PREFACE
Professional study is incomplete without the practicalknowledge. Now a days theory without practical is of little
use. No doubt theory provides the fundamental stone for
the guidance of practice but practice examines the element
of truth lying in the theory. Therefore a stand co-ordination
of theory and practice is very essential to make MMS
perfect. As a student of Business Management, we were
required to undergo 8 (Eight) weeks practical training in
any organization of repute connected with Animation
Education Industry. We were required to work on some
specific research project and work assigned by the
organization.
I completed this practical training at Ace PipelineContracts Pvt,Ltd Mumbai. This project report of the work
consists of preparation of budget & estimated cashflow
statement of pipeline construction projects of the Ace
Pipeline Contracts Pvt,ltd.
Full care has been taken to make this report error free.
Last but not the least i hope this research work will helpfulfor Ace Pipeline Contracts Pvt,Ltd.
-
8/9/2019 Ace Pipeline Contracts Pvt
3/41
Sr.No Title Page.No
1 Certificate
2 Acknowledgement
3 Executive Summery4 History Of Company
5 Hierarchy In the Company
6 Introduction
7 Details Of Work Done
8 Budgeting
9 Research Methodology
10 Methods Of making Budgeting
11 Actual Format Of Budgeting
12 Cashflow Statement
13 Methods Of Making Cashflow
Statement
14 Actual Format Of Cashflow Statement
15 Difference Between Budgeting &
Cashflow Statement
16 Advantages Of Budgeting & CashflowStatement
17 Recommendation
18
-
8/9/2019 Ace Pipeline Contracts Pvt
4/41
ACKNOWLEDGEMENTACKNOWLEDGEMENT
Apart from the efforts of me, the success of any project depends
largely on the encouragement and guidelines of many others.I
take this opportunity to express my gratitude to the people who
have been instrumental in the successful completion of this
project.
I take immense pleasure in thanking Mr.R.K.Singh The principle
of Mumbai Institute Of Management & Research, Wadala, for
having permitted me to carry out this project work.
I would like to show my greatest appreciation to Mr. Anoop Singhthe Managing Director Of Ace Pipeline Contracts Pvt,Ltd. for
giving me an opportunity to work in this esteemed organization.
I cant say thank you enough for tremendous support and help I
received from Mr.Bajirao, Industry Mentor. I feel motivated and
encouraged every time I interacted with him. Without hisencouragement and guidance this project would not have
materialized.
Lastly I would like to express my appreciation towards all the Staff
of Ace pipeline Contracts Pvt,Ltd. that I interacted with them for
sparing their valuable time and contributing towards thecompletion of my project.
-
8/9/2019 Ace Pipeline Contracts Pvt
5/41
Executive Summery
-
8/9/2019 Ace Pipeline Contracts Pvt
6/41
History Of Ace Pipeline Contracts
Pvt.Ltd.
Ace pipeline Contracts was established in 1989.and has had its
roots in Mumbai.They have grown over the years in our ability to
execute diverse contracts across the nation. Oil & hydrocarbon industry
provides the fuel to the growth of the nation, and they take pride in
building the critical supply chain to the wheels of the nation. Having
growth from the modest start of the execution of shutdown project, they
are transitioning towards the EPC projects and hope to take our values to
the world.
Mission Of Ace pipeline Contracts Pvt.
Ltd.
They are a Construction and Engineering company with a focus on the
hydrocarbon industry, we specialize in laying of cross country pipelines,
with a core competence in area such as pipeline engineering, hydro
testing ,pre-commissioning of the pipeline system, laying pipelines by
trenchless technologies and installation of cathodic protection systems of
pipeline.
Vision Of Ace pipeline Contracts Pvt.Ltd.
They invision ourselves as a leading provider of engineering services to
the hydrocarbon pipeline infrastructer encompassing
design,execution,preservation and O&M with projects across the globe.it
shall be their endeavor to blend technological advances with the benefit
of loe labour cost to provide our customers with world class solutions at
affordable prices.
-
8/9/2019 Ace Pipeline Contracts Pvt
7/41
ETHICS followed by company for its success are:
To work as a dedicated cohesive
organization.
Be the best employer in its business.
Committed to building and furthering a
reputation of reliability in all its dealing, both on
quality and on their ability to complete the
project schedule.
Building long lasting relationships with
Clients.
Ethical dealings across all our business.
Projectsto be Carried out By Acepipeline Contracts pvt.ltd.
Haldia Petrochemical Ltd.
Reliance Industries Ltd.
Oil & Natural gas Corporation
Oil India Ltd.
-
8/9/2019 Ace Pipeline Contracts Pvt
8/41
Guajrat State Petronet Ltd.
Bharat Petroleum Corporation Ltd.
Indian Oil Corporation Ltd
Hindustan Petroleum Corporation Ltd.
Mumbai Port Trust
GAIL Ltd & many more.
QUALITY POLICY
Ace Group Of Companies
Ace Pipeline Contracts Pvt.Ltd.
Ace Energy Infrastructure Pvt.Ltd.
Committed to
Maintain its position as a leader in pipeline
construction.
Continual improvement in quality
performance and set targets.
-
8/9/2019 Ace Pipeline Contracts Pvt
9/41
Assure customer satisfaction and compliance
to their stated and implied needs.
Provide necessary training to employees .
Its services are offered all over INDIA and with some
of the reputed clients like Hindustan Petroleum
Corporation Ltd, ONGC, Bharat petroleum
Corporation Ltd., Reliance industries ltd, etc.
-
8/9/2019 Ace Pipeline Contracts Pvt
10/41
ACEs quality Objectives
1.To build the corporate image of ACE as one of the
best pipeline project execution organization
through continual improvement and adherence to
quality management system as per ISO 9001:2008
2.To improves its turnover through quality services
in the area of engineering, procurement,
Costruction and project management by executingprojects within time schedules and budget
estimates.
3.To adopt Continual review and improvement as a
way of life by improving expertise and upgrading
competence of its staff through motivation and/or
training.
4.To establish goodwill for ACE with improved
customer satisfaction and fulfilling customer
requirements through data analysis, appropriate
feedback and feed forward reports.
5.To maintain rejection/defects levels of services
provided to a bear minimum level
6.To carry out human resources planning on short
term and long term basis so as to ensure optimum
resources utilization.
7.To conserve natural resources while
implementing the projects.
-
8/9/2019 Ace Pipeline Contracts Pvt
11/41
Hierarchy Of The company:
Managing Directors:Mr.Anoop Singh
Vice President:Mr.Ravneet Singh
Mr.Tarun Singh
Mr.K.Namdev
C.A(Finance Advisor):-Mr.Bharat Tansalia.
General Manager:Mr.S.Raghunathan
Finance Manager:-Mr.Bajirao
Account Head:Mr.Patil
Purchase Head:Mr.Modi
Hr.Head:Mr.Guman
-
8/9/2019 Ace Pipeline Contracts Pvt
12/41
Introduction
Budgeting
Budgeting meaning of budgeting in simple words is estimation or
making forcasting about future expense which company have to
incurred for execution of project activities.
Budget of any project will include all the expenses relate to the
project,so while making budgeting all the small expense also have
to be consider.
DOCUMENT REQUIRES FOR MAKING THE BUDGET
For making budget of any pipeline project first off all one should go
through the tender copy
TENDER COPY:-It is a document which gives all the detailsabout project, the terms & condition of the project.It includes main
things like:-
Project Period:-It gives the details about within what time all
mechanical as well as the commissioning part of the pipeline
should be completed.
Scope Of Work (SOW):-It gives the details about what exactly
the task have to do under main heads
Eg:-
Topographical survey:
Pipeline route study including locating the centre line of
pipeline alignment on the ground.
Soil investigation.
Reserved forests, Mining sites, Religious Places.
-
8/9/2019 Ace Pipeline Contracts Pvt
13/41
How many crossing are there on the path of the pipeline route
& on that basis what angle should keep for making horizontal
directional drilling.
How many power & telephone poles are there in between the
pipeline route. Corrossion Survey which includes chemical analysis of soil
investigation.
Scope Of Rate (SOR):-It gives the details about estimated cost for
executing all the activities related to the project.
Scope Of Quantity(SOQ):-It gives details about quantity of material
required.
Eg.
how much quantity of casing pipes of different diameter will be
required.
Payment Terms:-It gives the details about the payment terms likewhen the owner will make the payment, which further depends
upon the percentage of completion of work.
Eg:-
Piping Material:-
A) 90% Of item rate will be paid on receipt of all material at site.
B) 10% on completion of testing, insulation, commissioning.
Civil Work:-
A)75% till completion of all work
B)25% on acceptance of completion of entire job.
Structural Steel:-A)90% of item rate will be on receipt of all material at site
B)10% on completion of testing, insulation, commissioning
-
8/9/2019 Ace Pipeline Contracts Pvt
14/41
Details about liquidity damage:-it gives the details about how much
percentage of contract value as LD contractor have to pay for not
completing the project in time.
Details about Bank Garauntee :-It gives the details about how
much percentage of total project cost have to be kept aside in thebank in the favour of contractee.
Test to be carried out:-It gives the details about which different test
the contractor have to be carried out while execution of the project
Eg :-
Non-destructive test(NDT)
Electronic Gauge pigging(EGP)
Hydrostatic test.
Horizontal Directional Drilling(HDD)
Pipeline details:-It gives the details about pipeline
Eg:-How much will be the length of pipelines.
What are diameter pipes have to used for different pipelines.
All above mention details are important from budgeting point of
view.
-
8/9/2019 Ace Pipeline Contracts Pvt
15/41
CHAPTER-2
Work Done On Budgeting & preparation Of estimated cash flow
statement Of HINDUSTAN PETROLEUM CORPORATION
LIMITED Project.
Details of the projects:-
HPCL is planning to construct pipeline for white oil terminal & LPG
terminal, in which all white oil products except mineral turpentine
oil(MTO) & Hexane which will be received through cross country
pipeline from additional tankage package(ATP)to white oil
terminal.MTO will be received through cross country pipeline from
refinery to new white oil terminal & hexane will be received by tank
trucks & LPG facility will be capable of handling LPG ,Auto LPG &
Propylene,& major quantity of LPG will be supplied to GAIL
terminal.
Following products will be handled at white oil terminal
Mineral Turpentine Oil (MTO)
Aviation Turbine Fuel (ATF)
Naphtha
Super kerosene Oil (SKO)
High Speed Diesel(HSD)
Motor Spirit(MS)
-
8/9/2019 Ace Pipeline Contracts Pvt
16/41
Soft Super kerosene Oil (Soft SKO)
Following Products will be handled at LPG terminal
Liquefied Petroleum Gas(LPG)
Auto Liquefied Petroleum Gas(Auto LPG)
Propylene
Details Of pipeline
Sr.No PIPELINE NAME UNDERGROUNDPILELINELENGTH(Mtrs.)
ABOVEGROUNDPIPELINELENGTH(Mtrs.)
TOTALLENGTH(Mtrs.)
WHITE OIL TERMINAL PIPELINE DETAILS1 14FIRE WATER
PIPELINE903.16 460 1363.16
2 10ATFPIPELINE
903.16 749.22 1652.38
3 14NAPHTHAPIPELINE
903.16 749.22 1652.38
4 16MS PIPELINE 903.16 749.22 1652.38
5 16HSDPIPELINE
903.16 749.22 1652.38
6 16SKO/ATFPIPELINE
903.16 749.22 1652.38
7 24SKO/HSDPIPELINE
903.16 749.22 1652.38
8 12SSKOPIPELINE
903.16 153.37 1056.53
9 4MTO PIPELINE 3337.89 288.11 3626
10 24COMMON 3337.89 2712.16 6050.05
-
8/9/2019 Ace Pipeline Contracts Pvt
17/41
PIGGABLEWHITE OILPIPELINE
LPG TERMINAL PIPELINE DETAILS
1 12LPG GAILPIPELINE
692.49 - 692.49
2 6PROPYLENEPIPELINE
3337.89 800.28 4138.17
3 6AUTO LPGPIPELINE
3337.89 800.28 4138.17
4 12LPGPIPELINE
692.49 - 692.49
Project Duration
Sr.No Terminals Details Duration(Months)1 White Oil Terminal 10
2 LPG Terminal 8
Project Cost:-21.5 Cr.
Payment Terms:
Piping Material:-
A) 90% Of item rate will be paid on receipt of all material at site.
B) 10% on completion of testing, insulation, commissioning.
Civil Work:-
A)75% till completion of all work
B)25% on acceptance of completion of entire job.
Structural Steel:-
-
8/9/2019 Ace Pipeline Contracts Pvt
18/41
A)90% of item rate will be on receipt of all material at site
B)10% on completion of testing, insulation, commissioning
For Erection & laying Of Pipeline
For piping materialA)75% of item rate will be on fabrication & testing
B) 25% after completion of entire job.
Topographical Survey & Soil investigation
A) 75% of item rate on completion of specified job
B) 25% after completion of entire job.
Test to be carried out during the execution of the project
Non Destructive Test (NDT).
Cathodic Protection System (CPS).
Horizontal Directional Boring (HDB).
Soil Investigation test.
Hydrostatic test.
Geotechnical Survey.
-
8/9/2019 Ace Pipeline Contracts Pvt
19/41
Ace pipeline Contracts Pvt.Ltd will have to pay 7.5 % of
project value per week as LD for not completing the project
ontime & 15 % of the project value as bank garuntee have to
keep aside.
BUDGETING
The meaning of budgeting in simple words is estimation of
expenses or making forcasting about future expense which
company have to incurred for execution of project activities.
Budget of any project will include all the expenses relate to the
project,so while making budgeting all the small expense also have
to be consider.
As Ace pipeline Contracts Pvt.Ltd is basically dealing with pipeline
costruction project,so the major expenses in that area are:-
PROCUREMENT COST
SUBCONTRACTOR SERVISES COST
-
8/9/2019 Ace Pipeline Contracts Pvt
20/41
OTHER EXPENSE
RESEARCH METHODOLOGY
Sources of DATA COLLECTION
Finance Department
Account Department
Purchase Department
HR Department
Tendor Copy
-
8/9/2019 Ace Pipeline Contracts Pvt
21/41
Information Collected From Employees
Procedure for making the budgeting of project
Following Steps individual should follow to make the budget of any
project.
1.Go through the tender copy & understand the details about the
project.
2.Depending upon scope of work analyse the requirement of
material for the execution of the project,different test to be carried
out during the execution of the project.
3.With the help of Board of Director deside whether to give any
part of the project to be completed to the sub-contractors.
4.Analyse the different activity to be carried out & based on that
make proper analysis of requirement of labour,equipment,What will
be the Mobilisation cost & many more.
-
8/9/2019 Ace Pipeline Contracts Pvt
22/41
The standard Format of Budgeting of HPCL project
Procedure to find out the budget of procurement
1)First off all go through SOQ in the tender copy as well as through
the drawings & checked the required numbers of different material.
2)By concerning with the purchase department Cheque the
availability of the different vendors in the market for any particular
item with their rates & depending upon rate & their delivery date
finalize the vendor ,likewise follow the same pocedure for all the
material & depending upon the requirement of quantity make the
budget of the procurement expense.
Procedure to find out budget of Subcontractor Services
1) With the help of Board of directors first off all decide which part
of the project have to be given to the sub-contractor for execution
on contractors behalf.
2)Go through the tender copy to make bench marking of the
length of pipeline where subcontractor services have to be carried
out.
3)cheque the availability of different vendors for the execution of
the services & analyse their different rates to carry out those
services.
3)Analyze what will be requirement of different machinery required
to carried out that activity
Eg: For making the budget of Non destructive test (NDT) Xtechs.
Pvt. Ltd have following rates.
1)Rs.10/-per inch of exposed film using 3wide film
2)Rs.11/-per inch of exposed film using 4wide film
3)Rs.70/-per exposure for joints 2 inch & below
4)Rs1200/-per day unit charge for X-ray tube & Generator.
-
8/9/2019 Ace Pipeline Contracts Pvt
23/41
5)Service Tax @ 10.3 %
Estimated Cost of NDT
For carryingout NDTthrough X-ray
Diameter ofpipeline
length ofpipeline(Mtrs.) No.of joints
per jointcost Total cost
14" 3015.54 251 540 135699
10" 1652.38 138 480 6609516" 4957.14 413 600 247857
24" 7702.43 642 900 57768212" 1749.02 146 600 87451
4" 3626 302 300 90650
6" 8276.34 690 375 258636
subtotal 1464070
Gamma -rays
Diameter ofpipeline
length ofpipeline No.of joints
per jointcost Total cost
14" 3015.54 251 400 100518
10" 1652.38 138 450 6196416" 4957.14 413 600 247857
24" 7702.43 642 900 577682
12" 1749.02 146 480 69961
4" 3626 302 225 679886" 8276.34 690 270 186218
sub
total 1312187
-
8/9/2019 Ace Pipeline Contracts Pvt
24/41
machinerycost months
1200*30 8 288000
Mobilization &Demobilization 50000
Subtotal 3114258
Servicetax(10.3%) 320768.556
TotalCost 3435026.381
For making the budget of Cathodic Protection Services.
First off all we have to find out requirement of different material to
carried out test
Sr. No. Item Description
1 CPPSM
2 MMC Anode Bed
3 Anode Junction Box4 Cathode Junction Box
5 1C*35 sq mm cable6 1C*4 sq mm cable
7 3C*6Sq mm cable8 Reference cell
9 Computerized Test Station Unit
10 CTSU reader
11 Pin Brazing Consumables12 Any Other material & consumable required
for the completion of work
-
8/9/2019 Ace Pipeline Contracts Pvt
25/41
Then individual have to see the availability of the subcontractors
available to carried out that activity.
Sr. No. Pipeline Details Length Of
ThePipeline
Cost Per
Km.
Total Cost
White Oil terminal
1 14" fire water P/L 1.36316 51000 69521
2 10"ATF
1.65238
52221 86289
3 14" NAPHTHA
1.6523851000 84271
4 16"MS1.65238 49000 80967
5 16"HSD1.65238 49000 80967
6 16"SKO/ATF1.65238 49000 80967
7 24"SKO/HSD
1.6523826935
44507
8 12"SSKO 1.0565354000
57053
9 4"MTO 3.62660000
217560
LPG terminal
1 12LPG GAILPIPELINE
0.69249 54000 37394
2 6PROPYLEN
E PIPELINE 4.13817 58000 2400143 6AUTO LPG
PIPELINE 4.13817 58000 240014
4 12LPG 0.69249 54000 37394
-
8/9/2019 Ace Pipeline Contracts Pvt
26/41
PIPELINETotal 1519876
Likewise we can make the Budget Of different activities of the
subcontractor services.
Procedure for making budget of other expenses
For this first off all we have to see what will be the other
expenses.
A)Drawing Expense.
B)Equipment Rental Charges.
C)Labour Expense.
D)Mobilization,Demobilization expense
E)Site expenses
F)Diesel,Fuel Expense.G)Repair & maintenance Cost
& many more
To find out the budget of other expense first off all one must have
to analyse the execution of the project activity.
Eg.
Suppose one want to find out the labour requirement then as
at the starting of the project menpower requirement will be less as
in the starting all the topographical survey & documentation work
will be carried out & after few month the requirement of the
manpower will be more as project will lead to peak.& again at the
-
8/9/2019 Ace Pipeline Contracts Pvt
27/41
last menpower requirement will be less as at the last almost all the
task shall been completed.
Again depending upon the monthwise execution of the pipeline
project activity the requirement of the menpower will vary.
-
8/9/2019 Ace Pipeline Contracts Pvt
28/41
Designation No JUN JUL AUG SEP OCT NOV
no amt no amt no amt no amt no amt noaccount 1
10010 2
22510 2
22510 2
26510 2
26510 2
cook 21033
0 62857
5 62857
5 73881
5 73881
5 6
diesel dispn. 1 5000 21100
0 1 6000 1 6000 1 7500 1documentation 1
13000 1
13000 1
13000 1
13000 1
13000 1
driver 1 7000 3
29600 5
42920 5
42920 7
64090 7
engg 23900
0 61251
48 51042
90 36550
0 49034
0 5engg,ndt 1
27000 3
49290
p & a 1
1800
0 1
1800
0 1
1800
0 1
1800
0 1
1800
0 1
fitter 11124
0 22024
0 44424
0 55124
0 55374
0 4grinder 2
13800 4
28000 8
55832 9
60820 9
60820 5
operator 3
37500 8
86016 8
90000 10
111930 8
88000 7
pm 16000
0 16000
0 16000
0 16000
0 16000
0 1riggerforeman 1
10010 2
20020 1
10010 1
15010 1
15010 1
safety
officer 1
1200
0 1
1200
0 1
1200
0 1
1200
0 1
1200
0 1supervisor 2
50000 2
30000 6
118000 6
114420 6
114430 6
surveyor 3
55000 4
69780 4
69780 3
48750 3
45000 2
weldinghelper 3
11700 15
59715 17
67760 18
70730 18
71730 18
welder 1
20200 11
159440 12
158175 13
168460 13
181900 10
weldingsupervisor 1
12000 1
12000 1
12000 1
16000 1
16000 1
coatingsupervisor 1
12000 1
12000 2
32000 1
16000 1
coatinghepler 5
30000 3
18000 2
12000 3
20700 2
electricianhepler 1 4000 1 4000 1 4000 1 4000 1electrician 2
14410 2
14410 2
14410 2
16410 1
weldingengg 2
54000 2
54000 2
foreman 2
50000 1
25000 1
35000 1
gascutter 1 4500 1 4500 1 4500 1 5300 1helper 15
61116 19
97620 18
72460 18
72460 17
hydra
-
8/9/2019 Ace Pipeline Contracts Pvt
29/41
For making the equipment rental expense following steps must have to be
1)first of all analyse the requirement of the equipment for the execut
2)Cheque the availability of required equipment for the execution of the pr
3)find out what are the rental charges of equipment
For making the Site expense following steps should be taken:-
1)Analyse what will be the site expense like mess,office setup cost,campus
2)have to analyse what different activity have to be performed under the m
3)Depending upon the menpower how much will be the expense under diff
-
8/9/2019 Ace Pipeline Contracts Pvt
30/41
Site Expense
A. Mess
Sr.No Head Qty. Rate Month Amt
1 Premises 2 4000 10 80000
2 Elect.& water 2000 10 35000
3 Fridge 2 10000 20000
4 Chairs 42 300 12600
5 Dinning Table 8 8000 640006 Kitchen Utensils 20000
7 LPG gas 10 110000
8 Grossary 10 500000
9 Misc. 40000
Sub Total 881600
B. Campus Cost
Sr.No Head Qty. Rate Month Amt
1 Store room 2 40000 8 6400002 Elect.& water 25000 10 250000
3 Illumination 100000
4 Fencing 150000
Sub Total114000
0
C. Office Setup
Sr.No Head Qty. Rate Month Amt
1Building HireCharges 1 40000 10 400000
2 Electricity 10000 10 100000
3 Chairs 15 900 13500
4 Drinking Water 4000 10 40000
5 Table 15 2000 30000
6 Filing Racks 20 3000 60000
7 Computers 12 30000 360000
8 Printers 3 5000 15000
9 Fax machines 1 6000 6000
10 AC 4 10000 4000011 Fans 5 1000 5000
12 Tubelights 10 350 3500
13 Stationeries 60000
14 Misc. 50000
Sub Total118300
0
Total Site Expenses320460
0
-
8/9/2019 Ace Pipeline Contracts Pvt
31/41
-
8/9/2019 Ace Pipeline Contracts Pvt
32/41
CASHFLOW STATEMENT
In simple words Cash means Money,& there will be either cash inflow or ca
In project Cash inflow means the receipt of bills from the owner & cash o
incurred for execution of project.
Cash flow statement includes following details:-
Cash inflow
Openinig Balance
Internal Funds
Loan details
Sales receipts
Cash Outflow
Procurement Cost
Subcontractor Services Cost
-
8/9/2019 Ace Pipeline Contracts Pvt
33/41
Other expenses
Loan payment
Interest on loan payment
-
8/9/2019 Ace Pipeline Contracts Pvt
34/41
While making the cash flow statement individual must have the proper
activities of project.
Eg.
For making the cash flow statement of inflows
first of all individual have to see what are the terms & condition of the paym
that when contractor will receive the bills.
And based on that only individual can get idea about the monthly earning o
Again depending upon the loan terms & conditions when we wil
the loan term month wise.
For making the cash flow statement of cash outflow.
individual must have the proper analysis of monthwise execution of di
Eg.
For procurement individual must have to make the preplanning a
with the purchase department.
For the Subcontractor services expense & for other expenses indi
& have to make analysis which activity will carry out in which month &
monthly expenses of that activity.
by concerning with the fund manager the distribution of different lo
monthwise.
-
8/9/2019 Ace Pipeline Contracts Pvt
35/41
Difference Between Budget & Cashflow statement
Budget gives the details about the overall expense of the project
Cash flow statement gives the details about the monthwise expe
In budgeting individual only consider expenses (Cash outflow).
In Cashflow statement individual consider both inflow as well as t
-
8/9/2019 Ace Pipeline Contracts Pvt
36/41
-
8/9/2019 Ace Pipeline Contracts Pvt
37/41
Advantages of maintaining the actual cash flow statement while execu
The company will get idea about the running expense of the proj
The company can keep the track weather the estimated cost flo
also get idea about the efficiency level of the project.
-
8/9/2019 Ace Pipeline Contracts Pvt
38/41
Recommendations
There should be contribution of every department.
For making of exact cash flow statement there.
-
8/9/2019 Ace Pipeline Contracts Pvt
39/41
-
8/9/2019 Ace Pipeline Contracts Pvt
40/41
-
8/9/2019 Ace Pipeline Contracts Pvt
41/41
Recommendations
There should be contribution of every department.
For making of exact cash flow statement there.