abridged ms project guide

Upload: vignesh-dks

Post on 10-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Abridged MS Project Guide

    1/53

    Setting up and using MS Project

  • 8/8/2019 Abridged MS Project Guide

    2/53

    Using this Guide

    Section 1 How does MS Project Work

    Section 2 Setting Up for a project

    Section 3 Tasks and Relationships

    Section 4 Constraints

    Section 5 Resources

    Section 6 Levelling

    Section 7 Tracking

    Section 8 Costs

  • 8/8/2019 Abridged MS Project Guide

    3/53

    provide a quick reference to common tasks

    provide Best practises in using the tool

    vast amount of functionality in MS project and the aim is to give aglimpse of the features that will add value to the PMs planning and

    project process.

    The main objective is to ensure that PMs know that

    MS project is a tool that provides the answer to some questions,

    It does not set the questions or run the project

    If used properly can dramatically improve the speed and clarity of the

    project planning process.

    .

  • 8/8/2019 Abridged MS Project Guide

    4/53

    How does MS Project Work

  • 8/8/2019 Abridged MS Project Guide

    5/53

    MS Project

    It is a scheduling tool that adds up and subtracts

    It provides a graphical display of project data

    It allows rapid planning and What Ifs

    It follows rules that is set

    It stores all the data to plan, record, and track project

  • 8/8/2019 Abridged MS Project Guide

    6/53

    Working

    MS Project is a calculator..

    Earliest

    Start Time

    Duration Earliest

    Finish Time

    Activity Description

    Latest Start

    Time

    Slack Latest Finish

    Time

    It calculates every task using these formulae below Early Start + Duration = Early Finish

    Early Finish Latest Finish = Slack

    Latest Finish Duration = Latest Start

  • 8/8/2019 Abridged MS Project Guide

    7/53

    Forward pass Scheduling

  • 8/8/2019 Abridged MS Project Guide

    8/53

    Backward Pass Scheduling or Just in Time

    Latest start for

    launch is carried

    back to the

    predecessorsTasks with Zero Slack are said

    to be Critical and form the

    Critical Path.MS project

    adds and subtracts up thenumbers and displays the

    Critical path in RED

    Tasks with Slack are said to

    be Non Critical MS projectdisplays non Critical Tasks in

    BLUE

    Now MS Project starts from the end and works backwards

  • 8/8/2019 Abridged MS Project Guide

    9/53

    So What?.

    Changing just one duration..Train Astronauts causes all the yellow boxes to

    be recalculate

    In fact MS Project calculates the whole plan again from start to finish and back

    again.

    Build Apollo is no longer on the Critical Path but Train Astronauts is

    MS Project has told something significant.the Critical path has changed , now

    we have to take the next step

  • 8/8/2019 Abridged MS Project Guide

    10/53

    Setting up and using MS Project

  • 8/8/2019 Abridged MS Project Guide

    11/53

    Starting a new Project File

    Three basic steps to ensure

    Step 1 Set the Scheduling Rules

    Step 2 Create the Project Calendar

    Step 3 Set the Project Information

  • 8/8/2019 Abridged MS Project Guide

    12/53

    Setup Step 1 Go to ToolsOptionsSchedule

    Change default task type toFixed DurationThis will stopduration being changed if youadd more resource

    Un-Check New tasks areeffort driven.this stops theduration changing if you addmore resource

    Why..MS Project uses

    Work=Duration x Units (ofresource)

    If you fix duration then addingresource does not change theplan

    The Majority of tasks are NOT

    resource or effort drivenameeting does not get shorter ifyou have more peopleattend.Driving from Paris toMonte Carlo does not getshorter if you have two drivers

    Of course some tasks may be truly effort driven but you can change those on a task by task basis later.. But

    be carefuldoubling the effort does not always halve the time taken

    Change work entryto whatever you

    normally

    usemost people

    use Days, but youcan use whateversuits you

  • 8/8/2019 Abridged MS Project Guide

    13/53

    Setup Step 2 Go to ToolsChange Working

    Time

    Create a New Calendarbased on theStandardand give it a name

    Edit the Calendar to reflect your workingdays and Holidays

    Why..MS project uses the Calendar toschedule..the standard calendar appliesto all projects without their owncalendar.what may be good for thisproject may not be for others..also when

    combining projects differences in workingtime between Standard Calendarscreated on different machines can causestrange conflicts

    Do NOT adjust the hours of work unlessyou are very experienced especially afterthe start of your projectit will recalculateall the durationsMost people onlyschedule in days or parts of days it getsvery complicated if you start scheduling in

    hours and whos going to track it?working hours do not generally affectthe project..but they do affect People init so more about that when we talkabout resources

    Do NOT select Day titles when setting nonworking timeunless you intend notworking Mondays for eternity.nicethought but your manager may not like it

    This Changesselected days to

    Non Working

    You can create as many Calendars as you wish for different

    Countries or working practices to use later with individual tasks

  • 8/8/2019 Abridged MS Project Guide

    14/53

    Setup Step 3 Go to ProjectProject Information

    Set the project Start date and set thescheduling method.From Start date is thenorm.From Finish date makes it Just inTime.Backward scheduled also known asJust Too Late because there is no room forerrors.

    Current Date shouldonly be changed for

    What If Modellingso

    leave it alone.

    Most Importantselect the Calendar

    you created in Step 2

    as your project

    calendar.All tasks

    will now use that

    calendar for scheduling

    You can select

    different Calendars to

    schedule specific tasks

    on an individual

    basisTasks

    performed in different

    countries for example

  • 8/8/2019 Abridged MS Project Guide

    15/53

    Setup Complete

    Congratulations you cannow start entering Tasks andResources..

    Although not required to startyou can also set a few moreoptions..

    Currency

    Elect to show the project Summarytask (recommended)

    Show Outline number.. WBS code

    Take some time looking at theother options Tabs

  • 8/8/2019 Abridged MS Project Guide

    16/53

    Tasks and Relationships

  • 8/8/2019 Abridged MS Project Guide

    17/53

    Creating Tasks

    Enter the Name of the task and its Duration

    Duration can be entered as h hours, d- days, w- weeks and mo- months

    Duration can be planned or elapsed d ed, w ew

    Planned Duration takes into account the project Calendar

    Elapsed Duration takes no account of the project Calendar and is 24/7

    Use Elapsed duration for third party tasks where you have no control on theirworking practices or hours.Recruit staff via agency duration 3 weeks

    should be elapsed because the agency does not work to our calendar

    A question mark against duration means it is an estimate

    Look at the two tasks below and spot the differenceone is displayed across

    Sat and Sun because those days are non workingID Task Name Duration Start

    Install Server 2 days ri 30/0 /0

    T S S T T S S T T S S

    2 ay '03 02 Jun '03 09

    ID Task Name Duration Start

    Install Server 2 edays ri 30/0 /03

    T S S T T S S T T S S

    2 ay '03 02 Jun '03 09

  • 8/8/2019 Abridged MS Project Guide

    18/53

    Task Information

    Double click on a task to get

    Task Info

    You can change the task type to

    be effort driven if it really is

    You can Assign a calendar to the

    task.note default is

    None.that means it uses theproject calendar by default

    If you assign one then a calendar

    icon will appear in the Info

    column

    A task deadline can be assigned

    but this is NOT a constraint and

    does not lock the schedulebut

    Project will report when its

    missed

    ID Task Name Duratio tart inish Predecessor esource Name

    Install erver da ri / on /

    onfigure erver da ri / ri /

    T T T T T

    ay ' un '

    arning B ode can be changed

    manually but once it has been

    project will not update it again

    You can embed objectssuch as Docs, xls, ppt files

    in Notes

  • 8/8/2019 Abridged MS Project Guide

    19/53

    More Task Information in Tables

    There are over 2 fields to use about eachtaskThe good news is you dont have to usethem all!

    Data is arranged in Tablesthe default is theEntry Tableeach table displays differentInformation sets

    Select More Tables to get a bigger list You can also create you own tables and

    customise fields to store data Specific to yourProject

    The Organiser allows you toreuse table structures you

    have created in other

    Project Files

  • 8/8/2019 Abridged MS Project Guide

    20/53

    Creating your own tables

    You can putwhatever fields youlike in a table bestto copy an existingone and give it anew name

    There are 3 textfields forUser

    definition.Selectthe Text Field andenter a Title suchas Departmentthat is relevant tothe data you aregoing to store

    You can define,Date, Flag(Y/N),Number, Cost, Text,Start and Finish,Outline Numbers,Durations, to namea few

    Shows Table

    in main menu

    Durations and Start andFinish fields are used forWhat If modelling andscenario building

    Think how you can

    enhance your project by

    storing really useful

    information with every

    task

  • 8/8/2019 Abridged MS Project Guide

    21/53

    Creating Relationships (Dependencies)

    There are four types of Relationships between Tasks

    Start to Finish SF Task Finishes when predecessor Starts

    Finish to Start FS - % of tasks are related this way, Starts when

    predecessor Finishes

    Start to Start SS Starts at the same time as predecessor

    Finish to Finish FF Finishes at the same time as predecessor

    A

    B

    D

    F

    E

    C

    H

    G

    FS

    SF FF

    SS

  • 8/8/2019 Abridged MS Project Guide

    22/53

    Lead and Lag times

    A lead time is where you wish tasks to overlapExample.Task A manufacture 1 tinsof baked beans..Task B. put labels on tins You would want to start putting labels onafter say 5 % of the tins had been made you would therefore apply a 5 % lead timebetween A and B

    A lag time is a pause after the finish of one task before beginning the next..Task C OrderPC.wait for delivery 1 days.Task D. PC DeliveredTask D will have a 1 d lag

    Lags and leads can be expressed as duration or as a % of the Predecessor

    To set a lead or lag timedouble click on the link between two tasks on the Gantt Chart andenter a value in the lag box..

    A

    B

    D

    C

    1 d lag

    5 % Lead

    A minus -2 lag = a

    lead or enter a - %

  • 8/8/2019 Abridged MS Project Guide

    23/53

    To Create a Relationship (Link) in MS

    Project

    Highlight the two task names and selectLink Iconif the Tasks are not next toeach otheruse the CTRL key to selectthem.

    Always start with the uppermost task

    Alternately place the mouse in thecentre of a task on the Gantt Chart anddrag downwardsa link icon appearsand you can drop it on the task to belinked..

    AlternatelyOpen the Task informationbox and select the name of the task tolink in the Predecessors Tab

    Break Links using the Break Link buttonor double click on the link in the Ganttchartand chooseDelete

  • 8/8/2019 Abridged MS Project Guide

    24/53

    Relationship problems?..

    If you get this message like this whenyou create a relationship.its not anerror..It just says that there is notenough time to complete the tasksand preserve the relationship.

    So What.well if you choose tocontinuewhich you should.youhave to resort to brain power toresolve the conflict

    Shorten the tasksallow the

    successor task to moveAdd moreresource Work longer hoursWorkharder! Its up to YOU..Project hasdone its 25%. It told you that thereis a problem that requires youraction now its your 75%reasoning that counts

  • 8/8/2019 Abridged MS Project Guide

    25/53

    Creating Summary tasks

    Summary Tasks Roll up Durations and Costs and are useful for defining levels ofyour WBS

    Create a Summary task by Demoting the tasks underneath it using the Indentand Outdent buttons on the Tool bar

    Show the Outline Number to see WBS Code

    You can go down 5 levels to the Work Package.If you need more then

    perhaps your plan is too complex.Remember do not include detail that youcannot influenceClean Room.. Instead of. collect Brush, sweep from leftto right, put broom away, examine floor for specks of dust.thats overplanning. let the cleaner make their own plan!

    It is not good practise to Link Summary tasks together.link the individualtasks.. if necessary create and link milestones at the Start and end of eachsummary task

    ID Task Name Duration

    1 Server Install 3 days?

    . Install Server day

    1.2 Configure Server 2 days?

    . . Configure OS day

    5 . . Configure pps day

    W T S S T W T S S T W T S S

    ay '0 0 un '0 09

  • 8/8/2019 Abridged MS Project Guide

    26/53

    Milestones

    Milestones are tasks with no duration

    Enter the task as normal and set duration to Zero

    Milestone tasks may physically take up time. such as a contract

    signing which has taken 4 hours. but it is symbolic and still has zero

    duration for the purposes of the schedule

    If a tasks completion is the milestone then enter a task and a separate

    milestone to get the right meaning

    If you are planning correctly.you will find that many of your tasks are in

    some way linked to milestones..If they are not.perhaps another look

    at the plan..I ask ame uration

    1 Server Install 5 days?

    . Install er er day

    1.2 Configure Server 4 days?

    4 . . onfigure day

    . . onfigure pps 4 days

    . . onfig omplete 0 days 05/06

    M M M

    May '0 0 un '0 09

  • 8/8/2019 Abridged MS Project Guide

    27/53

    Displaying the Critical pathand more

    Use The Gantt Chart Wizard on the formatting toolbar to display the critical path

    Select Show Critical Path when asked and then follow the wizard

    MS project will display the Critical Tasks in Red and Non Critical in Blue

    You may also like to display Slack for non Critical tasksTry

    this..FormatBar styles

    Enter a new rowcall it

    Slackappearance

    underline.Normal,noncriticalfro

    m Early start to late finishif in

    doubt copy the screenshot. You get

    this. I call it the Slack Gantt

    ID Task Name Duration

    . . Configure S . days

    . . Install UPS day

    . . Configure pps days

    3r t tr t r,

    W T F S S M T W T F S S M T W T F S S M

    May ' un '

    The window of opportunity for

    the task is displayed

    The task can be completed any time. along the blue line

  • 8/8/2019 Abridged MS Project Guide

    28/53

    Constraints

  • 8/8/2019 Abridged MS Project Guide

    29/53

    Constraints

    Constraints allow you to specify a No later than, No Earlier than, ordo at aspecific time

    Constraints in general are badly used only apply constraints sparingly. ManyPMs apply constraints to every task thus locking the schedule.which turns MSproject into a wall chart producer

    Each time you set a constraint MS Project has less flexibility to change the

    schedule

    You should set constraints after you have done. planning and what ifs. andyou have allowed MS Project to move tasksand your resource plan works..Itshould be when you are ready to save your baseline for the first time

    You should set Constraints for absolute events that will Not change or are

    beyond your control to change You should set constraints for tasks whose time horizon does not allow them to

    be moved

    Remember this is a Plan.and Plans ChangeConstraints limit Change

  • 8/8/2019 Abridged MS Project Guide

    30/53

    Setting a Constraint

    Select a task and open the task

    Info box

    As Soon as Possible is default

    As Late as Possible is for JIT

    Start and Finish no Later than are

    flexible forward schedulingconstraints

    Start and Finish no Earlier than

    are used when using backward

    scheduling or JIT

    Must Start and Finish on are

    absolute constraints

    Select the most appropriate

    constraint.think carefully if you

    are applying what you meanand

    select the constraint date

    Think through

    the meaning of

    the constraint

    as applied toyour task

  • 8/8/2019 Abridged MS Project Guide

    31/53

    Messages you get when setting a

    Constraint

    Cancel if you pressed the wrongbutton!

    This is the opposite of what you meanto doso dont choose it

    This is what you intenda constraint

    will be setbut it may cause aconflict.

    I didn't mean it Option

    Continueyes please..

    So Whatthis is not an error. itis project telling you that you now haveto take some actionIts done its25%..Now its your 75% reasoningthat counts

  • 8/8/2019 Abridged MS Project Guide

    32/53

    Resolving a Conflict

    MS Project tells you about a conflict, to quantify how big the problem is.go tothe View menuTablesSchedule

    The schedule table shows you the total slack for the project and the task thatyou have set the constraint on..in this case you have to find 1 day to correct theschedule

    What to doShorten any task on the critical path (re-evaluation).work longer

    hours or non working days..add resource to shorten the task.introduceleads. reduce lag timesapply leadership and motivate..in fact its up toyou.whatever method you can take to shorten the critical path.crashing theschedule by one day!

  • 8/8/2019 Abridged MS Project Guide

    33/53

    Resources

  • 8/8/2019 Abridged MS Project Guide

    34/53

    Resources People, Materials, and Places

    Resources are defined in the project and assigned to tasks A resource can be Manpower, or a materiala place is treated as a material.

    Material performs no workbut may have a cost. It is assumed that only peopleperform work

    Consider with each resource you intend to use whether that resource will make atask effort driven and in particular. will it be linear..A machine working at

    double speed could be expected to produce double the output but doublingthe number of consultants on a task does not necessarily produce twice theoutputit depends on skills. the problem..interaction and so on..In otherwords in most cases it is better to decide how long a task will take .manually

    2 people in a meeting takes 1hour.6 people in a meeting is therefore 2Mins?..I dont think so..more like 2 hours MS Project cannot resolvelogic like this!

    Most tasks do not conform to being Effort Driven by resources in a linear mannerso do NOT make the mistake of letting MS project calculate the duration

  • 8/8/2019 Abridged MS Project Guide

    35/53

  • 8/8/2019 Abridged MS Project Guide

    36/53

    Resource Details

    Email address and

    Windows account forgroup working using

    project Server

    Overall availability FromTo

    Use the Working timetab to set holidays

  • 8/8/2019 Abridged MS Project Guide

    37/53

    Resource Details (contd)

    Resource Costs canbe entered andadjusted by time

    Either enter theexact amount orenter a percentage

    change from the lastfigure

    You can put in 25different rates oneach TAB

    TABs A to E allowdifferent rates to be

    applied to differenttasks.For exampleTAB A for interCompany Rate, TABB for ExternalConsulting rate

    Companypay Rise

    Promotion!

    Rate Tables are selected in the task usage view by

    double clicking on the resource name against the task

    to be charged

  • 8/8/2019 Abridged MS Project Guide

    38/53

    Assigning Resources

    When Resources are assigned MS Project calculates the Work, andcosts generated by that resource(s) and applies the formula

    Work=Duration x Units

    Total Costs are calculated according to the rate tables Cost =Work xrate specific Information of the resources assigned

    It is assumed that a resource works evenly across the task unless youspecify otherwise

    The next time you change either the Calendar, resource units, or timebased information, MS project will calculate. either a new duration,amount of work.. or number of units

    When we fixed duration and made tasks not effort driven in setting upthe project..we retained control Now adding or removing resourcewill only change the amount of Work and thus the cost. The PMthen decides what affect those changes has on duration and modifiesthem accordingly

  • 8/8/2019 Abridged MS Project Guide

    39/53

    Assigning Resource

    Select the task or tasks in the Gantt chart andclick the resource icon

    Select a resource or resources and .click

    assign

    You can assign resources how you like as

    long as it is consistent.25% = 1 engineer

    of their time.2 % = two engineers.or 4

    engineers at timeyou decide

    Material is assigned as a decimal with the

    label you entered

    You could even use it to suggest skillFred at

    8%, John at 8 % as he is less skilled..butthis is probably too advanced for first use!

    If you wish to change a resource use Replace

    rather than Removeit prevents recalculation

    occurring

    R/D is Requested or

    Demanded and is used

    for group working

  • 8/8/2019 Abridged MS Project Guide

    40/53

    Modifying a Resource on a Task

    Sometimes the situation you are trying to simulate is not representedcorrectly by the standard assignment

    In these cases go to.View..Task Usage. And Double click on aresource assigned to a task

    You can change the amountof work donehere theManager only does 1halthough assigned at 1 %all day

    You can also change the ratetable for alternate costs

    Work Contouring can bechanged but avoid this untilexperiencedKISS Keep itSimple.S

  • 8/8/2019 Abridged MS Project Guide

    41/53

    Levelling Resources

  • 8/8/2019 Abridged MS Project Guide

    42/53

    There are never enough resources

    With a finite pool of resource, conflicts are bound to ariseMS Project tells youwhen there is a conflict by showing that a resource is over allocated..in otherwords you have used the same resource on more than one task at the sametime..

    Without using MS Project we know how to resolve this.Replace the resourcewith another. Reschedule so that the tasks no longer overlap.. reduce the

    allocation to 5 % on each task.the list is endlessits just called management MS Project can only help you with rescheduling the tasks.this is called

    Resource levelling.

    Resource Levelling can be Time Constrained or Resource Constrained.Whatdoes that mean?.

    Time Constrained is when you do not wish to extend the project but work withthe available slack and if necessary add or change resources to shorten theschedule

    Resource constrained is when there is No more resource available and thus theduration of the project will have to be extended to resolve conflicts

    MS Project will suggest possible solutions.it will not unravel a bad plan

  • 8/8/2019 Abridged MS Project Guide

    43/53

    Levelling Resources

    Here the resource Tech head has been assigned to both Installingthe UPS and the Workstation on the same day.so there is aconflict.

    We choose first to Level resourceswithin the available slackyoucan see that both tasks have slack showing.MS project worksouts how much slack is available and Delays the start of InstallWorkstation by 1 day

    You can check out what has been applied.Go to

    ViewTables.More tables and select the Delay Table.You canmanually change the delay or even remove it as you wishso evenif it all went horribly wrong you can simply set the delays back toZeroID Task

    ame Duration

    1. .1 onfigure S 0. days

    1. . Install UPS 1 day

    1. . onfigure

    pps

    days

    1. .

    onfig omplete 0 days

    1. . Install Workstation 1 day

    3rd

    tyContractor,

    anager

    ech Head

    05

    06

    Tech Head

    W T S S M T W T S S M T W T S S M

    May '0 0 Jun '0 09 J

    ID Task ame Duration

    1.

    .1 onfigure ! S 0."

    days#

    "

    1.

    .

    Install UPS 1 day#

    $

    1.

    .%

    onfigure&

    pps

    days

    ' 1.

    .

    onfig omplete 0 days(

    1.

    ."

    Install Workstation 1 day#

    3rd

    tyContractor,

    anager

    Tech Head

    05

    06

    Tech Head

    W T ) S S M T W T ) S S M T W T ) S S M

    $

    May '0%

    0

    Jun '0%

    09 J

    Project has moved the task along

    the slack line by1 day..if you dont

    agree..put it back.. by clearing thelevelling or changing the table

  • 8/8/2019 Abridged MS Project Guide

    44/53

    Levelling Resources (contd)

    Use Manual it iseasier to see what

    happens

    Leave these uncheckeduntil you are more

    experienced!

    Time Constrained..only movesnon critical tasks..uncheck it and

    project will move Critical tasks aswell..providing there are no

    constraints set

    Takes into accounttask priorities if used

    Set this to your timehorizonthere is generallyno point in levelling things

    six months away

    Over allocationsDayby day..Week by week

    Clear all levelling..orbetween

    dates.this is theOh No Im a PMget

    me out of here

    button!

    hoose. Tools.Resource Levelling

  • 8/8/2019 Abridged MS Project Guide

    45/53

    When Levelling Messages start to appear

    This is NOT a disaster..MS Project is just telling you that you master piece of

    resource planning is not greatit means that within the time and constraints

    currently set there is no solution that project can offer you

    Back to your planyou need either more time..more resources.less

    tasks..again its up to you.MS project has done its 25% and told you that you

    have a problemNow you employ your 75% and figure out the

    solution.modify your plan and let MS project work it out againthis time if you

    resource plan is better MS project may be able to fine tune it for you

    Remember..MS Project applies delays when Levelling.there is no Magic!

  • 8/8/2019 Abridged MS Project Guide

    46/53

    Tracking

  • 8/8/2019 Abridged MS Project Guide

    47/53

    Base lining

    Before we can effectively track our project we mustbaseline itThis simply records a copy ofyou plans.dates costs. durations and otherdata for comparison later

    You can Baseline either the whole project orselected tasks.

    In a long project you may not want to baselineactivity until it falls within your time horizon

    Select Tools.Tracking.Save Baseline

    Save all or part of the projectand if you need tosave up to interim plans that reflect changes to the

    original baseline

    Now save a copy of your plan in case youaccidentally save the baseline again

    Big Tip!

    Do a Save Asevery time

    you make major changes to

    your plan..and put it in a safe

    place in case you mess up the

    current file..

  • 8/8/2019 Abridged MS Project Guide

    48/53

    Basic Tracking

    Task Update box

    Select a task and Mark it

    ,25,5 ,75,1 %dont bother with

    63.56% who can judge exactly?

    These 5 boxes are interrelatedChange

    one at a time..to show actual progress

    Select a task and Mark it

    ,25,5 ,75,1 %dont bother with

    63.56% who can judge exactly?

    Update all tasks up to the

    time line

    ID Task Name Leveling Delay

    1 1 Server Install 0 edays

    2 1.1 Install Server 0 edays

    3 1.2 Configure Server 0 edays

    4 1.2.1 Configure OS 0 edays

    5 1.2.2 Install UPS 0 edays

    Tech1

    ead

    3rd pty Contractor,Manager

    Tech1

    ead

    W T F S S M T W T F S S M T W T F S S M

    26 May ' 0 3 0 2 Jun ' 0 3 0 2 Ju

    Today

    Tasks completed to the right of the time line are Early,

    Not completed to the left are Late

    The Tracking Toolbar

  • 8/8/2019 Abridged MS Project Guide

    49/53

    Tables & Views to help you track

    Variance Tablegives you schedulevariance against the baselinePositivevariance is a slippageStart variance isgreater than Finish variance shows animprovement..

    Summary Table shows % complete and totalcost

    Tracking Gantt shows variance againstbaseline.. shown as grey bars below each

    taskI3 Task 4 ame

    5 Ser6

    er Install

    7 Install Server

    8 ConfigureSer6

    er9

    @ onfigure A S

    B Install UPS

    C @onfigure

    D

    pps

    E @onfig @ omplete

    FInstall

    G

    orkstation

    5 B

    5 00%

    0

    0%

    0%

    0%

    09

    0%

    HT

    G

    T F S SH

    TG

    T F S SH

    7 C H ay '0 8 0 7 Jun '0 8 09 Ju

  • 8/8/2019 Abridged MS Project Guide

    50/53

    Costs

  • 8/8/2019 Abridged MS Project Guide

    51/53

    Cost Basics

    Costs are Planned in two ways.when resources are assigned totasks.and as fixed costs against a task

    Costs are generated as work is performed..as you mark tasks% complete so the costs are recorded

    Costs are ChargedAt the startat the endor prorated overthe duration of a task according to the resource that has beenassigned

    When you save the baseline you record in effectyour budget

  • 8/8/2019 Abridged MS Project Guide

    52/53

    Cost Table

    Cost not associatedwith resources

    Your Budget

    Planned work x resource

    rates assigned..thischanges with your plan

    Actual cost is derived from % completebutyou can edit it once task has been 1 %

    completed

    Not yet Spent

    Install Server final cost was2 over budget, adjusted

    actual after 1 % complete

    Task 75% completeyoucannot edit the actual

    cost....change the amountof work performed and this

    figure will change

    Unplanned fixed cost

    creates 2 overbudget

    Summary tasks roll upvariances and totals

    Total Cost = Fixed costs + resource based costs

  • 8/8/2019 Abridged MS Project Guide

    53/53

    Cash Flow Views

    In the Task usage view ..right click and show just coststhen a cash flow view isimmediately availableuse the zoom controls to zoom out to weekly, monthly orquarterly costsSummary tasks roll up the costs..

    If you want to show revenues create tasks to concur with customer paymentsand enter a Negative Fixed cost for the task.