addendum no. 1 - charlotte, north carolinacharlottenc.gov/doingbusiness/lists/solicitations... ·...
TRANSCRIPT
ADDENDUM NO. 1
DATE ISSUED: May 1, 2017
FY17-RFQ-21
CONSTRUCTION MANAGER AT RISK SERVICES (CMAR) FOR
DOBY CREEK AND LITTLE SUGAR CREEK TRIBUTARY TO FAIRVIEW ROAD SANITARY SEWER IMPROVEMENTS
Proposers should acknowledge receipt of this addendum in their cover letter. Any Proposer not acknowledging receipt of an issued addendum may not be considered.
In the event additional changes or clarifications to this Request for Qualifications are warranted, all Proposers are responsible for monitoring CLTWater’s Contractor and Vendor Opportunities website at: http://charlottenc.gov/Water/Pages/Opportunities.aspx Please note the changes below. 1. Exhibit 1: Section 3 – Proposed Project Personnel, replace the text in the sections below with
the following:
Item A.2.
2. Provide three (3) similar gravity sewer projects by size, type, and duration that the proposed Project Manager for Preconstruction Phase Services (and proposed backup) has supervised/managed in the last 10 years for Applicant or other company. At least one example project must have a constructed value of at least $5,000,000. Proposers may provide wastewater treatment projects that include gravity sewer and/or trenchless pipe installation in lieu of gravity sewer projects. The following information shall be provided for all three projects:
Item B.2.
2. Provide three (3) similar gravity sewer projects by size, type, and duration that the
proposed Project Manager for Construction Phase Services (and proposed backup) has supervised/managed in the last 10 years for Applicant or other company. At least one example project must have a constructed value of at least $5,000,000. Proposers may provide wastewater treatment projects that include gravity sewer and/or trenchless pipe installation in lieu of gravity sewer projects. The following information shall be provided for all three projects:
Item C.2.
2. Provide three (3) similar gravity sewer projects by size, type, and duration that the proposed Site Superintendent (and proposed backup) has supervised/managed in the last 10 years for Applicant or other company. At least one example project must have a constructed value of at least $5,000,000. Proposers may provide wastewater treatment projects that include gravity sewer and/or trenchless pipe installation in lieu of gravity sewer projects. The following information shall be provided for all three projects:
2. Technical Memorandum No. 1 – Doby Creek Sanitary Sewer Improvements Routing Study completed by Hazen is attached and hereby incorporated into the RFQ as Exhibit 6.
Hazen and Sawyer • 9101 Southern Pine Blvd, Suite 250 • Charlotte, NC 28273 • 704.357.3150
Technical Memorandum
324
23-0
00
April 18, 2017
To: Charlotte Water
From: Kevin Bair, Hazen (Project Engineer/Preparer)Ellie Mierzejewski, Hazen (Project Engineer/Preparer)Jim Struve, Hazen (Project Manager/Reviewer)
Doby Creek Sanitary Sewer Improvements Routing Study
Technical Memorandum No. 1
Introduction
Charlotte Water (CLTWater) has retained Hazen and Sawyer (Hazen) toconduct an evaluation of the Doby Creek Sanitary Sewer to determine themost robust, expedient, and cost-effective course of action to upsize andincrease the hydraulic capacity of the existing gravity sewer toaccommodate current and future wastewater flows. As part of a separateconcurrent study, Brown and Caldwell performed hydraulic modeling todetermine the appropriate size of the replacement gravity sewer.Modeling results have estimated the size of the new gravity sewer to rangebetween 15 to 36-inches in diameter. This technical memorandum (TM)will consider the following key criteria as part of this evaluation.
Construction / Operation and Maintenance (O&M) Access Adjoining Property Owners Temporary / Permanent Construction Easements Materials of Construction Roadway Bores / Tunnels Stream Crossings Depth of Cover Rock Excavation Bypass Pumping Corrosion Protection
The findings of this evaluation are summarized herein along with recommendations (including a
construction cost estimate). Upon review and approval by CLTWater, the recommendations presented
herein will serve as the basis of design during development of plan and profile drawings and technical
specifications.
April 18, 2017
Charlotte Water 2 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
Table of Contents
1. Project Overview....................................................................................................... 3
2. Key Evaluation Criteria ............................................................................................. 3
2.1 Construction / Operation and Maintenance (O&M) Access ..................................................... 3
2.2 Adjoining Property Owners..................................................................................................... 4
2.3 Temporary / Permanent Construction Easements................................................................... 4
2.4 Materials of Construction........................................................................................................ 4
2.5 Roadway Bores / Tunnels ...................................................................................................... 5
2.6 Stream Crossings .................................................................................................................. 7
2.7 Depth of Cover....................................................................................................................... 7
2.8 Rock Excavation .................................................................................................................... 8
2.9 Bypass Pumping .................................................................................................................... 8
2.10 Corrosion Protection .............................................................................................................. 8
3. Construction Schedule.............................................................................................. 9
4. Construction Cost Estimate .................................................................................... 10
5. Recommendations .................................................................................................. 11
Appendix ....................................................................................................................... 12
April 18, 2017
Charlotte Water 3 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
1. Project Overview
The segment of Doby Creek sanitary sewer to be upsized is bound to the south by Mineral Springs Road
and to the north by the Mallard Creek Greenway. The existing sewer was constructed circa 1969 in a 20-
foot wide dedicated utility easement and consists of approximately 15,725 LF of predominantly vitrified
clay pipe ranging in size from 8 to 15-inches in diameter. The slope of the existing sewer is relatively flat
and shallow (i.e. 0.6% slope with an average depth of cover of 6-feet). As a result, there are multiple aerial
stream crossings along its alignment. Additionally, the existing sewer crosses under three major roadways
– University City Boulevard, University Pointe Boulevard, and WT Harris Boulevard. Figure 1 (appended
to the end of this TM) illustrates the upstream and downstream tie-in connections, alignment, and pipe sizes
of the existing Doby Creek sanitary sewer to be upsized.
The new upsized sewer is proposed to be installed in the existing pipe trench, where possible, in order to
expedite permitting, minimize cost, and to lessen the impact to the existing sewer corridor. However, this
will necessitate temporary bypass pumping.
2. Key Evaluation Criteria
2.1 Construction / Operation and Maintenance (O&M) Access
Due to limited easement width, roadway constraints (i.e., steep embankments), and stream crossings, the
Contractor will need several points of ingress / egress along the existing sewer easement to facilitate
construction. In order for CLTWater to facilitate future maintenance activities, it may be practical to keep
these access points as permanent rights of entry.
Based on recent site investigations, several potential ingress / egress access points for construction and
future O&M activities were identified and are summarized below and illustrated in Figures 2 through 5
appended to the end of this TM. These access locations will necessitate the acquisition of permanent
easements.
No. 1 – Mineral Springs Road at the upstream tie-in location
No. 2 – Doby Springs Drive (this will require a new permanent creek crossing)
No. 3 – Access from Vance High School access road
No. 4 – Access from Vance High School parking lot
No. 5 – Blyth easement in Duke ROW near Vance High School off of IBM Drive
No. 6 – Gated access off WT Harris Boulevard entrance ramp
No. 7 – Parking lots by Marriott and Wells Fargo properties off of Research Drive
No. 8 – Louis Rose Place between WT Harris Boulevard and Mallard Creek
No. 9 – Mallard Creek Greenway
April 18, 2017
Charlotte Water 4 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
2.2 Adjoining Property Owners
There are 15 properties that adjoin the existing Doby Creek sanitary sewer easement. Table 2.1 summarizes
the property owners name and associated parcel identification number, and references its respective
appended Figure number illustrating the parcel location with respect to the Doby Creek sanitary sewer.
Table 2.1: Properties Adjoining Doby Creek Sanitary Sewer
Property Owner Parcel ID No. Figure No.
IBM Corporation 04708213, 04708214, 04739110, 0473101, 04739109 2, 3, 4
CLT Mecklenburg Board of Education 04739108, 04739109 3
Ashford CLT LP 04714112 4
Charlotte Research 04714107 5
Polymers Center of Excellence 04714103A 5
Moldflow Corp 04714103B 5
KMB LLC 04714110, 04714117, 04714113 5
Assoc. of America TeachersInsurance & Annuity
04717131 5
Charlotte Mecklenburg School (CMS) and IBM are the predominant adjoining property owners. In prior
discussions with Charlotte Real Estate staff, acquiring additional temporary and permanent construction
easement from either entity will require significant time and effort (upwards of 6 months), and will most
likely require condemnation. Additionally, before easement discussions can begin, Charlotte Real Estate
requires plan and profile drawings be developed to the 90% completion level.
2.3 Temporary / Permanent Construction Easements
Temporary and permanent construction easements (TCEs and PCEs) will need to be acquired for the
following construction related activities:
All ingress / egress points of access (total of 9 locations)
All roadway bores (total of 4 locations)
TCEs and /or PCEs will also be required north of WT Harris Boulevard to realign the existing Doby Creek
sewer away from the meandering stream and from under the Duke Energy high voltage overhead electrical
(OHE) power lines. The additional easement will also provide sufficient buffer to protect the new upsized
sewer from future stream bank erosion. Locating the new sewer away from under the Duke Energy OHE
power lines will mitigate the potential of external pipe corrosion from stray currents, and more importantly,
will allow construction and future O&M activities to be more safely performed.
2.4 Materials of Construction
To mitigate the potential of internal corrosion due to microbial activity, non-ferrous pipe material (i.e., glass
reinforced plastic or polyvinyl chloride) is recommended when depth of cover is sufficient to protect the
April 18, 2017
Charlotte Water 5 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
pipe from anticipated construction / maintenance traffic loadings. To provide added pipe protection to
resist earth and live loads, crushed stone is recommended to be bedded from 6-inches below to 6-inches
above top of pipe.
Ferrous pipe material (i.e., ductile iron) is recommended for shallow bury conditions (i.e., < 3-feet). In
these instances, the ductile iron shall be specified with a protective internal lining such as Protecto 401.
When ductile iron pipe parallels or crosses under high voltage OHE power lines, the pipe is recommended
to be wrapped in a polyethylene baggy (i.e., Polywrap) for protection of external corrosion caused by stray
electrical currents.
Carbon steel or ductile iron pipe is recommended for all aerial stream crossings. The selection of pipe
material is dependent upon the length of the crossing. Since carbon steel can be fabricated to any length,
carbon steel is recommended for aerial crossings in excess of 40-feet. The carbon steel wall thickness is
recommended to include a sacrificial wall thickness allowance to account for internal / external corrosion.
Ferrous pipe at all aerial stream crossings will be bonded and grounded, and then isolated from buried pipe
with dielectric material.
Precast concrete manholes will be installed at all roadway bores / tunnels, aerial stream crossings, and
tributary sewer tie-in locations. Manhole spacing will not exceed 350-feet so as to accommodate sewer
inspection and cleaning equipment. Manholes will be specified to receive a microbial induced corrosion
(MIC) protective system utilizing either a concrete admixture or a 100% solids epoxy coating. Manholes
will be raised 2-feet above grade, installed with sealed / lockdown covers, and vented approximately every
1,000-feet.
2.5 Roadway Bores / Tunnels
Four (4) roadway bores / tunnels will be required for construction of the new upsized sanitary sewer. The
location of each bore / tunnel and its anticipated casing length is summarized in Table 2.2
Table 2.2: Roadway Bores / Tunnels
Location Casing Length
University City Boulevard 350 LF
CMS Access Road between Martin Middle School and Vance High School 160 LF
University Pointe Boulevard 120 LF
WT Harris Boulevard 460 LF
Encroachment contracts will be required with CDOT and NCDOT. The bores / tunnels will be permitted
to allow the contractor to either auger bore or hand-mine tunnel. The casing pipe will be a minimum
diameter of 48-inches in the event rock is encountered requiring the tunnel to be hand-mined. Additional
TCEs / PCEs will be required at each bore / tunnel entrance and exit pits. The existing sanitary sewer to be
abandoned under the roadways will be plugged and filled with flowable fill. Photos 2.1 through 2.4
illustrate the location of each bore / tunnel and the relatively steep roadway embankments that must be
negotiated.
April 18, 2017
Charlotte Water 6 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
Photo 2.1: University City BoulevardPhoto 2.2: School Access Road between James
Martin Elementary School and Vance High School
Photo 2.3: University Pointe Boulevard Photo 2.4: WT Harris Boulevard
April 18, 2017
Charlotte Water 7 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
2.6 Stream Crossings
The existing sanitary sewer alignment has eight (8) stream crossings. A preliminary site investigation
confirmed that the new upsized sewer will also require eight (8) stream crossings due to existing rock
outcroppings, connections to existing tributary sewers, and the meandering nature of Doby Creek. The
location of each stream crossing is illustrated in Figures 2 through 5 appended to the end of this TM.
A USACOE Nationwide Permit 3 or 12 will be necessary as construction activities will be required within
Doby Creek. Activities within the stream will be limited to the greatest extent possible so as to avoid
mitigation. No more than 150 LF of the stream can be permanently impacted without mitigation. A
permanent stream crossing located downstream of WT Harris Boulevard will be required to allow access
for the Contractor’s bore / tunnel equipment and for future CLTWater’s maintenance activities.
2.7 Depth of Cover
Pursuant to the existing record drawings, the majority of the existing length of sewer (13,510 LF) is installed
at a depth less than 6-feet. Of the remaining sewer length, approximately 1,560 LF is installed at a depth
between 6 to 8-feet and approximately 655 LF at a depth between 8 to 12-feet.
A 100 LF segment of existing 12-inch diameter sanitary sewer located immediately south of WT Harris
Boulevard is installed partially above grade (refer to Photo 2.5). It appears that this was done to minimize
rock excavation due to the presence of significant rock outcroppings along the stream bank and within the
stream. During detailed design, Hazen will evaluate if this segment can be re-aligned into the hillside to
allow some depth of cover for pipe protection.
Photo 2.5: Segment of Exposed Sanitary Sewer
April 18, 2017
Charlotte Water 8 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
2.8 Rock Excavation
Rock is prevalent throughout the project area. It is believed to be the primary reason the original sewer was
constructed at a shallow depth and why there are multiple aerial stream crossings. Hazen’s geotechnical
Subconsultant (S&ME) will be obtaining a rock core to determine if the existing rock is rippable via
conventional construction equipment or requires more expensive means and methods such as blasting by
explosives or jack-hammering. It is estimated that approximately 1-foot of rock will be required for removal
along the entire length of the new upsized sewer.
2.9 Bypass Pumping
The new upsized sanitary sewer is proposed to be installed predominantly in the existing sewer’s pipe trench
(i.e., dig and replace). To provide uninterrupted sewer service to CLTWater’s customers within the Doby
Creek Watershed, a temporary bypass pumping system will be required. This system will allow the
Contractor to “dig and replace” while bypassing flow around the active construction zone with mechanical
pumps.
The Contractor will be required to furnish and maintain the temporary bypass pumping system throughout
the construction duration. To mitigate the potential for sewer spills, redundant equipment (i.e., pumps,
controls, and suction / discharge piping) will be required. To size the system correctly, recent flow
monitoring data was obtained from Frazier Engineering, P.A. (Feb to Mar 2016) and CLTWater (Sep to
Nov 2016). The data is summarized in Table 2.3.
Table 2.3: Flow Monitoring Summary
Location
PipeDiameter(inches)
PipeCapacity
(mgd)
AverageDaily Flow
(mgd)1
PeakHourly Flow
(mgd)2
Upstream of Doby Creek 10 1.30 0.43 0.91
Downstream of Doby Creek 12 1.51 0.56 1.32
1. Frazier Engineering, P.A., Flow Monitoring Report University City Apartments, April 28, 2016.2. CLTWater flow monitoring data from Sep 26th rainfall event (5-inches of rainfall).
Based upon the data summarized in Table 2.3, the Contractor will be required to provide a temporary bypass
pumping system sized to convey a flow ranging from 0.4 mgd (average daily flow) to 3.0 mgd (peak hourly
flow).
2.10 Corrosion Protection
Directly North of WT Harris Boulevard, the existing sewer parallels under a Duke Energy high voltage
OHE power line for approximately 300 LF (refer to Photo 2.6). According to the Ductile Iron Pipe Research
Association, overhead alternating current power lines normally do not cause corrosion or safety concerns
to buried unrestrained ductile iron pipelines. This is because ductile iron pipelines are considered
electrically discontinuous due to the rubber-gasketed jointing system that offers a sufficient amount of
electrical resistance. However, in order to adhere to the limit of approach regulations governing
construction equipment, it is recommended that the new upsized sewer be re-aligned out from under the
OHE power line. As an extra precaution, Hazen recommends wrapping the pipe in a polyethylene baggy
April 18, 2017
Charlotte Water 9 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
(i.e., Polywrap) for protection of external corrosion caused by stray electrical currents if ductile iron pipe
is installed. If non-ferrous pipe is installed in this segment, no added protection (i.e., Polywrap) will be
required.
Photo 2.6: Existing Sewer Under Duke Energy OHE Power Line
3. Construction Schedule
Due to capacity limitations of the existing Doby Creek sanitary sewer and long lead times associated with
acquiring TCEs / PCEs and with obtaining NCDOT encroachment contracts, it is recommended that the
project be phased to expedite the construction schedule. Phase 1 will consist of dig and replacement of the
existing sewer with new while deferring all the roadway bores to Phase 2. Phasing will allow the majority
of the work to be started / completed while encroachment contracts and easement acquisition activities are
pursued. Table 3.1 illustrates the phased construction schedule.
Table 3.1: Phased Construction Schedule
Project Milestone Tentative Date
Phase 1 AdvertisePhase 1 Contractor NTPPhase 1 Substantial Completion
Aug 2017Nov 2017Aug 2018
Phase 2 AdvertisePhase 2 Contractor NTPPhase 2 Substantial Completion
Jan 2018April 2018Oct 2018
It is anticipated that design, including permitting, will be completed by August 2017 and January 2018 for
Phase 1 and Phase 2, respectively. This will allow 6 months for acquiring easements and obtaining
encroachment contracts for all the roadway bores / tunnels. Both Phase 1 and Phase 2 assume a 3 month
April 18, 2017
Charlotte Water 10 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
period from project advertisement through Contractor notice-to-proceed (NTP). Construction duration is
estimated at 9 months for Phase 1 and 6 months for Phase 2.
4. Construction Cost Estimate
Tables 4.1 and 4.2 summarize the estimated construction costs for Phase 1 and Phase 2, respectively. The
cost estimates are based on recent construction bids of projects of similar size and complexity. The cost
estimates do not include engineering fees associated with detailed design, bidding, construction
administration or field construction observation services. The total construction cost for both Phase 1 and
Phase 2 is estimated at $9,242,835.
Table 4.1: Phase 1 Construction Cost Estimate
Item Description Quanity Unit Unit Cost Extended Total
15-inch Sanitary Sewer 500 LF $165 $82,500
21-inch Sanitary Sewer 8,985 LF $225 $2,021,625
30-inch Sanitary Sewer 2,020 LF $315 $636,300
36-inch Sanitary Sewer 3,130 LF $375 $1,173,750
4-foot Diameter Manholes 35 Ea $6,000 $210,000
6-foot Diameter Manholes 23 Ea $9,000 $207,000
Aerial Stream Crossings 7 Ea $15,000 $105,000
Temporary Bypass Pumping 1 LS $200,000 $200,000
Clearing and Grubbing 14,540 LF $5 $72,700
Tie-In Connections 7 Ea $6,000 $42,000
Sedimentation Erosion Control 14,540 LF $4 $58,160
Seeding and Mulching 14,540 LF $1 $14,540
Rock Excavation 2,700 CY $40 $108,000
Select Backfill 2,700 CY $25 $67,500
Additional Stone 2,700 Ton $15 $40,500
Subtotal10% Engineering Contingency
$5,039,575$503,960
Subtotal3% Mobilization
$5,543,535$166,310
Subtotal3% Construction Allowance
$5,709,845$171,300
Total $5,881,145
April 18, 2017
Charlotte Water 11 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
Table 4.2: Phase 2 Construction Cost Estimate
Item Description Quanity Unit Unit Cost Extended Total
21-inch Sanitary Sewer 630 LF $225 $141,750
30-inch Sanitary Sewer 460 LF $315 $144,900
Guaranteed Bore / Tunnel 1,100 LF $2,200 $2,420,000
4-foot Diameter Manholes 6 Ea $6,000 $36,000
6-foot Diameter Manholes 2 Ea $9,000 $18,000
Tie-In Connections 4 Ea $6,000 $24,000
Sedimentation and Erosion Control 1 LS $20,000 $20,000
Seeding and Mulching 1 LS $10,000 $10,000
Rock Excavation 825 CY $40 $33,000
Select Backfill 825 CY $25 $20,625
Additional Stone 825 Ton $15 $12,375
Subtotal10% Engineering Contingency
$2,880,650$288,070
Subtotal3% Mobilization
$3,168,720$95,060
Subtotal3% Construction Allowance
$3,263,780$97,910
Total $3,361,690
5. Recommendations
To accommodate growth in the University City area, the Doby Creek sanitary sewer requires upsizing.
Based upon hydraulic modeling performed by Brown & Caldwell, the size of the new upsized sewer will
range between 15 and 36-inches in diameter. The new upsized sewer will predominantly be installed in the
existing pipe trench to minimize easement acquisition and rock removal. A phased construction schedule
is recommended to expedite the work effort due to immediate hydraulic limitations in the existing sewer
and long lead times to acquire TCEs / PCEs and to obtain encroachment contracts for the four (4) roadway
bores / tunnels. The estimated construction costs for each phase are summarized in Table 5.1.
Table 5.1: Estimated Construction Costs
Phase 1 $5,881,145
Phase 2 $3,361,690
Total Project $9,242,835
April 18, 2017
Charlotte Water 12 of 12Doby Creek Sanitary Sewer Improvements Routing StudyTechnical Memorandum No. 1
Appendix A: Figures
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
DobyCreek
MallardCreek
MallardCree k Mallard C re
ek
DobyC reek
Mallard C reek
Mal lard
Creek
Mallard Creek
Doby
Cree
k
Toby
Creek
Doby Creek Trib
DobyCreek
²0 1,250 2,500625
Feet
Legend8-inch Gravity
10-inch Gravity
12-inch Gravity
15-inch Gravity
Creek
!( Manhole
Downstream Tie-In
Upstream Tie-In
Doby Creek SanitarySewer Improvements
ProjectFIGURE 1
I-85
Upstream Tie-InLocation
Potential Ingress/Egress #1
Proposed 21" Gravity~2,525
Potential Ingress/Egress #2
Approx. Location ofUniversity City Bore
Stream Crossing #1
Proposed 15" Gravity~500 LF
IBM
IBM
Doby
Creek
Doby Creek
04739110
04739101
04708214
04708213
MMiinneerraall SSpprriinnggss RRdd
NN UUss 2299 BByy--ppaassss HHyy
RReeaaggaann DDrr
DDoobbyy SSpprriinnggss DDrr
N I -8 5 H
y
N I -8 5 H
y
R o c k yR o c k y
S p r i ng
S p r i ng
C tC t
S I -8 5 H
y
S I -8 5 H
y
AA mmaa r
r ii ll ll o
oDD rr
W e l l S p r i n g D r
W e l l S p r i n g D r
NN II--8855 SSeerrvviiccee RRdd
EEllddoorraaddoo AAvv
C i t y B vC i t y B v
NN UUss 2299 BByy--ppaassss HHyy
CC hh ee
yy ee nn
nn ee
DDrr
Ca n
y on
Dr
Ca n
y on
Dr
EEqquu ii ppmmeenn tt DD rr
²0 140 28070
Feet
Legend") Creek Crossing
!( Manhole
Proposed 15-inch Gravity
Proposed 21-inch Gravity
Proposed 30-inch Gravity
Proposed 36-inch Gravity
Existing Tributary
Duke OHE Line
Ingress/Egress
Creek
Parcel
Doby Creek SanitarySewer Improvements
ProjectFIGURE 2
TextApprox. Location ofUniversity City Bore
Approx. Location ofSchool Access Bore
Proposed 21" Gravity~4,100 LF
Potential Ingress/Egress #3
Potential Ingress/Egress #4
Potential Ingress/Egress #5
Creek Crossing #2
IBM
CMS
04739110
04739101
04708214
04739108
04739109
V i no y
V i no y
V i ew D
r
V i ew D
r
C i t y B vC i t y B v
V i n o y B vV i n o y B v
H ag e
nH a
g en
C tCt
Ci t
yC
i ty
Bv x
S I 8
5B
v xS
I 85
Ra
S BR
a S B
C a n y o n D r
C a n y o n D r
N I -8 5 H
y
N I -8 5 H
y
Wb C
i t yW
b Ci t y
Bv T o S b
Bv T o S b
I - 8 5 Ra
I - 8 5 Ra
S I -8 5 H
y
S I -8 5 H
y
C it y
Bv x
NC i
t y B
v xN
I 85
Ra
N BI 8
5 R
a N B
I B M D rI B M D r
S I 8 5 x C i t y B v R a S B
S I 8 5 x C i t y B v R a S B
N ea l
Rd
N ea l
Rd
²0 150 30075
Feet
Legend") Creek Crossing
!( Manhole
Proposed 15-inch Gravity
Proposed 21-inch Gravity
Proposed 30-inch Gravity
Proposed 36-inch Gravity
Existing Tributary
Duke OHE Line
Ingress/Egress
Creek
Parcel
Doby Creek SanitarySewer Improvements
ProjectFIGURE 3
Approx. Location ofUniversity Pointe Bore
Proposed 30" Gravity~5,300 LF
Potential Ingress/Egress #6
Approx. Location ofWT Harris Bore
Creek Crossing #6
Creek Crossing #4
Creek Crossing #5
Creek Crossing #3
IBM
Doby
Creek
Doby CreekTrib
Dob
yCreek
047141070471412004714118
04714112
04739108
04739109
P e a r l S
t
P e a r l S
t
W W T H a r r i s B v
W W T H a r r i s B v
S I -
8 5 H
yS
I -8 5
Hy
V i n o yV i n o yB vB v
N I -
8 5 H
yN
I -8 5
Hy
P ik e
Rd
P ik e
Rd
IBM
Dr
I BM
Dr
N I - 8 5 R aN I - 8 5 R a
N I - 8 5 R aN I - 8 5 R a
F i n n L nF i n n L n
V i n o y B v
V i n o y B vH
a g e nH
a g e nC
tC t
B r e n t mo o r D r
B r e n t mo o r D r
S I - 8 5 R aS I - 8 5 R a
W a c h o v i a D rW a c h o v i a D r
N I -8 5 R
a
N I -8 5 R
a
S I -
8 5 R
aS
I -8 5
Ra
²0 200 400100 Feet
Legend") Creek Crossing
!( Manhole
Proposed 15-inch Gravity
Proposed 21-inch Gravity
Proposed 30-inch Gravity
Proposed 36-inch Gravity
Existing Tributary
Duke OHE Line
Ingress/Egress
Creek
Parcel
Doby Creek SanitarySewer Improvements
ProjectFIGURE 4
Potential Ingress/Egress #9
Downstream Tie-In
Creek Crossing #8
Potential Ingress/Egress #8
Proposed 36" Gravity~3,300 LF
Potential Ingress/Egress #7
Creek Crossing #7
Approx. Location of WT Harris Bore
IBM
MallardCreek
Doby
Creek
Doby CreekTrib
Doby Cree
k
04714115
04714110
04714103
04714107
04714113
04714119
04714120
04714118
04714112
04739109
04717131
04714117
W W T H a r r i s B v
W W T H a r r i s B v
S I -8 5 H
y
S I -8 5 H
yN I -
8 5 Hy
N I -8 5 H
y
I B M D r
I B M D r
N I - 8 5 R aN I - 8 5 R a
D a v i d T a y l o r D r
D a v i d T a y l o r D r
V i l l a g eV i l l a g eS h o p p i n gS h o p p i n gC e n t e r D r NC e n t e r D r N
V i l l a g eV i l l a g eS h o p p i n gS h o p p i n gC e n t e r D r SC e n t e r D r S
J W
Cla
y B
vJ
W C
l ay
Bv
S I - 8 5 R aS I - 8 5 R a
N I- 8 5 R
aN
I - 8 5 Ra
S I -8 5 R
a
S I -8 5 R
a
N I
- 85
Ra
N I
- 85
Ra
R e s e a r c h Dr
R e s e a r c h Dr
²0 140 28070
Feet
Legend") Creek Crossing
!( Manhole
Proposed 15-inch Gravity
Proposed 21-inch Gravity
Proposed 30-inch Gravity
Proposed 36-inch Gravity
Existing Tributary
Duke OHE Line
Ingress/Egress
Creek
Parcel
Doby Creek SanitarySewer Improvements
ProjectFIGURE 5