  • Capacity Market Webinar

    Agreement Management – April 2016

  • Welcome

    Matthew MagillCapacity Market Manager

    Mark DuffieldEMR Delivery Manager

    Tushar SinghCustomer Account Manager

    2

  • Webinar Etiquette

    Calls on mute

    Q&A’s when requested

    Chat function in WebEx

    Email us [email protected]

    3

    mailto:[email protected]

  • Purpose for today...

    To take you through the upcoming AgreementManagement milestones and Statement of Works.

    Milestones include:

    Financial Commitment milestone

    6 monthly reporting of construction progress

    This webinar is primarily aimed at Capacity Agreement holders or thosewith an interest in understanding the milestones for

    New Build, Refurbishing, or Existing Generators, and / or Interconnectors

    4

  • Agenda

    Item Presenter

    Welcome

    Capacity Market update on EMR Delivery Body Matthew Magill

    Statement of Works Mark Duffield

    Upcoming Agreement Management milestones Tushar Singh

    Q&A

    Key Messages, Next Steps and Quick Poll Matthew Magill

    Close

    5

  • What is the Delivery Body doing at the moment?

    Expanding the size of the team for an additional auction is goingwell

    Interviewing for the enduring team

    Finalising the specifications for the System Operator Proceduresfor Stress Events

    Liaising with Stakeholders & Customers

    Developing and Testing Systems

    Talking to DECC about the outcomes of the consultations

    Preparing for Ofgem’s Rules consultation

    Running the ongoing Agreement Management activities

    6

  • Mark Duffield – EMR Delivery Manager

  • Statement of Works

    Aims to manage the cumulative impact ofdistribution connected generators on the wholesystem, including the transmission system

    Additional requirements / delays to connectionshave been triggered by recent volumes ofconnections in Wales and South of England

    Significant numbers of Distribution connectedgenerators with a CM agreement for 2018 or2019

    Action

    Check with your DNO if impacted by Statement of Works, even if youalready have a connection agreement

    Be aware if applying in this year’s auctions and planning on deferringprovision of a distribution connection agreement 8

    http://www.google.co.uk/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwj9uZ6O5JDMAhWKvhQKHQefAKkQjRwIBw&url=http://alfa-img.com/show/uk-outline.html&bvm=bv.119408272,d.bGs&psig=AFQjCNHz9SPyQzcnVQnb50L0J6tyMXLysg&ust=1460814224576412

  • Agreement Management Milestones

    Tushar Singh – CM Customer Account Manager

  • Financial Commitment Milestone

  • Financial Commitment Milestone – Rule 6.6

    Au

    cti

    on

    Ye

    ar

    CMU Type When(18 monthsafter theAuctionResults Day)

    What you need to provide…

    20

    14

    T-4 New Build &

    Refurbishing02/07/2016

    Assessment by Independent Technical Expert (ITE)as per the Required Technical Standard stating

    10% Capital Expenditure of the Total Project Spendhas been met

    OR Sufficient financial resources to meet Total Project

    Spend Capacity Provider has entered into a major contract

    ALONG WITH Directors’ resolution to complete project on or

    before start of Delivery Year Directors’ Certificate confirming sufficient financial

    resources and validity of the contract entered into

    20

    15

    T-4 New Build &

    Refurbishing22/06/2017

    11

  • Financial Commitment Milestone – Rule 6.6

    CMU demonstratesthat it..

    Delivery Body Settlement Body Applicant

    Has successfully

    met FinancialCommitment

    Milestone

    InformsSettlement Bodyand Applicant thatCredit Covershould bereturned.

    Updates CapacityMarket Register

    Returns CreditCover to theApplicant

    Gets CreditCover back

    Has not met

    FinancialCommitment

    Milestone

    TriggersTerminationNotice processinforming theApplicant,Secretary ofState, Ofgem andSettlement Body

    Issues invoice tothe Applicant forthe TerminationFee amount

    Pays Terminationfee of £5000/MW

    12

  • 6 Monthly Reports

  • 6 Monthly Progress Update Reports – Rule 12.2

    Au

    cti

    on

    Ye

    ar

    CMU Type When(every 6 months fromAuction date tillSubstantial CompletionMilestone is achieved)

    What you need to provide…

    20

    14

    T-4

    New Build &Refurbishing

    3rd report

    18/06/2016

    20

    15

    T-4

    New Build &Refurbishing

    1st report

    10/06/2016

    20

    15

    TA

    New Build

    1st report

    27/07/2016

    Progress Report including: Schedule of Construction

    Milestone dates and materialchanges

    Material changes to worksdescribed in the ConstructionPlan

    Assessment from ITE Directors’ Certificate

    14

  • 6 Monthly Progress Update Reports– Delivery Body Assessment

    Assessment

    ■ EMR Delivery Body will ask for missing/unclear items or further clarifications

    ■ If expected date to achieve SCM is beyond the Delivery Year, a Remedial Plan willbe requested.

    Remedial Plan – Rules 12.2.4 & 12.2.5

    ■ Should demonstrate the steps that can and will be taken to accelerate the buildprogram such that SCM is achieved by the start of the Delivery Year.

    ■ Must be accompanied by

    ■ A commentary from an Independent Technical Expert addressing whether theremedial plan is achievable; and

    ■ A certificate from 2 directors of the Capacity Provider stating that they believethe remedial plan is fair and achievable.

    ■ Must be provided as soon as reasonably practicable and within no more than 120days from the date of request.

    ■ Failure to provide a remedial plan will result in notification to the Secretary of Stateand Ofgem.

    15

  • Substantial Completion Milestone – Rule 6.7.2

    CMU Type SCM should beachieved by…

    What you need to provide…

    New Build

    Long Stop Date– 1 year after

    start of theDelivery Year

    Demonstrate that the: CMU is operational Physical generating capacity multiplied by

    de-rating factor ≥ 90% of Capacity Obligation

    Metering Assessment

    Line Diagrams

    Refurbishing

    Long Stop Date– date of thestart of the

    Delivery Year

    16

  • Matthew Magill, Capacity Market Manager

  • Key Messages

    There is a lot of work to do between now and Prequalification

    Statement of Works

    Check with your DNO (if impacted by Statement of Works) even if youalready have a connection agreement

    Be aware, if applying in this year’s auctions and planning on deferringprovision of a distribution connection agreement

    Agreement Management milestones

    Ensure you understand what is needed to achieve the FinancialCommitment, 6 Monthly Reporting and Substantial Completion Milestones

    We are here to support you and understand there is a lot of uncertaintyhowever we can build on all of our lessons learnt

    18

  • Guidance Documents

    https://www.emrdeliverybody.com/cm/home.aspx

    Achieving the Financial Commitment Milestone

    6 monthly progress reports

    Substantial Completion Milestone

    19

    https://www.emrdeliverybody.com/cm/home.aspxhttps://www.emrdeliverybody.com/Capacity Markets Document Library/Achieving the Financial Commitment Milestone.pdfhttps://www.emrdeliverybody.com/Capacity Markets Document Library/Achieving the Financial Commitment Milestone.pdfhttps://www.emrdeliverybody.com/Capacity Markets Document Library/Guidance on 6 Monthly Progress Reports Updated December 2015.pdfhttps://www.emrdeliverybody.com/Capacity Markets Document Library/Capacity Market - Meeting the Substantial Completion Milestone.pdf

  • Next Steps

    If you have an Agreement and are not sure of the next steps,please let us know & a member of the Capacity Market team willcontact you to discuss your specific requirements

    Slides will be made available

    Hold the Dates

    18 May – Amba Hotel, Charing Cross, London

    28 or 30 June - Venue TBC, London

    13 July - Amba Hotel, Charing Cross, London

    20

  • Contact us

    [email protected]

    https://www.emrdeliverybody.com/cm/home.aspx

    https://twitter.com/EMRDeliveryBody

    01926 655300

    21

    http://www.google.co.uk/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&ved=0ahUKEwjVlfan-snLAhUGRQ8KHVuHBegQjRwIBw&url=http://uxrepo.com/icon/mail-by-dripicons&psig=AFQjCNHXPY0BdVImxeEhe0D-mbnTSMFbzg&ust=1458380883730321&cad=rjthttps://www.google.co.uk/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwi8ve6p-8nLAhUHDA8KHUYXBV4QjRwIAw&url=https://www.iconfinder.com/icons/322538/internet_monitor_responsive_design_web_web_design_website_icon&psig=AFQjCNEUZjSso0-ax4h2whHhza-6GdXY6A&ust=1458381161467928mailto:[email protected]://www.emrdeliverybody.com/cm/home.aspxhttps://twitter.com/EMRDeliveryBody

  • Tell us what you think ….

    22

    Slide Number 1�WelcomeWebinar EtiquettePurpose for today...AgendaWhat is the Delivery Body doing at the moment?Slide Number 7Statement of WorksSlide Number 9Financial Commitment MilestoneSlide Number 11Slide Number 126 Monthly ReportsSlide Number 146 Monthly Progress Update Reports �– Delivery Body AssessmentSlide Number 16Slide Number 17Key MessagesGuidance DocumentsNext StepsContact usTell us what you think ….