agenda and background

12
ANSI-NIST Nuclear Energy Standards Coordination Collaborative David Matthews, Director, Division of New Reactor Licensing Larry Burkhart, Chief, AP1000 Projects Branch NRC’s Office of New Reactors July 23, 2013

Upload: ronald

Post on 22-Feb-2016

46 views

Category:

Documents


0 download

DESCRIPTION

ANSI-NIST Nuclear Energy Standards Coordination Collaborative David Matthews, Director, Division of New Reactor Licensing Larry Burkhart, Chief, AP1000 Projects Branch NRC’s Office of New Reactors July 23, 2013. Agenda and Background. Agenda - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Agenda and Background

ANSI-NISTNuclear Energy Standards Coordination

Collaborative

David Matthews, Director, Division of New Reactor LicensingLarry Burkhart, Chief, AP1000 Projects Branch

NRC’s Office of New Reactors

July 23, 2013

Page 2: Agenda and Background

Agenda and Background

Agenda• Background on status of AP1000 design review and licenses• New Reactor Designs/applications in the USA• Quick construction status – Vogtle and Summer AP1000s• Part 52 and lessons learned from a regulatory perspective

Background• Combined license – NRC authorization to construct and operate a nuclear power plant in

accordance with applicable laws, regulations, and conditions• Latest version of Westinghouse’s AP1000 standard design certified in December 2011• SNC, et al, received combined licenses for Vogtle Units 3 and 4 on February 10, 2012• SCE&G, et al, received combined licenses for Summer Units 2 and 3 on March 30, 2012• First Nuclear Concrete (FNC) for Summer Unit 2 poured 9 – 11 March 2013 • FNC for Vogtle Unit 3 poured 12 – 14 March 2013• 4 AP1000s under construction in China (Sanmen and Haiyang sites commenced in 2008) –

cooperation with China bilaterally and multilaterally• AP1000 design reviewed/under review in Canada, China, and the U.K. (MDEP)

2

Page 3: Agenda and Background

New Reactor ApplicationsUnder Review – Large LWRs+

3

ABWR

AP1000

EPR

ESBWR

USAPWR

+Large LWRs-- Large Light-Water Reactors, generally of the order of 1000 MW(e) or more

Page 4: Agenda and Background

Construction Status Vogtle

Vogtle Unit 3

4

Page 5: Agenda and Background

Part 52 - Fitting the Pieces Together

5

• Licensing decisions finalized before major construction begins• Inspections w/ITAAC (Inspections, Tests, Analyses, and Acceptance Criteria) to verify construction• Limited work may be authorized before COL issuance

Pre-Construction Construction Verification

Early Site Permit

Standard Design Certification

Combined License Review, Hearing,

and Decision

Verification of Regulations with ITAAC

ReactorOperationDecision

OptionalPre-Application

Review

LWA

Page 6: Agenda and Background

Lessons Learned in COL Reviews

First implementation of NRC’s 10 CFR Part 52 processes to issue COLs

• Bipartisan Policy Center Report (April 6, 2010)• Thorough and timely evaluation of license applications…however, there were

expected problems in navigating the new processes• The Commission should ensure the lessons learned are rigorously applied to

make the processing of subsequent applications more efficient• NRC’s Lessons Learned Review Report – April 213

• High quality applications with sufficient detail• Timely development and maintenance of regulatory guidance• Strong design standardization• Early identification and timely resolution of complex issues• Improve system of requests for additional information• Concurrent reviews of design certifications and combined license applications• Update to regulations incorporating lessons learned

6

Page 7: Agenda and Background

7

Current Licensing Basis

Definition of Licensing Basis (10 CFR 54.3)

• Obligations (Regulations, License Conditions, Technical Specifications, Environmental Protection Plan, and ITAAC)

• Mandated Licensing Basis Documents (FSAR, QA, EP, Security Plan, etc.)

Vogtle/Summer-FSAR:

• Summer — COL FSAR +Plant Specific DCD• Vogtle — ESP SSAR + COL FSAR + Plant Specific DCD

Page 8: Agenda and Background

8

FSAR

Plant –Specific DCD

Tier 1 Tier 2 Tier 2*

COL FSAR

E Plans QA

SecurityOp Programs

FFD

ESP SSAR(Vogtle Only)

E Plans Seismic

Hydrology

Page 9: Agenda and Background

Experience post-COL Issuance

First implementation of Part 52 processes (licensing basis maintenance) • License amendment (LARs), and exemptions, and ASME code relief requests

• LARs are expected as design evolves and due to in-situ conditions• Design changes to rebar (shear reinforcement details)• Turbine building bracing• Additional electrical penetration assemblies in the containment• Inconsistencies between Tier 1 and Tier 2• Other

• Preliminary Amendment Request (PAR) Process• Codified in license as an option for the licensee (following ISG-25)• Flexibility in making physical changes while licensing basis change is udner

review• Tied to an LAR• Obligation to construct in accordance with the licensing basis

• NRO is performing a self assessment of the experience during the first year of licensing Part 52 plants (with input from licensees, vendors, public, staff)

9

Page 10: Agenda and Background

Summary

• First implementation of Part 52 regulations to issue COLs and for post-licensing processes

• Vogtle and Summer licenses issued and construction ongoing• Experience gained in licensing pre and post COL isance

• A learning experience for regulator and licensee• Improvements can be made• Assessments to inform improvements

•Philosophy of Part 52 – Standardization• Importance of maintaining current licensing basis• Managing changes appropriately

• Proper change processes• Safety benefits• ITAAC completion• Safe operation

10OFFICIAL USE ONLY

Page 11: Agenda and Background

10 CFR Part 52

QUESTIONS?

www.nrc.gov/new-reactors/col-holder/html

11

Page 12: Agenda and Background

ACRONYMS

• CLB – current licensing basis• COL – combined license• DCD – design control document• EP – emergency plan• ESP – early site permit• FFD – fitness for duty• ITAAC – inspections, tests, analyses, and acceptance criteria• LAR – license amendment request• LWA – limited work authorization• LWR – light water reactors• SMR – small modular reactor• SSAR – site safety analysis report• UFSAR – updated final safety analysis report

12OFFICIAL USE ONLY