all definitions, interpretations and general provisions for … -c3... · web viewconcrete must be...

114
BID NUMBER ELM/1/1/2018T CONSTRUCTION OF INDWE FEEDLOT C3 Scope of Work EMALAHLENI MUNICIPALIY BID NUMBER ELM/1/1/2018T CONSTRUCTION OF INDWE FEEDLOT C.3 SCOPE OF WORKS All definitions, interpretations and general provisions for the General Conditions of Contract for Construction Work (2010) (2 nd editions are applicable. C3.1 Description of the Works C3.2 Engineering C3.3 Procurement C3.4 Construction C3.5 Management C3.6 Health and Safety C3.7 Projection Specifications Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Upload: tranxuyen

Post on 24-Mar-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

EMALAHLENI MUNICIPALIY

BID NUMBER ELM/1/1/2018T

CONSTRUCTION OF INDWE FEEDLOT

C.3 SCOPE OF WORKS

All definitions, interpretations and general provisions for the General Conditions of Contract for Construction Work (2010) (2nd editions are applicable.

C3.1 Description of the WorksC3.2 EngineeringC3.3 ProcurementC3.4 ConstructionC3.5 ManagementC3.6 Health and SafetyC3.7 Projection Specifications

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 2: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C3.1DESCRIPTION OF THE WORKS

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

TOPIC ASPECT COMMENTARY

DESCRIPTION OF THE WORKS

Employer’s objectives-

To Construct Feedlot for Indwe Community

Overview of the works-

Construction of New Indwe Feedlot

Page 3: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C3.2ENGINEERING

ENGINEERING

Design services and activity matrix

-Works designed by: Emalahleni MunicipalityConcept, feasibility and overall process: Emalahleni MunicipalityBasic engineering and detail layouts to tender stage: Not Applicable.Temporary works: Contractor

Drawings

-

Drawings provided by the Engineer :1. Layout Plan (Details of the Feedlot)

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 4: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C 3.3PROCUREMENT

PROCUREMENTThe Tenderers notice is drawn to the fact that the awarding of this tender will be in terms of the Supply Chain Management Policy of the Emalahleni Municipality and the Standard Conditions of tender as contained in Annexure F of the 28th May 2010 edition of the CIDB Standard for Uniformity in Construction Procurement

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 5: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C3.4CONSTRUCTION

CONSTRUCTIONWorks specifications

The South African Bureau of Standards, Standard Specifications for Civil Engineering Construction (SABS 1200) shall apply.

Refer to PROJECT SPECIFICATIONS

Particular / generic specifications Refer to PROJECT SPECIFICATIONS

Existing services Known services There is no information regarding known

services

Damage to services Contractor to be responsible for damage to services

Site establishment

Services and facilities provided by the employer

None

Facilities provided by the contractor See PROJECT SPECIFICATIONS

Storage and laboratory facilities See PROJECT SPECIFICATIONS.

Other facilities and services See PROJECT SPECIFICATIONS

Notice boards See PROJECT SPECIFICATIONS

Water for construction purposes

-The Contractor must make all arrangements for the procurement, transportation and storage of water required for consumption and construction.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 6: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C3.5MANAGEMENT

MANAGEMENTParticular / generic specifications

See PROJECT SPECIFICATIONS

Planning and programming

Contractor to provide a programme in bar chart form which will remain as the Contract Programme but will also be updated as and when necessary or when instructed by the Engineer

Methods and procedures

Methods and procedures

The Contractor will ensure that the Project Steering Committee is kept fully informed as to where and when work will commence in different areas and what the particular work consists of.All labour is to be recruited from the local communities through the Project Steering Committee and, if required by the communities, rotated in order to share the work throughout the area.

Quality plans and control

Refer to the relevant standards for testing requirements etc.

EnvironmentCare must also be taken to avoid at all costs any contamination of any kind of existing water courses or dams

Testing, completion, commissioning and correction of defects

All testing in accordance with the requirements of the applicable standards must be carried out and approved in the presence of the Engineer before being accepted.Certificates of Practical Completion, Completion, and Final Completion will be issued in accordance with Clause 51 of the General Conditions of Contract and all other conditions detailed in the same Clause will then apply

Recording of weather A rain gauge must be set up and the rainfall recorded on a daily basis

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 7: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Format of communications

A visitors Book must be placed on site which all visitors must be requested to sign.All Site Instructions will be issued in writing in a Site Instruction Book kept on siteAll requests for inspections by the Engineer must be made in writing at least 24 hours prior to being required

Management meetings Site Meetings will be held on a monthly basis at which the Contractor’s representative, representatives of the Project Steering Committee, representatives of the Employer and the Engineer, or his representative will attend.At this meeting the Contractor will be expected to table a marked up programme detailing progress and in the case of falling behind programme reasons why. The Contractor will also be expected to table any items of work which he feels need explanation or further detail.

Daily records All forms included in the Contract Document must be completed at the frequency indicated

Bonds and guarantees A Guarantee will be required as detailed in the Contract Data and Clause 7 of the General Conditions

Payment CertificatesMeasurements for Payment Certificates will be made jointly by the Project Manager and the Contractor’s representatives.All claims for materials on site must be accompanied by a copy of the tax invoice for that particular item.

Permits Not applicable

Health and Safety

Health and safety requirements and procedures

The tenderers are to submit a provisional Health and Safety Plan with their Tender.

Measures against disease and epidemics

Not applicable

Aids awareness The Contractor will be issued with a HIV/AIDS Specification in the Tender Document

ANNEXES

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 8: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C3.6HEALTH AND SAFETY

FOREWORD: *Complies with Occupational Health and Safety Act No. 85 of 1993 and Construction Regulations of July, 2003.*use as a management tool in order to comply with OH & S Act*Act takes preference over this document*Act must be used as the minimum requirement*contact originator of this document if unclear of anything.

1. TABLE OF CONTENTS *INTRODUCTION*BACKGROUND TO H & S SPECIFICATION*PURPOSE OF H & S SPECIFICATION*IMPLEMENTATION OF H & S SPECIFICATION

2. HEALTH AND SAFETY SPECIFICATION *SCOPE*INTERPRETATION

-Application-Definitions

*MINIMUM ADMINISTRATIVE REQUIREMENTS-Notification of intention to commence construction-P.C’s assignment of 16(2) responsible person-Competence of 16(2)-COID Act-Occupational h & s policy-H & S Organogram-Preliminary Hazard identification and Risk Assessment-H & S Representatives-H & S Committees-H & S Training

-Induction-AwarenessCompetence

-General Record Keeping-H & S Audits, Monitoring and Reporting-Emergency ProceduresFirst Aid boxes and equipment-Accident and incident reporting and investigating-Hazards and potentially hazardous situations- P.P.E.-OH & S Signage-Contractors and sub-contractors-Public and site visitor h & s-Penalties

*PHYSICAL REQUIREMENTS-Existing structures-Edge protection-Stacking of materials-Hazardous chemical substances-Asbestos and asbestos work

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 9: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

*PLANT AND MACHINERY-Construction plant-Fire extinguishers and firefighting equipment-Hired plant and machinery-Scaffolding / working in elevated positions-Roof work-Formwork and support work-Ladders and ladder work-Electrical installations and portable electrical tools

*OCCUPATIONAL HEALTH-Occupational hygiene-Welfare facilities-Alcohol and other drugs

3.*PRINCIPAL CONTRACTOR COMPLIANCE DATES4.*ASSIGNMENT OF RESPONSIBLE PEOPLE

-Appointment forms5.*GENERAL COMPLIANCE REQUIREMENTS

-Progress meetings6.*PRELIMINARY Hazard identification and Risk Assessment7.*ACKNOWLEDGEMENT OF RECEIPT OF H & S SPECIFICATION

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 10: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

COMPANY:

HEALTH AND SAFETY SPECIFICATION

1. INTRODUCTION AND BACKGROUND

The Construction Regulations No. R1010 of 18 th July, 2003, requires the Client to prepare a pre-construction health and safety specification, with all existing risks identified.

PURPOSE OF HEALTH AND SAFETY SPECIFICATION

To assist in achieving compliances with the Occupational Health and Safety Act No. 85 of 1993 and the Construction Regulations of July, 2003, in order to, as far as is practicable, reduce or eliminate incidents or injuries.The Principal Contractor shall use this specification as a basis for the drafting of his and any Contractor’s construction health and safety plans.The Specification sets out the requirements to be followed by all Contractors so that the health and safety of all persons who may be affected by the construction may receive the same priority as other project facets.

IMPLEMENTATION

The health and safety specification forms an integral part of the contract, and the Principal Contractor is required to use it when drawing up his health and safety plan. He must forward a copy to all Contractors at their bidding stage to enable them to prepare their own health and safety plans.

2. HEALTH AND SAFETY SPECIFICATION.

2.1 SCOPEThis specification covers the requirements for eliminating and mitigating incidents and injuries at Company/Site/Project level. The scope addresses legal compliance, hazard identification and risk assessment, risk control, and promoting a health and safety culture on the project. The specification also provides for the protection of those persons other than employees.

2.2 INTERPRETATION.ApplicationThis specification is a compliance document drawn up in terms of the Occupational Health and Safety Act No.85 of 1993, and the Construction Regulations of July, 2003, and is therefore binding.

DefinitionsThe definitions as listed in the Occupational Health and Safety Act and Construction Regulations shall apply.

2.3 MINIMUM ADMINISTRATIVE REQUIREMENTS.

2.3.1 Notification of intention to commence construction work.The Principal Contractor shall notify the Provincial Director of Labour in writing before construction work commences, a copy of which shall be kept in the health and safety file.

2.3.2 Assignment of Principal Contractor’s/Contractor’s responsible person to supervise health and safety on site.The appointments shall be made in writing, a copy of which is to be kept in the health and safety file.

2.3.3 Competence of the responsible person/s.The criteria as stipulated under the definition of “competent” in the Construction Regulations shall apply.2.3.4 Compensation for Occupational Injuries and Diseases Act 130 of 1993.The Principal Contractor shall keep a copy of the letter of good standing with his Compensation Assuror in the health and safety file as proof of registration. Each contractor shall provide a copy of his letter of good standing to the Principal Contractor for the health and safety file.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 11: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

2.3.5 Occupational health and safety policy.The Principal Contractor and each Contractor shall submit a health and safety policy signed by its Chief Executive Officer, outlining the Employers objectives and how they will be implemented.

2.3.6 Health and safety organogram.The Principal Contractor and each Contractor shall prepare an organogram detailing each site management health and safety appointment of the competent person.

2.3.7 Preliminary Hazard Identification and Risk Assessment. (HIRA)The Principal Contractor shall cause a hazard identification to be performed by a competent person before the commencement of construction work. The assessed risks shall form part of the construction phase health and safety plan submitted for approval by the Client. The assessment must include:a) a list of hazards and potential hazards;b) a documented risk assessment based on the list of hazards;c) a set of safe work procedures (method statements) to eliminate, reduce or control the risks;d) a monitoring and review procedure as the risks change.

The Principal Contractor shall ensure that all Contractors inform, instruct and train their workers regarding any hazards, risks and related safe work procedures before any work commences and thereafter at regular intervals as conditions change. Contractors are to conduct their own toolbox talks weekly, and submit proof of these talks to the Principal Contractor. Contractors are to conduct risk assessments specific to their operations and submit a copy to the Principal Contractor.

2.3.8 Health and safety representatives.The Principal Contractor and Contractors shall appoint in writing and provide training for health and safety representatives who shall carry out inspections of the workplace, keep records and report all findings to the responsible person, and at health and safety meetings. A representative is required once 20 employees are on site, and one representative for every 50 employees thereafter.

2.3.9 Health and safety committees.The Principal Contractor shall ensure that committee meetings are held monthly and minutes are kept. The responsible person shall chair the meetings and all representatives are to attend. Contractors shall hold their own meetings, with a copy being forwarded to the Principal Contractor’s responsible person.

2.3.10 Health and safety traininga) Induction. The Principal Contractor shall ensure that all site personnel undergo site-specific health and safety induction training before they start work. A record of attendance shall be kept in the health and safety file.b) Awareness. The Principal Contractor shall ensure that on-site toolbox talks take place at least once per week, dealing with risks relevant to the work at hand. Contractors shall provide proof to the Principal Contractor.

2.3.11 General record keeping. The Principal Contractor shall keep and maintain health and safety records to demonstrate compliance with this Specification, with the OH & S Act, and with the Construction Regulations. He shall ensure that all records of incidents/accidents, emergency procedures, training, inspections, audits, etc, are kept in the health and safety file. He shall ensure that all contractors maintain such a file.

2.3.12 Health and safety audits, monitoring and reporting.The Client shall conduct monthly health and safety audits of the work place as well as an audit of the administration of health and safety. The Principal Contractor shall conduct similar audits monthly of any contractor, who will in turn audit any sub-contractor.

2.3.13 Emergency procedures.The Principal Contractor must prepare a detailed emergency procedure for approval by the Client prior to commencement on site. The procedure shall detail the response plan, including:a) list of key competent personnel;b) details of emergency services;

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 12: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

c) actions to be taken in the event of an emergency;d) information on any hazardous material/situation.Emergency procedures shall include: fire; chemical spill; injury; damage; hazardous substances; bomb threat; major incident/accident. The Principal Contractor shall advise the Client in writing of any such event, including action taken. A contact list of all service providers (fire dept. ambulance, police, doctor, hospital) shall be available to site personnel.

2.3.14 First aid boxes and first aid equipment.The Principal Contractor shall appoint a certified first aider in writing. A copy of the certificate shall be placed in the health and safety file. An adequately stocked first aid box must be provided by the Principal Contractor, as well as a first aid station. A contractor with 5 or more employees must provide his own first aid box. Where there are 10 or more employees, a certified first aider must be appointed and be on site at all times.

2.3.15 Accident/incident reporting and investigation.The Principal Contractor must investigate all injuries and report to the Client.The P.C. may categorize incidents as follows: incidents; first aid; medical; disabling; fatal. He will detail the procedure to follow for each such event.

2.3.16 Hazards and potentially hazardous situations.The Principal Contractor shall immediately notify any contractors and the Client in writing of any hazardous or potentially hazardous situation that may arise during the performance of construction activities.

2.3.17 Personal Protective Equipment.The Principal Contractor shall ensure that all site employees wear the P.P.E. as identified in the risk assessment. He is to ensure that an adequate supply of P.P.E. is available on request as either replacement for lost items or worn out items. A record is to be kept of issues to each employee. Each contractor is responsible for supplying his own staff with P.P.E.

2.3.18 Occupational health and safety signage.The Principal Contractor must provide adequate on-site signage. Examples are: no unauthorized entry; visitors report to site office; site office; hard hat area; construction vehicles; noise zone; first aid. Signs are to be posted on access routes, entrances, scaffolding, and other risk areas.

2.3.19 Contractors and sub-contractors.The Principal Contractor shall ensure that all contractors comply with this Specification, the OH & S Act, Construction Regulations and any other relevant legislation that may relate to the activities. A contractor shall ensure compliance of any sub-contractor appointed by him.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 13: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

2.3.20 Public and site visitor health and safety.The Principal Contractor shall ensure that every person working on or visiting the site, as well as the general public, shall be made aware of the dangers likely to arise from site activities, including the precautions to be taken to avoid or minimize those dangers. Appropriate health and safety notices and signs shall be posted up.Both the Client and the Principal Contractor have a duty in terms of the OH & S Act to do all that is reasonably practicable to prevent members of the public and site visitors from being affected by the construction activities.The site must be suitably hoarded at all times with a limited number of restricted access points. Adequate notices are to be displayed.Hoarding is to be inspected daily and gates locked at the end of each work day.

2.3.21 PenaltiesPenalties may be imposed on Contractors who do not comply with this health and safety Specification.

2.4 PHYSICAL REQUIREMENTS

2.4.1 Existing structures.Any existing structure must be deemed safe by means of a structural inspection and report compiled by a competent person and forwarded to the Client and the Principal Contractor.

2.4.2 Edge protection and penetrations.The Principal Contractor must ensure that all edges and openings are guarded and demarcated at all times until permanent protection is erected. The guards must be constructed of scaffold type tubing, with guardrails, painted yellow, located one meter above floor level.

2.4.3 Stacking of materials.The Principal Contractor must appoint in writing a stacking supervisor and all materials, formwork and other equipment is stacked and stored safely, on level, firm ground, out of access ways and height complying with regulations.

2.4.4 Hazardous Chemical Substances. (h.c.s)The Principal Contractor is to appoint a competent person in writing to control the storage, transport and use of any h.c.s. Material safety data sheets (msds) are to be maintained and available on site. First aiders are to be informed of the presence of h.c.s. and how to treat incidents.

2.4.5 Asbestos and asbestos work.The removal and maintenance of asbestos containing products must be conducted under controlled conditions as specified in the Asbestos Regulations.A set of safe work procedures must be drawn up by the Principal Contractor and submitted to the Client for approval.

2.4.6 Demolition work.A competent person is to be appointed in writing to supervise and control all demolition work on site.A method statement on the procedure to be followed in demolishing the structure is to be developed by a competent person prior to the work being carried out.The Construction Regulations section 12 conditions shall apply.

2.5 PLANT AND MACHINERY

2.5.1 Construction plant.This includes all types of plant used in the construction process, and must comply with the OH & S Act and the Construction Regulations.The Principal Contractor shall appoint a competent person in writing to inspect and record the findings of such inspections.Only authorized competent persons are to operate such machinery. Appropriate p.p.e. and clothing must be provided, used and maintained.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 14: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

2.5.2 Fire extinguishers and firefighting equipment.The Principal Contractor and Contractors shall provide adequate, serviced and maintained firefighting equipment, located at suitable locations on site. Appropriate notices and signs must be posted up.

2.5.3 Hired plant and machinery.The Principal Contractor shall ensure that the hired plant and machinery is safe for use and complies with 2.5.1 above.

2.5.4 Scaffolding/working in elevated positions.The Principal Contractor must submit a risk-specific fall protection plan to the Client for approval before any work commences. All scaffolding must comply with SANS 10085 standards.Scaffolding must be declared safe for use by a competent person who has been appointed in writing, with the register being updated weekly, after inclement weather, after alterations, after an accident, and before dismantling.Adequate protection must be provided over a walkway, pavement or public access.The fall protection plan must include a risk assessment and safe work procedures. All persons working at height must be evaluated for physical and psychological fitness. Training must be provided. All openings and edges must be adequately guarded. Workers must be trained in the use of fall harnesses, which must be kept in a good condition.All scaffolding must be complete with guard rails and toe boards and be fully boarded.

2.5.5 Roof work.All roof work must be conducted in accordance with Construction Regulation 8, with a fall protection plan in place.

2.5.6 Formwork and support work.The Principal Contractor shall appoint a competent person in writing to inspect the formwork and support work immediately before, during and after the placement of concrete and thereafter on a daily basis until the removal thereof.Notices and signs are to be posted. Walkways, passages and pavements are to be protected from falling objects.

2.5.7 Ladders and ladder work.The Principal Contractor shall appoint a competent person in writing to inspect all ladders monthly and record such findings in a register. Ladders are to extend one meter above a landing and must be secured at the top and have a secure, non-slip base.

2.5.8 Electrical installations and portable electric tools.The Client must ensure that the Principal Contractor is aware of the position of all electrical power lines. The P.C. must comply with the electrical installation regulations, electrical machinery regulations and the construction regulations. The P.C. shall carry a copy of the Certificate of Compliance. Temporary electrical installations must be inspected weekly. Portable electrical tools are to be visually inspected daily with a register updated monthly.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 15: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

2.6 OCCUPATIONAL HEALTH.

2.6.1 Occupational hygiene.Exposure to occupational health hazards in construction is common and Contractors must ensure that proper health and hygiene measures are in place to prevent exposure to such hazards. Prevent inhalation, ingestion, absorption and noise induced hearing loss.

2.6.2 Welfare facilities.The Principal Contractor must supply sufficient toilets (1 per 30 workers), changing facilities, hand wash facilities, soap, toilet paper and hand drying material. There must be safe, clean storage areas for workers to store personal belongings and clean, sheltered eating areas.

2.6.3 Alcohol and other drugs.No alcohol or other drugs will be allowed on site. No one under the influence of alcohol or drugs will be allowed on site. Any person suffering from any illness/condition which may affect his safety on site must report to his supervisor.Disciplinary action is to be taken against anyone found under the influence whilst on site.

3. PRINCIPAL CONTRACTOR COMPLIANCE DATES

Requirement Submission date

a) Health and safety plan Before commencement on site. b) Notification of intention to Before commencement on

Commence construction site. c) Assignment of responsible Before commencement on Persons to supervise site. Construction work.d) Competence of responsible Together with H & S Plan Personse) Occupational health and safety policy Together with H&S Planf) Health and safety organogram Together with H&S Plang) Initial hazard identification Together with H&S Plan And risk assessment

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 16: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

4. ASSIGNMENT OF PRINCIPAL CONTRACTOR’S RESPONSIBLE PERSONS

1. Appointment Reference

2. CEO Assignee OH&S Act sect. 16(2)

3. Construction work supervisor CR 6.1

4. Subordinate supervisor CR6.2

5. Health & safety representatives OH&S Act sect. 17

6. Incident investigator GAR 8

7. Risk assessment co-ordinator CR7

8. Fall protection plan co-ord. CR8

9. First aiders GSR 3

10. Scaffold inspector/supervisor SANS 10085 & CR14

11. Scaffold erector GSR13D

12. Formwork/support work CR10

13. Excavation inspector CR11

14. Ladder inspector GSR13A

15. Temporary electrical installation CR22

16. Firefighting equipment inspector CR27

17. Safety officer CR6.6

18. Demolition Supervisor CR 12(1)

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 17: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

5. GENERAL COMPLIANCE REQUIREMENTS

1. Construction health and safety plan. Monthly review.

2. Health and safety file. Open, at meetings.

3. OH&S Act regulations Monthly review.

4 Induction training. Every worker

5. Toolbox talks. Weekly

6. Health & safety reports Monthly.

7. Emergency procedures Monthly.

8. Risk assessments Monthly.

9. Safe work procedures Before start.

10. General inspections. Daily, weekly.

11. List of contractors. Update weekly.

12. Workman’s compensation. Ongoing.

13. Section 37 Mandatary Ongoing.

6. PRELIMINARY RISK ASSESSMENT

(Available from the MBA upon request)

7. ACKNOWLEDGEMENT OF RECEIPT

I, ……………………….., representing…………………………….

Principal Contractor/Contractor, have received the Health and Safety Specification in good order and shall ensure that the Principal Contractor/Contractor and its personnel comply with all obligations/requirements/specifications in respect thereof.

This document is legally binding in terms of Regulation 4(1)(a) of the Construction Regulations 2003.

Signature of Principal Contractor/Contractor………………………………DATE…………………

Signature of Client/Client’s Agent……………………………………………DATE………………….

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 18: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

C3.7PROJECT SPECIFICATIONS

CLAUSE DESCRIPTION PAGE

PROJECT SPECIFICATIONS FOR THE CONSTRUCTION OF SHEARING SHED1…….............................SCOPE………………………………………………………………………………………………………………… 4PORTION 1…………………………………………………………………………………………………………… 4PORTION 2…………………………………………………………………………………………………………… 4PORTION 3…………………………………………………………………………………………………………… 4PORTION 4………………………………………………………………………………………………………………4PS 1 DISCLAIMER…………………………………………………………………………………………………….. 4PS2 APPLICABLE STANDARDS…………………………………………………………………………………….4PS 3 SITE FACILITIES…………………………………………………………………………………………………4PS 4 COMMUNICATION WITH LOCAL COMMUNITIES…………………………………………………………..6

HEALTH AND SAFETY……………………………………………………………………………………………….. 8PAM 2.2 INTERPRETATIONS………………………………………………………………………………………....8PAM 2.3MINIMUM ADMINISTRATIVE REQUIREMENTS OF THE DEPARTMENT OF AGRICULTURE…….8PAM 2.4SPECIFIC PROJECT REQUIREMENTS…………………………………………………………………...12PAM 2.5OCCUPATIONAL HEALTH…………………………………………………………………………………..15PAM 3MEASUREMENT AND PAYMENT…………………………………………………………………………….16PAM 4TASK COMPLETION FORM…………………………………………………………………………………...16PAM 5ASSIGNMENT OF PRINCIPAL CONTRACTOR’S RESPONSIBLE PERSONS…………………………18PAM 6OTHER REQUIREMENT……………………………………………………………………………………….19PAM 7MEASUREMENT AND PAYMENT…………………………………………………………………………….19

ENVIRONMENTAL MANAGEMENT PLAN………………………………………………………………………….22PEM ENVIRONMENTAL MANAGEMENT PLAN……………………………………………………………………22PEM.1 PURPOSE……………………………………………………………………………………………………….22PEM.2 RESPONSIBILITIES FOR ENVIRONMENTAL MANAGEMENT…………………………………………..22PEM.3 TRAINING AND INDUCTION OF EMPLOYEES…………………………………………………………….22PEM.4 COMPLAINTS REGISTER AND ENVIRONMENTAL INCIDENT BOOK…………………………………22PEM.5 ENVIRONMENTAL SAFETY………………………………………………………………………………….22PEM.6 .MEASUREMENTS AND PAYMENT…………………………………………………………………………28

EARTH WORKS…………………………………………………………………………………………………………29PPS EW1 SITE CLEARANCE………………………………………………………………………………………….29PPS EW2 MEASUREMENT AND PAYMENT: SITE CLEARANCE………………………………………………..30PPS EW3 MEASUREMENT AND PAYMENT: EXCAVATION……………………………………………………..30PPS EW4 MEASUREMENT AND PAYMENT: SUB GRADE FILLING AND COMPACTION…………………...32

CONCRETE WORKS…………………………………………………………………………………………………...33CONCRETE, FORMWORK AND REINFORCEMENT………………………………………………………………33PPS C1.2 SAND (FINE AGGREGATE): ……………………………………………………………………………...33PPS C1.3 STONE (COARSE AGGREGATE): ……………………………………………………………………….33PPS C2 CONCRETE: …………………………………………………………………………………………………..34PPS C3 STRENGTH CONCRETE: ...…………………………………………………………………………………34PPS C4 SLUMP TEST………………………………………………………………………………………………….34PPS C5 CONCRETE QUALITY: ………………………………………………………………………………………35PPS C6 CONCRETING: …………………………………………………………………………………………….....35PPS C7 CURING OF CONCRETE: …………………………………………………………………………………..36PPS C8 BUILDING ON CONCRETE FOOTINGS AND BEAMS: …………………………………………………36

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 19: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PPS C9 SLIP JOINTS BETWEEN CONCRETE AND BRICKWORK: …………………………………………….36PPS C10 MOVEMENT JOINTS: ………………………………………………………………………………………37PPS C11 PRE-STRESSED CONCRETE LINTELS………………………………………………………………….37PPS C12 FORMWORK: ………………………………………………………………………………………………..37PPS C13 SMOOTH FORMWORK: ……………………………………………………………………………………38PPS C14 REINFORCING RODS: ……………………………………………………………………………………..38PPS C15 CONCRETE REINFORCEMENT: …………………………………………………………………………38PPS C16 DAMP-PROOF MEMBRANE: ……………………………………………………………………………...40PPS C17 MEASUREMENT AND PAYMENT: ……………………………………………………………………….40

MASONRY WORKS ……………………………………………………………………………………………………41PPS MS1 BRICK AND BLOCK WORK ……………………………………………………………………………….41PPS MS1.1 CEMENT …………………………………………………………………………………………………..41PPS MS1.2 SAND ………………………………………………………………………………………………………41PPS MS1.3 BURNT CLAY BRICKS …………………………………………………………………………………..41PPS MS1.4 CONCRETE BLOCKS …………………………………………………………………………………...41PPS MS1.5 CEMENT MORTAR ………………………………………………………………………………………41PPS MS1.6 VENTILATION BRICKS ………………………………………………………………………………….41PPS MS1.7 BRICKWORK ……………………………………………………………………………………………..41PPS MS1.9 BLOCK / BRICK REINFORCING ……………………………………………………………………….42PPS MS1.10 BEARING PLATES ON WALLS ……………………………………………………………………… 42PPS MS1.11 SECURING OF ROOFS ………………………………………………………………………………..42PPS MS2 DAMP-PROOF COURSE ………………………………………………………………………………….42PPSMS3PLASTERING…………………………………………………………………………………………………42PPS MS4 MEASUREMENT AND PAYMENT: ………………………………………………………………………43

WINDOWS / DOORS / FITTINGS …………………………………………………………………………………….44PPS F1 STEEL WINDOWS ……………………………………………………………………………………………44PPS F2 PRESSED STEEL DOOR FRAMES ………………………………………………………………………..44PPS F3 HARD WOOD DOORS ……………………………………………………………………………………….44PPS F4 STEEL ROLLER SHUTTER DOOR ………………………………………………………………………...44PPS F5 PURPOSE MADE SLIDING DOORS ……………………………………………………………………….44PPS F6 WATER TANK, TANK BASE AND PIPING ………………………………………………………………...45PPS F7 MEASUREMENT AND PAYMENT: …………………………………………………………………………45

PAINTING ………………………………………………………………………………………………………………..46PPS P1 PAINTING – GENERAL ………………………………………………………………………………………46PPS P2 ON PLASTERED WALLS ……………………………………………………………………………………46PPS P3 ON METAL SURFACES ……………………………………………………………………………………..46PPS P4 ON WOODEN SURFACES ………………………………………………………………………………….46PPS P5 APPLICABLE SABS CODES ………………………………………………………………………………..46PPS P6 MEASUREMENT AND PAYMENT: …………………………………………………………………………46

ROOFING ………………………………………………………………………………………………………………..48PPS R1 THE ROOF …………………………………………………………………………………………………….48PPS R2 PRE-FABRICATED ROOF TRUSSES ……………………………………………………………………..48PPS R3 TIMBER ………………………………………………………………………………………………………..48PPS R4 HURRICANE CLIPS ………………………………………………………………………………………….49PPS R5 FACIA BOARDS ………………………………………………………………………………………………49PPS R6 GUTTERS AND DOWN PIPES 49PPS R7 ROOF SHEETING …………………………………………………………………………………………….49PPS R7.2 TRANSLUCENT SHEETING ……………………………………………………………………………...49PPS R8 MEASUREMENT AND PAYMENT: …………………………………………………………………………49

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 20: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PIT TOILET ……………………………………………………………………………………………………………...50PPS P1 PIT TOILET …………………………………………………………………………………………………….50PPS P2 ROOF STRUCTURE ………………………………………………………………………………………….50PPS P3 PEDESTAL …………………………………………………………………………………………………….50PPS P4 VENTILATION PIPE ………………………………………………………………………………………….50PPS P5 MEASUREMENT AND PAYMENT: …………………………………………………………………………50

DIP TANK, FOOT BATH AND ANIMAL HANDLING FACILITY…………………………………………………..51PPS D1 DIP TANK ……………………………………………………………………………………………………...51PPS D2 CONCRETE FLOOR …………………………………………………………………………………………51PPS D3 SUBGRADE GRAVEL COVERING ………………………………………………………………………...51PPS D4 FOOTBATH ……………………………………………………………………………………………………51PPS D5 WATER CONNECTION AND HOSE ……………………………………………………………………….51PPS D6 ANIMAL HANDLING FACILITY …………………………………………………………………….............51PPS D7 MATERIALS …………………………………………………………………………………………………...52PPS D9 MEASUREMENT AND PAYMENT: …………………………………………………………………………53

FENCINGPPS F1……………………………………………………………………………………………………………………54

SHEARING EQUIPMENT ……………………………………………………………………………………………...54PPS EQ1 WOOL SORTING TABLE ………………………………………………………………………………….54PPS EQ2 PIECE PICKING TABLE ……………………………………………………………………………………54PPS EQ3 WOOL BINS …………………………………………………………………………………………………54PPS EQ4 WOOL BASKETS …………………………………………………………………………………………...54PPS EQ5 BALE LIFTING HOOKS …………………………………………………………………………………….54PPS EQ6 SHEARING BOARDS ………………………………………………………………………………………54PPS EQ7 MECHANICAL WOOL PRESS …………………………………………………………………………….54PPS EQ8 WOOL SCALE ………………………………………………………………………………………………55PPS EQ9 SHEEP SHEARS ……………………………………………………………………………………………55PPS EQ10 DIP HOOK AND STAFF …………………………………………………………………………………..55PPS EQ11 DEMONSTRATION OF EQUIPMENT …………………………………………………………………..55PPS EQ12 MEASUREMENT AND PAYMENT: ……………………………………………………………………..55

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 21: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

SCOPE

PORTION 1Covers the construction of a standard shearing shed fitting for general use in communal farming areas of the Eastern Cape Province.

PORTION 2Covers the construction of a pit toilet addition to the standard shearing shed.

PORTION 3Covers the construction of a longitudinal dip tank and animal handling facilities as an addition to the standard shearing shed.

PORTION 4Covers the shearing equipment needed for a standard shearing operation.

PS 1 DISCLAIMERThe information regarding subsurface conditions, materials on site and site information supplied, is provided in good faith for the contractor’s convenience as an indication of conditions likely to be encountered. No responsibility will be accepted for, and there is no guarantee of the information being representative of the whole area of the works or materials.

The information provided will not be regarded as in way limiting. The contractor will be held to have satisfied himself of all conditions to be encountered on site and to allow accordingly in his tendered rates.

PS2 APPLICABLE STANDARDSPW371 and The South African Bureau of Standards, Standard Specifications for Civil Engineering Construction (SABS 1200) shall apply. It shall however be noted that reference is made in certain of the specifications to other standardized specifications which may or may not be included in this document. Where such specifications are not included, they shall however be deemed to be included in the Contract documents.

The Contractor shall have available for reference on site at all times a full set of the above specifications, together with any other to which they refer. These specifications shall remain the property of the Contractor but shall be made available to the Engineer whenever required throughout the duration of the Contract.

PS 3 SITE FACILITIES

PS 3.1 FACILITIES FOR THE ENGINEER

No facilities are required for the Engineer; the Engineer will however make use of the Contractor’s site office for the site meetings.

PS 3.2 SANITARY FACILITIESThe Contractor shall supply chemical toilets for use by his employees and temporary workers and shall be entirely responsible for maintaining such toilets in a clean and sanitary condition to the satisfaction of the Engineer and the health authorities. The number of toilets shall be based on one toilet per fifteen personnel on site and the Contractor shall make his own arrangements and pay all charges for the removal of sewage. (Also see PAM 2.5.2)

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 22: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PS 3.3 CONTRACTOR’S CAMP SITE

The establishment of all labour, plant and materials on site and all arrangements in this respect is the responsibility of the Contractor.

The Contractor shall provide within his own on-site facilities, a suitably furnished office or other venue capable of comfortably accommodating a minimum of ten (10) persons at site meetings. The Engineer shall be allowed free use of such a venue for the conducting of any other meetings concerning the Contract at all reasonable times. The cost of providing the above facility will be viewed to be inclusive of the Contractor’s establishment costs.

Before the erection of his camp, office, stores, plant and accommodation units or any facilities, the Contractor shall satisfy the Engineer that he is familiar with and has taken due cognizance of any pertinent local by-laws, availability of services and statutory regulations. The Contractor’s attention is specifically drawn to the regulations pertaining to the accommodation of labourers.

PS 3.4 TELEPHONE AND COMMUNICATION FACILITIESThe Contractor shall provide and maintain a continuous means of on-site communication between his site supervision staff (i.e. the people responsible for the day to day running of the Contract) and the staff of the Engineer’s Representative.

The Engineer and his Representative will use their own cellular and office telephones for this contract. The provision and use of cellular phones for the Contractor’s personnel will be for his own cost.

PS 3.5 ACCOMMODATION FOR EMPLOYEESThe Contractor shall make his own arrangements for the accommodation of his employees.

PS 3.6 SECURITYThe Contractor shall be responsible for the security of his personnel and constructional plant on and around the site of the works and for the security of his camp, and no claims in this regard will be considered by the Employer.

PS 3.7 SETTING OUT OF WORKSThe Engineer shall stake out the four outer corner positions for the shearing shed. The Engineer shall also stake out the corner post positions for the fenced area. The contractor must use these set out points to position and dimension the rest of the works. Construction may only commence after the points have been staked out.

PS 3.8 WATER, POWER SUPPLY AND OTHER SERVICESThe Contractor shall make his own arrangements concerning the supply of water, electrical power and all other services for use at the site camps, as well as for all construction and maintenance purposes. No direct payment will be made for the provision of water, electrical power and other services. The cost thereof shall be deemed to be included in the rates and amounts tendered for the various items of work.

PS 3.9 FEATURES REQUIRING SPECIAL ATTENTIONPS 3.9.1 PUBLIC SAFETYThe Contractor shall at all times ensure that his operations do not endanger any member of the public or of his own personnel.

PS 3.9.2 ADJOINING PROPERTIESThe sites of the Works are surrounded by private properties. The Contractor shall exercise strict control over his employees to ensure that they do not trespass outside the road reserve or interfere in any way with the adjacent owners, tenants and their properties. In addition, the Contractor shall liaise with the owners regarding all matters that may affect them such as the provision of water and the like.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 23: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PS 3.9.3 CONSTRUCTION AND MAINTENANCE ACTIVITIES IN CONFINED AREASIt may be necessary for the Contractor to work within confined areas. Except where provided for in the project specifications, no additional payment will be made for work done in restricted areas.

The Contractor must note that measurement and payment will be in accordance with the specified cross-sections and dimensions only, irrespective of the method used for achieving these cross-sections and dimensions and that the tendered rates and amounts shall include full compensation for all special equipment and construction / maintenance methods and for all difficulties encountered when working in confined areas and narrow widths, and at or around obstructions, and that no extra payment will be made nor will any claim for additional payment be considered in such cases.

PS 3.9.4 EXISTING SERVICESItems have been allowed in the Bill of Quantities for dealing with and protecting existing services where they are known.

The Contractor will, however, ensure that prior to construction all the necessary Record Drawings and Way-leaves for all services have been obtained and verified on site by the relevant Service Providers in his presence. The Contractor must request in writing the relevant Official to indicate the said services within 48 hours prior to commencement of work, after which the responsibility rests with the Service Department if the services are not indicated to the Contractor as requested.

The Contractor shall take whatever extra precautions are required to protect all existing services from damage during the period of the Contract. Any damage to existing services indicated by the relevant service providers or other damage as a result thereof, shall be for the Contractor’s account.

PS 4 COMMUNICATION WITH LOCAL COMMUNITIES

A Project Steering Committee will be formed by the Contractor through the appropriate Local Ward Councillors or existing official structures if required, to act as the communication channel between the Contractor and the residents. This Project Steering Committee will identify a Community Liaison Officer to be appointed by the Contractor. A provisional sum is allowed in the schedule of quantities to cover the cost of the Community Liaison Officer.

The Contractor shall use the Community Liaison Officer, and the Project Steering Committee to timeously reach mutually acceptable employment agreements with the affected communities and to deal with any labour-related issues.

The Contractor must include in his rates for the cost of attending an average of one Project Steering Committee meeting each month. The meetings will not necessarily be during normal working hours and it is accepted that the Contractor tendering for the works is familiar with dealing with communities and understands the implications of keeping the community informed. Minutes of such meetings must be recorded and distributed by the Contractor and the cost is deemed to be included in the rates.

The Community Liaison Officer (CLO) is to be selected by the Project Steering Committee (PSC) and the Employer (through his agent) and appointed by the Contractor. The Contractor shall, however, accept the appointment as part of his management personnel.

PS 4.1 the duties of the CLO will be:

To be available on site daily during normal working hours and at other times as the need arises. His normal working day and his period of employment will be mutually agreed upon by the Employer and the Engineer accordingly.

To determine, in consultation with the Contractor, the needs of the local labour for relevant training.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 24: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

To communicate daily with the Contractor and the Engineer to determine the labour requirements with regard to numbers and skill, to identify possible labour disputes and to assist in their resolution.

To attend all meetings in which the community and/or labour is present or is required to be represented. In particular, he will attend the first part of the monthly/site meeting to report on the local community involvement.

To inform local labour of their conditions of temporary employment and to inform local labourers as early as possible when their period of employment will be terminated.

To attend disciplinary proceedings to ensure that hearings are fair and reasonable.

To keep a daily written record of his interviews and project liaison conducted.

All such other duties as agreed upon between all parties concerned.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 25: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

HEALTH AND SAFETY

PAM 2.2 Interpretations

PAM 2.2.1 Application

This specification is a compliance document drawn up in terms of South African legislation and is therefore binding. It must be read in conjunction with relevant legislation as noted previously.

PAM 2.2.2 Definitions

The definitions as listed in the Occupational Health & Safety Act 85/1993 and Construction Regulations (July 2003) shall apply.

PAM 2.3 Minimum Administrative Requirements of the Department of Agriculture

PAM 2.3.1 Notification of Intention to Commence Construction Work

The Contractor shall notify the Provincial Director of the Department of Labour in writing before construction work commences. A copy of this notification must be forwarded to the Employer prior to work commencing on site.

PAM 2.3.2 Assignment of Contractor’s Responsible Persons to Supervise Health and Safety on Site

The Contractor shall submit supervisory appointments as well as any relevant appointments in writing (as stipulated by the OHS Act and Construction Regulations), prior to commencement of work. Proof of competency must be included. See Annexure B.

PAM 2.3.3 Competency for Contractor’s Appointed Competent Persons

Contractors’ competent persons for the various risk management portfolios shall fulfil the criteria as stipulated under the definition of Competent in accordance with the Construction Regulations (July 2003). Proof of competence for the various appointments must be included.

PAM 2.3.4 Compensation of Occupational Injuries and Diseases Act 130 of 1993(COIDA)

The Principal Contractor shall submit a letter of good standing with its Compensation Insurer to the Employer as proof of registration. Sub - Contractors shall submit proof of registration to the Principal Contractor before they commence work on site.

PAM 2.3.5 Occupational Health and Safety Policy

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 26: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The Principal Contractor and all Sub Contractors shall submit a Health and Safety Policy signed by their Chief Executive Officer. The Policy must outline objectives and how they will be achieved and implemented by the Company / Contractor.

PAM 2.3.6 Health and Safety Organogram

The Principal Contractor and all Sub Contractors shall submit an organogram, outlining the Health and Safety Site Management Structure including the relevant appointments/competent persons. In cases where appointments have not been made, the organogram shall reflect the intended positions. The organogram shall be updated when there are any changes in the Site Management Structure.

PAM 2.3.7Preliminary Hazard Identification and Risk Assessment and Progress Hazard Identification and Risk Assessment

The Contractor shall cause a hazard identification to be performed by a competent person before commencement of construction work, and the assessed risks shall form part of the construction phase health and safety plan submitted for approval to the Employer. The risk assessment must include;

A list of hazards identified as well as potentially hazardous tasks;A documented risk assessment based on the list of hazards and tasks;A set of safe working procedures (method statements) to eliminate, reduce and/or control the risks assessed;A monitoring and review procedure of the risks assessment as the risks change.

The Principal Contractor shall ensure that all Sub Contractors are informed, instructed and trained by a competent person regarding any hazards, risks and related safe work procedures before any work commences and thereafter at regular intervals as the risks change and as new risks develop. Proof of this must be kept for inspection by the Employer or the Employer’s Representative.

The Principal Contractor shall be responsible for ensuring that all persons who could be negatively affected by its operations are informed and trained according to the hazards and risks and are conversant with the safe work procedures, control measures and other related rules (tool box talk strategy to be implemented).

PAM 2.3.8 Health and Safety Representative(s)

The Principal Contractor and all other Contractors shall, after due consultation with the parties concerned, ensure that an H&S Representative is appointed in writing as soon as there are 20 persons employed on a site. Additional H&S Representatives are required once the workforce exceeds 50 persons. Copies of the appointments are to be attached to the H&S plan. Each H&S Representative(s) is to be trained to carry out their respective functions and must carry out regular inspections, keep records, and report all findings to the responsible person forthwith, and also at the next H&S meeting. Copies of these documents are to be kept in the Project H&S File.

PAM 2.3.9 Health and Safety Committees

The Principal Contractor shall ensure that project health and safety meetings are held monthly and minutes are kept on record. Meetings must be organised and chaired by the Principal Contractor’s Responsible Person. All Contractors’ Responsible Persons and Health & Safety Representatives shall attend the monthly health & safety meetings. Sub-Contractors shall also have their own internal health & safety committees in accordance with the OHS Act 85/1993 and minutes of their meetings shall be forwarded to the Principal Contractor on a monthly basis.

PAM 2.3.10 Health and Safety Training

PAM 2.3.10.1 Induction

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 27: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The Principal Contractor shall ensure that all site personnel undergo a risk-specific health & safety induction training session before starting work. A record of attendance shall be kept in the health & safety file. A suitable venue must be supplied to house this training.

PAM 2.3.10.2 Awareness

The Principal Contractor shall ensure that, on site, periodic toolbox talks take place at least once per week. These talks should deal with risks relevant to the construction work at hand. A record of attendance shall be kept in the health & safety file. All Contractors have to comply with this minimum requirement. At least one of the Toolbox talks shall be on an environmental related issue.

PAM 2.3.10.3 Competency of Site Personnel

All competent persons shall have the knowledge, experience, training, and qualifications specific to the work they have been appointed to supervise, control, and carry out. This will have to be assessed on regular basis e.g. periodic audits by the Employer, progress meetings, etc. The Principal Contractor is responsible to ensure that competent Sub Contractors are appointed to carry out construction work.

PAM 2.3.10.4 Rules of conduct.

Principal contractors, their sub-contractors and all employees under their control, including any visitor brought onto site must adhere to the following rules of conduct on site.

YOU MAY NOT:Partake, possess or sell drugs or alcoholic beverages on site. Any employee or visitor whose action and demeanour show symptoms of possible narcosis or drunkenness shall be removed from site.Indulge in practical jokes, horseplay, fighting or gambling.Destroy or tamper with safety devices, symbolic signs, or wilfully and unnecessarily discharge fire extinguishers.Bring onto site or have in your possession a firearm or lethal weapon.Assault, intimidate or abuse any other person.Operate construction equipment (vehicles or plant) without the necessary training, license and authorization.Display insubordination towards any supervisor, foreman or Manager, in respect of carrying out properly issued instructions or orders for health and Safety reasons.Enter any area where you have no business, unless authorized to do so by the person in charge.Negligently, carelessly or wilfully cause damage to property of others.Refuse to give evidence, or deliberately make false statements during investigations.

PAM 2.3.11 General Record Keeping

The Principal Contractor and all Sub Contractors shall keep and maintain Health and Safety records to demonstrate compliance with this Specification, with the OHS Act 85/1993; and with the Construction Regulations (July 2003). The Principal Contractor shall ensure that all records of incidents/accidents, training, inspections, audits, etc. are kept in a health & safety file held in the site office. The Principal Contractor must ensure that every Sub Contractor opens its own health & safety file, maintains the file and makes it available on request.

PAM 2.3.11.1 Inspections

The following items must be regularly inspected and maintained (where applicable) and appropriate records kept on site:First Aid dressing registers.Fire equipmentLifting equipment

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 28: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Lifting GearPortable electrical equipmentStacking and storage inspectionsExplosive power toolsMaterials hoist (were applicable)Pressure VesselsLaddersExcavationsSafety harnessesScaffold - static and mobile.Pneumatic toolsConstruction vehicles and mobile plant.Health and Safety Representative’s checklists.

PAM 2.3.12 Health & Safety Audits, Monitoring and reporting

The Employer (or the Employer’s Representative) shall conduct monthly health & safety audits of the work operations including a full audit of physical site activities as well as an audit of the administration of health & safety. The Principal Contractor is obligated to conduct similar audits on all Sub Contractors appointed by them. Detailed reports of the audit findings and results shall be reported on at all levels of project management meetings/forums. Copies of the Employer’s audit reports shall be kept in the Primary Project Health & Safety File while the Principal Contractor audit reports shall be kept in their file, a copy being forwarded to the Employer. Sub-Contractors have to audit their sub-contractors and keep records of these audits in their health & safety files, and make them available on request.

PAM 2.3.13 Emergency Procedures

The Principal Contractor shall submit a detailed Emergency Procedure for approval by the Employer prior to commencement of work on site. The procedure shall detail the response plan including the following key elements:List of key competent personnel;Details of emergency services;Actions or steps to be taken in the event of specific types of emergencies;Information on hazardous material/situations.

Emergency procedure(s) shall include, but shall not be limited to fire, spills, accidents to employees, use of hazardous substances, bomb threats, major incidents/accidents, etc. The Principal Contractor shall advise the Employer in writing forthwith of any emergencies, together with a record of action taken. A contact list of all service providers (Fire Department, Ambulance, Police, Medical and Hospital, etc.) must be maintained and available to site personnel.

PAM 2.3.14 First Aid Boxes and First Aid Equipment

The Principal Contractor and all Sub Contractors shall appoint in writing First aider(s). The appointed First aider(s) are to be qualified or sent for accredited first aid training. Valid certificates are to be kept on site. The Principal Contractor shall provide an on-site First Aid Station with first aid facilities, including first aid boxes adequately stocked at all times. All Sub Contractors with more than 5 employees shall supply their own first aid box. Sub-Contractors with more than 10 employees shall have a trained, certified first aider on site at all times.

PAM 2.3.15 Accident/Incident Reporting and Investigation

Injuries are to be categorized into first aid; medical; disabling; and fatal. The Principal Contractor must stipulate in its construction phase health & safety plans how it will handle each of these categories. When reporting injuries to the Employer, these categories shall be used. The Principal Contractor shall investigate all injuries, with a report being forwarded to the Employer forthwith. All Contractors have to report on the 4 categories of injuries to the Principal Contractor at least monthly. The Principal Contractor must report all injuries to the

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 29: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Employer in the form of a detailed injury report at least monthly. Where necessary, in terms of Clause 24(1) of the Occupational Health & Safety Act, incidents shall be reported to an inspector.

PAM 2.3.16 Hazards and Potential Situations

The Principal Contractor shall immediately notify other Sub Contractors as well as the Employer of any hazardous or potentially hazardous situations that may arise during performance of construction activities.

PAM 2.3.17 Personal Protective Equipment (PPE) and Clothing

The Principal Contractor shall ensure that all workers are issued and wear hard hats, safe footwear and overalls. The Principal Contractor and all Sub Contractors shall make provision and keep adequate quantities of SABS approved PPE on site at all times. The Principal Contractor shall clearly outline procedures to be taken when PPE or Clothing is:Lost or stolen;Worn out or damaged.The above procedure applies to Sub Contractors and their contractors, as they are all Employers in their own right.

PAM 2.3.18 Occupational Health and Safety Signage

The Contractor shall provide adequate on-site OHS signage. Including but not limited to ‘no unauthorised entry’, ‘report to site office‘, ’site office’, ‘beware of overhead work’, ‘hard hat area’. Signage shall be posted up at all entrances to site as well as on site in strategic locations e.g. access routes, stairways, entrances to structures and buildings, scaffolding, and other potential risk areas/operations.

PAM 2.3.19 Permits

Permits may be required for certain activities and these are not limited to but may include the following:Use of Explosives and BlastingWork for which a fall prevention plan is requiredUse of cradlesExcavation

PAM 2.3.20 Contractors and their Sub-contractors

The Principal Contractor shall ensure that all Sub Contractors under its control comply with this Specification, the OHS Act 85/1993, Construction Regulations (July 2003), and all other relevant legislation that may relate to the activities directly or indirectly. The Contractor, when appointing other Contractors as ‘Sub-contractors’, shall mutatis mutandis ensure compliance.

PAM 2.3.21 Non-Compliance

Should the Contractor fail to comply with the provisions of the Regulations 3 to 28 as listed in Regulation 30, he will be guilty of an offence and will be liable, upon conviction, to the fines or imprisonment as set out in Regulation 30.

PAM 2.4 SPECIFIC PROJECT REQUIREMENTS

PAM 2.4.1 Demolition Work

Prior to any demolition work being carried out, the Principal Contractor shall submit a safe working procedure and a detailed engineering survey for approval by the Employer. Approval will then be issued to the Principal Contractor to proceed with the demolition work. The Principal Contractor shall ensure that demolition work complies with the Construction Regulations (July 2003).

PAM 2.4.2 Excavations, Shoring, Dewatering or Drainage

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 30: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The Principal Contractor and any relevant Sub Contractors shall make provision in their tender for shoring, dewatering or drainage of any excavation as per this specification.

The Contractor shall make sure that:The excavations are inspected before every shift, each occurrence of rain or change to the excavation / shoring and a record is kept thereof;Any excavation shall be adequately shored if people are required to work in the excavation and the depth is more than 1.5 metres or where conditions render this necessary at lesser depths. Undercutting is not allowed; Safe work procedures have been communicated to the workers; Excavated material shall be placed as far from the trench as practically possible and a close watch shall be maintained at all times for signs of slipping(e.g. cracks developing at the edges of the excavation);Safe work procedures are enforced and maintained by the Contractor’s Responsible Persons at all times;The requirements as per section 11 of the Construction Regulations are adhered to.

PAM 2.4.3 Edge Protection and Penetrations

The Principal Contractor must ensure that all exposed edges and openings are guarded and demarcated at all times until permanent protection has been erected. The Principal Contractor’s risk assessment must include (where applicable) protection of decking edges, finished floor slab edges, stairways, floor penetrations, lift shafts, and all other openings and areas where a person may fall.

PAM 2.4.4 Explosives and Blasting

The Principal Contractor shall ensure that a competent Contractor undertakes the use of explosives and blasting (where required). A Safe Work Procedure (SWP) must be submitted to the Employer for approval before commencement of blasting work. All blasting work shall comply with Explosives Act and Regulations.

PAM 2.4.5 Piling

The Contractor shall ensure that piling is undertaken by a competent Contractor. A SWP shall be submitted to the Employer for approval before commencement of this work.

PAM 2.4.6Stacking of Materials

The Principal Contractor and other relevant Sub Contractors shall ensure that there is an appointed staking supervisor and all materials, formwork and all equipment is stacked and stored safely.

PAM 2.4.7 Speed Restrictions and Protection

The Principal Contractor shall ensure that all persons in its employ, all Sub Contractors, and all those that are visiting the site are aware and comply with the site speed restriction(s). Separate vehicle and pedestrian access routes shall be provided, maintained, controlled, and enforced.

PAM 2.4.8 Hazardous Chemical Substances (HCS)

The Principal Contractor and other relevant Sub Contractors shall provide the necessary training and information regarding the use, transport, and storage of HCS. The Principal Contractor shall ensure that the use, transport, and storage of HCS are carried out as prescribed by the HCS Regulations. The Contractor shall ensure that all hazardous chemicals on site have a Material Safety Data Sheet (MSDS) on site and the users are made aware of the hazards and precautions that need to be taken when using the chemicals. The First aider’s must be made aware of the MSDS and how to treat HCS incidents appropriately.

PAM 2.4.9 Asbestos

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 31: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The Principal Contractor is responsible for ensuring that all work involving asbestos complies with the Asbestos Regulations. Any Contractor involved in asbestos work must obtain temporary registration as an asbestos contractor from the Dept. of Labour. Written safe work procedures and the relevant risk assessments must govern all asbestos work. An asbestos contractor must provide exposed employees with the necessary training and information regarding asbestos, as well as the necessary personal protective equipment. Wetting down and low speed cutting techniques must be employed wherever possible to prevent airborne asbestos.

Any work involving friable asbestos (e.g. lagging or insulation), which falls under the definition of Demolition work as defined under the Asbestos Regulations, Shall utilise an Approved Inspection Authority to carry out air monitoring, and a decontamination unit must also be provided.

PAM 2.4.10 Construction Equipment

“Construction Equipment” includes all types of equipment including but not limited to, cranes, piling rigs, excavators, road vehicles, and all lifting equipment.

The Principal Contractor shall ensure that all such construction equipment complies with the requirements of the OHS Act 85/1993 and Construction Regulations (July 2003). The Principal Contractor and all relevant Sub Contractors shall inspect and keep records of inspections of the construction equipment used on site. Only authorised/competent persons are to use machinery and only under proper supervision. Appropriate PPE and clothing must be provided and maintained in good condition at all times. Proof of medical tests as required by the Construction regulations shall be made available for inspection by the Employer.

Vehicles shall not enter the site with:

Defective exhaust systemsSerious oil or fuel leaksUnsafe bodywork or loadsNon-standard equipment fitted.Improperly seated passengersAny obvious mechanical defects.

All earth moving equipment shall be operated in accordance with good safety practice so as to protect the safety of the operator and other workers or persons in the area. All earth moving equipment shall be equipped with a reverse siren

PAM 2.4.11 Vessels under Pressure (VuP) and Gas Bottles

The Principal Contractor and all relevant Sub Contractors shall comply with the Vessels under Pressure Regulations, including:

Providing competency and awareness training to the operators;Providing PPE or clothing;Inspect equipment regularly and keep records of inspections;Providing appropriate fire fighting equipment (Fire Extinguishers) on hand.

PAM 2.4.12 Fire Extinguishers and Fire Fighting Equipment

The Principal Contractor and relevant Sub Contractors shall provide adequate and regularly serviced firefighting equipment, located at strategic points on site, specific to the classes of fire likely to occur. The appropriate notices and signs must be posted up as required. A competent person must conduct a Fire risk survey and proof of this survey must be kept in the Site Safety File.

PAM 2.4.13 Hired Construction Equipment and Machinery

The Principal Contractor shall ensure that any hired construction equipment and machinery used on site is safe for use. The necessary requirements as stipulated by the OHS Act 85/1993 and Construction Regulations (July 2003) shall apply. The Principal Contractor shall ensure that operators hired with machinery are

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 32: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

competent and that certificates are kept on site in the health & safety file. All relevant Sub Contractors must ensure the same.

PAM 2.4.14 Scaffolding / Working at Heights

Working at heights includes any work that takes place in an elevated position. The Principal Contractor must submit a risk-specific fall prevention plan in accordance with the Construction Regulations (July 2003) before this work is undertaken. The Employer must approve the fall prevention plan before work may commence.

PAM 2.4.15 Formwork and Support work for Structures

The Principal Contractor shall ensure that the provisions of section 10 of the Construction Regulations (July 2003) are adhered to. These provisions must include but not be limited to ensuring that all equipment used is examined for suitability before use; that all formwork and support work is inspected by a competent person immediately before, during and after placement of concrete or any other imposed load and thereafter on a daily basis until the formwork and support work has been removed. Records of all inspections must be kept in a register on site.

PAM 2.4.16 Lifting Machines and Tackle

The Principal Contractor and all Contractors shall ensure that lifting machinery and tackle is inspected before use and thereafter in accordance with the Driven Machinery Regulations and the Construction Regulations (section 20). There must be competent lifting machinery and a tackle inspector must inspect the equipment daily or before use, taking into account that:All lifting machinery and tackle has a safe working load clearly indicated;Regular inspection and servicing is carried out;Records are kept of inspections and of service certificates;There is proper supervision in terms of guiding the loads that includes a trained banks man to direct lifting operations and check lifting tackle;The tower crane bases have been approved by an engineer;The operators are competent as well as physically and psychologically fit to work and in possession of a medical certificate of fitness to be available on site.

PAM 2.4.17 Ladders and Ladder Work

The Principal Contractor shall ensure that all ladders are inspected monthly, are in good safe working order, are the correct height for the task, extend at least 1m above the landing, are fastened and secured, and at a safe angle. Records of inspections must be kept in a register on site. Sub-Contractors using their own ladders must ensure the same. Ladders shall not be used as horizontal walkways or as scaffolding. Tools or equipment must be carried in suitable slung containers or hoisted up to the working position.

PAM 2.4.18 General Machinery

The Principal Contractor and relevant Sub Contractors shall ensure compliance with the Driven Machinery Regulations, which include inspecting machinery regularly, appointing a competent person to inspect and ensure maintenance, issuing PPE or clothing, and training those who use machinery

PAM 2.4.19 Portable Electrical Tools and Explosive Powered Tools

The Principal Contractor shall ensure that use and storage of all explosive powered tools and portable electrical tools are in compliance with relevant legislation. The Principal Contractor shall ensure that all-electrical tools, electrical distribution boards, extension leads, and plugs are kept in safe working order. Regular inspections and toolbox talks must be conducted to make workers aware of the dangers and control measures to be implemented e.g. personal protection equipment, guards, etc.

The Principal Contractor shall ensure the following:A competent person undertakes routine inspections and records are kept;

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 33: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Only authorised trained persons use the tools;The safe working procedures apply;Awareness training is carried out and compliance is enforced at all times; PPE and clothing is provided and maintained;A register indicating the issue and return of all explosive rounds is kept;Ensure that the cartridges and explosive tool is lock up separately; andSigns are posted up in the areas where explosive powered tools are being used. (WARNING - EXPLOSIVE POWERED TOOL IN USE - KEEP CLEAR).

PAM 2.4.20 High Voltage Electrical Equipment

There are overhead and underground high voltage electrical cables present on the site. These cables are shown on the drawing and due care shall be taken when working or travelling in their vicinity.

PAM 2.4.21 Public and Site Visitor Health & Safety

The Principal Contractor shall ensure that every person working on or visiting the site, as well as the public in general, shall be made aware of the dangers likely to arise from site activities, including the precautions to be taken to avoid or minimise those dangers. Appropriate health and safety notices and signs shall be posted up, but shall not be the only measure taken.

Both the Employer and the Principal Contractor have a duty in terms of the OHS Act 85/1993 to do all that is reasonably practicable to prevent members of the public and site visitors from being affected by the construction activities.

Site visitors must be briefed on the hazards and risks they may be exposed to and what measures are in place or should be taken to control these hazards and risks. A record of these ‘inductions’ must be kept on site in accordance with the Construction Regulations.

PAM 2.4.22 Night Work

The Principal Contractor must ensure that adequate lighting is provided to allow for work to be carried out safely.

PAM 2.4.23 Transport of Workers

The Principal Contractor and other Sub Contractors shall not:Transport persons together with goods or tools unless there is an appropriate area or section to store them;Transport persons in a non-enclosed vehicle, e.g. truck; there must be a proper canopy (properly covering the back and top) with suitable sitting area. Workers shall not be permitted to stand or sit at the edge of the transporting vehicle.

PAM 2.4.24 Work in Confined Spaces

The Principal Contractor is to ensure that all persons, who are required to enter the jacked sleeve, are provided with sufficient ventilation, illumination, personal protective equipment and transport (e.g. a trolley and guide rope if necessary) to perform the required work.

PAM 2.4.25 Tunnelling

The Contractor shall comply with Regulation 13 wherever tunnelling of any kind is involved. All requirements as set out in the Mines Health and Safety Act and Regulations (Act 29 of 1996) must be complied with.

PAM 2.5 Occupational Health

PAM 2.5.1 Occupational Hygiene

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 34: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Exposure of workers to occupational health hazards and risks is very common in any work environment, especially in construction. Occupational exposure is a major problem and all Principal Contractors must ensure that proper health and hygiene measures are put in place to prevent exposure to these hazards. Prevent inhalation, ingestion, and absorption of any hazardous substance and high noise level exposure. Site-specific health risks are tabled in Annexure C (e.g. cement dust, wet cement, wood-dust, noise, etc.).

PAM 2.5.2 Welfare Facilities

The Principal Contractor must supply sufficient toilets (1 toilet per 15 workers), showers (1 for every 15 workers), changing facilities, hand washing facilities, soap, toilet paper, and hand drying material. Waste bins must be strategically placed and emptied regularly. Safe, clean storage areas must be provided for workers to store personal belongings and personal protective equipment. Workers should not be exposed to hazardous materials/substances while eating and must be provided with sheltered eating areas.

PAM 2.5.3 Alcohol and other Drugs

No alcohol and other drugs will be allowed on site. No person may be under the influence of alcohol or any other drugs while on the construction site. Any person on prescription drugs must inform his/her superior, who shall in turn report this to the Principal Contractor forthwith. Any person suffering from any illness/condition that may have a negative effect on his/her safety performance must report this to his/her superior, who shall in turn report, this to the Principal Contractor forthwith. Any person suspected of being under the influence of alcohol or other drugs must be sent home immediately, to report back the next day for a preliminary inquiry. A full disciplinary procedure must be followed by the Principal Contractor or Sub Contractor concerned and a copy of the disciplinary action must be forwarded to the Principal Contractor for his records.

PAM 3 MEASUREMENT AND PAYMENT

PAM 3.1 Principles

Tenderers (including those sub-contractors and/or suppliers who are preparing prices/quotations for submission to the main Tenderer) must ensure that they make adequate financial provision in their tenders for full compliance with the OHS Act, the Regulations thereto and this H&S specification. Financial provision shall therefore be made by each Tenderer for, inter alia, the following:Carrying out and documenting risk assessments of all work to be carried out under the contract.Preparation of safe work procedures.Preparation of an H&S plan, discussing it with the Employer, and then amending it as agreed.Preparation of a Project H&S File.Regular updating of all of the foregoing.Provision of PPE and protective clothing for employees Complying with all H&S requirements for the duration of the contract.Provision of forced ventilation (as required when working in confined spaces).The completion and checking of the safety file upon completion of the works and handing it over to the Employer.

To enable the Employer to appraise the allowances that Tenderers have made for H&S in their tenders, so that he/she can fulfil his/her obligations in terms of Clause 4 (h) of the Construction Regulations, separate items have been included in the Bill of Quantities for Health and Safety.

Failure by a Tenderer to submit realistic prices for the scheduled H&S items may prejudice his tender. ANNEXURE A (to H&S specification)

PAM 4 TASK COMPLETION FORM

The Principal Contractor and Sub Contractors must submit proof of compliance with Annexure A with the construction phase H&S plan where applicable.

PAM

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 35: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Item No .Requirement OHSA Requirement Submission Date2.3.1 Notification of Intention to Commence Construction / Building Work Complete Schedule 1 (Construction Regulations) before commencement on site2.3.2 Assignment of Responsible Person to Supervise Construction Work All relevant appointments, as per OHS Act and Construction Regulations.Before commencement on site2.3.3 Competence of Responsible PersonsEmployer Requirement & OHS Act Together with H&S plan2.3.4 Compensation of Occupational Injuries and Diseases Act (COIDA) 130 of 1993 COIDA Requirement Together with H&S plan2.3.5 Occupational Health and Safety Policy OHS Act Together with H&S plan2.3.6 Health and Safety Organogram Employer Requirement Together with H&S plan2.3.7 Initial Hazard Identification and Risk Assessment based on the Employer’s assessment

Construction Regulations. Together with H&S plan2.3.8 Health and Safety Representative OHS Act Submit as soon as there are more than 20 employees on site

Other ANNEXURE B (to H&S specification)PAM 5 ASSIGNMENT OF PRINCIPAL CONTRACTOR’S RESPONSIBLE PERSONS

The Principal Contractor shall make the following appointments according to the initial risk assessment: (further appointments could become necessary as project progresses)

Appointment OHSA Reference RequirementCEO Assignee Section 16(2) A competent person to assist with the on-site H&S overall responsibility – Contractor’s Responsible PersonConstruction Work Supervisor CR 6.1 A competent person to supervise and be responsible of Health & Safety related issues on site. The person is appointed to assist the CEO with his/ her overall duties.Subordinate Construction Work Supervisors CR 6.2 A competent person to assist with daily supervision of construction / building work. The person assists the Construction Work Supervisor.Health & Safety Representative(s) Section 17 A competent person(s) to inspect H&S in reference to plant, machinery and Health & Safety of persons in the workplace.Health & Safety Committee Member(s) Section 19 A competent person(s) representing the employer to assist with the on site Health & Safety matters.Incident Investigator GAR 8 A competent person to investigate incidents / accidents on site and could be:• The employer• H&S Representative• Designated person• Member of the H&S CommitteeRisk assessment co-ordinator CR 7 A competent person to co-ordinate all risk assessments on behalf of the Principal Contractor. The same applies to Contractors.Fall protection plan co-ordinator CR 8 A competent person to prepare & amend the fall protection plan.First Aiders GSR 3 A qualified person to address all on site first aid cases.Machinery Inspector GSR 2.1 A competent person to supervise machinery.Lifting machine & equipment inspector DMR 18 A competent person to inspect lifting machines equipment & tackle.Scaffolding Inspector SABS 085 A competent person to inspect scaffolding before use and every time after bad weather, etc.Scaffolding erector GSR 13D A competent person to erect scaffolding.Scaffolding supervisor SABS 085 A competent person to supervise scaffolding.Formwork & support work inspector CR 10 A competent person to inspect formwork & support work.Excavation Inspector CR 11 A competent person to inspect excavation work and ensure that approved safe working procedures. are followed at all times.Appointment OHSA Reference Requirement

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 36: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Ladder Inspector GSR 13A A competent person to inspect ladders daily and ensures they are safe for use, keeping monthly record.Stacking Supervisor CR 26 A competent person to supervise all stacking and storage operations.Explosive powered tools inspector/supervisor CR 19 A competent person to inspect & clean the tool daily and controlling all operations thereof.Temporary electrical installations supervisor CR 22 A competent person to control all temporary electrical installations.Fire-fighting equipment inspector CR 27 A competent person to inspect fire-fighting equipment.

ANNEXURE C (to H&S specification)PAM 6 OTHER REQUIREMENTS

The Principal Contractor shall comply but not be limited to the following requirements and shall report on these to the Employer at progress meetings or at least monthly which ever is sooner.What When Output Accepted by Employer & dateInduction training

Every worker before he/she starts work.Attendance registersAwareness Training (Tool Box Talks) At least weekly Attendance registersHealth & Safety Reports

Monthly Report covering:• Incidents / accidents and investigations• Non conformances by employees & contractors• Internal & External H&S audit reportsEmergency procedures

Ongoing evaluation of procedureTable procedure in writing as well as tel. numbersRisk assessment Updated and signed off at least monthly Documented risk assessmentSafe work procedures Drawn up before workers are exposed to new risks Documented set of safe work procedures (method statements) updated and signed off.General Inspections

Weekly & daily Report OHS Act compliance:• Scaffolding• Excavations• Formwork & support work• Explosive toolsGeneral Inspections

Monthly • Firefighting equipment• Portable electrical equipment• Ladders• Lifting equipment/slingsList of contractors

List to be updated weeklyTable list, number of workers and Company tel. numbersWorkman’s Compensation

OngoingTable a list of Contractors’ workman’s compensation proof of good standing.Construction site rules & Section 37.2 Mandatory Agreement Ongoing Table a report of all signed up Mandatories.

PAM 7 MEASUREMENT AND PAYMENT

Basic principles

In addition to those aspects covered by 7.2 below, Occupational Health and safety aspects related to particular items of work will be held to be covered by the tendered sum or rate for that work.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 37: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Scheduled items

General safety obligations……………………………………………………………………………………………………. Unit: Sum

Compliance with the general health and safety obligations will be measured and paid by the sum. This item may be scheduled as a fixed charge item and a time-related item.

The tendered sum(s) shall cover the cost, not included under the scheduled work items nor under 7.2.2 to 7.2.6 below, of establishing and maintaining, on an on-going basis, the general health and safety systems and general compliance with the Act and its construction regulations.

Risk assessment……………………………………………………………………………………………………. Unit: Sum

Risk assessment will be measured and paid by the sum. This work may be scheduled as a fixed-charge item only.

The tendered sum shall cover the cost of carrying out a risk assessment in terms of PAM 2.3.7 above at the start of the Contract and any subsequent risk assessment that is proved necessary as the work proceeds and the inclusion thereof in the health and safety plan.

Health and safety plan……………………………………………………………………………………………………. Unit: Sum

The health and safety plan will be measured and paid by the sum. This item may be scheduled as a fixed-charge item and a time-related item.

The tendered sums shall cover the Contractor’s cost of the preparation, approval process, maintenance and implementation of an approved health and safety plan required in terms of 7.2.2 above.

Construction Safety Officer and other appointments……………………………………………………………………………………………………. Unit: Sum

The Construction (Health and Safety Officer) and other appointments will be measured and paid by the sum. This item may be scheduled as a time-related item only.

The tendered sum shall cover the cost of the provision of a Construction (Health and Safety Officer) and such other appointments of competent persons as required on the site in terms of the Act.

Training……………………………………………………………………………………………………. Unit: Sum

Training, as required by the Construction Regulations will be measured and paid by the sum. Training may be scheduled as a fixed-charge item only and may, through sub items distinguish between the various aspects of training.

Medical assessment of employees………………………………………………………………………………………………Unit: Sum

Medical assessment of employees will be measured and paid by the sum. This work may be scheduled as a fixed-charge item only.

The tendered sum shall cover the cost of having the Contractor’s employees medically assessed with regard to their medical fitness for the work that they will be required to perform and/or vehicles or plant they are required to operate and the provision of the appropriate certificate.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 38: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

ENVIRONMENTAL MANAGEMENT PLAN

PEM ENVIRONMENTAL MANAGEMENT PLANPEM.1PURPOSE

The purpose of the EMP is to encourage good management practices through planning and commitment with respect to environmental issues, and to provide rational and practical environmental guidelines to minimise disturbance of the natural environment.

PEM.2 RESPONSIBILITIES FOR ENVIRONMENTAL MANAGEMENT

The contractor will be responsible for environmental control on site during construction and the maintenance period. The construction activities will be monitored by an independent environmental specialist and audited against the EMP.

PEM.3 TRAINING AND INDUCTION OF EMPLOYEES

The contractor has a responsibility to ensure that all those people involved in the project are aware of and familiar with the environmental requirements for the project (this includes sub-contractors, casual labour, etc.).

PEM.4 COMPLAINTS REGISTER AND ENVIRONMENTAL INCIDENT BOOK

Any complaints received by the project team from the community will be recorded. The complaint will be brought to the attention of the site manager.

All complaints received will be investigated and a response given to the complainant within 28 days.

All environmental incidents occurring on the site will also be recorded.

PEM.5 ENVIRONMENTAL SAFETY

The management of impacts associated with various categories of concern is discussed as separate topics, indicated below.

PEM.5.1 Soil

Topsoil should be temporarily stockpiled, separately from (clay) subsoil and rocky material, when areas are cleared. If mixed with clay sub-soil the usefulness of the topsoil for rehabilitation of the site will be lost.

Stockpiled topsoil should not be compacted and should be replaced as the final soil layer. No vehicles are allowed access onto the stockpiles after they have been placed.

Stockpiled soil should be protected by erosion-control berms if exposed for a period of greater than 14 days during the wet season. The need for such measures will be indicated in the site-specific report.

Topsoil stripped from different sites must be stockpiled separately and clearly identified as such. Topsoil obtained from sites with different soil types must not be mixed.

Topsoil stockpiles must not be contaminated with oil, diesel, petrol, waste or any other foreign matter, which may inhibit the later growth of vegetation and microorganisms in the soil.

Soil must not be stockpiled on drainage lines or near watercourses without prior consent from the Project Manager.

Soil should be exposed for the minimum time possible once cleared of invasive vegetation, that is the timing of clearing and grubbing should be co-ordinated as much as possible to avoid prolonged exposure of soils to wind

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 39: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

and water erosion. Stockpiled topsoil must be either vegetated with indigenous grasses or covered with a suitable fabric to prevent erosion and invasion by weeds.

Limited vehicular access is allowed across rocky outcrops and ridges.

All cut and fill surfaces need to be stabilized with appropriate material or measures when major civil works are complete.

Erosion and donga crossings must be dealt with as river crossings. Appropriate soil erosion and control procedures must be applied to all embankments that are disturbed and de-stabilized.

All equipment must be inspected regularly for oil or fuel leaks before it is operated. Leakages must be repaired on mobile equipment or containment trays placed underneath immobile equipment until such leakage has been repaired.

Soil contaminated with oil must be appropriately treated and disposed of at a permitted landfill site or the soil can be regenerated using bio-remediation methods.

Runoff must be reduced by channelling water into existing surface drainage system.

PEM.5.2 Water

Adequate sedimentation control measures must be instituted at any river crossings when excavations or disturbance of a riverbanks or riverbeds takes place.

Adequate sedimentation control measures must be implemented where excavations or disturbance of drainage lines of a wetland may take place.

All fuel, chemical, oil, etc spills must be confined to areas where the drainage of water can be controlled. Use appropriate structures and methods to confine spillages such as the construction of berms and pans, or through the application of surface treatments that neutralise the toxic effects prior to the entry into a watercourse.

Oil absorbent fibres must be used to contain oil spilt in water.

During construction through a wetland, the majority of the flow of the wetland should be allowed to pass down stream.

Vehicular traffic across wetland areas must be avoided.

No dumping of foreign material in streams, rivers and/or wetland areas is allowed.

The wetland area and/or river must not be drained, filled or altered in any way including alteration of a bed and/or, banks, without prior consent from the DWAF. The necessary licenses must be obtained in terms of Section 21 and 22 of the National Water Act, 36 of 1998 from DWAF.

No fires or open flames are allowed in the vicinity of the wetland, especially during the dry season.

No swimming, washing (including vehicles and equipment), fishing or related activity is permitted in a wetland or river without written permission from the Project Manager.

Disturbances to nesting, breeding and roaming sites of animals in or adjacent to wetland areas must be minimized.

PEM.5.3 Air

Speed limits must be implemented in all areas, including public roads and private property to limit the levels of dust pollution.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 40: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Dust must be suppressed on access roads and construction sites during dry periods by the regular application of water or a biodegradable soil stabilisation agent. Water used for this purpose must be used in quantities that must not result in the generation of run-off.

The site-specific investigation will quantify the impact of dust on nearby wetlands, rivers and dams in terms of sedimentation. Mitigation measures identified during the site specific study must be implemented.

The Contractor must notify the Principal of all schools within 50m of the site of proposed activities. The Principal must in turn ensure that children with allergies and respiratory ailments take the necessary precautionary measures during the construction period. The Contractor must ensure that construction activities do not disturb school activities e.g. dust clouds may reduce visibility affecting sports activities.

Waste must be disposed of, as soon as possible at a municipal transfer station, skip or on a permitted landfill site. Waste must not be allowed to stand on site to decay, resulting in malodours.

Noise control measures must be implemented. All noise levels must be controlled at the source. All employees must be given the necessary ear protection gear. IAP’s must be informed of the excessive noise factors.

The Contractor must inform all adjacent landowners of any after-hour construction activities and any other activity that could cause a nuisance e.g. the application of chemicals to the work surface. Normal working hours must be clearly indicated to adjacent land owners.

No loud music is allowed on site and in construction camps.

No fires are allowed if smoke from such fires will cause a nuisance to IAP's.

PEM.5.4 Social and Cultural

Access by non-construction people onto any construction sites must be restricted. The Contractors activities and movement of staff must be restricted to designated construction areas only.

The Contractors crew must be easily identifiable due to clothing, identification cards or other methods.

Rapid migration of job seekers could lead to squatting and social conflict with resident communities and increase in social pathologies if not properly addressed. The Contractor must ensure that signs indicating the availability of jobs are installed.

Criteria for selection and appointment (by the Contractor) of construction labour must be established to allow for preferential employment of local communities. The Local Authority must be actively involved in the process of appointing temporary labourers.

Sub-Contractors and their employees must comply with all the requirements of this document and supporting documents e.g. the Contract document that applies to the Contractor. Absence of specific reference to the sub-contractor in any specification does not imply that the sub-contractor is not bound by this document.

No member of the construction workforce is allowed to wander around private property, except within the immediate surrounding of the site.

The Contractor must provide suitable sanitation facilities for site staff. Sanitation provided during the construction phase should be managed so that it does not cause environmental health problems. The use of the surrounding fields or grounds for toilet purposes is not permitted under any circumstance.

The Contractor must arrange for all his employees and those of his sub-contractors to be informed of the findings of the environmental report before the commencement of construction to ensure:A basic understanding of the key environmental features of the work site and environments, and

Familiarity with the requirements of this document and the site specific report.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 41: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Supervisory staff of the Contractor or his sub-contractors must not direct any person to undertake any activities which would place such person in contravention of the specifications of this document endanger his/her life or cause him/her to damage the environment.

The demand for construction materials and supplies will have an effect on the local economy. This impact can be optimised by sourcing and purchasing materials locally and regionally wherever possible, insofar as the material complies with the design specification.

The Contractor must maintain a detailed complaints register. This must be forwarded, together with solutions, to the authorities when requested.

PEM.5.5 Aesthetics

(a) Scenic Quality

Damage to the natural environment must be minimized.

Trees and tall woody shrubs must be protected from damage to provide a natural visual shield. Excavated material must not be placed on such plants and movement across them must not be allowed, as far as practical.

The clearing of all sites must be kept to a minimum and surrounding vegetation must, as far as possible, be left intact as a natural shield.

No painting or marking of natural features must be allowed.

(b) All above ground structures could be treated or painted to blend in with the natural environment.

Cut and fill areas, river and stream crossings and other soil stabilisation works must be constructed to blend in with the natural environment.

Natural outcrops, rocky ridges and other natural linear features, must not be bisected. Vegetation on such features must, as far as possible, not be cut unless absolutely necessary for construction.

Excavated material must be flattened (not compacted) or removed from site. No heaps of spoil material must be left on site once the Contractor has moved off site either temporarily or permanently.

Any complaints from interest groups regarding the appearance of the construction site must be recorded and addressed promptly by the Contractor.

PEM.5.6 Archaeology and Cultural Sites

All finds of human remains must be reported to the nearest police station.

Human remains from the graves of victims of conflict, or any burial ground or part thereof which contains such graves and any other graves that are deemed to be of cultural significance may not be destroyed, damaged, altered, exhumed or removed from their original positions without a permit from the South African Heritage and Resource Agency (SAHRA).

Work in areas where artefacts are found must cease immediately.

Under no circumstances must the Contractor, his/her employees, his/her sub-contractors or his/her sub-contractors’ employees remove, destroy or interfere with archaeological artefacts. Any person who causes intentional damage to archaeological or historical sites and/or artefacts could be penalised or legally prosecuted in terms of the National Heritage Resources Act, 25 of 1999.

A fence at least 2 m outside the extremities of the site must be erected to protect archaeological sites.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 42: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

All known and identified archaeological and historical sites must be left untouched.

Work in the area can only be resumed once the site has been completely investigated. The Project Manager will inform the Contractor when work can resume.

PEM.5.7 Flora

All suitable and rare flora and seeds must be rescued and removed from the site. They must be suitably stored, for future use in rehabilitation.

The felling and/or cutting of trees and clearing of bush must be minimised.

Bush must only be cleared to provide essential access for construction purposes.

The spread of alien vegetation must be minimized.

Any incident of unauthorised removal of plant material, as well as accidental damage to priority plants, must be documented by the Contractor.

Woody vegetative matter stripped during construction must either be spread randomly throughout the surrounding fields so as to provide biomass for other microorganisms and habitats for small mammals and birds, or it may be stockpiled for later redistribution over the reinstated top soiled surface. No vegetative matter must be burnt or removed for firewood other than those removed during the grubbing and clearing phase. Such vegetation can be made available to the local inhabitants to be used as firewood.

No tree outside the footprint of the Works area must be damaged.

PEM.5.8 Fauna

No species of animal may be poached, snared, hunted, captured or wilfully damaged or destroyed.

Snakes and other reptiles that may be encountered on the construction site must not be killed unless the animal endangers the life of an employee.

Anthills and/or termite nests that occur must not be disturbed unless it is unavoidable for construction purposes.

Disturbances to nesting sites of birds must be minimized.

The Contractor must ensure that the work site is kept clean and free from rubbish, which could attract pests.

PEM.5.9 Infrastructure

The relevant authorities must be notified of any interruptions of services, especially the District Municipality, Local Municipality, National Road Agency, Spoornet, TELKOM and ESKOM. In addition, care must be taken to avoid damaging major and minor pipelines and other services.

The integrity of property fences must be maintained.

No telephone lines must be dropped during the construction operations, except were prior agreement by relevant parties is obtained. All crossings must be protected, raised or relocated as necessary.

All complaints and/or problems related to impacts on man-made facilities and activities must be promptly addressed by the Contractor and documented.

Storage Facilities

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 43: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Proper storage facilities should be provided for the storage of oils, grease, fuels, chemicals and hazardous materials.

The Contractor must ensure that accidental spillage does not pollute soil and water resources.

Fuel stock reconciliation must be done on all underground tanks to ensure no loss of oil, which could pollute groundwater resources.

Cement must be stored and mixed on an impermeable substratum.

Traffic Control

All reasonable precautions must be taken during construction to avoid severely interrupting the traffic flow on existing roads, especially during peak periods.

Before any work can start the Local Traffic Department must be consulted about measures to be taken regarding pedestrian and vehicular traffic control.

Access Roads

The Contractor and the affected landowner must collaborate on the planning and construction of new access routes and the repair or upgrading of existing routes.

Access to the site must be controlled such that only vehicles and persons directly associated with the work gains access to the site.

Temporary access roads must not be opened until required and must be restored to its former state as soon as the road is no longer needed.

Batching Plants

Concrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside this area, must be promptly removed by the Contractor and taken to a permitted waste disposal site. After all concrete mixing has been completed, all waste concrete must be removed from the batching area and disposed of at an approved dumpsite. Stormwater must not be allowed to flow through the batching area. Water laden with cement must be collected in a retention area for evaporation and not allowed to escape the batching area. Operators must wear suitable safety clothing.

Chemical toilet facilities should be managed and serviced by a qualified company. No disposal or leakage of sewerage should occur on or near the site.

Blasting

Blasting must not endanger public or private property.

Noise mufflers and/or soft explosives must be used to minimize the impact on animals.

All the provisions of the Explosives Act, 26 of 1956 and the Minerals Act, 50 of 1991 must be complied with.

The Contractor must take measures to limit fly rock.

PEM.5.10 Safety

Measures must be taken to prevent any interference that could result in flashover of power lines due to breaching of clearances or the collapse of power lines due to collisions by vehicles and equipment.

Measures must be taken during thunderstorms to protect workers and equipment from lightning strikes.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 44: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

All tall structures must be properly earthed and protected against lightning strikes.

The process of excavation and back filling must be carried out as a sequential process following one another as quickly as possible. Excavations must only remain open for a minimum period of time and during this time they must be clearly demarcated. If excavations place the public at risk these sites must be fenced.

The residents directly affected by open trenches must be notified of the dangers. This will be done during the site-specific phase.

PEM.5.11 Waste

PEM 5.11.1 Solid Waste

Littering on site and the surrounding areas is prohibited.

Clearly marked litterbins must be provided on site. The Contractor must monitor the presence of litter on the work sites as well as the construction campsite.

All bins must be cleaned of litter regularly.

All waste removed from site must be disposed at a municipal/permitted waste disposal site.

Excess concrete, building rubble or other material must be disposed of in areas designated specifically for this purpose and not indiscriminately over the construction site.

The entire works area and all construction sites must be swept of all pieces of wire, metal, wood or other material foreign to the natural environment.

Contaminated soil must be treated and disposed of at a permitted waste disposal site, or be removed and the area rehabilitated immediately.

Waste must be recycled wherever possible.

PEM 5.11.2 Liquid Waste

The Contractor must maintain mobile toilets on site.

The Contractor must provide adequate and approved facilities for the storage and recycling of used oil and contaminated hydrocarbons. Such facilities must be designed and sited with the intention of preventing pollution of the surrounding area and environment.

All vehicles must be regularly serviced in designated area within the Contractors camp such that they do not drip oil.

All chemical spills must be contained and cleaned up by the supplier or professional pollution control personnel. Run-off from wash bays must be intercepted.

PEM 5.11.3 Hazardous Waste

No hazardous materials must be disposed of in the field or anyplace other than a registered landfill for hazardous material. Hazardous waste must be stored in containers with tight lids that must be sealed and must be disposed at an appropriately permitted hazardous waste disposal site. Such containers must not be used for purposes other than those originally designed for.

The Contractor must maintain a hazardous material register.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 45: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PEM.5.12 Rehabilitation and Site clearance

When all major construction activities are completed, the site must be inspected to determine site-specific rehabilitation measures. This may be considered as unplanned work e.g. soil rehabilitation due to oil spills.

All temporary buildings and foundations, equipment, lumber, refuse, surplus materials, waste, construction rubble fencing and other materials foreign to the area must be removed.

If waste products cannot be recycled they must be disposed of at a permitted landfill site.

All drainage deficiencies including abandoned pit latrines and waste pits must be corrected.

Cut and fill areas must be restored and re-shaped.

The area must be restored to its natural vegetation condition using indigenous trees, shrubs and grasses as directed by a grassland and/or rehabilitation expert.

Borrow pits must be re-shaped into even slopes and surfaces to blend with the natural terrain and topsoil must be replaced.

The grass mix, shrubs and trees used for rehabilitation must be compatible with the species identified in the site-specific investigation.

Areas compacted by vehicles during construction must be scarified to allow penetration of plant roots and the regrowth of natural vegetation.

PEM.6 MEASUREMENTS AND PAYMENT

No additional payment will be made to the Contractor to comply with the above actions as it will be deemed to be included in the rates tendered.

EARTH WORKS

PPS EW1 SITE CLEARANCEAreas to be cleared and grubbed. Both borrow areas and the portions of the site on which excavations are to be carried out and the shed constructed, shall be cleared or grubbed, or both, the Contractor shall excavate the top 150mm of topsoil including all of the smaller vegetation (grass and shrubs, bushes) and stockpile it. The contractor shall not commence with clearing and grubbing until the Engineer has designated, in writing and in detail, the exact areas to be stripped of topsoil and the time at which the work to be started.

Cutting of trees. The contractor shall take the necessary precautions to prevent injury to persons and animals and damage to structures and other private and public property. Where necessary, trees shall be cut in sections from the top downwards.

Branches overhanging boundaries. The branches of trees to be left standing shall be so trimmed as not to encroach upon the space (of height at least 7m) vertically above any carriageway, railway formation, or other designated area.

Preservation of trees. No tree shall be cut down until the engineer has given written authorization for such work to commence.

Clearing. Clearing shall consist of:

The removal of all trees, rubbish, fences, and all other material that may interfere with the construction of the work.The disposal of all material resulting from clearing.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 46: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The removal of rocks and boulders of size up to 0.15m3 that are lying on the surface to be cleared or exposed during the clearing operations.Where fences have to be taken down, sorting, coiling, and stacking of the material.The removal and stacking of other reusable materials as scheduled.

The moving of a certain amount soil or gravel may be inherent in or unavoidable during the process of clearing. No extra payment will be made for the removal such soil or gravel.

Grubbing. All stumps and roots larger than 75mm in diameter shall be removed to a depth of at least 600mm below the finished level and at least 100mm below the original ground level. Where the area has to be compacted, all stumps and roots including matted roots shall be removed to a depth of at least 200mm below the cleared surface.Except in borrow areas, cavities resulting from grubbing shall be backfilled with approved material and compacted to a density at least equal to that of the surrounding ground.

Re-clearing of vegetation. If during the contract period vegetation should again grow on any portion of the site, borrow areas, or the areas that have been cleared in accordance with the specification, the Engineer may, if considers it necessary, order that such area be re-cleared.

Such re-clearing shall include the removal and disposal of grass, shrubs, and other vegetation, as in the first clearing operation.

Conservation of topsoil. The terms of Sub-clause 5.2.2 of SANS 1200DA: 1988 shall apply.

EXCAVATIONThe permissible degree of accuracy for all excavations shall be of accuracy III (Table 2).Table 1: Permissible deviations: excavations

Permissible Deviation (PD)Degree of Accuracy IIIMm

Position on plan. PD in plan of any point measured from the nearest grid line. ±50

Dimensions on plan. PD from the design dimensions ±75Footing level. PD in level of surface of excavation trimmed to receive concrete. ±75

Level. PD from designated level with reference to the nearest transferred bench mark of any floor slab ±20

After the topsoil has been removed, excavation shall be carried out first to any general levels to which the ground has to be reduced and after that to the depths indicated on the drawings or to such greater depths as may be ordered or approved to ensure satisfactory foundation levels.

The excavated surfaces for shall be trimmed to function as the formwork for the floor slabs and the column foundations to the dimensions as indicated on the drawing.

Immediately before any permanent construction is commenced, the bottom of each excavation shall be cleaned of all loose material and soft material shall be rammed to the level as indicated on the drawings.

Should the Contractor excavate to dimensions in excess of those stipulated or permitted, he shall fill in the excess at his own expense in the manner specified or approved by the Engineer.

Topsoil shall be stockpiled temporarily and returned to be spread over the surrounding site.

The Contractor properly deals with and disposes of water to ensure that the works are kept sufficiently dry for their proper execution. His responsibility will be held to include the provision of adequate protection against flooding and damage by storm water, flow from springs, and seepage, and to include provision for the repair, at his expense, any of the damage to the works that may arise as a result of the inadequacy of the protection

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 47: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

provided by him. Except where the use of tremies has been approved, foundation and floor excavations shall be kept free from water at all times until they have been inspected and approved and the concrete have been cast.

The Contractor/Bidder shall drain borrow areas to prevent pools forming.

PPS EW2 MEASUREMENT AND PAYMENT: SITE CLEARANCEBasic principles.The items scheduled for clearance will be classified according to the nature of the materials involved and the methods of their disposal.Only those areas designated to be cleared will be measured for payment.The removal of topsoil from the specified area will be measured as excavation and no payment will be made for it under clearing and grubbing.

Scheduled items.Clear and grub…………………………………………………………………………………………..m2The area designated by the Engineer and cleared and grubbed will be measured to the nearest 0.1m2. The rate shall cover the cost of removing boulders of size up to 0.15m3, grubbing of trees and tree stumps, cutting of trunks and branches exceeding 0.5m in girth into transportable lengths, backfilling of cavities, removing, transporting, and disposing of material thus cleared, grubbed and cut. Boulders over 0.15m3 will be dealt with as excavation in terms of the items scheduled for bulk excavations. The rate is for the shed, handling facilities and toilet.Remove and grub large trees and tree stumps of girth:Over 1m and up to and including 2m…………………………………………………………...No.Over 2m and up to and including 3m…………………………………………………………...No.Over 3m, in steps of 1m………………………………………………………………………….No.The girth of a tree or stump will be measured at the narrowest point of the tree or stump in the first meter of its length above the ground level. Trees and stumps of girth exceeding 1m will be measured individually and classified according to the size in increments of 1m as indicated above.

The unit of measuring the site clearance will be in number as indicated.The rate shall cover the cost of clearing and grubbing trees and stumps of all sizes, cutting branches, backfilling holes, and removing, transporting, and disposing of all such trees, stumps, and branches and associated material.

PPS EW3 MEASUREMENT AND PAYMENT: EXCAVATION

Figure 1: Classes of Excavation: Measurement and Payment

Basic principlesThe basic principles for measurement and payment for all earthworks are that the rates tendered for excavation shall cover the cost of excavating and re-use of the material in backfilling and required slopes for the floor and furrow, and the cost of disposal of surplus and unsuitable material within the free haul distance of 500m. Separate additional payment will be made for filling excess excavation, forming banks or terraces, disposing of surplus material, or any other contingent work, only where specifically prescribed and scheduled.Excavations which are required to be backfilled will be measured as if taken out with vertical sides regardless of whether they have been taken out with sloping sides. They will be measured from the net plan of the finished concrete footing except that, in the case of conical or other such structures, the volume will be measured from the finished outline of the concrete as shown on the drawings.Where extra excavation for outside formwork or working space is specified or ordered prior to the start of bulk excavation for a structure, such excavation will be measured as part of the bulk excavation.Computation of quantitiesEarthworks will be measured by volume once only, in excavation. Measurements will be to finished shapes, sections and profiles as shown on the drawings or ordered, and no excavation outside the specified lines and levels will be included in the measurements unless such extra work has been done on the written instructions of the Engineer.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 48: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The volumes of material handled will be computed from plan dimensions and the total depth excavations. Volumes removed incidentally will be disregarded in excavation quantities but the volumes (computed from areas and depths) moved in excavation of stated depth of topsoil will be added to the scheduled “Remove topsoil” volume.Scheduled items.

Remove Topsoil and stockpile……………………………………………………………………………..m2The rate shall cover the cost of removing the topsoil to a depth of 150mm, together with such vegetation and small roots occur within the specified depth, and of stockpiling it on designated sites. The rate is for the shed, handling facilities and toilet.

ExcavationExcavate in all materials and use for floor slope preparation and backfill and dispose of excess as ordered………………………………………………………………………………………………m3Separate items will be scheduled for each type of excavation and for each type or manner of disposal of excavated material.The rate shall cover the cost of excavation, basic selection, loading, transportation within the free haul distance of 500m, offloading, spreading or backfilling, watering, compacting, final grading, complying with the requirements for tolerances, and disposal of soil, all in accordance with the requirements given on the drawings.

Extra over forIntermediate excavation………………………………………………………………...m3Hard rock excavation……………………………………………………………………m3Boulder excavation, Class A……………………………………………………………m3Boulder excavation, Class B……………………………………………………………m3The rate shall cover the additional cost of the operations enumerated in “Excavate in all materials and use for floor slope preparation and backfill and dispose of excess as ordered” above for any portion of the excavation that is classified as intermediate, hard rock, boulder class A or boulder Class B, as applicable (Figure 2)

The unit of measuring the excavation will be in cubic meter when completed.The rate tendered shall cover the cost for all excavations, handling and transporting of all materials, as specified on the drawings to include labour and hiring of plant.

PPS EW4 MEASUREMENT AND PAYMENT: SUB GRADE FILLING AND COMPACTIONFilling under solid floor and over site is to be executed with approved dry earth, free from clay and spread evenly in layers not more than 200mm thick, well watered and compacted. If in-sito material is not suitable in the opinion of the engineer, suitable filling material will be imported, and compacted as described.

When in the opinion of the engineer, the density of the ground under surface is not suitable, the surface shall be scarified to a depth of 150mm with a mechanical ripper or other approved equipment, watered and re-compacted.

PPS 4.1 Scheduled items.Filling and compacting…………………………………………………………………………………………………..mᶟFilling and compaction shall be measured in cubic meter. The rate shall cover importing of material where required, watering, compacting, ripping where needed, and supplying of labour.

PPS EW5 MEASUREMENT AND PAYMENT: SAND FILLING AND BEDDINGBedding of dip tank shall be done with washed river sand, which is clean of any stones and clay and any organic material. Sand shall be placed according to specification PPS D1.

PPS 5.1 Scheduled items.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 49: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Sand filling and bedding…………………………………………………………………………………………………..mᶟFilling shall be measured in cubic meter. The rate shall cover importing of material where required, washing, placing and compacting and supplying of labour.

CONCRETE WORKS

CONCRETE, FORMWORK AND REINFORCEMENT

NB: All in situ concrete work (mass and reinforced) shall comply with SABS Specification 1200G ("8. Measurement and Payment" is not applicable) supplemented by the clauses in this section. Where SABS Specification 1200G and the clauses in this section are in conflict the clauses in this section shall take precedence.

Where the term "plain concrete" appears in SABS Specification 1200G it shall be read as "mass concrete"

PPS C1.1 CEMENT:Cement shall be Portland cement complying with the requirements of SABS Specification 471 or PC15 complying with SABS Specification 831.

Samples of cement from any one, or from every consignment, may be required by the Representative/Agent for test purposes. Cement in any consignment from which a sample may have been taken for testing shall not be used until it has been approved. Allowance must be made for possible delay in that tests may take 10 days to carry out.

Bags of cement shall be stacked in a waterproof, solidly constructed shed with a central door and a floor rendered damp-proof with a tarpaulin. The bags of cement shall be closely stacked (but not against walls) in order to reduce air circulation in such a manner that the cement is used in the order in which it was received, i.e. first in first out.

Unless otherwise specified in the tender documents the use of ordinary Portland cement blended with ground granulated blast furnace slag complying with SABS Specification 1491, or ordinary Portland Cement blended with Pulverised Fly Ash complying with SABS Specification 1466 will be allowed in certain instances as an alternative, after acceptance of tender, but only with the approval of and at the sole discretion of the Department. If not so specified in the tender documents the Contractor must demonstrate a saving in favour of the Department together with his alternative tender. The saving offered will be adjudicated by the Engineer/Quantity Surveyor for the service and acceptance of the alternative will be in accordance with the reasonableness thereof.

PPS C1.2 SAND (FINE AGGREGATE):The fine aggregate shall comply with the requirements of SABS Specification 1083. Other aggregates may be approved if they have a satisfactory history and/or test results.

No aggregate may be used until it has been approved. Samples having a mass of 25 kg (16,5 litre) of the aggregate proposed to be used may be required by the Representative/Agent for test purposes. Samples having a mass of 25 kg shall be forwarded every 3 months during concreting work and also if the source of supply is changed. Allowance must be made for possible delay in that the tests may take 14 days to carry out.

PPS C1.3 STONE (COURSE AGGREGATE):5.3.1 The coarse aggregate shall comply with the requirements requirements of SABS Specification 1083.No aggregate may be used until it has been approved. Samples having a mass of 25 kg (16, 5 litre) of the aggregate it is proposed to use may be required by the Representative/Agent for test purposes. Samples shall be forwarded every three months during concreting work and also if the source of supply is changed. Allowance must be made for possible delay in that the tests may take 14 days to carry out.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 50: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

NB: Certain fine grained sand and stone originating from the Beaufort Series and Karoo Systems which are known by reputation, local experience or tests, to exhibit excessive shrinkage when used in concrete, may be deemed unacceptable by the Representative/Agent.

5.3.2 A certificate of proof is required from the Contractor that the aggregates are not alkali reactive. The cost of testing and certification are to be borne by the Contractor.

PPS C2 CONCRETE:The strength given in the below shall be the minimum required at 28 days. Unless otherwise specified.

Maximum concrete slumps acceptable for different types of construction concrete are as follows:(a) Vibrated reinforced concrete = 50 mm(b) Unvibrated reinforced concrete = 75 mm(c) Mass concrete = 75 mm

When so required by the Representative/Agent, and whilst concreting is in progress, the consistency of the mixture shall be ascertained by means of the slump test as later described herein.

PPS C3 STRENGTH CONCRETE:The Contractor shall be responsible for the design of strength concrete and for the measurement of the constituent materials to produce concrete that complies with the specified requirements.

The relevant Engineer will decide the class and grade designation of the concrete required for each part of the work and determine suitable limitations on the constituent materials and mix proportions in accordance with the said requirements.

(a) Trial mixes:The Contractor must ensure that samples of the constituent materials of the concrete, together with evidence that they comply with the provisions, are supplied for approval in good time and provide the Engineer with—

i) a statement from an approved independent laboratory of the results of tests, orii) an authoritative and acceptable report, or record of the previous use of, and experience with, the material concerned.

The cement, types of aggregate and their origins may not be changed throughout the duration of the contract without giving prior notification to the Engineer who shall verify that the above requirements are complied with and that the important qualities of the concrete will not be impaired.

(b) Durability:For each grade of concrete the Engineer will, notwithstanding strength considerations, specify the cement/water ratio appropriate to the exposure conditions indicated in Table 5, SABS Specification 1200G, Subclause 5.5.1.5.

(c) Consistency:Unless otherwise indicated by the general workability of the concrete, method of transportation, conditions of placement or otherwise specified by the Engineer, the suggested slump values, for different mixes of concrete shall be as specified in Clause 3.4.

(d) Workability:Ensure that the concrete is of such workability that it can be readily compacted into the corners of the formwork and around reinforcement without segregation of the materials and without excessive "bleeding" of free water at the surface.

PPS C4 SLUMP TEST:The apparatus and the method of determination of the slump of freshly mixed concrete shall comply with SABS STM 862.

(a) Apparatus:

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 51: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

(i) A mould in the form of a frustum of a cone and having the following nominal internal dimensions:Bottom diameter: 200 mmTop diameter: 100 mmHeight: 300 mm

The mould shall be of a metal (other than brass or aluminium) of side thickness at least 1,6 mm and shall have a smooth internal surface. The mould shall have suitable base plate and handles to facilitate lifting it from the test specimen in a vertical direction.

(ii) The tamping bar shall have a nominal diameter of 16 mm, a length of 600 mm and with sharp corner rounded off at one end.

(b) Procedure:The test shall be carried out in an area that is free from vibration and shocks. Ensure that the internal surfaces of the mould are free from set concrete and are clean and dry. Place the mould with the bottom on a smooth, horizontal, rigid, non-absorbent surface and hold the mould firmly in place while it is being filled as follows:

(i) Fill the mould in four layers, each thickness approximately one-quarter of the height of the mould. Tamp each layer with 25 strokes uniformly spaced over the cross-section of the mould. Tamp the bottom layer throughout its depth and ensure that when tamping the second and subsequent layers the strokes penetrate into the underlying layer.

(ii) After the top layer has been tamped, strike off the concrete level so that the mould is exactly filled. Clean off any concrete that may have leaked out between the mould and the supporting baseplate surface. Remove the mould from the concrete immediately by slowly and carefully raising it in a vertical direction. This will allow the concrete to subside.

Immediately measure the slump, to the nearest 5 mm, by determining the difference between the height of the mould and the height of the specimen. If a slump specimen collapses or shears off laterally regard the test as invalid, discard the result and repeat the test.

PPS C5 CONCRETE QUALITY:Should the engineer dispute concrete quality, the contractor shall at his own cost, proves to the satisfaction of the Engineer that the estimated actual strength of cores taken from the structure (by an approved independent testing laboratory and determined in accordance with SABS STM 865) is not less than the specified strength. If the concrete fails to meet the strength criteria stipulated, the Engineer may at his sole discretion and in addition to the options listed in SABS Specification 1200G-

(a) accept the concrete subject to approved remedial measures being undertaken by the Contractor at his own cost; or

(b) Permit the concrete to remain, subject to reduced payment for lower strength concrete.

PPS C6 CONCRETING:It is essential that the foreman who has charge of the construction of all concrete work, whether reinforced or not, shall be skilled in this class of work, and shall personally superintend the whole construction, paying special regard to—(a) The quality, testing and mixing of the materials.(b) The laying of the material in place and the thorough compaction of the concrete to ensure solidity and freedom from voids;(c) The construction and removal of formwork; and(d) The sizes and positions of the reinforcement.

Particular care shall be taken to work concrete against formwork and around reinforcement. Internal vibrators may be used with the approval of the Representative/Agent but external vibrators which act only on the formwork will not be permitted.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 52: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Concrete to be reinforced shall be deposited in such quantities as will permit of it being properly compacted around the reinforcement.

The placing of concrete shall be completed within half-an-hour after mixing or within half-an-hour after agitating and within 2,5 hours after mixing in the case of ready mixed concrete. On no account shall concrete be incorporated into the work after it has attained its initial set.

Care shall be taken to prevent, as far as possible, the formation of laitarice or scum. Laitance is to be understood to mean the scum of strengthless and inert material which forms on the surface of concrete.

Concrete must not be dropped into position from a height greater than 2,5 m unless prior approval isObtained from the Engineer.

If an inclined chute is used for transporting concrete, it shall be of such slope as will ensure a continuous flow of concrete without the use of an excessive quantity of water and without segregation of the aggregates. The chute must be flushed out and properly cleaned before and after each working period. All waste from flushing shall be discharged outside the formwork.

In beams, each portion of a successive layer shall be placed as soon as the concrete below has been properly worked around rods and against formwork. Concreting shall be carried forward in irregular steps, that is to say, one layer shall not be completed over the whole section before the succeeding layer is commenced. Concreting of slabs and beams shall, as far as possible, be carried forward in one operation. When concreting has to be interrupted the concrete shall be left with a level, rough top surface with ends vertical. The concrete shall not be merely sloped down.

On resuming concreting, the old surface shall be roughened and all laitance thoroughly and carefully removed before any new concrete is deposited. This must be carried out by brushing the surface of the concrete while it is still green. Great care must be taken to avoid any weakness at the junction of old and new concrete, and the old surface shall be coated with a thin layer of cement and sand mortar, in the same proportions as that of the adjoining concrete.

While the concrete is setting it shall not be disturbed or shaken by traffic, either on the concrete itself or upon adjoining formwork.

No holes in concrete elements shall be patched or filled in without inspection, instruction and approval of the Engineer.

No concreting shall be carried out when the air temperature is below 4 °C when it is rising and 8 °C when it is falling.

Before concreting is commenced the Contractor shall give the Representative/Agent 24 hours’ notice of his intention to do so. On sites further than 200 km from the Representative/Agent, 48 hours’ notice must be given.Concrete surface beds, excluding heavy industrial floors etc. shall be Class C concrete and shall be laid in suitable size panels not exceeding 20 m2 in area and with the length of any panel not exceeding 4,5 m.

Where concrete beams are supported on concrete columns, the columns are to be concreted up to the underside of such concrete beams and then concreted up to the top of the beams, integral with the beams.

NB: Any finish applied to the surface of concrete floors, is to be understood as being additional to the thickness of the concrete described or shown on the drawings.

PPS C7 CURING OF CONCRETE:

After the concrete has been placed, all exposed surfaces shall be kept continuously damp for at least 10 days by methods as may be approved by the Representative/Agent, such as covering with approved building paper, or by means of wet canvas, wet sacks, wet sand, by continuous hosing or ponding with water.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 53: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PPS C8 BUILDING ON CONCRETE FOOTINGS AND BEAMS:

No brickwork, stone walling or other structure shall be built on concrete footings until at least three days after placement of the concrete in the case of mass concrete footings and after seven days in the case of reinforced concrete footings or as may otherwise be directed by the Representative/Agent.

No brickwork, stone walling or other structure shall be built on reinforced concrete beams or similar members until the formwork and all props or supports have been removed.

PPS C9 SLIP JOINTS BETWEEN CONCRETE AND BRICKWORK:

Slip joints shall be provided between brickwork and concrete slabs and beams by levelling up and trowelling smooth the bearing surfaces of brickwork with 3:1 cement mortar and covering the bearings before the concrete is cast, with two layers of one side smooth tempered hardboard, with the smooth sides in contact.

The ends and sides of beams and edges of concrete slabs shall be separated from the brickwork with 13 mm thick bitumen impregnated soft board or expanded polyethylene strips placed vertically against the brickwork before the concrete is cast.

Similar slip joints shall be provided between brickwork and concrete lintels cast In situ, but without soft board or expanded polyethylene strips at ends.

PPS C10 MOVEMENT JOINTS:

All movement joints are to be filled in with approved bitumen impregnated soft board or expanded polyethylene strip unless otherwise specified or detailed on drawings. Form similar movement joints where pathways adjoin buildings externally. Descriptions (prices) of movement joints shall be deemed to include formwork.

PPS C11 PRE-STRESSED CONCRETE LINTELS.

The dimensions of the lintels used must be 140mm × 75mm. The lintels must be installed as such that the width is 140mm and the vertical height is 75mm. The concrete lintels must comply with the requirements of SANS 1504: 1990.

Standard pre-stressed concrete lintels of 0,9m must be placed above all sliding doors.Standard pre-stressed concrete lintels of 1,2m must be placed above all the windows.Standard pre-stressed concrete lintels of 1,5m must be placed above all the doors.Standard pre-stressed concrete lintels of 3,0m must be placed above the garage door.

PPS C12 FORMWORK:Formwork shall include all shuttering, casing and centring of wever material required for the laying and forming of concrete floors, slabs, beams, lintels, walls, steps, columns, piers, pilasters and any other concrete work requiring moulds or forms and shall embrace all cleats, battens, fillets, wedges, struts, trestles, braces, props, shores and other requirements of wever material for keeping all in correct position. All materials used for formwork must be suitable and substantial and all joints must be tight enough to prevent leakage of liquid matrix.

All formwork must be designed by the Contractor and if requested to do so, he must submit fully detailed and dimensioned working drawings to the Representative/Agent for checking purposes.

Acceptance of the proposals shall not relieve the Contractor of his responsibility for the safety and stability thereof nor for any loss or damage arising out of defective design, materials and/or workmanship.

The formwork must be so constructed that its partial removal can be carried out to the satisfaction of the Representative/Agent and in such stages as are required by the working conditions. As far as possible, wedges

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 54: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

and clamps must be used in preference to nails. All formwork in its various sections for floors, beams, etc. must be so arranged that the whole may be raised or lowered either independently or together with other sections by means of wedges or other approved methods.

Immediately before concreting is begun, the formwork in contact with the concrete must be thoroughly cleaned, wetted and kept damp whilst the concrete is being placed. Great care must be taken to keep the formwork wedged up to its correct height and this must be checked by taking levels immediately before concreting is commenced and immediately after it has been completed.

All beams shall have a camber of 6 mm to every 3 m of length.

The minimum periods that the formwork to the various parts of the structure is to remain in positionafter concreting shall be 7 days.

When determining the stripping time for formwork the weather shall be considered to be "normal" when the temperature is above 18 °C and "cold" when the temperature is between 5° and 10 °C, these being the average daily temperatures of the atmosphere adjacent to the concrete. When the average daily temperature lies between the above values for "normal" and "cold" weather the minimum period for stripping of formwork shall be determined by the Representative/Agent.

Notwithstanding the above minimum periods, formwork may be struck immediately the concrete in the various parts of the structure has attained the crushing strengths required by the Representative/Agent. The crushing strengths must be determined by proper tests, which shall be carried out by the Contractor.

No formwork of any nature whoever shall be struck, either after the elapse of the minimum periods stated in the above table or on the attainment of the required crushing strengths of the concrete, without the prior consent of the Representative/Agent? Such consent will not absolve the Contractor of his responsibility for the safety of the structure.

In structures having either in whole or in part, two or more reinforced concrete floors, props shall be provided under the soff its of any beam or slab of any floor which is being used to support the formwork and wet concrete of the floor above, all to the approval of the Representative/Agent. The props shall not be removed until the formwork supporting the concrete of the floor above has been struck.

On no account shall steel formwork be oiled where concrete is to receive plaster.

Formwork is measured to the net surfaces of concrete to be supported, except at intersections of beams with beams, columns, walls, etc. and tops of columns with slabs, beams, etc. where no deductions have been made and descriptions (prices) shall be deemed to include use and waste, except where the formwork is of a permanent nature or is to be left in, fitting together to all required shapes, all cutting, intersections, cambering where required, holes for rods, bolts, pipes and the like, propping, maintaining, keeping damp whilst the concrete is being deposited and removing. Formwork "left in" and permanent formwork shall be deemed to include leaving in formwork, props, etc.

Descriptions (prices) of formwork to soffits shall be deemed to include propping not exceeding 3,5 m high unless otherwise described. Descriptions (prices) of formwork to walls and columns shall be deemed to be not exceeding 3,5 m high above bearing level unless otherwise described. Descriptions (prices) of formwork to sof fits of solid slabs shall be deemed to be to slabs not exceeding 250 mm thick unless otherwise described.

PPS C13 SMOOTH FORMWORK:

Smooth formwork shall be any material approved by the Representative/Agent which is to be used to leave concrete surfaces smooth when removed and where no other finish is to be applied.

Descriptions (prices) shall be deemed to include for rubbing off all projections at seams etc. after removal of the formwork, making good any defects with 2:1 cement mortar and leaving a smooth surface with all arises slightly rounded, all to the satisfaction of the Representative/Agent.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 55: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PPS C14 REINFORCING RODS:

18.1 Mild steel:Mild steel shall comply with the requirements of SABS Specification 920, Type A or B.

18.2 High tensile steel:High tensile steel shall comply with the requirements of SABS Specification 920, Type C or D.

18.3 Pre-manufactured reinforcing sheet mesh:Pre manufactured reinforcing sheet mesh shall comply with the relevant SABS codes, and shall be of the reference code as specified in the drawings.

PPS C15CONCRETE REINFORCE MENT:

15.1 Rod reinforcement:Bending and hooking of rods shall be done in accordance with SABS Specification 82. Rods shall be bent cold in an effective bending machine, or properly designed rod-bender using a steady pressure and not by hammering.

Diameters, lengths and positions of rods as shown on the drawings must be strictly adhered to. Joints in rods in beams, stairs, etc. will be permitted only where shown on drawings.

Before being placed in position, the rods shall be thoroughly cleaned of all grease, dirt, bituminous material, scale and loose rust.

All distribution rods shall be straight and shall extend at least 150 mm into beams or other support.

Unless otherwise shown on the drawings, all joints in reinforcing rods shall be lapped 40 times the diameter of the rod. The laps shall be securely tied with 1, 25 mm diameter annealed mild steel binding wire.

Reinforcement for piles, column footings, columns and walls shall be tied at every intersection, or as directed or shown on drawings, with similar binding wire.

Reinforcement in beams shall be tied at alternate intersections in a diamond pattern, unless circumstances demand every intersection.

Great care must be taken to retain the reinforcement in its correct position during the entire period of concreting. Blocks of fine concrete, size approximately 40 x 40 mm, or plastic spacers, shall be provided on the formwork to soff its of beams to ensure than the rods are retained in position and then the correct concrete covering to the main reinforcing rods is provided. The blocks shall be of thickness required and shall be placed under the mainreinforcing rods at approximately 600 mm centres.

Reinforcement in the top of slabs and the like shall be retained in position by means of cradles (stools), formed of steel reinforcing rod as follows:R10 for height range 100-300 mm and maximum width of 300 mm.R12 for height range 310-500 mm and maximum width of 450 mm.

Recommended spacing of supports for horizontal bars in slabs:Not further than 600 mm apart (cradles ±1000 mm c/c in both directions) for bar diameters up to 12 mm.Not further than 1 000 mm apart (cradles ±1 500 mm c/c in both directions) for bar diameters of 16 mm and over.

Stools are to be placed on the bottom layer of reinforcement, securely retained in position and with correct concrete cover as specified. Cradles are to be securely wired to the slab reinforcement with binding wire. Beam rods in different layers shall be separated by means of steel spacer bars of suitable diameters and lengths.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 56: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Double mats in concrete walls shall be kept in their respective positions by means of suitable steel clips as follows:Recommended spacing of supports for vertical bars in walls:1 000 mm centres in both directions for bars up to 12 mm diameter,1 500 mm centres in both directions for bars of 16 mm diameter and over.

Supports can be spaced more closely by the design Engineer, depending upon the circumstances.

All stirrups shall be properly fastened to the rods so as to retain their relative positions during the entire period of concreting.

Welding of main rods will not be permitted unless approval has been given by the Representative/Agent. Spot welding in lieu of wiring may be used to secure rods and stirrups in position.

The concrete covering the main reinforcement, unless otherwise specified, shall not be less 50mm.

Depending on the condition of exposure and fire resistance requirements, concrete cover can be varied by the design engineer but in no case shall the concrete cover be less than the diameter of the rod to be covered.

The cover shall be measured from the face of the concrete to the outside of main reinforcement nearest the face of the concrete, and shall exclude plaster and similar finishing materials.

Three samples of each diameter of reinforcing rods, each approximately 600 mm long, must be taken from each consignment of rods of similar diameter, for testing.

If any sample is found unsatisfactory, the whole consignment of rods from which the samples were taken will be rejected.

Top reinforcement in cantilever slabs to be kept in position with a first row of stools or chairs 300 mm from the beam or support, and thereafter at a maximum of 40 bar diameters under each bar.

The cover blocks, spacers, bars and stools or chairs are to be placed and/or wired in position by the steel fixer.

PPS C16 DAMP-PROOF MEMBRANE:The damp-proof membrane under floor shall, unless otherwise specified, be of polyethylene sheeting complying with SABS Specification 952 0,5 mm thick (500 microns) and manufactured in widths of 1000 mm and greater, all laid in the widest practical widths to minimise joints, turned up and dressed to load bearing walls and, if applicable, lapped with the damp-proof course in the walls. All joints shall be sealed with pressure sensitive tape applied over the leading edge of the joint.NB: All cutting of plastic membranes shall be carried out using sharp instruments.

PPS C17 MEASUREMENT AND PAYMENT:

Item Unit

PPS C17.1Mass concrete foundations (15MPa) ……………………………………………………………………mᶟThe unit of measurement shall be in cubic meter. The tender rate shall include full compensation for the design of concrete mixes, testing of concrete and materials, supply, delivery, handling and storage of all materials, mixing placement, shaping, floating, curing, and striking, of all components.

PPS C17.2Mass concrete floors, apron and ramp (20MPa) ………………………………………………………mᶟThe unit of measurement shall be in cubic meter. The tender rate shall include full compensation for the design of concrete mixes, testing of concrete and materials, supply, delivery, handling and storage of all materials, mixing placement shaping, floating, curing, and striking, of all components.

PPS C17.3 Pre-stressed concrete lintel…………………………………………………………………….….Number

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 57: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The unit of measurement shall be in number of various sizes as specified in drawings and bill of quantities. The tender rate shall cover the full cost of supply, delivery storage and placing of lintels according to drawings and specifications.

PPS C17.4Reinforced concrete slab (20MPa) …………..…………………………………………………………mᶟThe unit of measurement shall be in cubic meter. The tender rate shall include full compensation for the design of concrete mixes, testing of concrete and materials, supply, delivery, handling and storage of all materials, mixing, placement, working and packing around reinforcement, shaping, floating, curing, and striking, of all components.

PPS C17.5 Steel reinforcement ……………………………………………………………………………………..SumThe unit of measurement will be a total sum. The tender rate shall include the supply, delivery and storage of all material. The rate shall include cutting, bending, waste, binding, and binding materials, and placing of all reinforcing elements as specified in drawings and specifications.

PPS C17.6.1 Damp proof membrane……………………………………………………………………………….. m²The unit of measurement will be in square meter. The tender rate shall include the supply, delivery and storage of all material. The rate shall include cutting, placing of all damp proof sheeting, sealing of joints and compensation for wastage as specified in drawings and specifications.

PPS C17.6.2 Damp proof sheeting - walls……………………………………………………………………………..mThe unit of measurement will be in running meter to the specified width. The tender rate shall include the supply, delivery and storage of all material. The rate shall include cutting, placing of all damp proof sheeting, sealing of joints and compensation for wastage as specified in drawings and specifications.

MASONRY WORKS

PPS MS1 BRICK AND BLOCK WORK

PPS MS1.1 CEMENTCement shall be as described in PPS 4.

PPS MS1.2 SANDSand shall comply with the requirements of SABS Specification 1090, unless specialist advice is obtained. A sample of 25 kg must be delivered to the Departmental Laboratory for testing purposes.

PPS MS1.3 BURNT CLAY BRICKSBurnt clay bricks shall comply with the requirements of SABS Specification 227, and shall be equal in all respects to the selected samples.Clay bricks for foundations shall be as described as above, but extra hard burnt.Where bricks with holes are used, the holes in such bricks must only be filled in solid with mortar where specifically specified. All bricks that do not carry the SABS Mark, must be approved by the Departmental or sent to an approved laboratory at the cost of the contractor.

PPS MS1.4 CONCRETE BLOCKSStandard No M6 (390 x 190 x 190 mm) concrete building blocks that are vermin proof will be used for all outside walls and must comply with SANS227 / SANS 285 / SANS 987 or SANS 527 codes.Standard No M5 (390 x 140 x 190 mm) concrete building blocks that are vermin proof will be used for all inside walls and must comply with SANS227 / SANS 285 / SANS 987 or SANS 527 codes.

PPS MS1.5 CEMENT MORTARCement mortar shall be composed of 5 parts (by volume) of sand and 1 part (by volume) of cement. The material shall be mixed dry until of uniform colour and then water added and the mixture turned over until the ingredients are thoroughly incorporated. Cement mortar shall be produced in such quantities as can be used before commencing to set as no cement mortar that has once commenced to set shall be used in any way.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 58: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Care shall be taken in mixing cement mortar to remove from the mixing machine or platform any old mortar that has already set as such mortar may not be incorporated into any new batch.

PPS MS1.6 VENTILATION BRICKSStandard vermin proof ventilation airbricks shall be used and must comply with relevant SANS specifications.

PPS MS1.7 BRICKWORKBrickwork, wherever practicable, shall be built in English bond. No false headers shall be used and none but whole bricks employed, except where legitimately required to form bond. Brickwork shall be built level and plumb with mortar as specified. The bricks shall be laid on a solid bed of mortar and all joints thoroughly grouted up solid throughout the whole width of each course.The brickwork shall be carried up in a uniform manner, no one portion being raised more than 1,2 m above another at any one time.

Clay bricks shall be well saturated with water, in the stack or dump, approximately 2 hours before being used. The tops of walls left unfinished shall be well wetted before work recommences.

NB: Cement or concrete bricks shall not be wetted.

All rough and fair cutting, cutting of splays, skewbacks, chamfers, etc. shall be properly performed. Form or leave all necessary openings for pipes etc. and make good after pipes etc. are fixed in position.

PPS MS1.8 BUILDING INEnds of timbers, holdfasts, cramps, gratings, air bricks, dowels, etc. shall be built-in in cement mortar.Door and window frames, lift door frames and the like shall be set up in position for building in and securely strutted to prevent distortion whilst the brickwork, lintels, etc. are being built.Pressed steel door frames and lift door frames shall be grouted in solid at back with cement mortaras the work proceeds.Wood slips, fixing bricks, hoop iron roof ties, etc. shall be built in as the work proceeds.

PPS MS1.9 BLOCK / BRICK REINFORCINGUnless otherwise described, block and brick work reinforcement is to of approved SA manufactured welded high-tensile steel wire reinforcing fabric of the width stated, cut to length and lapped full width at corners and passing. Rate shall be included in the rate of brick and block work, built into walls at every third layer.

PPS MS1.10 BEARING PLATES ON WALLSBearing plates shall be bedded in mortar similar to that used in masonry work, and shall be set level.

PPS MS1.11 SECURING OF ROOFSRoof trusses shall be fixed at each support to walls with ties of 1,6 mm thick galvanised hoop iron, 32 m wide, built 750 mm deep into brickwork or embedded 300 mm deep into concrete or wrapped around bottom layer of reinforcing in a reinforced concrete beam and wrapped over truss and fixed with four galvanised nails, 40 mm long.

PPS MS2 DAMP-PROOF COURSEThe horizontal and vertical damp-proof course shall be of black polyethylene sheeting complying with SABS Specification 952 Type B having embossed surfaces, 0,38 mm thick (375 microns) and manufactured in widths of less than 1000 mm.

The damp-proof course shall be the full thickness of walls above foundations, plus the width of floor plates where these occur, and shall be laid without longitudinal joints. At end joints, angles and intermediate junctions the sheeting shall be lapped for 150 mm.

Where so required all laps in the damp-proof course shall be sealed over the whole area of laps as recommended by the Manufacturer. Care shall be taken not to tear or otherwise damage the sheeting.Similar damp-proof course, 120 mm wide x 250 mm long, shall be laid on sleeper piers under the floor bearers.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 59: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Similar damp-proof course, but in unbroken lengths, shall be laid behind all window sills, sealed with an approved bituminous solution to the back of the sills and taken down within the thickness of the wall and under the first full course of external brickwork.

PPS MS3 PLASTERING

PPS MS3.1 CEMENT PLASTERCement plaster for 1 coat work on brickwork shall be composed of 4 parts of sand to 1 part of cement for internal work and 5 parts of sand to 1 part of cement for external work, all measured by volume, and mixed as described for cement mortar.

PPS MS3.2 THICKNESS OF PLASTERPlaster on walls shall be not less than 12 mm or more than 20 mm in thickness and plaster on concrete ceilings and beams shall not be less than 9 mm or more than 16 mm in thickness.

PPS MS3.3 APPLICATION OF PLASTERWalls shall be well wetted before plastering is commenced.

The surfaces of plastered walls internally shall be steel trowelled to a smooth, even and true finish. All external plaster shall be finished to a true and even surface with a wood float. All plaster surfaces shall be free from blemish.

Plaster shall be returned into reveals and soffits of openings and all angles shall be true and straight with salient angles slightly rounded.

The rendering coat of plaster in two coat work shall be approved by the Representative/Agent before the setting coat is applied and notice shall be given to the Representative/Agent when the plaster is ready for inspection.

All cracks, blisters and other defects shall be cut out, made good and the whole left perfect at completion.

PPS MS4 MEASUREMENT AND PAYMENT:

Item Unit

PPS MS4.1Foundation walls (Brick work)..……… …………………………………………………………………m²The unit of measurement shall be in square meter in cement mortar as described, including brick force work. The tender rate shall include full compensation for the supply of labour, materials, placing, cutting, wastage, reinforcing, bracing and protection of work during construction.

PPS MS4.2Outer and inner walls (Block work)..……… ……………………………………………………………m²The unit of measurement shall be in square meter in cement mortar as described, including brick force work. The tender rate shall include full compensation for the supply of labour, materials, placing, cutting wastage, reinforcing, bracing and protection of work during construction.

PPS MS4.3 Damp proof membrane………………………………………………………………………………….. mThe unit of measurement will be in square meter. The tender rate shall include the supply, delivery and storage of all material. The rate shall include cutting, placing of all damp proof sheeting, sealing of joints and compensation for wastage as specified in drawings and specifications.

PPS MS4.4Ventilation bricks..……… ………………………………………………………………………………NoThe unit of measurement shall be in number in cement mortar as described, including brick force work. The tender rate shall include full compensation for the supply of labour, materials, placing, reinforcing, bracing and protection of work during construction.

PPS MS4.5Plaster work…………………….…… ……………………………………………………………………m²

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 60: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The unit of measurement shall be in square meter for all plaster work. The tender rate shall include full compensation for the supply of labour, materials, placing, and wastage, finishing, and clearing of wastage.

WINDOWS / DOORS / FITTINGS

PPS F1 STEEL WINDOWSSteel windows shall be in accordance with SABS 727 and additions shall comply with the following:

Suitable weather bars shall be provided to bottom of opening in and vertically pivot hung ventilators and also to the bottom of all opening out ventilators where they occur above other ventilators and elsewhere as may be required to render the opening sections watertight.

Windows and components, shall, before leaving the Manufacturer's works, be cleaned by acid pickling, rinsing and drying, all as laid down in SABS Code of Practice 064, or by other approved means, to removeall scale, rust, grease, oil and foreign matter and then primed with red oxide zinc chromate primer complying with the requirements of SABS Specification 909, applied by dipping or by means of a spray gun.

Windows shall be fitted with brass handles, stays, catches and other fittings having polished finishand those to all other windows tumbled finish. The fittings shall be fixed in such a way as to be removable after windows have been glazed.

After the windows have been built in, but before being glazed, they shall be overhauled, adjusted as necessary and left in good order.

All windows shall be of type SS33, as specified in drawings.

Glass in panes not exceeding 0, 65 m2 of surface area shall be clear float glass of "GG" quality (Glazing quality) and of 3 mm thickness.

The glazing and fixing of glass in buildings shall be carried out in strict accordance with SABS Code of Practice 0137.

PPS F2 PRESSED STEEL DOOR FRAMESPressed steel door frames shall be of an approved South African manufacturer, constituting of mild steel cold-rolled sheet 1,63mm thick for single rebated frames and 1,22mm thick for double rebated frames. Rebate sizes suitable for standard 44mm thick timber doors.

Members to be accurately bent to profile, and corners mitred and welded and reinforced. 1.63mm thick adjustable 228mm long corrugated lugs with end split and bent for building in are to be supplied with every frame, three at each side.

The frames must be grease, scale and rust free, and painted with one coat of zinc-chromate primer, in the factory.

PPS F3 HARD WOOD DOORSRed meranti hard wood doors, 40mm thick, will be of a solid construction, with a flush finish on the outer face. Doors to be fitted with a SABS approved locking mechanism, pre-approved by the engineer. No two locks will have inter-changeable keys, and all are to have duplicate keys.

PPS F4 STEEL ROLLER SHUTTER DOORA heavy duty steel roller door for the opening of 2200 x 2300mm to be fitted flat against surface of opening andconsist of curtain, vertical guides and overhead mechanism. The Roller shutter door shall be of SerrandaGrande or equal approved manufacture, constructed of galvanized steel components.

PPS F5 PURPOSE MADE SLIDING DOORS

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 61: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The animal entrance sliding doors to be manufactured as specified on drawings, and fitted flush to inside of wall.To be free of rust, and coated with two coats of zinc-chromate primer. The mechanism to operating smoothly,and lubricated.

PPS F6 WATER TANK, TANK BASE AND PIPINGThe 5000 liters polythene water tank shall be manufactured from LLDPE, UV stabilized raw materials, and comply with F&DA regulation 177.1520 for food contact application, and carry a minimum five (5) year manufacturer’s guarantee. The tank must be supplied with at least a 40mm inlet connector at the top, a 40mm outlet connector at the bottom, and a 450mm lid. The tank must be supplied with a 25mm outlet adaptor at its bottom and connected to roof gutters, securely mounted on the stand.

The tank base shall be constructed as per specifications on the drawing. All specifications applicable under concrete work, and masonry work will apply.

All water installations must be neat and watertight without any leakages and be tested. The stand must be constructed to the specification on the plan to a height of at least 0.6m high. The water tank must be securely tied down and mounted on the stand and must have a 25mm tap.

PPS F7 MEASUREMENT AND PAYMENT:

Item Unit

PPS F7.1Windows ………...……… …………………………………………………………………………………NoThe unit of measuring the windows will be in number, measured as fitted and glazed.The tendered rate will be in full compensation for material and transport fitment, glazing and labour.

PPS F7.2Steel door frames...……… …………………………………………………………………………………NoThe unit of measuring the door frames will be in number, measured as fitted. The tendered rate will be in full compensation for material and transport fitment, and labour.

PPS F7.3Hardwood doors.....……… …………………………………………………………………………………NoThe unit of measuring the doors will be in number, measured as fitted. The tendered rate will be in full compensation for material and transport fitment, and labour, including fittings and locking mechanisms.

PPS F7.4 Purpose made sliding doors………………………………………………………………………………..NoThe unit of measuring the doors will be in number, measured as fitted. The tendered rate will be in full compensation for material and transport fitment, and labour, including fittings and locking mechanisms.

PPS F7.5Steel roller shutterdoor………………………………………………………………………………………NoThe unit of measuring the doors will be in number, measured as fitted. The tendered rate will be in full compensation for material and transport fitment, and labour, including fittings and locking mechanisms.

PPSF7.6. 5000liter water tank and fittings……………………………...……………………………………………NoThe unit of measuring the tank will be in number, measured as fitted. The tendered rate will be in full compensation for material and transport fitment, and labour, including fittings and plumbing work.

PPS F7.7Water tank base …….…… …………………………………………………………………………………NoThe unit of measuring the tank base will be in number, measured constructed. The tendered rate will be in full compensation for material and transport construction, and labour according to drawings and specifications.

PAINTING

PPS P1 PAINTING - GENERALAll surfaces to be painted will be filled in where necessary with an appropriate filler, brushed down, sanded and washed where necessary to ensure clean, dust, stain and oil free surfaces. All surfaces to be sufficiently dry, and inspected by the engineer before painting may commence.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 62: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Where special brands of paint are to be used, the manufacturer`s prescriptions regarding priming, cleaning and applying will be followed. Where ever possible paint to be used must be from South African manufacturer.

All colours and tints and type of paint used, are to be selected and/or approved by the engineer, before painting commence.

The Contractor shall provide all necessary dust sheets, covers, etc. and shall exercise all necessary care to prevent marking surfaces, walls, floors, glass, electrical fittings, etc. and shall keep all parts of the works perfectly clean and free at all times from spotting, accumulation of rubbish, debris or dirt arising from the operations. Any surface disfigured or otherwise damaged shall be completely renovated or replaced as necessary by the Contractor at his own expense to the Representative/Agent's approval.

PPS P2 ON PLASTERED WALLSPlastered wall, after prepared to the satisfaction of the engineer, must first be painted with one coat of plaster primer (bonding liquid), and one coat of universal undercoat in accordance with SABS 681, and two finishing coats of Plascon Wall and All with Teflon, or similar approved paint. The same procedure to be followed both on internal and external walls.

PPS P3 ON METAL SURFACESPPS P3.1 WINDOWS AND DOOR FRAMESPrepare as described, tough up where necessary with one coat of red oxide steel primer, one coat of universal undercoat in accordance to SABS 681, and two finishing coats of Plascon Polyurethane enamel or similar approved paint.

PPS P3.2 PURPOSE MADE SLIDING DOORSPrepare as described and paint with two coats of red oxide steel primer.

PPS P4 ON WOODEN SURFACESPrepare as previously described and apply with two coats of Dulux clear exterior varnish, or similar approved product.

PPS P5 APPLICABLE SABS CODES(i) High gloss enamel paint: SABS Specification 630.(ii) Oil gloss: SABS Specification 631.(iii) Flat and eggshell: SABS Specification 515.(iv) Emulsion paint (interior): SABS Specification 633, Grade I.(v) Emulsion paint (exterior): SABS Specification 634 Synthetic Polymer Base Type, but pure aery lie resin base for fibre cement surfaces.(vi) Aluminium paint: SABS Specification 682, Grade II.(vii) Roof paint: Alkaline type SABS Specification 683, Type B.(viii) Structural steel paint: SABS Specification 684, Type B.(ix) Textured wall coatings, emulsion base, for interior and exterior use: SABS Specification 1227.

PPS P6 MEASUREMENT AND PAYMENT:

Item Unit

PPS P6.1Walls: Plaster primer .......................................................................................................................m²The unit of measurement shall be in square meter of paint on plastered surfaces for both internal and external walls. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PPS P6.2Walls: Universal undercoat ..................................................................................................................m²

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 63: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The unit of measurement shall be in square meter of paint on plastered surfaces for both internal and external walls. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PPS P6.3Walls: 2 finishing coats .......................................................................................................................m²The unit of measurement shall be in square meter of paint on plastered surfaces for both internal and external walls. The tendered rate shall include full compensation for all materials, transport and labour as per specification. PPS P6.4Windows and door frames ................................................................................................................No.The unit of measurement shall be in number of windows and door metal frames for all paintwork as described under PPS 39.1. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PPS P6.5Doors ................................................................................................................................................No.The unit of measurement shall be in number of doors for all paintwork as described under PPS 40. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PPS P6.6Purpose made sliding doors..............................................................................................................No.The unit of measurement shall be in number of doors for all paintwork as described under PPS 39.2. The tendered rate shall include full compensation for all materials, transport and labour as per specification

ROOFING

PPS R1 THE ROOFThe roof design shall be outsourced by the contractor, at the cost of the contractor. Only pre-manufactured trusses shall be used, and the design and construction certified by a registered professional engineer. Any drawings shown in the tender drawings, are for illustrative purposes only.The roof must be a pitched roof with a minimum angle of 20°.The maximum truss spacing allowed is 1,2m.The maximum purline spacing allowed is 1m.Five full lengths of translucent sheeting shall be spaced evenly over the length of the roof on each side, for additional light in the structure.

PPS R2 PRE-FABRICATED ROOF TRUSSESPre-fabricated timber roof trusses shall comply with the requirements of SABS Specification 0163 and be constructed of South African pine as described, to the designs shown on the Manufacturer's detail drawings. The timber shall be of cross-sectional dimensions shown, cut to correct lengths with ends square or at the required angle. Trusses shall be assembled in truss fabricating jigs with the truss having the proper camber, all tightly clamped together with joints secured using approved connector plates of galvanised steel sheet. Connector plates shall be pressed into the timber simultaneously from both sides of the truss with a hydraulic press capable of exerting such pressure as will ensure complete penetration of the teeth into the timber. The connector plates shall be of such size as will ensure that the joints so made will adequately withstand the forces exerted on the joints.

In coastal areas connector plates in buildings without ceilings shall be painted with two coats of epoxy tar complying with SABS Specification 801 Type 2, or rust neutralising paint.

Approval of pre-fabricated roofing systems shall be subject to the following requirements:(a) The Manufacturer of the pre-fabricated trusses shall hold a certificate of competence issued by the Institute for Timber Construction.(b) A drawing, size A3 having a minimum thickness, shall be submitted by the Contractor to the engineer at an early stage for approval.(c) The drawings shall be signed by a Registered Professional Engineer.

The following minimum information shall be shown on the drawings:

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 64: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

(a) Details of the roof system with the position of the rafters and purlins indicated thereon as well as typical elevations.(b) Bracing as recommended by the Institute for Timber Construction.(c) Sizes and grading of the timber components.(d) Truss sizes, e.g. height of ridge or angle of pitch.(e) Plate sizes for every connection point. (Code numbers only are deemed insufficient.)(f) Separate connection details for hip, valley and jack rafters.(g) Maximum spacing for purlins to be as described in the specification in this document.(h) The type of roof covering as well as the design load.

Over and above the supervision undertaken by the Representative/Agent, the Truss Fabricator or his Design Engineer shall inspect the completed roof structure and issue a certificate of confirmation to the Department that:"The roof structure(s) has (have) been erected in accordance with the Design Engineer's drawings, as accepted by the Department, and the relevant details given in the manual "THE ERECTION AND BRACING OF TIMBER ROOF TRUSSES" issued by the National Timber Research Institute and the Institute for Timber Construction."Descriptions (prices) of pre-fabricated roof trusses shall be deemed to include design.

PPS R3 TIMBERAll timber that will be used in the roof structure must be SA pine, grade 5 preservative treated according to the standards of SANS 05. The grade stresses must comply with SANS 1783-2.

PPS R4 HURRICANE CLIPSHurricane clips must be used in the construction of the roof. Hurricane clips must be prefabricated units as supplied within the industry for timber construction. The hurricane clips must be galvanized to 275g/m².

PPS R5 FACIA BOARDSTreated coated timber or PVC or fibre cement fascia boards all around roof of 150 x 10 mm in dimension, to be securely fitted.

PPS R6 GUTTERS AND DOWN PIPES152 mm PVC half round gutters, 76mm down pipes, bends, fittings and must be UV resistant according to SANS standards. Pipes and tank end of building shall discharge into the tank. Pipes sloped evenly and well secured to wall.

PPS R7 ROOF SHEETING

PPS R7.1 CHROMADEK SHEETINGOnly Chromadek sheeting shall be allowed, of the IBR type, and a minimum sheet thickness of 0,5mm.

INLAND: Chromadeck standard shall be allowed, composed of hot-dip galvanized sheeting, pre-primed with an epoxy/chroma pre-primer 4-6 microns thick, and finished with a final paint coat of 20-22 microns thick on the top surface.

COASTAL:Chromadek PLUS shall be used, composed of hot-dip galvanized sheeting, pre-primed with primer 20-25 microns thick, and a finishing with a final paint coat 20-22 microns thick on the top surface.

The colour to be as specified by the engineer.

PPS R7.2 TRANSLUCENT SHEETINGOnly clear polycarbonate translucent sheeting shall be used, of the IBR type, and a minimum thickness of 1,2mm. The sheeting shall be UV-protected on at least the top side, with a minimum tensile strength of 70MPa.

PPS R8 MEASUREMENT AND PAYMENT:

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 65: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

Item

Unit

PPS R8.1Roof structure complete ………………………………………………………………………………… Sum The unit of measurement shall be in lump sum, for the complete roof structure. The tendered rate shall

include the design of the structure, all materials, timber, bracing, sheeting fasteners, labour, transport, inspection and certification fees as specified.

PPS R8.2Gutters …………………………………………………………………………………………………… Sum The unit of measurement shall be in lump sum, gutters. The tendered rate shall include full

compensation for all materials, transport and labour as per specification.

PPS R8.3Down pipes ……………………………………………………………………………………………… Sum The unit of measurement shall be in lump sum, down pipes. The tendered rate shall include full

compensation for all materials, transport and labour as per specification.

PPS R8.4Facia boards ……………………………………………………………………………………………… Sum The unit of measurement shall be in lump sum, gutters. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PIT TOILET

PPS P1 PIT TOILET

All applicable specifications and clauses will apply as for Earth work, Concrete work, Masonry work, Doors, and Paint Work, as previously specified in this document, and on the drawings.

Only the following addendums are applicable:

PPS P2 ROOF STRUCTUREThe roof shall be constructed as specified on drawings. All relevant specifications for sheeting, timber and fasteners shall be applicable, as specified in the Roofing section of this document.

PPS P3 PEDESTALThe toilet pedestal shall be a Jo-Jo VIP200, high quality PVC pedestal and seat, on similar approved by the engineer. The pedestal shall be secured and fitted strictly according to the manufacturer's instructions.

PPS P4 VENTILATION PIPEThe ventilation pipe shall consist of a 110mm PVC pipes and fittings, UV protected and complying to the relevant SANS specifications. The pipe shall be secured to the back of the toilet building, securely fitted and sealed in the concrete slab. The pipe shall be black, or painted black in order to improve airflow.

PPS P5 MEASUREMENT AND PAYMENT:

Item Unit

PPS P5.1Roof structure complete …………………………………………………………………………………SumThe unit of measurement shall be in lump sum, for the complete roof structure. The tendered rate shall include the all materials, timber, sheeting, fasteners, labour, and transport as specified.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 66: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PPS P5.2 Pedestal ……………………………………………………………………………………………………NoThe unit of measurement shall be number for the pedestals. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PPS P5.3 Ventilation pipes ………………………………………………………………………………………..…NoThe unit of measurement shall be in number for the ventilation pipes. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

DIP TANK, FOOT BATH AND ANIMAL HANDLING FACILITY

All applicable specifications and clauses will apply as for Earth work, Concrete work and Masonry work as previously specified in this document, and on the drawings.

PPS D1 DIP TANKThe dip tank shall be a pre-manufactured fibreglass dip tank, Poldale catch dip, or similar approved. Installation shall be done as follows:The excavation of the whole will be done into solid soil, and the material removed and disposed of according to the engineer's instruction. Care must be taken that the excavation is well shaped, and approximately 150mm larger than the dip tank on all sides. The bottom must be completely level.Spread a layer of washed river sand on the bottom of the excavation, making sure that it is level and that there is no stones in the sand.Place the pre-fabricated dip tank on the sand, ensuring that there is an even space all around, between the tank and the excavation.Now fill the space around the tank with dry washed river sand. Ensure that the sand fills the gap completely and that no voids are left.Pour the collar around the tank, as shown on drawing no. 4, with 20MPa concrete, ensuring that the edge of the tank is sealed in properly.Now the rest of the concrete floor of the entrance and exit pens can be casted.

PPS D2 CONCRETE FLOORClear the area of the entrance and exit pens of all organic and loose material, and ensure that it is shaped as prescribed in drawing no. 3. Compact the soil where necessary before casting the 20MPa floor, in blocks no bigger than 3 x 2m, according to the specification of concrete, as set out in the section for concrete work.

PPS D3 SUBGRADE GRAVEL COVERINGThe area as indicated on drawing no. 1, must be cleared of all organic material, and then covered with imported subgrade gravel material, spread evenly 75mm thick, and well compacted.

PPS D4 FOOTBATHThe footbath supplied shall be a pre-fabricated fibreglass footbath, with the approximate dimensions of 2.4m long x 225mm wide and 425mm high side walls. It shall be a Poldale footbath, or similar approved. The footbath is not a fixture, and must be supplied to the beneficiaries, whom must store it, for use when needed.

PPS D5 WATER CONNECTION AND HOSEThe water tank shall be fitted with a 20mm brass tap, with a screw-on hose connection. The beneficiaries must be supplied with a 20m, 20mm diameter, 5-year dragline hose, with the necessary fitting to connect to the water tank.

PPS D6 ANIMAL HANDLING FACILITYThe animal handling facility shall be constructed according to the layout as shown in the drawings. The fence lines of the animal facility, consist of two types of fences, marked XX and YY on the drawings. Care must be taken to construct fences strictly according to the specified type.

Posts shall be accurately set in holes and shall be provided with concrete basis to the dimensions shown on the drawings. Holes shall be dug to the full specified depth. All posts shall be accurately aligned and set plumb.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 67: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

After posts have been firmly set in accordance with the foregoing requirements, fence wires shall be attached thereto at the spacing shown on the drawings.

All fencing wire shall be tied to the sides of posts to prevent the wires from being displaced or becoming loose. The wire shall be carefully tensioned without sagging, and true to line, care being exercised not to tension the wire to such an extent that it will break, or that end, corner, straining or gate posts will be pulled out, or that it will be easily damaged during veld fires. A tension of 1,0 kN (kilo Newton) per wire shall be required as working stress. This stress will be determined seven days after erection.

Each strand of fencing wire shall be securely tied in the correct position hard up to each post with soft galvanized tying wire. The ends of the tying wire shall be wound at least four times around the fencing wire and post to prevent it from moving in a vertical direction.

At all straining posts at terminal points, gates, corners, and other specified positions, the fencing wire shall be securely wrapped twice around the post and secured against slipping by tying the end tightly around the wire by means of at least six snug tight twists.

Where high-tensile wire is used, two long twists may first be made followed by the six tight, snug twists around the post to prevent the wire from breaking at the first twist. When smooth wire is used, the loose end shall preferably be bent over and hooked into the notch between the fencing wire and the first twist.

Where netting wire is used in the fences, wire netting shall be stretched against the fence and properly tied to the fencing wire as shown on the drawings. The wire netting shall be secured by soft tying wire at 0,5 m centers along the top, middle and bottom wires.

Gates shall be erected at the positions indicated by the engineer. The gates shall be hung on gate fittings in accordance with the requirements shown on the drawings. Gates shall be so erected as to swing in a horizontal plane at right angles to the gate posts, clear of the ground in all positions. Clearance below the gates shall not exceed 75 mm with the gates closed.

PPS F1 FENCING

ALL STRAIGHT POLES SHALL BE ANCHORED FOR A MINIMUM DEPTH OF 600MM AND POLES WITH AND OVERHANG FOR A MINIMUM DEPTH OF 750MM

ALL GATES AND GATES RELATED MATERIAL SHALL BE HOT DIPPED GALVANISED AFTER MANUFACTURING.

TOP OF ALL CONCRETE BASES TO BE 20MM ABOVE GROUND LINE.

END POSTS REQUIRE ONE STAY ONLY

GATE POSTS SHALL BE A MINIMUM 100MM FOR FENCING HIGHER THAN 1.2M

FENCE HEIGHT SHOULD BE AT LEAST 1.8M HIGH, USING GALVANISED CAMPEON BARBED WIRE (315 X 2.5)

WELDED MESH ATTACHED TO TOP AND BOTTOM WIRES @ 150C/C WITH WITT- HARTCO CLIPS (ORSIMILAR APPROVED) WELDED MESH ATTACHED TO STRAINING WIRES @ 300C/C

DOUBLE GALVANISED GATE (5000MM WIDE)

FLAT WRAP SIZES500MM 700MM 915MM

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 68: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PPS D7 MATERIALSPPS D7.1 POSTS AND DROPPERS

Posts, stays, and droppers shall be of the type and size indicated on the drawings. Timber posts shall comply with the requirements of SABS 457. Timber posts shall be treated with a preservative in accordance with the requirements of SABS 1288 (Preservative treated timber) or SABS 05 (Creosote treated timber).

Droppers shall timber droppers and shall be treated with a preservative in accordance with the requirements of SABS 1288 (Preservative treated timber) or SABS 05 (Creosote treated timber).

PPS D7.2 Smooth wireSmooth wire shall comply with the requirements of SABS 675 and shall be of the types specified below:

Straining wire shall be 4,00 mm diameter fully galvanized zinc-coated high-tensile-grade steel wire.

Fencing wire shall be high-tensile-grade steel 2,24 mm diameter fully galvanized zinc-coated wire.

Tying wire shall be 2,50 mm diameter mild-steel fully galvanized zinc-coated wire for tying fencing wire to standards and droppers and 1,6 mm mild-steel fully galvanized zinc-coated wire for tying netting and mesh wire to the fencing wire.

PPS D7.3 WIRE NETTINGWire netting shall be fully galvanized mild-steel wire with a minimum diameter of 1,8 mm, with 75 mm hexagonal mesh. The width shall be as shown on the drawings.

PPS D7.4 GATES

Gates shall be manufactured to the dimensions and details shown on the drawings. Gates shall be complete in every respect, including hinges, washers, bolts and locking chains attached to the gate. Gates shall be zinc-coated as specified in SABS 763 for class B1 articles.

PPS D8 MANUFACTURING TOLERANCES FOR WIREThe actual diameter of wire supplied shall equal the specified diameter subject to the appropriate tolerance given in SABS 675.

PPS D9 MEASUREMENT AND PAYMENT:

Item Unit

PPS D9.1 Pre-manufactured dip tank ................................................................................................................No.The unit of measurement shall be in number. The tendered rate shall include full compensation for the supply, transport and delivery as specified.

PPS D9.2 Pre-manufactured footbath ................................................................................................................No.The unit of measurement shall be in number. The tendered rate shall include full compensation for the supply, transport and delivery as specified.

PPS D9.3 Water connection to dip tank ..........................................................................................................SumThe unit of measurement shall be in a lump sum. The tendered rate shall include full compensation for all materials, transport and labour as per specification.

PPS D9.4 Fence Type XX ............................................................................................................................... mThe unit of measurement shall be in running meter completed fence. The tendered rate shall include all materials, posts, concrete, wires and droppers, labour wastage as per running meter of fence, as specified in the drawings and specifications.

PPS D9.5 Fence Type YY ............................................................................................................................... m

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 69: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

The unit of measurement shall be in running meter completed fence. The tendered rate shall include all materials, posts, concrete, wires and droppers, labour wastage as per running meter of fence, as specified in the drawings and specifications.

PPS D9.6 Gates ...............................................................................................................................................NoThe unit of measurement shall be in number, according to the dimensions as indicated on the drawings. The tendered rate shall include full compensation for all materials, transport, fitment and labour as per specification.SHEARING EQUIPMENT

PPS EQ1 WOOL SORTING TABLEThe wool sorting table shall be specially manufactured with mild steel members, strictly as specified on drawings. The table shall have removable legs. All the ends of hollow members shall be closed off by adding end caps to members. The manufacturer shall take special care to ensure that there is no sharp edges, and that all welding and cutting edges are smoothed.

All mild steel members shall be prepared, and painted as specified in the Painting section, with two one coat of red oxide steel primer, and two coats of aluminium silver solvent based paint.

PPS EQ2 PIECE PICKING TABLEThe piece picking table shall be specially manufactured with mild steel members, strictly as specified on drawings. The table shall have removable legs. All the ends of hollow members shall be closed off by adding end caps to members. The manufacturer shall take special care to ensure that there is no sharp edges, and that all welding and cutting edges are smoothed.

All mild steel members shall be prepared, and painted as specified in the Painting section, with one coat of red oxide steel primer, and two coats of aluminium silver solvent based paint.

PPS EQ3 WOOL BINSThe wool bins will be manufactured with mild steel members, according to specifications on drawings. The wool bins shall be collapsible, and interlinked. Wool bins will be covered with 50 x 50mm wire mesh, or diamond mesh. The manufacturer shall take special care to ensure that there is no sharp edges, and that all welding and cutting edges are smoothed.

All mild steel members shall be prepared, and painted as specified in the Painting section, with one coat of red oxide steel primer, and two coats of aluminium silver solvent based paint.

PPS EQ4 WOOL BASKETSThe wool baskets shall be manufactured with mild steel members, according to specifications on drawings. Wool bins shall be fitted with four industrial type, swivel bearing casters on each corner, with a wheel diameter of at least 50mm. The manufacturer shall take special care to ensure that there is no sharp edges, and that all welding and cutting edges are smoothed.

All mild steel members shall be prepared, and painted as specified in the Painting section, with one coat of red oxide steel primer, and two coats of aluminium silver solvent based paint.

PPS EQ5 BALE LIFTING HOOKSBale lifting hooks shall be manufactured with 12mm mild steel round bar, bent and shaped as shown on drawing.

All mild steel members shall be prepared, and painted as specified in the Painting section, with one coat of red oxide steel primer, and two coats of aluminium silver solvent based paint.

PPS EQ6 SHEARING BOARDSShearing boards shall be manufactured of treated SA Pine grade 5 wood as specified on drawing. Member shall be attached with 50mm wood screws, counter sunk with no sharp extrusions. The boards will be sanded to a smooth finish, and all corners rounded to prevent injury to the animals.

PPS EQ7 MECHANICAL WOOL PRESS

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 70: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

A mechanical single base wool press, pre-approved by the engineer shall be supplied. The wool press shall be durable be fitted with heavy duty industrial casters to assist with moving the instrument. The press mechanism shall be heavy duty, with a minimum thrust of 5 tons on the plunger and operating smoothly. The system shall be such that it can be operated by one person.

The wool rack shall be at least 1,2m high and 700 x 700mm in width with hooks to attach wool bags. The wool rack shall be easily collapsible to assist with the removal of the bale. Side panels of the wool rack, shall be manufactured with W-shaped steel panels of not less than 2,5mm thickness.

The wool press shall be South African manufactured. The wool press shall have a one year defects guarantee, and the manufacturer shall be able to provide a after sales service within 5 working days, for the repair of defects.

The wool press shall be coated with at least one coat of red oxide steel primer, and two coats of high quality enamel paint.

PPS EQ8 WOOL SCALEThe wool scale shall be an industrial mechanical, movable (trolley), platform scale. The platform shall be at least 600 x 400mm or larger. The scale shall have a minimum weighing capacity of 250kg, weighing in minimum steps of 200g.

PPS EQ9 SHEEP SHEARSThe sheep shears shall be manual hand shears, shall be manufactured of high quality carbon steel, and shall be "Drummer boy 160mm(no.10)" shears, or similar approved.

PPS EQ10 DIP HOOK AND STAFFThe dip hook and staff shall be manufactured from 12mm mild steel round bar, bent and shaped as specified in the drawings. Care must be taken that ends are properly rounded with no sharp edges. The handle shall be manufactured of Eucalyptus wood and 2m in length, and securely attached to hook.

All mild steel members shall be prepared, and painted as specified in the Painting section, with one coat of red oxide steel primer, and two coats of aluminium silver solvent based paint.

PPS EQ11 DEMONSTRATION OF EQUIPMENTThe suppliers shall on delivery of the equipment, conduct a demonstration cession during which selected members of the community will be trained in the operation of all the equipment supplied. The supplier shall demonstrate the assembly, dismantling, adjusting and operation of all the equipment. The suppliers shall further train the community members on the maintenance of the equipment, and operational safety.

PPS EQ12 MEASUREMENT AND PAYMENT:

Item Unit

PPS EQ12.1Equipment ......................................................................................................................................NoThe unit of measurement shall be in number, of all the equipment as specified in this document, drawings and bill of quantities. The tendered rate shall include full compensation for all materials, transport, fitment and labour as per specification.

PPS EQ12.2Demonstration of equipment ..........................................................................................................NoThe unit of measurement shall be a lump sum for the demonstration cession. The tendered rate shall include full compensation for all materials, transport and time related items.

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 71: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

MONTHLY REPORT FORMS TO BE COMPLETED BY THE CONTRACTOR

Form Description

MATERIALS ON SITE

OVERALL PROJECT WORKER SCHEDULE

WEEKLY TASK WAGE REGISTER

LOCAL LABOUR AND MATERIAL SCHEDULE

NOTE: THESE FORMS ARE FOR INFORMATION ONLY DURING TENDER STAGE AND WILL ONLY NEED TO BE COMPLETED ON A MONTHLY BASIS BY THE APPOINTED CONTRACTOR ONCE THE CONTRACT IS AWARDED.

THE COMPLETION OF THESE FORMS BY THE APPOINTED CONTRACTOR IS MANDATORY AND PAYMENT CERTIFICATES WILL NOT BE PROCESSED IF THEY ARE NOT ACCOMPANIED BY THE PROPERLY COMPLETED FORMS

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 72: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

TRANSFER OF RIGHTS

CONSTRUCTION OF ZINGQOLWENI SHEARING SED: ELM/1/7/2017T CONTRACTOR: ……………………………………………………………………………………………………………..

CLAIM FOR PAYMENT NO: …………………………………… DATE: ………………………..

I, the undersigned, ………………………………………………………………………………………

in my capacity as …………………………………………………………………………………………………….

of …………………………………………………………………………………………………….

(hereinafter referred to as “the TRANSFEROR”) (I having been duly authorised hereto by virtue of Resolution of the Board of Directors of the Transferor passed on the . . . . . . . . . . . . . . . . .day of . . . . . . . . . 20. . . . . . . . . .) hereby warrant that the materials and goods listed are the Transferor’s bona -fide property, ownership of which vests in the Transferor, and I hereby transfer, cede and assign all the Transferor’s rights, title and interest in and to the said materials and goods unto and in favour of

………………………………………………………………………………………………………………………..

(hereinafter referred to as “the TRANSFEREE”). Insofar as the Transferor retains actual control of the materials and goods, the right of ownership thereof passes to the Transferee by constitutum possessorium.

This transfer shall become effective upon conclusion of the Transferor receiving payment from the Transferee or from any other person on behalf of the Transferee for the materials and goods as Materials on Site (payment of retention money thereon excluded).

I further confirm that I am fully responsible for all materials and goods listed under this transfer of rights and that they have been insured adequately against all risks and will remain insured until they are built into or used in the permanent works and taken over by the Employer.

TOTAL VALUE OF CLAIM FOR MATERIALS ON SITE IN ACCORDANCE WITH THE ATTACHED LIST :

………………………………………………………………………………………………………………………………

………………………………………………………………………………………………………………………………

……………………………………………………………………………( R ……………………………………………)

SIGNED: …………………………………………………………………………………………………………..

DATE: …………………………………………………………………………………………………………..

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 73: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

BID NUMBER ELM/1/1/2018TCONSTRUCTION OF INDWE FEEDLOT

C3 Scope of Work

PART : 1

CONTRACTOR MONTHLY REPORT

Project No: …………………. Project Name: ………………………….

Contract No: ………………..

Contractor Name: ………………………………………………………………………

Claim No: …………………….. For Period Ending: ………………………………

Date of Report: ……………………………….

The Contractors Monthly Report comprises an integral part of the Contractors Payment Claim and processing of the payment claim is not permitted without this report also being submitted i.e.

“NO REPORT – NO PAYMENT”.

Attachments:Part 2 Overall Project Worker Schedule: Schedule of all local labourers employed since the start of

the project

Part 3 Weekly Task Wage Register

Part 4 Local Labour Schedule

Contractor Witness 1 Witness 2 Employer Witness 1 Witness 2

Page 74: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACTELM/1/1/2018T

Construction of Indwe FeedlotC3 Scope of Work

19. OVERALL PROJECT WORKER SCHEDULE (local labourers only) Contract No: …………… PART 2Project No. ……………………………….. Project Name: …………………………………………………………………….Month of Report: ………………………………………………. Sheet: ………….. of ………….

Names of all Local Workers employed at any time on the project are to be entered in the table below irrespective of how long they worked on the project.No. Name of Local

LabourerIdentity Number Month

Worker Started

AgeTick if Yes

Place a tick in the box which corresponds to the Gender

andAge of the Worker

Fem

ale

Hea

d of

H

ouse

hold

with

D

epen

dant

s

Dis

able

d

Labo

urer

Sem

i-Ski

lled

Ski

lled

Sup

ervi

sor

Cle

rical

Man

ager

ial

Pro

fess

iona

l

Women Men

Over 25 yrs2A

25 yrs &

under2B

Over 25 yrs2C

25 yrs &

under2D

Totals for this sheetTotals from previous sheetTotals carried forward

(A) (B) (C) (D) (E) (F) (G) (H) (I)(J) (K) (L) (M) (N) = (J+K+L)

20.

Completed by: Name: …………………………… Signature:…………………………… Capacity …………………… Date:…..………..

Page 75: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACTELM/1/1/2018T

Construction of Indwe FeedlotC3 Scope of Work

21. WEEKLY TASK WAGE REGISTER (local labourers only) Contract No: ………………… PART 3

Project No. …………………….. Project Name: ……………………………. Week Ending: ……………………. Sheet:….. of ….Entries in this portion to be completed by Foreman Entries in this portion to be Completed by Contractor

No. Name of local worker

Day Tasks Worked Payment

Mon Tue Wed Thu Fri Sat Sun

Total DAY TASKS

worked this week

Rate per DAY TASK

Total Payment due

to Worker

Workers signature on receipt of

Payment

Date Payment Received by

Worker

Totals This SheetTotals Brought Forward From previous Totals Carried Forward

(A) (B)

Completed by: Name: ……………………. Signature: ………………… Capacity: ……………… Date: …………………….

Page 76: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

LOCAL LABOUR AND MATERIAL SCHEDULE PART 4Contract No: ……………….. Date of Report: ……………………………….

Project No: …………………. Project Name: …………………………………

Claim No: …………………….. For Period Ending: …………………………….

Contractor Name: ……………………………...………………………………………………

1. Summary of Day Tasks worked and Amount Spent on Local Labour this monthWeek No.

Week Ending Total Day Tasks /

Person Days Worked

Total Amount Paid

(Total of (A) from Form 4

for each week)

(Total of (B) from Form 4 for each

week)1 R2 R3 R4 R5 R6 R

Total R

2. Summary of Amount Spent on Local Labour to date1. Previous Amount Spent on Local Labour (From previous claim) R2. Amount Spent on Local Labour this month (From Total above) R

3. Total Amount Spent on Local Labour to date (3)=(1+2) R

3. Local Labour Schedule Summary of Local Labour Employed No. of local

workers who worked on the project to date(From Part 2)

% of Total

Columns refer to Columns in Part 2

1. Total No. of individual local workers who have worked on the Project (Column N) 100%

10. How many of the Total No. are local youth (25 yrs and under) (Column B & D)

11. How many of the Total No. are local women (Column A + B)

4. Summary of Amount Spent on Material to Date (Cumulative)Item This Month Total to

date1. Material from Local Municipality

2. Material from Local District Municipality3. Material from Outside the Eastern Cape

4. Material from other areas within the Eastern Cape

Total Material

Total material as percentage of contractor expenditure

Total as percentage of contractor budget

5. Training of Local Workers

Page 77: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

Category of training Name of course No. trained Days trained Comments on

progress

(a) Technical training

for implementation

Bricklaying

Carpentry

Plumbing

Fencing

Plastering

Painting

House Building

Handyman

Electrical

(b) Institutional

training for local

management beyond

construction

(c ) Technical training

for OMM

(d) Institutional

training for

implementation

(e) HIV/ Aids etc.

Other – Please

specify

Total

Completed by: ………………………. …..……………………… …..………………. ……………………….

Name Signature Capacity Date

Page 78: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

EMALAHLENI MUNICIPALIY

ELM/3/11/2017TCONSTRUCTION OF INDWE FEEDLOT

C.4: SITE INFORMATION

Site information will be finalised at the time of the site meeting and forwarded to all parties involved.

C4.1 Tender Drawings

Page 79: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

C.4.1:LOCALITY PLAN

Page 80: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

C4.2:TENDER DRAWINGS

Tender drawings are issued separately in a Book of Reduced Drawings.

Page 81: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

EMALAHLENI MUNICIPALIY

ELM/1/1/20178T

CONSTRUCTION OF INDWE FEEDLOT

C5: APPENDICES

The following documents are attached hereto and form part of the Contract.

Appendix A Annex F (Normative) Standard Conditions of TenderAppendix B Emalahleni Municipality Supply Chain Management PolicyAppendix C Emalahleni Municipality Health and Safety Specification

Page 82: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

APPENDIX A:ANNEX F (NORMATIVE)

STANDARD CONDITIONS OF TENDER

Page 83: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

APPENDIX B:EMALAHLENI MUNICIPALITY

SUPPLY CHAIN MANAGEMENT POLICY

Page 84: All definitions, interpretations and general provisions for … -C3... · Web viewConcrete must be mixed only in an area demarcated for this purpose. All concrete spilled outside

THE CONTRACT

C3 Scope of Work

APPENDIX C:EMALAHLENI MUNICIPALITY

HEALTH AND SAFETY SPECIFICATION