addendum no. 1 june 23, 2017 - town of bloomfield ct · addendum no. 1 – june 23, 2017 filley...
TRANSCRIPT
F:\P1979\79235\C20\Bidding\Addendum 1\Addendum No 1_20170622.Docx
ADDENDUM NO. 1 – June 23, 2017
RE: Filley Park Restoration – Phase II: Pond & Stream Improvements
Bloomfield, Connecticut
FROM: Fuss & O'Neill, Inc.
146 Hartford Road
Manchester, Connecticut
TO: Prospective Bidders
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated June 2017. All instruction contained in this addendum shall be reflected in the Bid and will be made part of the Contract Documents when the Contract is awarded. It is the responsibility of contractors bidding the project to distribute copies of this addendum to all subcontractors, suppliers, and other entities providing quotations. Acknowledge receipt of this Addendum in the space provided, and provide a signed copy in with the sealed bid. Failure to do so may subject Bidder to disqualification. This Addendum consists of four (4) pages, with an additional fifteen (15) pages of attachments as follows:
1. A four page List of Attendees who attended the Pre-Bid Conference held at 1:00 p.m., E.S.T., on Tuesday June 14, 2017 at the Bloomfield Town Hall.
2. Revised Specification Section 05 52 10 – PIPE AND TUBE RAILINGS 3. Revised plan sheet CD-507: Decorative railing must be removable and lockable
INFORMATION DISCUSSED AT THE PRE-BID MEETING:
The entire site is in the 100-year floodplain. Requirements for managing flammable materials are
indicated in the bid documents.
A Water Control Plan Submittal must be made as indicated in the bid documents. The Plan will be
reviewed by the Town of Bloomfield and the Connecticut Department of Energy and Environmental
Protection.
Question: When is the anticipated construction start date?
Answer: Early August, 2017
QUESTIONS/INFORMATION REQUEST SUBMITTED IN WRITING:
Question: The notes on the plans indicate that the bridges are to be made of painted weathering
steel. While this can be accommodated, it is uncommon. Typically weathering steel is
unpainted, and if we are supplying a painted structure then generally it is painted over bare
carbon steel. Please clarify
ADDENDUM NO. 1 – June 23, 2017 Filley Park Restoration – Phase II Pond & Stream Improvements Page 2
F:\P1979\79235\C20\Bidding\Addendum 1\Addendum No 1_20170622.Docx
Answer: It is the stated goal of the project to provide a long-term installation that
requires minimal long-term maintenance with near zero short-term maintenance. As part
of that goal, painted weathering steel has been requested in the construction documents.
Question: Please indicate how many coats of paint will be required on the bridges. A 2-coat system is
typical; 3-coat systems are typically required on DOT projects.
Answer: Given the purpose of the bridge, a 2-coat system would be appropriate.
Question: Please clarify the safety railing requirements on the bridges. The plans indicate “pickets to
be horizontal cable wire” and to be painted black. This statement includes references to
multiple types of safety railings, including horizontal tubes, vertical pickets, and stainless
steel cable railings. Also, if they are to be stainless steel cables, typically these are not
painted. The specification says “standard rails by manufacturer” which could be
interpreted that the manufacturer can supply whatever they want
Answer: The intent is to use steel cables as the horizontal safety rails as noted on the
ConTech website and literature. These cables should be stainless, and can be left un-
painted. For both structures, standard safety rail spacing, pedestrian hand rails and all
attachments and related details should be appropriate for a pedestrian bridge per the
manufacturer’s standards and any applicable AASHTO or local regulations
Question: What is the required height of the safety railings on the bridges above the deck?
Answer: 54” minimum.
Question: Is a toe plate required on the bridges?
Answer: Toe plate would be appropriate for a pedestrian bridge. It should be painted
black to match the structure.
Question: Special provision section 1.1-A references a “bow truss” style for the bridges. Please
confirm that they are to be the Link style with a straight top and bottom chord, and two
diagonals per bay, as shown on plans and referenced in section 1.3-A of the spec.
Answer: A “Link”-style bridge with parallel top and bottom chords and two diagonal per
bay is appropriate.
Question: The deflection criteria for the bridges per special provision 1.3-D-4 is L/400 of the span
length. This is more stringent than AASHTO’s criteria of L/360. Please confirm it will be
acceptable to use AASHTO’s criteria.
ADDENDUM NO. 1 – June 23, 2017 Filley Park Restoration – Phase II Pond & Stream Improvements Page 3
F:\P1979\79235\C20\Bidding\Addendum 1\Addendum No 1_20170622.Docx
Answer: We would prefer the more stringent deflection of L/400 over AASHTO’s
minimum of L/360.
Question: AASHTO’s Pedestrian Guide Spec advises that pedestrian bridges with clear widths
greater than 10’ be designed for an H-10 (20,000 lb) vehicle load. Please confirm that the
H-10 load should be used and not the 10,000 lb load listed on the plans and specs.
Answer: Given the similar loading between the full pedestrian loading and the heavier
vehicle, the H-10 (20,000 lb) loading can be used for the 12’ wide “vehicular” bridge.
Question: Only 2.5” of concrete deck thickness is allowed on the bridges. At least 4” total concrete
thickness at a minimum will be needed, possibly as much as 6”, in order to accommodate
the required loading criteria. Will it be acceptable for the manufacturer to design the deck
with a greater concrete thickness?
Answer: More concrete could be applied if the manufacturer feels it is
required. However, the deck would still have to accept the brick pavers and drainage
details as noted on the plans, and the deck dams would need to be sized
appropriately. Further, the minimum bottom chord elevations noted on the plans for each
structure cannot be breached. It was anticipated that the manufacturer would consider the
entire deck system (pavers, bedding sand, concrete) as the deck and not the 2.5” of
concrete at the bottom alone.
Question: A 15 year warranty is required for the bridges per special provision section 1.7. The
industry standard is 10 years. Will it be acceptable for the 15 year requirement to be
reduced to 10 years?
Answer: Given the extra precautions taken on the structure (i.e. – painting weathering
steel), we would request that the warranty be extended to 15 years.
Question: The plans indicate that the deck slope on the bridges is to be cambered at 4%. Slope and
camber are different things; typically the camber is set at 1% which will keep all deck
slopes to less than 5% in order to ensure ADA compliancy. Will this approach be
acceptable?
Answer: As stated in the specifications 1.3.2, it is not the intention to slope the deck in
either direction (longitudinally or transversely) more than 5% per ADA. However, it is the
design intention to add exaggerated camber (up to 4%) to the structure to increase its low
chord elevations and to give the structures more definition when installed, as noted in the
“Deck Drainage Path” details on the plans. It was assumed (and literature indicates) that
the deck when installed would be parallel with the bottom chord of the truss, but if this is
not the case, the contractor shall not exceed slope limits as prescribed by ADA.
F:\P1979\79235\C20\Bidding\Addendum 1\Addendum No 1_20170622.Docx
ADDENDUM NO. 1 – June 23, 2017 Filley Park Restoration – Phase II Pond & Stream Improvements Page 3.1
Construction Drawing Set (i.e. the bid plan set): The Sheet Index on Sheet GI-001 of the Construction Drawing Set of the Bid Documents lists, as the last page of the set, a Sheet CD-510 (“Dam Construction Details”) in error. There is not, and there is not intended to be, a Sheet CD-510 in the Construction Drawing Set. All prospective Bidders are directed to ignore said reference to Sheet CD-510 in said Sheet Index.
ADDENDUM NO. 1 – June 23, 2017 Filley Park Restoration – Phase II Pond & Stream Improvements Page 4
F:\P1979\79235\C20\Bidding\Addendum 1\Addendum No 1_20170622.Docx
END OF ADDENDUM
Attachments: List of Pre-Bid Meeting Attendees (4 pages)
Revised Sheet CD-507 (1 page)
Revised Specification Section 05 52 10 Pipe and Tube Railings – Aluminum (10 pages)
BIDDER ACKNOWLEDGES RECEIPT OF ADDENDUM
I hereby acknowledge receipt of Addendum No. 1
Signature Date
(PRECAST SECTIONS)
01979235.C50
05/26/2016
TOWN OF BLOOMFIELD
DAM CONSTRUCTION DETAILS
FILLEY PARK RESTORATION
BLOOMFIELD CONNECTICUT
AS SHOWN
AS SHOWN
146 HARTFORD ROADMANCHESTER, CONNECTICUT 06040860.646.2469www.fando.com
SEALSEAL
SCALE:
DATUM:
VERT.:
HORZ.:
VERT.:
HORZ.:
PROJ. No.:
DATE:
MS
V
IE
W:
LA
YE
R S
TA
TE
:
DATENo.DESCRIPTION
DESIGNER REVIEWER
File
P
ath
: J:\D
WG
\P
79
\7
92
35
\C
50
\C
ivil\P
la
n\0
19
79
23
5C
50
_D
ET
02
.d
wg
L
ayo
ut: C
D-5
07
P
lo
tte
d: F
ri, Ju
ne
2
3, 2
01
7 - 1
0:0
4 A
M U
se
r: C
EL
IC
IA
B
OY
DE
N
Plo
tte
r: D
WG
T
O P
DF
.P
C3
C
TB
F
ile
: F
O 2
00
8 M
ON
O.C
TB
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 1
SECTION 05 52 10 – PIPE AND TUBE RAILINGS
PART 1 - GENERAL
1.1 Related Documents
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
1.2 Summary
A. Section Includes:
1. Aluminum railings.
B. Related Sections:
1. Division 32 Section "Curbing" for railings set in granite curbing.
1.3 Performance Requirements
A. Delegated Design: Design railings, including comprehensive engineering analysis by a qualified
professional engineer, using performance requirements and design criteria indicated.
B. Structural Performance: Railings shall withstand the effects of gravity loads and the following loads
and stresses within limits and under conditions indicated:
1. Handrails:
a. Uniform load of 50 lbf/ ft. applied in any direction.
b. Concentrated load of 200 lbf applied in any direction.
c. Uniform and concentrated loads need not be assumed to act concurrently.
C. Thermal Movements: Allow for thermal movements from ambient and surface temperature
changes acting on exterior metal fabrications by preventing buckling, opening of joints,
overstressing of components, failure of connections, and other detrimental effects.
1. Temperature Change: 120 deg F ambient; 180 deg F, material surfaces.
D. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals
and other materials from direct contact with incompatible materials.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 2
1.4 Submittals
A. Product Data: For the following:
1. Manufacturer's product lines of mechanically connected railings.
2. Railing brackets.
3. Grout, anchoring cement, and paint products.
B. Shop Drawings: Include plans, elevations, sections, details of railings, and attachments to other
work.
C. Samples for Initial Selection: For products involving selection of color, texture, or
design, including mechanical finishes on aluminum.
D. Samples for Verification: For each type of exposed finish required.
1. Sections of each distinctly different linear railing member, including handrails, top rails,
posts, and balusters.
2. Fittings and brackets.
1.5 Quality Assurance
A. Source Limitations: Obtain each type of railing from single source from single manufacturer.
B. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M,
"Structural Welding Code - Steel."
C. Welding Qualifications: Qualify procedures and personnel according to the following:
1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."
2. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum."
3. AWS D1.6, "Structural Welding Code - Stainless Steel."
1.6 Project Conditions
A. Field Measurements: Verify actual locations of walls and other construction contiguous with metal
fabrications by field measurements before fabrication.
1.7 Coordination and Scheduling
A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint
and coating manufacturers' written recommendations to ensure that shop primers and topcoats are
compatible with one another.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 3
B. Coordinate installation of anchorages for railings. Furnish setting drawings, templates, and
directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with
integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project
site in time for installation.
C. Schedule installation so wall attachments are made only to completed walls. Do not support
railings temporarily by any means that do not satisfy structural performance requirements.
PART 2 - PRODUCTS
2.1 Metals, General
A. Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller
marks, rolled trade names, stains, discolorations, or blemishes.
B. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as
supported rails unless otherwise indicated.
2.2 Aluminum Railings
A. Tubing: ASTM B 210.
1. Provide powder coated black finish for exterior installations.
B. Pipe: ASTM B429
1. Provide powder coated black finish for exterior installations.
C. Plates, Shapes, and Bars: ASTM B209.
1. Provide powder coated black finish for exterior installations.
2.3 Fasteners
A. General: Provide the following:
1. Aluminum Railings/Posts: Aluminum coated steel fasteners per ASTM F1136.
B. Fasteners for Anchoring Railings to Other Construction: Select fasteners of type, grade, and class
required to produce connections suitable for anchoring railings to other types of construction
indicated and capable of withstanding design loads.
C. Fasteners for Interconnecting Railing Components:
1. Provide concealed fasteners for interconnecting railing components and for attaching them
to other work, unless otherwise indicated.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 4
2. Provide concealed fasteners for interconnecting railing components and for attaching them
to other work, unless exposed fasteners are unavoidable or are the standard fastening
method for railings indicated.
3. Provide tamper-resistant flat-head machine screws for exposed fasteners unless otherwise
indicated.
D. Post-Installed Anchors: Torque-controlled expansion anchors capable of sustaining, without
failure, a load equal to six times the load imposed when installed in unit masonry and four times the
load imposed when installed in concrete, as determined by testing according to ASTM E 488,
conducted by a qualified independent testing agency.
1. Material for Exterior Locations: Alloy Group 1 (A1) stainless-steel bolts, ASTM F 593
(ASTM F 738M), and nuts, ASTM F 594 (ASTM F 836M).
2.4 Miscellaneous Materials
A. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout
complying with ASTM C 1107. Provide grout specifically recommended by manufacturer for
interior and exterior applications.
B. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and
compatible with paints specified to be used over it.
C. Universal Shop Primer: Fast-curing, lead- and chromate-free, universal modified-alkyd primer
complying with MPI#79 and compatible with topcoat.
1. Use primer containing pigments that make it easily distinguishable from zinc-rich primer.
D. Epoxy Zinc-Rich Primer: Complying with MPI#20 and compatible with topcoat.
E. Shop Primer for Galvanized Steel: Primer formulated for exterior use over zinc-coated metal and
compatible with finish paint systems indicated.
F. Anchoring Cement: Factory-packaged, nonshrink, nonstaining, hydraulic-controlled expansion
cement formulation for mixing with water at Project site to create pourable anchoring, patching,
and grouting compound.
1. Water-Resistant Product: At exterior location provide formulation that is resistant to
erosion from water exposure without needing protection by a sealer or waterproof coating
and that is recommended by manufacturer for exterior use.
2.5 Fabrication
A. General: Fabricate railings to comply with requirements indicated for design, dimensions, member
sizes and spacing, details, finish, and anchorage, but not less than that required to support structural
loads.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 5
B. Assemble railings in the shop to greatest extent possible to minimize field splicing and assembly.
Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for
reassembly and coordinated installation. Use connections that maintain structural value of joined
pieces.
C. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of
approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on
exposed surfaces.
D. Form work true to line and level with accurate angles and surfaces.
E. Fabricate connections that will be exposed to weather in a manner to exclude water. Provide weep
holes where water may accumulate.
F. Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar items.
G. Connections: Fabricate railings with welded connections unless otherwise indicated.
H. Welded Connections: Cope components at connections to provide close fit, or use fittings
designed for this purpose. Weld all around at connections, including at fittings.
1. Use materials and methods that minimize distortion and develop strength and corrosion
resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove flux immediately.
4. At exposed connections, finish exposed surfaces smooth and blended so no roughness
shows after finishing and welded surface matches contours of adjoining surfaces.
I. Welded Connections for Aluminum Pipe: Fabricate railings to interconnect members with
concealed internal welds that eliminate surface grinding, using manufacturer's standard system of
sleeve and socket fittings.
J. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings.
Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.
1. Fabricate splice joints for field connection using an epoxy structural adhesive if this is
manufacturer's standard splicing method.
K. Form changes in direction as follows:
1. As detailed.
L. Bend members in jigs to produce uniform curvature for each configuration required; maintain cross
section of member throughout entire bend without buckling, twisting, cracking, or otherwise
deforming exposed surfaces of components.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 6
M. Close exposed ends of railing members with prefabricated end fittings.
N. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated. Close ends of
returns unless clearance between end of rail and wall is 1/4 inch (6 mm) or less.
O. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and
anchors to interconnect railing members to other work unless otherwise indicated.
1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-
resistant fillers, or other means to transfer loads through wall finishes to structural supports
and prevent bracket or fitting rotation and crushing of substrate.
P. Provide inserts and other anchorage devices for connecting railings to concrete or masonry work.
Fabricate anchorage devices capable of withstanding loads imposed by railings. Coordinate
anchorage devices with supporting structure.
Q. For removable railing posts, fabricate slip-fit sockets from stainless-steel tube or pipe whose ID is
sized for a close fit with posts; limit movement of post without lateral load, measured at top, to not
more than one-fortieth of post height. Provide socket covers designed and fabricated to resist
being dislodged.
1. Provide chain with eye, snap hook, and staple across gaps formed by removable railing
sections at locations indicated. Fabricate from same metal as railings.
R. Toe Boards: Where indicated, provide toe boards at railings around openings and at edge of open-
sided floors and platforms. Fabricate to dimensions and details indicated.
2.6 Finishes, General
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary
protective covering before shipping.
C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are
acceptable if they are within one-half of the range of approved Samples. Noticeable variations in
the same piece are not acceptable. Variations in appearance of other components are acceptable if
they are within the range of approved Samples and are assembled or installed to minimize contrast.
D. Provide exposed fasteners with finish matching appearance, including color and texture, of railings.
2.7 Metal Finishes
A. Galvanized Railings:
1. Hot-dip galvanize exterior steel railings, including hardware, after fabrication.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 7
2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings.
3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware.
4. Do not quench or apply post galvanizing treatments that might interfere with paint
adhesion.
5. Fill vent and drain holes that are exposed in the finished Work, unless indicated to remain as
weep holes, by plugging with zinc solder and filing off smooth.
B. For galvanized railings, provide hot-dip galvanized fittings, brackets, fasteners, sleeves, and other
ferrous components.
C. Preparing Galvanized Railings for Shop Priming: After galvanizing, thoroughly clean railings of
grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner.
D. For nongalvanized-steel railings, provide nongalvanized ferrous-metal fittings, brackets, fasteners,
and sleeves; however, galvanize anchors to be embedded in exterior concrete or masonry.
E. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with SSPC-
SP 6/NACE No. 3, "Commercial Blast Cleaning." SSPC-SP 3, "Power Tool Cleaning."
1. Exterior Railings: SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."
2. Railings Indicated to Receive Zinc-Rich Primer: SSPC-SP 6/NACE No. 3, "Commercial
Blast Cleaning."
3. Railings Indicated to Receive Primers Specified in Section 099600 "High-Performance
Coatings": SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."
4. Other Railings: SSPC-SP 3, "Power Tool Cleaning."
F. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated.
Comply with requirements in SSPC-PA 1, "Shop, Field, and Maintenance Painting of Steel," for
shop painting. Primer need not be applied to surfaces to be embedded in concrete or masonry.
1. Shop prime uncoated railings with universal shop primer.
G. Shop-Painted Finish:
1. Color: Black
PART 3 - EXECUTION
3.1 Examination
A. Examine surfaces to verify that locations of concealed reinforcements have been clearly marked for
Installer. Locate reinforcements and mark locations if not already done.
3.2 Installation, General
A. Fit exposed connections together to form tight, hairline joints.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 8
B. Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in
location, alignment, and elevation; measured from established lines and levels and free of rack.
1. Do not weld, cut, or abrade surfaces of railing components that have been coated or finished
after fabrication and that are intended for field connection by mechanical or other means
without further cutting or fitting.
2. Set posts plumb within a tolerance of 1/16 inch in 3 feet (2 mm in 1 m).
3. Align rails so variations from level for horizontal members and variations from parallel with
rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet (5 mm in 3
m).
C. Corrosion Protection: Coat concealed surfaces of aluminum that will be in contact with grout,
concrete, masonry, wood, or dissimilar metals, with a heavy coat of bituminous paint.
D. Adjust railings before anchoring to ensure matching alignment at abutting joints.
E. Fastening to In-Place Construction: Use anchorage devices and fasteners where necessary for
securing railings and for properly transferring loads to in-place construction.
3.3 Railing Connections
A. Nonwelded Connections: Use mechanical or adhesive joints for permanently connecting railing
components. Seal recessed holes of exposed locking screws using plastic cement filler colored to
match finish of railings.
B. Welded Connections: Use fully welded joints for permanently connecting railing components.
Comply with requirements for welded connections in "Fabrication" Article whether welding is
performed in the shop or in the field.
C. Expansion Joints: Install expansion joints at locations indicated but not farther apart than required
to accommodate thermal movement. Provide slip-joint internal sleeve extending 2 inches (50 mm)
beyond joint on either side, fasten internal sleeve securely to one side, and locate joint within 6
inches (150 mm) of post.
3.4 Anchoring Posts
A. Form or core-drill holes not less than 5 inches (125 mm) deep and 3/4 inch (20 mm) larger than
OD of post for installing posts in concrete. Clean holes of loose material, insert posts, and fill
annular space between post and concrete with nonshrink grout mixed and placed to comply with
anchoring material manufacturer's written instructions.
B. Leave anchorage joint exposed with 1/8-inch (3-mm) buildup, sloped away from post anchoring
material flush with adjacent surface.
Filley Park Restoration – Phase II
Bloomfield, CT
April 2017 01979235.C50
PIPE AND TUBE RAILINGS 05 52 10 - 9
3.5 Adjusting and Cleaning
A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded
areas of shop paint, and paint exposed areas with the same material as used for shop painting to
comply with SSPC-PA 1 requirements for touching up shop-painted surfaces.
1. Apply by brush or spray to provide a minimum 2.0-mil dry film thickness.
B. Touchup Painting: Cleaning and touchup painting of field welds, bolted connections, and abraded
areas of shop paint.
3.6 Protection
A. Protect finishes of railings from damage during construction period with temporary protective
coverings approved by railing manufacturer. Remove protective coverings at time of Substantial
Completion.
END OF SECTION