional studies be
conducted for the project and they are Social and Herpetology studies. The studies were
conducted accordingly and they form part of the Amended Scoping Report. This report will be
made available for public review on 27 August 2010 to 28 August 2010 at the venues which
were previously used for the first draft. The Interested and Affected Parties will once again be
informed accordingly on the availability of the amended report.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 39 of 39
9. CONCLUSIONS AND RECOMMENDATIONS
Based on the identification and preliminary assessment of the potentially significant issues, it is
recommended that further investigations be conducted for all preferred powerline alignments for
the transmission lines and site alternatives for the proposed substation, and these will be
assessed in the Environmental Impact Assessment (EIA) Phase of the process. The Scoping
process has not revealed any environmental fatal flaws associated with any of the alternatives
under consideration.
In order to ensure that the required mitigation measures are implemented, it is recommended
that an EMP be compiled for the project, and attached to the final Environmental Impact
Assessment report, in order to transfer the findings of the environmental studies into practical
measures. This EMP should form part of the contract for the construction and operation of the
proposed project.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 40 of 40
10. PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT
10.1. Process Phases
The environmental studies will be undertaken within the two phases, as follows:
• Environmental Scoping Study
A desk-top issues-based Environmental Scoping Study has been undertaken for the proposed
project. Existing information and input from specialists, the Authorities and Interested and
Affected Parties (I&APs) was used to identify and evaluate potential environmental impacts
(both social and biophysical) associated with the proposed project. No environmental fatal
flaws associated with the proposed project were identified through the Environmental Scoping
Study, although a number of potentially significant environmental impacts have been identified
as requiring further in-depth study. Therefore, the EIA is required to be undertaken in order to
provide an assessment of these potential impacts and recommend appropriate mitigation
measures where required. The EIA will be used as an instrument to further identify, discuss and
evaluate alternative sites.
• Environmental Impact Assessment (EIA)
All potentially significant environmental impacts (social and biophysical) associated with the
proposed project have been identified in the Scoping Study and will be further investigated and
assessed within the EIA through specialist studies. Mitigation measures will be proposed,
where required. The EIA will also be utilised as an instrument for the identification and
evaluation of the corridor alternatives. The EIA will aim to adequately investigate and address
all environmental issues in order to provide DEA ad MDARDLA with sufficient information to
make an informed decision regarding the proposed project.
10.2. Particulars of the Applicant
Applicant: Eskom Distribution Northern Region
Contact Person: Mr Josiah Zungu
Telephone Number: 013 755 9655
Email: [email protected]
10.3. Environmental Consultants
Consultant: Bohlweki-SSI Environmental
Contact Person: Ms Sibongile Gumbi
Telephone number: 011 798 6449
Email: [email protected]
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 41 of 41
• Environmental Study Team
Bohlweki SSI Environmental has been appointed by Eskom Distribution Northern Region as
independent environmental consultants, to undertake the Environmental Scoping Study for the
proposed project. Details of the environmental study team and their fields of specialisation are
as follows:
Team Member Responsibility
EAP
Malcolm Roods Project Manager for EIA. He will provide strategic input into the
Scoping and EIA phases, as well as into the EMP. In addition, he
will be responsible for the review of specialist studies
Sibongile Gumbi Sibongile responsibilities will include regular liaison with the Client
and the environmental authorities, and on-going review of progress
of all aspects of the project. She will also be responsible for the
compilation of a consolidated EIA Report and an EMP for the
Project. This will include recommendations regarding appropriate
mitigation measures. She will provide support in the management
of the public participation process for the project.
Sibongile Hlomuka Sibongile is responsible for the management of the Public
Participation Process. She will be responsible for the day-to-day
management and co-ordination of the public participation process
SPECIALISTS
Luke Strugnell
(Endangered Wildlife
Trust)
Specialist input with regards to the identification and evaluation of
potential impacts on avifauna.
Riaan Robbeson (
Bathusi Environmental
Consulting)
Specialist input with regards to the identification and evaluation of
potential impacts on biodiversity.
Luke Verburgt ( Enviro-
Insight)
Specialist input with regards to the identification and evaluation of
potential impacts on herpetofauna.
Udo Kussel ( African
Heritage Consulting)
Specialist input with regards to the identification and evaluation of
potential impacts on heritage resources.
Nonka Byker ( Master
Q Research)
Specialist input with regards to the identification and evaluation of
potential impacts on social issues.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 42 of 42
10.4. Approach to undertaking the project
• Authority Consultation
Consultation with all relevant authorities initiated during the Scoping Phase will continue
throughout the duration of the project. The representatives from the relevant Departments will
be requested to formally provide input into the EIA process. The authorities to be consulted
include:
• National Department of Environmental Affairs
• Mpumalanga Department of Agriculture, Rural Development and Land Administration
• Environmental Impact Assessment
Aims of the Environmental Impact Assessment
The Environmental Impact Assessment (EIA) will aim to achieve the following:
• to provide an overall assessment of the social and biophysical environments affected by the
proposed project;
• to assess the study area in terms of environmental criteria;
• to identify and recommend appropriate mitigation measures for potentially significant
environmental impacts; and
• to undertake a fully inclusive public participation process to ensure that I&AP issues and
concerns are recorded.
Detailed Specialists Studies to be undertaken as part of the EIA
A number of potentially significant issues were identified within the Scoping Study. These issues
require further investigation within an EIA in order to ensure that potential environmental
impacts associated with the proposed project are limited through mitigation. The specialist
studies to be undertaken during the EIA will take the relevant DEA and MDARDLA Guidelines
into account.
• Avifauna
The avifauna study will identify the following impacts namely impacts of powerlines on birds,
comparison of substation alternative sites and powerline route alignment, selection of the
preferred alignment for the powerline and preferred site for the substation and provide mitigation
measures.
The Terms of Reference for the avifaunal impact assessment is as follows:
• Provide a profile of the baseline information with respect to the Avifauna, from both a
regional and local perspective with a specific focus on the local context and the study area,
particularly along the proposed route alignments and new substation sites. As part of this
description the following aspects are to be covered:
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 43 of 43
o Identify and describe the main ecosystems and habitats in the area, with emphasis on
protected, threatened and vulnerable ones.
o Identify and describe the land use types and plant communities within the study area.
o Identify potentially occurring bird species and those of conservation concern.
• Assess the biodiversity status of the study area with the view of identifying sensitivities and
areas that may be considered as ‘no-go’ areas. Also suggest any local deviations where
appropriate. Provide supporting reasons in each option.
• Map all relevant aspects.
• Give an indication of likely environmental issues and, or potentially occurring impacts on the
ecological biodiversity that can be expected as a result of the proposed activity (pre-
construction, construction, operational and decommissioning phases). Also address
cumulative impacts that have been identified.
• Biodiversity
The following terms of reference will be used in assessing the biodiversity impacts
• Assessment of Biophysical Attributes
o Data Selection Process
o Biophysical Sensitivities - GIS Analysis
• Assessment of Floristic Attributes
o Floristic Patterns & Regional Diversity
o Floristic Sensitivity
o Red Data Flora Assessment
• Assessment of Faunal Attributes
o General Faunal Diversity
o Red Data Fauna Probabilities
o Faunal Habitat Sensitivities
• Criteria for the Classification of an Impact
o Nature
o Extent (Scale)
o Duration
o Intensity
o Probability
o Significance
o Impact Categories
• Assessment of route alignments and nomination of the preferred.
• Assessment of substation sites and nomination of the preferred.
• Herpetology
Herpetology study will be use the following methodology in assessing the impacts.
• Assessment of impacts on herpetofauna
• Assessment of habitat destruction
• Assessment of Substation alternative sites and powerline route alignment and
• Nomination of the preferred alignment route and substation site.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 44 of 44
• Heritage
The following terms of reference will be used in assessing the heritage impacts
• Assessment of heritage artefacts
• Assessment of substation alternatives and powerline route alignment and
• Nomination of the preferred route alignment and substation site
• Social
The following methodology will be used in adequately potential assessing the social impacts as
outlined below.
Information Requirements Proposed Methodology
GEOGRAPHICAL CHANGE PROCESSES
1. The agricultural potential of the farmlands along the corridors and at the substation sites;
2. Detail on landownership along the corridors and for the substation sites;
3. The size and number of expected construction and operational vehicles as well as which route(s) will be used to gain access to the various construction sites;
4. Planned developments for the study area; and
5. Whether or not any land claims exist on any of the land along the route alternatives.
1. Obtain information from the agricultural potential specialist study for inclusion in the assessment.
2. Obtain landowner detail from the public participation consultant. Consult with these landowners via the public participation focus group meetings.
3. Obtain information from Eskom on the size and number of construction and operational vehicles and the frequency with which these vehicles will pass through the area.
4. Consult with the local municipality via the public participation focus group meetings to determine where future developments will take place.
5. Obtain information from the public participation consultants on any land claims in the area.
DEMOGRAPHICAL CHANGE PROCESSES
1. Confirmation on the composition of the construction workforces in terms of size, skills levels, and origin;
2. The composition of the maintenance workforce and their activities;
3. The number of local employment opportunities as this could influence the number of people entering the area; and
4. A more refined route alignment within the various route corridors to gain a better understanding of the space constraints and the resultant potential for relocation of households and/or infrastructure.
1. Verify information on the construction workforce in terms of size, skills level and origin with Eskom.
2. Obtain information from Eskom on the size of the maintenance workforce and their activities.
3. Obtain information from Eskom on the potential for local employment.
4. If available, obtain information from the specialist workshop and Eskom on a more refined route alignment to determine the number of potential relocations within a corridor.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 45 of 45
Information Requirements Proposed Methodology
ECONOMICAL CHANGE PROCESSES
1. The total size of affected farm portions;
2. The types of activities that are pursued on any given (affected) property;
3. The income derived from these activities;
4. Capital investments that have been made on (affected) properties with the aim to generate income;
5. The number of people that are employed by affected farmlands;
6. Future plans/activities for the affected properties;
7. The negotiation process with private landowners in terms of land acquisition, e.g. how compensation is calculated, when the process will take place, etc.;
8. The local employment opportunities that will be created, both direct and indirect formal and informal job opportunities;
9. Future development plans for the area in general and how the proposed development could affected and/or enhance such development plans; and
10. If available, the average period of employment and an outline of a typical salary package for unskilled labour, if such labour will be sourced from within the local community.
1-6. Consult with affected landowners via the
public participation focus group meetings.
7. Verify information on the negotiation process with Eskom.
8. Obtain information from Eskom on the potential for local employment.
9. Consult with the local municipality via the public participation focus group meetings to determine where and what future developments will take place.
10. Obtain information from Eskom on the average period of employment and an outline of a typical salary package for construction workers.
INSTITUTIONAL AND LEGAL CHANGE PROCESSES
1. Local communities’ perception on the proposed project and their issues and concerns;
2. The affected municipalities’ ability to sustain additional connections to the local municipal network in the event that these services are acquired from the municipalities at the construction site (and in the event that a residential construction village is utilised); and
3. Whether a construction village will be used, and if so, the most likely location for such a construction village, how many workers would be housed within the construction village, and the housing conditions.
1. Assess the issues and response register. Consult with interest groups via the public participation focus group meetings.
2. Consult with the local municipality via the public participation focus group meetings.
3. Obtain information from Eskom to determine the likelihood for the use of a residential construction village and how the location for such a village is determined.
SOCIO-CULTURAL CHANGE PROCESSES
1. The history of the areas affected and of these areas’ local residents;
1. Undertake a desktop study to expand the information on the history of the local area.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 46 of 46
Information Requirements Proposed Methodology
2. What residents value in the local area (i.e. why have the settled in the area);
3. The cultural dynamics of the existing settlements and their ability to accommodate and/or integrate workers from outside their community;
4. The daily activities of surrounding residents and their cultural attachment to the area; and
5. Information on areas that hold a specific significance for local residents.
2. Consult with local residents via the public participation focus group meetings.
3-5. Assess information obtained from focus group meetings.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 47 of 47
10.5. Public Participation Proccess for the EIA Phase
• On-going Consultation with all I&APs
On-going consultation with key stakeholders (e.g. local authorities, relevant government
departments, local business), and other identified I&APs will ensure that I&APs are kept
informed regarding the EIA findings and proposed mitigation measures. Networking with I&APs
will effectively continue throughout the duration of the project until the closure of the EIA phase.
The database and issues trail will be continually updated throughout the process.
• Public Involvement
A public meeting will be held to provide the general public with feedback regarding the findings
of the EIA, and to provide detail regarding mitigation measures proposed. In accordance with
the requirements of the EIA Regulations, the public meetings will be advertised 10 days prior to
the event. I&APs registered on the project database will be notified of this public meeting by
letter. In addition, local authorities will be invited to attend a focus group meeting, in order to
encourage continued participation in the process. Formal minutes of the public meeting and
focus group meetings will be compiled and distributed to the attendees. These proceedings will
also be included in the final EIA report.
• Social Issues Trail
Issues and concerns raised during the public participation process of the EIA phase will be
compiled into an Issues Trail. Proceedings of meetings and comments received will also form
part of the document. This record of issues will provide a consolidated list in order to ensure
that all issues and concerns raised by I&APs are considered within the EIA process.
10.6. Compilation of the Environmental Impact Report
The EIA Report will include and address the following:
• a project description (including a description of the proposed activity, plans illustrating the
study area and proposed site, and detailed technical details regarding the proposed
project);
• a description of the pre-construction environment;
• a description of the public participation process, including the identification of I&APs, a
record of the procedures followed, and the perceptions and views of the I&APs regarding
the activity;
• a description of environmental (biophysical and social) issues identified and potential
impacts of the proposed project on these aspects (i.e. how the environment may be affected
as a result of the proposed activity)
• assessment of impacts identified in the Scoping Study which were determined to be
significant. These impacts will be assessed in terms of the nature, extent, duration, intensity,
severity and probability of the impact occurring;
• conclusions and recommendations regarding the presence of any environmental fatal flaws
and recommendations (including a preferred site and mitigation and management
measures) regarding the proposed project.
• Furthermore, the EIA Report will comply with Regulation 32 of GN 385 and other applicable
regulations/guidelines insofar as content and issues addressed are concerned.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 48 of 48
• The integration of the specialist studies into a consolidated report will allow for easy
assessment of the potential environmental aspects. In order to evaluate the significance of
the identified impacts, the following characteristics of each potential impact will be identified:
• the nature, which shall include a description of what causes the effect, what will be affected
and how it will be affected;
• the extent, wherein it will be indicated whether the impact will be local (limited to the
immediate area or site of development) or regional;
• the duration, wherein it will be indicated whether the lifetime of the impact will be of a short
duration (0–5 years), medium-term (5–15 years), long term (> 15 years) or permanent;
• the probability, which shall describe the likelihood of the impact actually occurring, indicated
as improbable (low likelihood), probable (distinct possibility), highly probable (most likely), or
definite (impact will occur regardless of any preventative measures);
• the significance, which shall be determined through a synthesis of the characteristics
described above and can be assessed as low, medium or high; and
• the status, which will be described as either positive, negative or neutral.
• Eskom Distribution have the responsibility to avoid or minimise impacts and plan for their
management (in terms of the EIA Regulations), the mitigation of significant impacts will be
discussed and conclusions and recommendations regarding the preferred alternative.
10.7. Review of Environmental Impact Report
• Public Review of the draft Environmental Impact Report
The draft Environmental Impact Report will be made available at public places for public review
and comment, in accordance with the EIA Regulations. A 30-day period will be allowed for this
review process. An advert indicating the availability of this report and the information regarding
the public meeting will be placed in the local newspaper. In addition, all I&APs registered on the
project database will be notified of the public meeting and the availability of this report and the
review period by letter. All I&AP comments received during the 30-day public review period will
be incorporated into a final Environmental Scoping Report. This final report will be submitted to
the Authorities for their review and consideration.
• Authority Review of the Environmental Impact Report
The Environmental Impact Report will be submitted to DEA who will review and also consider
the comments provided by MDARDLA when making a final decision. It is envisaged that the
Final EIA report will be submitted to DEA and MDARDLA at the end of November 2010 for final
review and decision-making.
10.8. Environmental Authorisation
On receipt of the Environmental Authorisation for the project, the I&APs registered on the
project database will be informed of this Environmental Authorisation and its associated terms
and conditions in writing via fast mail and email.
Hilltop to The Rest 132kV Sub-Transmission line
E02.JNB.000540
Eskom Distribution Northern Region
02
8/27/2010
Bohlweki-SSI Environmental
Page 49 of 49
10.9. Work Programme
The environmental programme for the Environmental Impact Study and the key dates relevant
to the project are outlined in the table below:
Activity Timeframe
Obtain written approval of ESS and POS for EIA
from DEA October 2010
Specialist studies September 2010
Consultation with I&APs On going process
Compile a draft EIA Report September 2010
Make a draft EIA Report available for public
comment October-November 2010
Public review period October-November 2010
Finalise EIA Report November 2010
Submit Final EIA Report to DEA and MDARDLA November 2010
Full Authority review period December 2010-January
2011
Record of Decision March 2011