LAPORAN KEMAJUAN PROJEK NO.16
‘DISEMBER 2008’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 47.00%SEBENAR : 55.19%KESELURUHAN : 8.11% ( 59 HARI )
Jumlah Hari (Kontrak) : 729 hariJumlah Hari Terpakai : 569 hariBaki Hari Tinggal : 160 hari
TARIKH LAPORAN : 14 DEC 2008
KEMAJUAN KERJA KEWANGAN
JADUAL : 52.35%SEBENAR : 56.36%KESELURUHAN : 4.01% ( 29 HARI )
TARIKH LAPORAN : 14 DEC 2008
Graf Kemajuan Kerja Keseluruhan Sehingga 4/12/2008
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Bulan
Per
atu
s %
% Kem. Fizikal J adual
% Kem. Fizikal Sebenar
% Kem. Kewangan J adual
% Kem. Kewangan Sebenar
% Kem. Fizikal J adual 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 61.60 74.17 87.80 98.95 100.00
% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19
% Kem. Kewangan J adual 0.00 0.94 2.05 3.93 5.77 8.92 10.71 13.46 17.45 22.24 25.62 27.75 31.15 34.56 35.93 39.26 42.63 45.59 48.62 52.35 66.72 77.62 89.39 99.09 100.00
% Kem. Kewangan Sebenar 0.00 3.97 6.30 13.91 15.50 17.58 17.26 19.52 22.30 25.93 30.26 32.79 35.32 38.47 38.97 43.62 47.34 48.16 52.42 56.36
16/05/07 25/06/07 24/07/07 20/08/07 13/09/07 18/10/07 09/11/07 05/12/07 12/01/08 21/02/08 27/03/08 15/04/08 29/05/08 08/07/08 15/07/08 22/08/08 19/09/08 28/10/08 14/11/08 04/12/08 15/01/09 15/02/09 15/03/09 15/04/09 13/05/09
Actual Physical 55.19%
Actual Financial
56.36%
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 95.86% 52.30% - 43.56%
DEC 08’ 100.00% 63.63% - 36.44%
MECHANICAL PLANNED
ACTUAL
AIR COND 91.00% 40.34%
FIRE FIGHTING 93.52% 12.48%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 18.75%
SUBMAIN CABLE 100.00% 71.34%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 0.00%
PA 100.00% 1.37%
SMATV 100.00% 11.23%
CCTV 0.00% 0.00%
ICT 100.00% 9.06%
DEWAN BESAR
DEWAN BESAR
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 80.21% 69.50% -10.71%
DEC 08’ 88.19% 75.93% -12.26%
MECHANICAL PLANNED
ACTUAL
AIR COND - -
FIRE FIGHTING - -
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 22.67%
SUBMAIN CABLE 100.00% 99.03%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD
LPS
PA
SMATV
CCTV 93.74% 0.00%
ICT
LOBI UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 60.43% 60.85% 0.42%
DEC 08’ 66.43% 64.09% -2.34%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 55.34%
FIRE FIGHTING 7.73% 41.33%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 42.86% 10.72%
SUBMAIN CABLE 0.00% 87.62%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 41.11% 0.00%
PA 0.00% 1.13%
SMATV
CCTV
ICT 0.00% 9.24%
DEWAN KULIAH UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 76.47% 76.47% 0.00%
DEC 08’ 77.77% 79.99% 2.22%
MECHANICAL PLANNED
ACTUAL
AIR COND 24.16% 78.15%
FIRE FIGHTING 20.20% 60.84%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 51.13%
SUBMAIN CABLE 35.71% 87.84%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 59.20% 73.99%
PA 65.93% 20.18%
SMATV 78.44% 26.27%
CCTV
ICT 15.45% 4.33%
PUSAT SUMBER / PERPUSTAKAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 71.37% 70.99% - 0.38%
DEC 08’ 74.06% 76.86% 2.80%
MECHANICAL PLANNED
ACTUAL
AIR COND 11.02% 56.89%
FIRE FIGHTING 38.79% 32.96%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 67.86% 59.29%
SUBMAIN CABLE 0.00% 78.27%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 34.36% 37.62%
PA 8.87% 9.20%
SMATV 24.79% 20.00%
CCTV 0.42% 3.70%
ICT 5.90% 0.58%
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 67.09% 86.39% 19.30%
DEC 08’ 68.75% 88.90% 20.15%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 30.00%
FIRE FIGHTING 12.65% 22.60%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 78.67%
SUBMAIN CABLE 0.00% 99.15%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD
LPS 29.98% 0.00%
PA 0.00% 7.59%
SMATV 0.00% 0.00%
CCTV
ICT 0.00% 66.50%
KAFETERIA
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 71.69% 79.83% 8.14%
DEC 08’ 75.87% 83.53% 7.66%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 65.30%
FIRE FIGHTING 8.61% 32.10%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 42.86% 60.11%
SUBMAIN CABLE 0.00% 22.31%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 43.90% 47.76%
PA 0.00% 29.51%
SMATV 0.00% 23.92%
CCTV 0.00% 31.07%
ICT 0.00% 6.91%
BENGKEL TEKNOLOGI MAKLUMAT
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 64.52% 81.46% 16.94%
DEC 08’ 67.06% 84.11% 17.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 63.16%
FIRE FIGHTING 20.14% 49.93%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR 0.00% 45.04%
DUST CONTROL - -
PROCESS COOLING
0.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 65.15%
SUBMAIN CABLE 0.00% 77.15%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 41.58% 49.21%
PA 0.00% 19.79%
SMATV
CCTV 0.00% 24.63%
ICT 0.00% 16.58%
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 65.32% 76.84% 11.52%
DEC 08’ 67.85% 80.57% 12.73%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 55.57%
FIRE FIGHTING 14.83% 57.70%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR 0.00% 55.12%
DUST CONTROL 0.00% 22.50%
PROCESS COOLING
0.00 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 71.43%
SUBMAIN CABLE 0.00% 50.28%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 35.66% 54.32%
PA 0.00% 18.88%
SMATV
CCTV 0.00% 26.40%
ICT 0.00% 11.21%
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 66.86% 77.12% 10.26%
DEC 08’ 68.02% 79.88% 11.86%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 42.06%
FIRE FIGHTING 17.84% 52.91%
KITCHEN EQUIP.
LPG INSTALL.
COMPRES. AIR 0.00% 53.44%
DUST CONTROL 0.00% 22.50
PROCESS COOLING
0.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 60.60%
SUBMAIN CABLE 0.00% 83.20%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 35.85% 51.07%
PA 0.00% 16.59%
SMATV
CCTV 0.00% 26.40%
ICT 0.00% 16.64%
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 68.79% 69.12% 0.32%
DEC 08’ 70.13% 73.47% 3.35%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 52.80%
FIRE FIGHTING 13.15% 34.36%
KITCHEN EQUIP.
LPG INSTALL.
COMPRES. AIR 0.00% 7.38%
DUST CONTROL 0.00% 15.00%
PROCESS COOLING
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMIMAN KUALITI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 65.06%
SUBMAIN CABLE 0.00% 78.37%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 32.75% 61.56%
PA 0.00% 19.23%
SMATV 0.00% 15.70%
CCTV 0.00% 24.63%
ICT 0.00% 11.10%
BENGKEL KEJ. JAMINAN KUALITI
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 67.42% 65.00% -2.42%
DEC 08’ 68.59% 77.02% 8.07%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 64.34%
FIRE FIGHTING 7.77% 34.52%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR 0.00% 30.93%
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 44.68%
SUBMAIN CABLE 0.00% 3.22%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 35.45% 48.54%
PA 0.00% 18.85%
SMATV 0.00% 18.73%
CCTV 0.00% 21.63%
ICT 0.00% 6.10%
BENGKEL MIKRO ELEKTRONIK
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 68.88% 90.78% 21.90%
DEC 08’ 74.99% 95.35% 20.37%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING
KITCHEN EQUIP.
LPG INSTALL.
COMPRES. AIR
DUST CONTROL
PROCESS COOLING
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 69.05% 99.41%
SUBMAIN CABLE 0.00% 100.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 44.45% 0.00%
PA
SMATV 20.49% 36.35%
CCTV 10.80% 3.24%
ICT 48.30% 55.35%
KUARTERS KELAS ‘B’
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 61.32% 91.15% 29.83%
DEC 08’ 67.99% 96.06% 28.07%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING
KITCHEN EQUIP.
LPG INSTALL.
COMPRES. AIR
DUST CONTROL
PROCESS COOLING
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 30.95% 98.69%
SUBMAIN CABLE 0.00% 100.00%
DB
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 31.95% 0.00%
PA
SMATV 0.00% 40.63%
CCTV
ICT 0.00% 16.90%
KUARTERS KELAS ‘C’
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 62.06% 90.39% 28.33%
DEC 08’ 64.72% 95.45% 30.73%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING - -
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 66.67% 98.36%
SUBMAIN CABLE 0.00% 100%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 40.81% 0.00%
PA
SMATV 17.93% 39.12%
CCTV
ICT 41.77% 51.57%
KUARTERS KELAS ‘C’ + ‘D’
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 66.39% 84.39% 17.99%
DEC 08’ 70.42% 89.51% 19.09%
MECHANICAL PLANNED
ACTUAL
AIR COND - -
FIRE FIGHTING - -
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 46.67% 99.40%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 47.17%
MAIN S/BOARD 0.00% 0.00%
LPS 66.75% 37.51%
PA
SMATV 81.76% 53.54%
CCTV
ICT 74.84% 28.60%
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 66.37% 90.77% 24.40%
DEC 08’ 71.62% 92.42% 20.80%
MECHANICAL PLANNED
ACTUAL
AIR COND - -
FIRE FIGHTING - -
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 53.33% 89.71%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 48.16%
MAIN S/BOARD 0.00% 0.00%
LPS 71.49% 31.06%
PA
SMATV 82.18% 52.42%
CCTV
ICT 89.58% 28.60%
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 85.66% 90.71% 5.05%
DEC 08’ 93.89% 92.14% -1.75%
MECHANICAL PLANNED
ACTUAL
AIR COND 24.44% 85.00%
FIRE FIGHTING 14.96% 36.02%
KITCHEN EQUIP. 0.00% 0.00%
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 76.59%
SUBMAIN CABLE 100.00% 2.27%
DB 66.67% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 33.33% 0.00%
LPS 85.52% 0.00%
PA 100.00% 7.19%
SMATV 94.32% 55.86%
CCTV
ICT 100.00% 0.00%
DEWAN MAKAN
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 72.85% 85.86% 13.10%
DEC 08’ 76.37% 89.04% 12.68%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 10.00%
FIRE FIGHTING 32.86% 63.40%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 9.52% 79.75%
SUBMAIN CABLE 0.00% 23.22%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 41.42% 27.77%
PA 0.00% 12.71%
SMATV 0.00% 40.51%
CCTV 0.00% 17.84%
ICT 0.00% 6.14%
ASRAMA LELAKI A & B
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 62.51% 87.64% 25.13%
DEC 08’ 65.45% 90.09% 24.63%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 10.00%
FIRE FIGHTING 5.12% 66.42%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 26.19% 89.66%
SUBMAIN CABLE 0.00% 27.33%
DB 0.00% 0.00%
LUMINAIRE 0.00% 30.79%
MAIN S/BOARD 0.00% 0.00%
LPS 45.29% 27.77%
PA 0.00% 15.02%
SMATV 0.00% 40.51%
CCTV 0.00% 17.84%
ICT 0.00% 15.29%
ASRAMA PEREMPUAN C & D
MONTH PLANNED ACTUAL AHEAD / DELAY
NOV 08’ 56.66% 70.53% 13.86%
DEC 08’ 63.83% 71.39% 7.57%
MECHANICAL PLANNED
ACTUAL
AIR COND - -
FIRE FIGHTING 0.00% 0.00%
KITCHEN EQUIP. - -
LPG INSTALL. - -
COMPRES. AIR - -
DUST CONTROL - -
PROCESS COOLING
- -
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 10.55%
SUBMAIN CABLE 0.00% 100.00%
DB
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 32.45% 33.33%
PA 0.00% 3.25%
SMATV
CCTV
ICT
SURAU
BANGUNAN SOKONGAN
ASTAKA
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 67.81% 76.45% 8.63%
BANGUNAN SOKONGAN
M&E PLANT ROOM
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 65.37% 72.10% 6.73%
PEMBINAAN PINTU MASUK UTAMA
BANGUNAN SOKONGAN
GARAJ KENDERAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 76.36% 100% 23.64%
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
WAKAF
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA - JALAN
GELANGGANG PERMAINAN - FUTSAL
M&E INSTALLATION – PUSAT SUMBER
M&E INSTALLATION – PUSAT SUMBER
M&E INSTALLATION – PUSAT SUMBER
MAIN TNB SUB STATION
• SEKIAN TERIMA KASIH