acquisition policy update
DESCRIPTION
Air Armament Center. Acquisition Policy Update. Emily Jay AAC/PK [email protected] 882-4398. DISTRIBUTION STATEMENT A : Approved for public release; distribution is unlimited. Agenda. Update on Anticipated Changes from Last Year Contract Incentives - PowerPoint PPT PresentationTRANSCRIPT
War-winning Capabilities…On Time, On Cost
Air Armament CenterAir Armament Center
Emily JayAAC/[email protected]
Acquisition Policy UpdateAcquisition Policy Update
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
War-winning Capabilities…On Time, On Cost
Agenda
• Update on Anticipated Changes from Last Year
• Contract Incentives• Changes to Source Selection Process• Firm Fixed Price Development Contracts• Other Hot Topics
War-winning Capabilities…On Time, On Cost
Update From Last Year
• Congress and DAPA “Conspiracy of Hope”Advocated Change in our Processes
– Source Selection Improvement Team• Requirements Traceability MatrixMore Education of Teams “Do’s and Don’ts”• DFARS Guidance Regarding DownselectsIncreased Use of Oral ProposalsIncreased Emphasis on Cost Realism/RiskIncreased Emphasis on Structuring Contracts to Limit
OverrunsMove to Risk Based Source Selection
– Award Fee Policy Revisions
War-winning Capabilities…On Time, On Cost
Contract Incentives
• April/May 2006 – OSD/AF letters• June 2007 – OSD/AF letters• More OSD and AFFARS change pending• AAC Local Procedures
– CPFF (PI) Contract Type allows Min Base Fee with Performance Incentives
– Cost, Schedule, and Performance are tied– Incentives Need to Consider Length of Effort,
Scope of Work and determine if:• Graduated Plans Should Be Used• Interim Evaluations Should Be used
War-winning Capabilities…On Time, On Cost
Incentive Fee Example #1Non-Graduated, Complete in 1 Year
• Small % Fixed Fee• The Cost, Schedule, and Technical criteria are "final
performance criteria" for a Performance Incentive Fee of X%– Only be earned if the combined criteria are all accomplished. – The criteria are interdependent, all criteria must be met to
earn the performance incentive fee.
• Sample Criteria– Cost: CPI of 1.0 or higher at contract completion– Schedule: All SDD major events complete IAW kt– Performance: Successful completion of DT
War-winning Capabilities…On Time, On CostIncentive Fee Example #2
Cost Plus 3% Fixed Fee with 12% Incentive Fee for meeting Cost AND Schedule AND
PerformanceCost AND Schedule AND Performance % Incentives
Earned+ 3 %
Excellent Zero or positive variance
Completes ahead of contract milestones
Meets ALL Thresholds and some objectives
100% 15%
Very Good Within
- 2%
Meets contract milestones
Meets ALL Thresholds 90% 13.8%
Satisfactory Within
- 5%
Misses contract milestones – Does Not Break Baseline
Meets ALL KPPs, other thresholds with workarounds
70% 11.4%
Unsatisfactory Greater than
- 5%
Misses contract milestones – Breaks Baseline
Misses Key Performance Parameters (KPPs)
0 3%
War-winning Capabilities…On Time, On Cost
Changes to Source Selection
• AF Standardized Source Selection Process– All source selection plans approved on or after 31
Mar 08 must comply with the revised procedures– Individual Deviations approved at AFMC– Program Tailoring Comes In Developing Evaluation
Criteria
• Changes will be implemented in AFFARS
War-winning Capabilities…On Time, On Cost
Integrated Risk BasedSource Selection Criteria
Air Armament Center
Cost Risk Mission Capability Past Performance Cost/Price
Technical Rating Risk Rating
Example
Sub factor
Rating ExampleSub factor
Rating ExampleSub factor
Rating ExampleSub factor
Rating ExampleSub factor
Rating
•Instant Kt Cost/Price•AUPP•LCC
Realism•High•Moderate•Low
•Reqts•Support-ability
•Blue•Green•Yellow•Red
•Reqts•Support-ability
•Low•Moderate•High •Unacceptable
•Cost•Schedule•Perform-ance•SB Subcon-tracting Compliance
•Substantial Confidence•Sat
Confidence•Limited•No
Confidence•Unknown
•Inst KT Cost/Price•AUPP•LCC
Reason-ableness
Tools Tools Tools Tools Tools
•LHA•SEA •TRA•MRA•Demos •IBR•IMP/IMS•Test Plan•PoPS•MPC•Proposed Management Reserve
•Spec•ILSP
•LHA•SEA•TRA•MRA•Demos•IBR•IMP/IMS•Test Plan•PoPS
•CPARS•Questionnaires•PoPS•MRA
APC
MPC
War-winning Capabilities…On Time, On Cost
Source Selection Evaluation Matrix
Past Performance
Mission Capability
Cost/Price ** This factor may require a risk assessment
as described in Paragraph 5.5.4.
Subfactor 1 Subfactor 3Subfactor 2
Ris
k R
atin
g
Past Performance
Cost/Price
Subfactor 1
Tec
hn
ical
Rat
ing
* For use on cost reimbursement or fixed-price incentive contracts where Cost/Price Risk is an Evaluation Factor; Most Probable Cost is utilized
Tec
hn
ical
Rat
ing
Tec
hn
ical
Rat
ing
Mission Capability
Cost/Price Risk *
Ris
k R
atin
g
Ris
k R
atin
g
Subfactor 2 Subfactor 3
CURRENT
Proposal Risk
NEW
War-winning Capabilities…On Time, On CostCost / Price Risk Ratings
NEWCURRENTTABLE 2 - PROPOSAL RISK RATINGS
Rating Description
High Likely to cause significant disruption of schedule, increased cost or degradation of performance. Risk may be unacceptable even with special contractor emphasis and close government monitoring.
Moderate Can potentially cause disruption of schedule, increased cost, or degradation of performance. Special contractor emphasis and close government monitoring will likely be able to overcome difficulties.
Low Has little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal government monitoring will likely be able to overcome any difficulties.
TABLE 4 – COST/PRICE RISK RATINGS
Rating Description
Low Little difference exists between the offeror’s proposed cost/price and the government most probable cost which may cause minor or even negligible impact to program’s probability of success. Cost growth is unlikely to occur as indicated by this difference and/or other anomalies related to cost/price, but the impact is manageable.
Moderate Some difference exists between the offeror’s proposed cost/price and the government most probable cost that may impact the program’s probability of success. Cost growth is possible to occur as indicated by this difference and/or other anomalies related to cost/price.
High Significant difference exists between the offeror’s proposed cost/price and the government most probable cost which may substantially impact the program’s probability of success. Cost growth is likely to occur as indicated by this difference and/or other anomalies related to cost/price.
War-winning Capabilities…On Time, On Cost
Cost Risk Ratings
• Cost– The Offeror’s proposal will be assigned a cost proposal risk rating to
characterize the extent to which the proposed costs indicate a clear understanding of solicitation requirements and reflect a sound approach to satisfying those requirements, including the planning for sufficient Management Reserve to accommodate risk. This will be accomplished by assessing the difference between the Offeror’s Cost Proposal and the Government’s Most Probable Cost estimate (MPC) of the Offeror’s approach, including the Government’s estimate of risk associated with the Offeror’s approach.
• High Risk ( Estimate is > 20% above or below MPC)• Moderate Risk ( Estimate is 11%-20% above or below MPC)• Low Risk (Estimate is < 10% above or below MPC)
– Individual programs may tailor % and upper boundary for high risk
War-winning Capabilities…On Time, On Cost
Factors – Cost/Price Risk
• Elevated Cost/Price Risk as a separate evaluation factor
– Moves Cost/Price risk from within the Cost/Price evaluation factor.
– Only applies to ACAT programs in a System Development and Demonstration (SDD) phase utilizing Most Probable Cost (Cost Reimbursement or Fixed-Price Incentive contract)
– Mandatory discussions of cost model prior to RFP release
– Requires robust discussions with each offeror on how the government’s best estimate of Probable Costs is calculated
• Each offeror will have its own MPC based on their unique approach
• When used, Cost/Price Risk shall be a significant factor
War-winning Capabilities…On Time, On Cost
NEWCURRENT
Mission Capability Technical Ratings
TABLE 1 - MISSION CAPABILITY TECHNICAL RATINGS
Color Rating Description
Blue Exceptional Exceeds specified minimum performance or capability requirements in a way beneficial to the government. A proposal must have one or more strengths and no deficiencies to receive a blue.
Green Acceptable Meets specified minimum performance or capability requirements. A proposal must have no deficiencies to receive a green but may have one or more strengths.
Yellow * Marginal There is doubt regarding whether an aspect of the proposal meets a specified minimum performance or capability requirements, but any such uncertainty is correctable.
Red Unacceptable Fails to meet specified minimum performance or capability requirements. The proposal has one or more deficiencies and is not awardable.
TABLE 1 - MISSION CAPABILITY RATINGS
Color Rating Description
Blue Exceptional Exceeds specified minimum performance or capability requirements in a way beneficial to the government; proposal must have one or more strengths and no deficiencies to receive a blue.
Green Acceptable Meets specified minimum performance or capability requirements delineated in the Request for Proposal; proposal rated green must have no deficiencies but may have one or more strengths.
Yellow * Marginal Does not clearly meet some specified minimum performance or capability requirements delineated in the Request for Proposal, but any such uncertainty is correctable.
Red Unacceptable Fails to meet specified minimum performance or capability requirements; proposal has one or more deficiencies. Proposals with an unacceptable rating are not awardable.
War-winning Capabilities…On Time, On Cost
Mission Capability RiskRatings
NEWTABLE 2 – MISSION CAPABILITY RISK RATINGS
Rating Description
Low* Has little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal government monitoring will likely be able to overcome any difficulties.
Moderate* Can potentially cause disruption of schedule, increased cost or degradation of performance. Special contractor emphasis and close government monitoring will likely be able to overcome difficulties.
High* Likely to cause significant disruption of schedule, increased cost or degradation of performance. Extraordinary contractor emphasis and rigorous government monitoring may be able to overcome difficulties.
Unacceptable The existence of a significant weakness (or combination of weaknesses) that is very likely to cause unmitigated disruption of schedule, drastically increased cost or severely degraded performance. Proposals with an unacceptable rating are not awardable.
CURRENTTABLE 2 - PROPOSAL RISK RATINGS
Rating Description
High Likely to cause significant disruption of schedule, increased cost or degradation of performance. Risk may be unacceptable even with special contractor emphasis and close government monitoring.
Moderate
Can potentially cause disruption of schedule, increased cost, or degradation of performance. Special contractor emphasis and close government monitoring will likely be able to overcome difficulties.
Low Has little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal government monitoring will likely be able to overcome any difficulties.
+ Used when risk is in the upper boundaries of a Mission Capabilities Risk Rating but not enough to merit the next inferior rating
War-winning Capabilities…On Time, On Cost
Proposal Risk – Pre SDD
TRL/Integration IMP/IMS Planning Risk Management Producibility
Low All technologies required for tech solution are > TRL 5,
Integration begun
Scope of integration and test efforts are benchmarked and relected in robust ingtegrated IMP & IMS
Contractor’s plan and proposed costs reflect robust risk management and a methodology to conduct iterative trade studies to offer options as needed to complete the program within target cost and schedule
Key Suppliers are selected, and are an integral part of the team/proposal. Key processes are identified and producibility planning is part of early design process
Low to Moderate All technologies required for tech solution are > TRL 5 X X
Majority of key suppliers are selected and their work is reflected robustly in the proposal. Producibility planning is part of early design
Moderate All technologies required for the tech solution are > TRL 4
Integration and test efforts are planned but lack sufficient detail within the IMP/IMS. Benchmarking is poorly implemented
Contractor’s plan reflects limited risk management and/or limited methodology to conduct iterative trade studies needed to complete program on cost and schedule
Majority of key suppliers are selected and their work is reflected robustly in the proposal.
Moderate to High More than one key technology is only at a TRL 3 X X
Major suppliers are identified but not selected.
High More than one key technology is < a TRL 3
Integration and test efforts are not yet planned so the IMIP/IMS are insufficient to establish cost and schedule targets. No benchmarking is implemented
The program plan assumes success and does not include trade study methodology
Key Suppliers are not identified and are not part of the team or incorporated into the proposal process. Key processes are not identified, and no evidence of procducibiity planning
War-winning Capabilities…On Time, On Cost
Past Performance Ratings
TABLE 3- PERFORMANCE CONFIDENCE ASSESSMENTS
Rating Description
SUBSTANTIAL CONFIDENCE
Based on the offeror’s performance record, the government has a high expectation that the offeror will successfully perform the required effort.
SATISFACTORY CONFIDENCE
Based on the offeror’s performance record, the government has an expectation that the offeror will successfully perform the required effort.
LIMITED CONFIDENCE
Based on the offeror’s performance record, the government has a low expectation that the offeror will successfully perform the required effort.
NOCONFIDENCE
Based on the offeror’s performance record, the government has no expectation that the offeror will be able to successfully perform the required effort.
UNKNOWN CONFIDENCE
No performance record is identifiable or the offeror’s performance record is so sparse that no confidence assessment rating can be reasonably assigned.
NEWTABLE 3- PERFORMANCE CONFIDENCE ASSESSMENTS
Rating Description
HIGH CONFIDENCE
Based on the offeror’s performance record, the government has high confidence the offeror will successfully perform the required effort
SIGNIFICANT CONFIDENCE
Based on the offeror’s performance record, the government has significant confidence the offeror will successfully perform the required effort
SATISFACTORY CONFIDENCE
Based on the offeror’s performance record, the government has confidence the offeror will successfully perform the required effort. Normal contractor emphasis should preclude any problems.
UNKNOWN CONFIDENCE
No performance record is identifiable.
LITTLE CONFIDENCE
Based on the offeror’s performance record, substantial doubt exists that the offeror will successfully perform the required effort.
NO CONFIDENCE Based on the offeror’s performance record, extreme doubt exists that the offeror will successfully perform the required effort.
CURRENT
War-winning Capabilities…On Time, On Cost
Fixed Price Development Contracts
• FY07 Authorization Act – PL 109-364, sec 818• DFARS Case 2006-D053
– MS B – MDA, with advice of the Contracting Officer, selects contract type for development program
– Basis for Contract Type Documented in Acq Strategy• Include explanation of level of risk• If high risk, steps taken to taken to reduce program risk and
reasons for proceeding despite the high level of program risk
– Cost Type Contract Requires a Written Determination• Program is so complex and technically challenging…not
practicable to reduce program risk to a level permitting FP contract”
• Complexity and technical challenge is not a result of failure to meet 10USC2366a
DFARS Case – Out for Public Comment - Closes 24 March 08
War-winning Capabilities…On Time, On Cost
MDA Certification
• National Defense Authorization Act for 2006• Implemented in USD/ATL letter dated 2 May 06
– Prior to MSB approval, MDA must certify
• Technology has been demonstrated in a relevant environment
• Program demonstrates high likelihood of accomplishing its mission
• Program is affordable when considering the per unit cost and total acquisition cost
• AoA has been conducted
• Program is affordable when considering alternative systems
• JROC has completed review, including analysis of reqts
• Program complies with all policies, regs, directives
War-winning Capabilities…On Time, On Cost
Other Hot Topics
• Sole Source Negotiations– Receive same level of Risk Assessment/Review
Prior to Handshake– Congressional requirement for Service Contract
Reviews• OSD looking at broader applications
• UCA Definitizations– Increased Emphasis on 180 Day Definitization
War-winning Capabilities…On Time, On Cost
Summary
• Congress, OSD, and AF continue to advocate realism and accountability in estimates and contracts
• Risk is now assessed in POM Submissions, MDA Certifications, Source Selections and Sole Source Awards
• OSD and AF increasing use of Standardized Procedures to ensure min level of quality/realism