admiralty inlet pilot tidal project · construction, monitoring, and operation of the project,...

51
ADMIRALTY INLET PILOT TIDAL PROJECT Marine Aquatic Resource Committee May 19, 2014 1

Upload: others

Post on 06-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

ADMIRALTY INLET PILOT TIDAL PROJECT

Marine Aquatic Resource Committee May 19, 2014 1

Page 2: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

MARC Members As stated in the FERC License, the MARC is comprised of: • Snohomish PUD (District) • National Marine Fisheries Service (NMFS) • U.S. Fish and Wildlife Service (USFW) • Washington Department of Fish and Wildlife (WDFW) • Washington Department of Ecology (Ecology) • Washington Department of Natural Resources (DNR) • Tulalip Tribes • Suquamish Tribe • Swinomish Indian Tribal Community • Sauk-Suiattle Tribe Additional members may be added by unanimous agreement by the MARC.

2

Page 3: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Purpose and Key Functions of MARC

• Purpose of MARC is to advise the District on aquatic resource issues related to construction, monitoring, and operation of the Project, including:

– Review results of project monitoring

– Review and comment on proposed changes to monitoring plans, as required and as necessary due to adaptive management triggers

3

Page 4: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Establishment of MARC

• No separate license article establishing MARC

• FERC is “requiring implementation of monitoring plans, including the consultation and adaptive management requirements.”

• FERC lacks authority to require any entity to participate, but requires the District to document consultation with MARC entities on specific monitoring plans

4

Page 5: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Adaptive Management Framework

• Purpose of meetings will be to review required consultation materials and discuss questions

• During project operation, MARC will review results of monitoring plan studies

• Group will follow the Adaptive Management Framework and seek to reach consensus when a vote is necessary; however some meetings will not require voting

5

Page 6: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

• Frequency of meetings will be determined by milestone events such as:

– Required consultation document is due

– Project monitoring results are compiled

– Monitoring plan changes are proposed

– Adaptive management trigger is initiated

6

Adaptive Management Framework

Page 7: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

MARC Consultation Requirements The FERC License requires consultation on any proposed changes to the following: • Acoustic Monitoring and Mitigation Plan (Article 404) • Benthic Habitat Monitoring and Mitigation Plan (Article

405) • Near-Turbine Monitoring and Mitigation Plan (Article 406) • Marine Mammal Monitoring and Mitigation Plan (Article

407) • Derelict Gear Monitoring Plan (Article 409) • In-water construction schedule (Article 410) In addition, development of the Project Removal and Site Restoration Plan is a condition of Ecology’s 401 WQC and requires MARC consultation.

7

Page 8: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

8

Project Installation Overview

Page 9: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Project Implementation Partners

9

PCCE Supply Sub-Contractor

Page 10: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

REGIONAL MAP

10

Page 11: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

OVERVIEW MAP

Marine Cables

HDD

11

Page 12: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

TURBINE DEPLOYMENT SITE

12

Page 13: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

OVERVIEW MAP

Marine Cables

HDD

13

Page 14: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

ONSHORE DETAILS

OVERVIEW

1. TRANSFORMERS 2. POWER CONTROL &

CONDITIONING BLDG. (PCCB)

3. BATTERY STORAGE SYSTEM

4. GRID CONNECTION EQUIPMENT

5. CONCRETE FENCED YARD

LESS BUSY

TO G

RID

14

Page 15: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

15

Power Conditioning and Control Building

Page 16: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

16

HORIZONTAL DIRECTIONAL DRILLING (HDD)

• 600 lineal feet under the shoreline environment

• Minimum 2-6” diameter conduits

• 19-meters – requiring shallow dive support

• Avoids conflicts with sensitive near-shore habitat

Page 17: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

DETAILED MARINE OPERATIONS

• Marine Operations separated into 3-discrete operations with limited coordination requirements:

Cable Installation (Qty-2) – By PWC

Turbine Deployment (Qty-2) – By OpenHydro

Cable Connection (Qty-2) – By PWC

17

Page 18: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Installation - PWC

18

• Barge of opportunity PWC Leased Self powered or Z-Drive tug powered

• Equipment spread PWC Leased, owned or fabricated

equipment

Typical Cable Lay Vessel

Page 19: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Installation - PWC

19

START HERE

HDD

Page 20: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

20

Cable Installation 1. Surface laid cable 2. 24-HOUR OPERATION 3. Standby Tugs onsite for entire duration 4. ROV Monitors Cable Installation 5. 35,000# cable working strength

Cable Installation – By PWC

Subsea Cable Skid (SCS)

ROV Support Vessel Cable Lay Vessel

ROV

Page 21: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Installation – By PWC

21

Cable-Lay Vessel continues operation until it reaches Admiralty Bay. Vessel is arranged into a 4-point moor near the HDD exit E

W

Acoustic Release Buoy

Preset 4-Point Mooring Anchors

& Lines CALM WATERS OF

ADMIRALTY BAY

Page 22: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

22

E

W

Small Assist Vessel

Cable Buoy Float

Blue Line: End of Main Export Cable to Shore Red Line: Main Export Cable from Turbine

Cable Installation – By PWC

HDD Pull Head (HPH)

Page 23: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

23

E

W

Shore Cable 1. Assist Vessel Arrives at End of HDD near Shoreline

Cable Installation – By PWC

HDD CONDUIT

Page 24: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Installation – By PWC

24

Shore Cable 1. Assist Vessel Arrives at Shoreline 2. Dynamometer Monitors Tension on CLV 3. Diver Monitors Installation at Bellmouth

Small Assist Vessel

Floatation Buoy

HDD Pull Head (HPH)

Existing HDD Pipe With Bellmouth

Pull Line

19 m

Page 25: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Installation – By PWC

25

Shore Cable 1. Assist Vessel Removes Floatation Buoys as Needed 2. Diver Monitors Cable Catenary and Directs Cable through

the HDD

Trunk Cable

Page 26: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

26

Shore Cable 1. Cable End Loop is Maneuvered Out of the Pan & Chutes 2. Excess Cable in Bay is Being Pulled Through HDD 3. Floatation Buoys are Being Removed at HDD End

Final Cable “Loop”

Cable Installation – By PWC

Page 27: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

27

Shore Cable 1. Final Cable Loop is Lowered Over Cable Chute 2. Assist Vessels Continue Monitoring Installation

Cable Installation – By PWC

Page 28: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

28

Shore Cable 1. Floatation Buoys are Removed at Each End. 2. Cable Catenary is monitored by Diver & Assist Vessels

Cable Installation – By PWC

Page 29: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

29

Shore Cable 1. Cable is Installed on Seabed in Final Position 2. Remaining Buoys are Removed as Cable End is Pulled Through HDD 3. Diver Monitors Installation

Cable Installation – By PWC

Page 30: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

30

Shore Cable 1. Final Cable Position 2. Remaining Slack is Removed from Cable 3. Second Cable is a repeat performance

Cable Installation – By PWC

Page 31: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Turbine Deployment By OpenHydro

31 “OpenHydro Installer” Barge

Tug

Page 32: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Legend:

Umbilical Cable

Barge Winch Cable

Marker Buoy

OpenHydro Arrives on Station. Unit positioned over site & lowered.

OpenHydro Turbine Deployment

32

Page 33: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Legend:

Umbilical Cable

Barge Winch Cable

Marker Buoy

Fine timing of positions using tug tow line & 2-drives. Direction of tide & flow is measured & monitored closely as assembly approaches sea floor.

33

OpenHydro Turbine Deployment

Page 34: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Legend:

Umbilical Cable

Barge Winch Cable

Marker Buoy

On bottom – Confirmation of positions, ensure unit is level & feet have not sunk. Release of hydraulics.

34

OpenHydro Turbine Deployment

Page 35: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Legend:

Umbilical Cable

Barge Winch

Marker Buoy

Recovery frame is now disconnected from the subsea base & raised back up to the barge.

35

OpenHydro Turbine Deployment

Page 36: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Connection By PWC

36

Cable Lay Vessel • Winch recovers each end • Performs system health check • Completes umbilical and cable connection

• Deploys connected in-line pressure vessel

Support Vessel • Operates ROV

• Monitors operations • Records final locations

Trunk Cable Umbilical Cable

Page 37: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Arrival Onsite 1. Barge Arrives During Weakening Flood 2. ROV is Deployed to Recover Line from Main Export Cable End 3. Modified Construction Barge Station Keeps

Cable Connection – By PWC

37

Modified CLV or Construction Barge

ROV

Subsea Cable Skid (SCS)

Page 38: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Recovery 1. ROV Maneuvers Towards Construction Barge

Cable Connection – By PWC

38

Page 39: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Retrieval 1. Linear Cable Engine (LCE) Winches in Cable

End to the barge platform. 2. ROV Maneuvers Towards Subsea Base

Cable Connection – By PWC

39

Page 40: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Retrieval 1. LCE Secures Cable End Aboard the Barge 2. System Health Check is Performed on Main Export Cable 3. Subsea Skid Remains on Seafloor for Future Use

Cable Connection – By PWC

40

FIBER LOW POWER HIGH POWER

Remove Flange Cover Plate

Fiber Test Continuity Test

Megger Test

Secured to LCE

Bend Restrictor

Page 41: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Tail Line Retrieval 1. ROV Releases cable from Integrated Capture Device (ICD) 2. ROV Recovers a Tag Line from the Cable Platform

Cable Connection – By PWC

41

ICD

TUSP

ROV Platform

Page 42: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Tail Line Retrieval 1. Linear Cable Engine Winches Cable Tail Towards Barge 2. ROV Docks at Subsea Base & Monitors the Cable Recovery

Cable Connection – By PWC

42

Weakening Flood

Page 43: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Tail Line Retrieval 1. Cable Tail is Brought Aboard the Barge 2. System Health Check is Performed on Cable Tail

Cable Connection – By PWC

43

FIBER LOW POWER HIGH POWER

Remove Flange Cover Plate

Main Termination Bottle

Armor Termination

Bend Restrictor

Fiber Test Continuity Test

Megger Test

Secured to LCE

Slack water

Page 44: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Redeployment 1. Barge Begins Lowering Cable in “S” Pattern 2. ROV Monitors Cable Placement on the Seafloor

Cable Connection – By PWC

44

Completed IPV Connection w/Bending Radius Protection”

Developing Ebb

Page 45: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Cable Connection – By PWC

45

Cable Redeployment 1. Connector Housing is Deployed on Seafloor 2. ROV Monitors Final Placement

Plan View of Installation

Developing Ebb

Page 46: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Commissioning Effort

• Coordinated Effort

Turbine System

Battery Storage System

Grid Connection System

Supervisory Control and Data Acquisition

46

Page 47: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Strobe

Hydrophone

ADCP

Camera

SeaEye Falcon ROV

Instrument Frame

Pilot-Scale Monitoring Objectives

Acoustic Characterization – turbine sound

Benthic Habitat – artificial reef

development, scour or sedimentation

around subsea base

Near-turbine – interactions between

aquatic species and turbine rotor

Marine Mammals – behavioral changes for

seals, harbor porpoise, and Southern

Resident killer whales in response to

turbine sound

Adaptive Monitoring Package (AMP)

47

Page 48: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

UNIVERSITY OF WASHINGTON RECOVERABLE AMP DEVELOPMENT

48 48

Page 49: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Project Schedule Overview

49

Page 50: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Upcoming MARC Consultation Items **next meeting date TBD**

• Monitoring Objectives – Brian Polagye

• Monitoring Plan revisions

• In-water construction schedule

50

Page 51: ADMIRALTY INLET PILOT TIDAL PROJECT · construction, monitoring, and operation of the Project, including: –Review results of project monitoring –Review and comment on proposed

Questions

51