adtec pre no.20 april 09
DESCRIPTION
TRANSCRIPT
LAPORAN KEMAJUAN PROJEK NO.20
‘APRIL 2009’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 99.14%SEBENAR : 73.45%KESELURUHAN : -25.69%
TARIKH LAPORAN : 16 APRIL 2009
KEMAJUAN KERJA KEWANGAN
JADUAL : 99.26%SEBENAR : 74.19%KESELURUHAN : -25.07% @ 182 HARI
(LEWAT )
TARIKH LAPORAN : 16 APRIL 2009
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 99.12% 74.17% - 24.95%
APRIL 09’ 100% 85.77% - 14.23%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 83.25%
FIRE FIGHTING 100.00% 42.40%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 87.50%
SUBMAIN CABLE 100.00% 80.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 55.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA 100.00% 38.17%
SMATV 100.00% 28.33%
CCTV NA NA
ICT 100.00% 0.00%
DEWAN BESAR
DEWAN BESAR
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 95.00% 89.22% -5.78%
APRIL 09’ 100.00% 94.30% -5.70%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 87.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD NA NA
LPS NA NA
PA NA NA
SMATV NA NA
CCTV 100.00% 72.63%
ICT NA NA
LOBI UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 94.20% 74.34% -19.87%
APRIL 09’ 99.45% 81.81% -17.64%
MECHANICAL PLANNED
ACTUAL
AIR COND 62.86% 82.50%
FIRE FIGHTING 86.64% 7.73%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 56.25% 80.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 80.61%
PA 100.00% 34.76%
SMATV NA NA
CCTV NA NA
ICT 100.00% 0.00%
DEWAN KULIAH UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 96.79% 85.99% -10.80%
APRIL 09’ 100.00% 91.94% -8.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 82.76%
FIRE FIGHTING 100.00% 34.78%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 87.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 85.10%
PA 100.00% 41.75%
SMATV 100.00% 76.21%
CCTV NA NA
ICT 40.84% 4.84%
PUSAT SUMBER / PERPUSTAKAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 96.07% 83.49% -12.58%
APRIL 09’ 100.00% 88.93% -11.07%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 82.44%
FIRE FIGHTING 100.00% 40.30%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 55.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 79.94%
PA 100.00% 19.15%
SMATV 100.00% 69.40%
CCTV 100.00% 2.36%
ICT 100.00% 4.36%
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 94.82% 93.88% -0.95%
APRIL 09’ 100.00% 96.14% -03.86%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 0.00%
FIRE FIGHTING 100.00% 6.32%
KITCHEN EQUIP. 82.89% 18.00%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 10.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD NA NA
LPS 100.00% 66.47%
PA 100.00% 27.35%
SMATV 100.00% 67.06%
CCTV NA NA
ICT 100.00% 0.00%
KAFETERIA
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 95.07% 84.50% -10.56%
APRIL 09’ 99.67% 89.84% -9.82%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 66.97%
FIRE FIGHTING 100.00% 15.93%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 84.62%
PA 100.00% 50.29%
SMATV 100.00% 78.82%
CCTV 100.00% 37.46%
ICT 100.00% 0.00%
BENGKEL TEKNOLOGI MAKLUMAT
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 88.52% 90.27% 1.75%
APRIL 09’ 99.20% 94.41% -4.79%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 80.11%
FIRE FIGHTING 100.00% 45.37%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 100.00% 75.00%
DUST CONTROL NA NA
PROCESS COOLING
100.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 85.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 91.49%
PA 100.00% 56.22%
SMATV NA NA
CCTV 100.00% 55.21%
ICT 89.05% 2.35%
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 87.48% 91.18% 3.70%
APRIL 09’ 99.13% 94.65% -4.48%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 78.34%
FIRE FIGHTING 100.00% 32.95%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 100.00% 75.00%
DUST CONTROL 100.00% 24.40%
PROCESS COOLING
100.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 87.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 85.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 82.52%
PA 100.00% 48.47%
SMATV NA NA
CCTV 100.00% 56.15%
ICT 94.14% 1.16%
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 81.17% 90.55% 9.38%
APRIL 09’ 98.21% 92.30% -5.91%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 78.29%
FIRE FIGHTING 98.01% 33.30%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 100.00% 75.00%
DUST CONTROL 100.00% 9.09%
PROCESS COOLING
100.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 85.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 89.38%
PA 100.00% 49.95%
SMATV NA NA
CCTV 100.00% 63.51%
ICT 100.00% 2.36%
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 91.91% 83.93% -7.97%
APRIL 09’ 99.71% 91.02% -8.70%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 59.54%
FIRE FIGHTING 100.00% 21.39%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 100.00% 75.00%
DUST CONTROL 100.00% 29.45%
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 55.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 81.69%
PA 100.00% 39.94%
SMATV 100.00% 45.52%
CCTV 100.00% 44.98%
ICT 100.00% 0.00%
BENGKEL KEJ. JAMINAN KUALITI
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 89.92% 87.86% -2.06%
APRIL 09’ 98.51% 90.05% -8.47%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 81.50%
FIRE FIGHTING 100.00% 11.16%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 100.00% 75.00%
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 25.00%
LUMINAIRE 100.00% 55.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 84.16%
PA 100.00% 47.63%
SMATV 100.00% 61.66%
CCTV 100.00% 58.47%
ICT 89.84% 0.00%
BENGKEL MIKRO ELEKTRONIK
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 95.86% 96.63% 0.77%
APRIL 09’ 100.00% 96.79% -3.21%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 90.40%
PA NA NA
SMATV 100.00% 35.86%
CCTV 100.00% 37.80%
ICT 100.00% 90.00%
KUARTERS KELAS ‘B’
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 95.03% 96.71% 1.68%
APRIL 09’ 100.00% 96.94% -3.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 90.63%
PA NA NA
SMATV 100.00% 27.51%
CCTV NA NA
ICT 100.00% 62.02%
KUARTERS KELAS ‘C’
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 92.69% 96.33% 3.63%
APRIL 09’ 100.00% 96.38% -3.62%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 91.85%
PA NA NA
SMATV 100.00% 35.86%
CCTV NA NA
ICT 100.00% 90.00%
KUARTERS KELAS ‘C’ + ‘D’
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 85.15% 94.13% 8.98%
APRIL 09’ 99.68% 94.20% -5.48%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 88.80%
PA NA NA
SMATV 100.00% 81.76%
CCTV NA NA
ICT 100.00% 67.18%
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 86.68% 93.87% 7.19%
APRIL 09’ 99.33% 93.98% -5.35%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G
(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 77.27% 100.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 88.80%
PA NA NA
SMATV 100.00% 81.76%
CCTV NA NA
ICT 100.00% 69.85%
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 98.39% 96.95% -1.44%
APRIL 09’ 100.00% 97.34% -2.66%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 75.00%
FIRE FIGHTING 100.00% 12.24%
KITCHEN EQUIP. 82.98% 18.00%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 75.00%
LUMINAIRE 100.00% 80.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 88.67%
PA 100.00% 51.18%
SMATV 100.00% 67.06%
CCTV NA NA
ICT 100.00% 1.40%
DEWAN MAKAN
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 92.69% 95.69% 3.00%
APRIL 09’ 100.00% 97.10% -2.90%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 10.00%
FIRE FIGHTING 100.00% 38.83%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 90.48% 90.00%
DB 22.22% 50.00%
LUMINAIRE 62.50% 90.00%
MAIN S/BOARD 43.75% 0.00%
LPS 100.00% 84.86%
PA 100.00% 57.78%
SMATV 100.00% 60.98%
CCTV 100.00% 37.44%
ICT 100.00% 73.53%
ASRAMA LELAKI A & B
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 90.09% 96.91% 6.82%
APRIL 09’ 99.99% 97.67% -2.32%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 10.00%
FIRE FIGHTING 100.00% 46.61%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 55.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 85.86%
PA 100.00% 54.28%
SMATV 100.00% 60.98%
CCTV 100.00% 35.21%
ICT 100.00% 78.12%
ASRAMA PEREMPUAN C & D
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 86.10% 84.06% -2.04%
APRIL 09’ 98.65% 92.10% -6.55%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 100.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB NA NA
LUMINAIRE 92.31% 25.00%
MAIN S/BOARD 100.00% 0.00%
LPS 95.12% 81.70%
PA 100.00% 27.47%
SMATV NA NA
CCTV NA NA
ICT NA NA
SURAU
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 99.03% 98.59% -0.45%
APRIL 09’ 100.00% 98.86% -1.14%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 100.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - ASTAKA
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 96.86% 69.95%
PA 100.00% 34.34%
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
ASTAKA
MONTH PLANNED ACTUAL AHEAD / DELAY
APRIL 09’ 100.00% 99.77% -0.23%
MECHANICAL PLANNED
ACTUAL
AIR COND 98.48% 83.47%
FIRE FIGHTING 100.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 80.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 85.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA NA NA
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
M&E PLANT ROOM – PUSAT SUMBER
BANGUNAN SOKONGAN
M&E PLANT ROOM - BENGKEL
DECORATIVE FENCE
BANGUNAN SOKONGAN
GARAJ KENDERAAN
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
WAKAF
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA – JALAN UTAMA
GELANGGANG PERMAINAN
GELANGGANG PERMAINAN
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION
BENGKEL MIKROELEKTRONIK – CLEAN ROOM
BENGKEL MIKROELEKTRONIK – CLEAN ROOM
• SEKIAN TERIMA KASIH