abridged ms project guide
TRANSCRIPT
-
8/8/2019 Abridged MS Project Guide
1/53
Setting up and using MS Project
-
8/8/2019 Abridged MS Project Guide
2/53
Using this Guide
Section 1 How does MS Project Work
Section 2 Setting Up for a project
Section 3 Tasks and Relationships
Section 4 Constraints
Section 5 Resources
Section 6 Levelling
Section 7 Tracking
Section 8 Costs
-
8/8/2019 Abridged MS Project Guide
3/53
provide a quick reference to common tasks
provide Best practises in using the tool
vast amount of functionality in MS project and the aim is to give aglimpse of the features that will add value to the PMs planning and
project process.
The main objective is to ensure that PMs know that
MS project is a tool that provides the answer to some questions,
It does not set the questions or run the project
If used properly can dramatically improve the speed and clarity of the
project planning process.
.
-
8/8/2019 Abridged MS Project Guide
4/53
How does MS Project Work
-
8/8/2019 Abridged MS Project Guide
5/53
MS Project
It is a scheduling tool that adds up and subtracts
It provides a graphical display of project data
It allows rapid planning and What Ifs
It follows rules that is set
It stores all the data to plan, record, and track project
-
8/8/2019 Abridged MS Project Guide
6/53
Working
MS Project is a calculator..
Earliest
Start Time
Duration Earliest
Finish Time
Activity Description
Latest Start
Time
Slack Latest Finish
Time
It calculates every task using these formulae below Early Start + Duration = Early Finish
Early Finish Latest Finish = Slack
Latest Finish Duration = Latest Start
-
8/8/2019 Abridged MS Project Guide
7/53
Forward pass Scheduling
-
8/8/2019 Abridged MS Project Guide
8/53
Backward Pass Scheduling or Just in Time
Latest start for
launch is carried
back to the
predecessorsTasks with Zero Slack are said
to be Critical and form the
Critical Path.MS project
adds and subtracts up thenumbers and displays the
Critical path in RED
Tasks with Slack are said to
be Non Critical MS projectdisplays non Critical Tasks in
BLUE
Now MS Project starts from the end and works backwards
-
8/8/2019 Abridged MS Project Guide
9/53
So What?.
Changing just one duration..Train Astronauts causes all the yellow boxes to
be recalculate
In fact MS Project calculates the whole plan again from start to finish and back
again.
Build Apollo is no longer on the Critical Path but Train Astronauts is
MS Project has told something significant.the Critical path has changed , now
we have to take the next step
-
8/8/2019 Abridged MS Project Guide
10/53
Setting up and using MS Project
-
8/8/2019 Abridged MS Project Guide
11/53
Starting a new Project File
Three basic steps to ensure
Step 1 Set the Scheduling Rules
Step 2 Create the Project Calendar
Step 3 Set the Project Information
-
8/8/2019 Abridged MS Project Guide
12/53
Setup Step 1 Go to ToolsOptionsSchedule
Change default task type toFixed DurationThis will stopduration being changed if youadd more resource
Un-Check New tasks areeffort driven.this stops theduration changing if you addmore resource
Why..MS Project uses
Work=Duration x Units (ofresource)
If you fix duration then addingresource does not change theplan
The Majority of tasks are NOT
resource or effort drivenameeting does not get shorter ifyou have more peopleattend.Driving from Paris toMonte Carlo does not getshorter if you have two drivers
Of course some tasks may be truly effort driven but you can change those on a task by task basis later.. But
be carefuldoubling the effort does not always halve the time taken
Change work entryto whatever you
normally
usemost people
use Days, but youcan use whateversuits you
-
8/8/2019 Abridged MS Project Guide
13/53
Setup Step 2 Go to ToolsChange Working
Time
Create a New Calendarbased on theStandardand give it a name
Edit the Calendar to reflect your workingdays and Holidays
Why..MS project uses the Calendar toschedule..the standard calendar appliesto all projects without their owncalendar.what may be good for thisproject may not be for others..also when
combining projects differences in workingtime between Standard Calendarscreated on different machines can causestrange conflicts
Do NOT adjust the hours of work unlessyou are very experienced especially afterthe start of your projectit will recalculateall the durationsMost people onlyschedule in days or parts of days it getsvery complicated if you start scheduling in
hours and whos going to track it?working hours do not generally affectthe project..but they do affect People init so more about that when we talkabout resources
Do NOT select Day titles when setting nonworking timeunless you intend notworking Mondays for eternity.nicethought but your manager may not like it
This Changesselected days to
Non Working
You can create as many Calendars as you wish for different
Countries or working practices to use later with individual tasks
-
8/8/2019 Abridged MS Project Guide
14/53
Setup Step 3 Go to ProjectProject Information
Set the project Start date and set thescheduling method.From Start date is thenorm.From Finish date makes it Just inTime.Backward scheduled also known asJust Too Late because there is no room forerrors.
Current Date shouldonly be changed for
What If Modellingso
leave it alone.
Most Importantselect the Calendar
you created in Step 2
as your project
calendar.All tasks
will now use that
calendar for scheduling
You can select
different Calendars to
schedule specific tasks
on an individual
basisTasks
performed in different
countries for example
-
8/8/2019 Abridged MS Project Guide
15/53
Setup Complete
Congratulations you cannow start entering Tasks andResources..
Although not required to startyou can also set a few moreoptions..
Currency
Elect to show the project Summarytask (recommended)
Show Outline number.. WBS code
Take some time looking at theother options Tabs
-
8/8/2019 Abridged MS Project Guide
16/53
Tasks and Relationships
-
8/8/2019 Abridged MS Project Guide
17/53
Creating Tasks
Enter the Name of the task and its Duration
Duration can be entered as h hours, d- days, w- weeks and mo- months
Duration can be planned or elapsed d ed, w ew
Planned Duration takes into account the project Calendar
Elapsed Duration takes no account of the project Calendar and is 24/7
Use Elapsed duration for third party tasks where you have no control on theirworking practices or hours.Recruit staff via agency duration 3 weeks
should be elapsed because the agency does not work to our calendar
A question mark against duration means it is an estimate
Look at the two tasks below and spot the differenceone is displayed across
Sat and Sun because those days are non workingID Task Name Duration Start
Install Server 2 days ri 30/0 /0
T S S T T S S T T S S
2 ay '03 02 Jun '03 09
ID Task Name Duration Start
Install Server 2 edays ri 30/0 /03
T S S T T S S T T S S
2 ay '03 02 Jun '03 09
-
8/8/2019 Abridged MS Project Guide
18/53
Task Information
Double click on a task to get
Task Info
You can change the task type to
be effort driven if it really is
You can Assign a calendar to the
task.note default is
None.that means it uses theproject calendar by default
If you assign one then a calendar
icon will appear in the Info
column
A task deadline can be assigned
but this is NOT a constraint and
does not lock the schedulebut
Project will report when its
missed
ID Task Name Duratio tart inish Predecessor esource Name
Install erver da ri / on /
onfigure erver da ri / ri /
T T T T T
ay ' un '
arning B ode can be changed
manually but once it has been
project will not update it again
You can embed objectssuch as Docs, xls, ppt files
in Notes
-
8/8/2019 Abridged MS Project Guide
19/53
More Task Information in Tables
There are over 2 fields to use about eachtaskThe good news is you dont have to usethem all!
Data is arranged in Tablesthe default is theEntry Tableeach table displays differentInformation sets
Select More Tables to get a bigger list You can also create you own tables and
customise fields to store data Specific to yourProject
The Organiser allows you toreuse table structures you
have created in other
Project Files
-
8/8/2019 Abridged MS Project Guide
20/53
Creating your own tables
You can putwhatever fields youlike in a table bestto copy an existingone and give it anew name
There are 3 textfields forUser
definition.Selectthe Text Field andenter a Title suchas Departmentthat is relevant tothe data you aregoing to store
You can define,Date, Flag(Y/N),Number, Cost, Text,Start and Finish,Outline Numbers,Durations, to namea few
Shows Table
in main menu
Durations and Start andFinish fields are used forWhat If modelling andscenario building
Think how you can
enhance your project by
storing really useful
information with every
task
-
8/8/2019 Abridged MS Project Guide
21/53
Creating Relationships (Dependencies)
There are four types of Relationships between Tasks
Start to Finish SF Task Finishes when predecessor Starts
Finish to Start FS - % of tasks are related this way, Starts when
predecessor Finishes
Start to Start SS Starts at the same time as predecessor
Finish to Finish FF Finishes at the same time as predecessor
A
B
D
F
E
C
H
G
FS
SF FF
SS
-
8/8/2019 Abridged MS Project Guide
22/53
Lead and Lag times
A lead time is where you wish tasks to overlapExample.Task A manufacture 1 tinsof baked beans..Task B. put labels on tins You would want to start putting labels onafter say 5 % of the tins had been made you would therefore apply a 5 % lead timebetween A and B
A lag time is a pause after the finish of one task before beginning the next..Task C OrderPC.wait for delivery 1 days.Task D. PC DeliveredTask D will have a 1 d lag
Lags and leads can be expressed as duration or as a % of the Predecessor
To set a lead or lag timedouble click on the link between two tasks on the Gantt Chart andenter a value in the lag box..
A
B
D
C
1 d lag
5 % Lead
A minus -2 lag = a
lead or enter a - %
-
8/8/2019 Abridged MS Project Guide
23/53
To Create a Relationship (Link) in MS
Project
Highlight the two task names and selectLink Iconif the Tasks are not next toeach otheruse the CTRL key to selectthem.
Always start with the uppermost task
Alternately place the mouse in thecentre of a task on the Gantt Chart anddrag downwardsa link icon appearsand you can drop it on the task to belinked..
AlternatelyOpen the Task informationbox and select the name of the task tolink in the Predecessors Tab
Break Links using the Break Link buttonor double click on the link in the Ganttchartand chooseDelete
-
8/8/2019 Abridged MS Project Guide
24/53
Relationship problems?..
If you get this message like this whenyou create a relationship.its not anerror..It just says that there is notenough time to complete the tasksand preserve the relationship.
So What.well if you choose tocontinuewhich you should.youhave to resort to brain power toresolve the conflict
Shorten the tasksallow the
successor task to moveAdd moreresource Work longer hoursWorkharder! Its up to YOU..Project hasdone its 25%. It told you that thereis a problem that requires youraction now its your 75%reasoning that counts
-
8/8/2019 Abridged MS Project Guide
25/53
Creating Summary tasks
Summary Tasks Roll up Durations and Costs and are useful for defining levels ofyour WBS
Create a Summary task by Demoting the tasks underneath it using the Indentand Outdent buttons on the Tool bar
Show the Outline Number to see WBS Code
You can go down 5 levels to the Work Package.If you need more then
perhaps your plan is too complex.Remember do not include detail that youcannot influenceClean Room.. Instead of. collect Brush, sweep from leftto right, put broom away, examine floor for specks of dust.thats overplanning. let the cleaner make their own plan!
It is not good practise to Link Summary tasks together.link the individualtasks.. if necessary create and link milestones at the Start and end of eachsummary task
ID Task Name Duration
1 Server Install 3 days?
. Install Server day
1.2 Configure Server 2 days?
. . Configure OS day
5 . . Configure pps day
W T S S T W T S S T W T S S
ay '0 0 un '0 09
-
8/8/2019 Abridged MS Project Guide
26/53
Milestones
Milestones are tasks with no duration
Enter the task as normal and set duration to Zero
Milestone tasks may physically take up time. such as a contract
signing which has taken 4 hours. but it is symbolic and still has zero
duration for the purposes of the schedule
If a tasks completion is the milestone then enter a task and a separate
milestone to get the right meaning
If you are planning correctly.you will find that many of your tasks are in
some way linked to milestones..If they are not.perhaps another look
at the plan..I ask ame uration
1 Server Install 5 days?
. Install er er day
1.2 Configure Server 4 days?
4 . . onfigure day
. . onfigure pps 4 days
. . onfig omplete 0 days 05/06
M M M
May '0 0 un '0 09
-
8/8/2019 Abridged MS Project Guide
27/53
Displaying the Critical pathand more
Use The Gantt Chart Wizard on the formatting toolbar to display the critical path
Select Show Critical Path when asked and then follow the wizard
MS project will display the Critical Tasks in Red and Non Critical in Blue
You may also like to display Slack for non Critical tasksTry
this..FormatBar styles
Enter a new rowcall it
Slackappearance
underline.Normal,noncriticalfro
m Early start to late finishif in
doubt copy the screenshot. You get
this. I call it the Slack Gantt
ID Task Name Duration
. . Configure S . days
. . Install UPS day
. . Configure pps days
3r t tr t r,
W T F S S M T W T F S S M T W T F S S M
May ' un '
The window of opportunity for
the task is displayed
The task can be completed any time. along the blue line
-
8/8/2019 Abridged MS Project Guide
28/53
Constraints
-
8/8/2019 Abridged MS Project Guide
29/53
Constraints
Constraints allow you to specify a No later than, No Earlier than, ordo at aspecific time
Constraints in general are badly used only apply constraints sparingly. ManyPMs apply constraints to every task thus locking the schedule.which turns MSproject into a wall chart producer
Each time you set a constraint MS Project has less flexibility to change the
schedule
You should set constraints after you have done. planning and what ifs. andyou have allowed MS Project to move tasksand your resource plan works..Itshould be when you are ready to save your baseline for the first time
You should set Constraints for absolute events that will Not change or are
beyond your control to change You should set constraints for tasks whose time horizon does not allow them to
be moved
Remember this is a Plan.and Plans ChangeConstraints limit Change
-
8/8/2019 Abridged MS Project Guide
30/53
Setting a Constraint
Select a task and open the task
Info box
As Soon as Possible is default
As Late as Possible is for JIT
Start and Finish no Later than are
flexible forward schedulingconstraints
Start and Finish no Earlier than
are used when using backward
scheduling or JIT
Must Start and Finish on are
absolute constraints
Select the most appropriate
constraint.think carefully if you
are applying what you meanand
select the constraint date
Think through
the meaning of
the constraint
as applied toyour task
-
8/8/2019 Abridged MS Project Guide
31/53
Messages you get when setting a
Constraint
Cancel if you pressed the wrongbutton!
This is the opposite of what you meanto doso dont choose it
This is what you intenda constraint
will be setbut it may cause aconflict.
I didn't mean it Option
Continueyes please..
So Whatthis is not an error. itis project telling you that you now haveto take some actionIts done its25%..Now its your 75% reasoningthat counts
-
8/8/2019 Abridged MS Project Guide
32/53
Resolving a Conflict
MS Project tells you about a conflict, to quantify how big the problem is.go tothe View menuTablesSchedule
The schedule table shows you the total slack for the project and the task thatyou have set the constraint on..in this case you have to find 1 day to correct theschedule
What to doShorten any task on the critical path (re-evaluation).work longer
hours or non working days..add resource to shorten the task.introduceleads. reduce lag timesapply leadership and motivate..in fact its up toyou.whatever method you can take to shorten the critical path.crashing theschedule by one day!
-
8/8/2019 Abridged MS Project Guide
33/53
Resources
-
8/8/2019 Abridged MS Project Guide
34/53
Resources People, Materials, and Places
Resources are defined in the project and assigned to tasks A resource can be Manpower, or a materiala place is treated as a material.
Material performs no workbut may have a cost. It is assumed that only peopleperform work
Consider with each resource you intend to use whether that resource will make atask effort driven and in particular. will it be linear..A machine working at
double speed could be expected to produce double the output but doublingthe number of consultants on a task does not necessarily produce twice theoutputit depends on skills. the problem..interaction and so on..In otherwords in most cases it is better to decide how long a task will take .manually
2 people in a meeting takes 1hour.6 people in a meeting is therefore 2Mins?..I dont think so..more like 2 hours MS Project cannot resolvelogic like this!
Most tasks do not conform to being Effort Driven by resources in a linear mannerso do NOT make the mistake of letting MS project calculate the duration
-
8/8/2019 Abridged MS Project Guide
35/53
-
8/8/2019 Abridged MS Project Guide
36/53
Resource Details
Email address and
Windows account forgroup working using
project Server
Overall availability FromTo
Use the Working timetab to set holidays
-
8/8/2019 Abridged MS Project Guide
37/53
Resource Details (contd)
Resource Costs canbe entered andadjusted by time
Either enter theexact amount orenter a percentage
change from the lastfigure
You can put in 25different rates oneach TAB
TABs A to E allowdifferent rates to be
applied to differenttasks.For exampleTAB A for interCompany Rate, TABB for ExternalConsulting rate
Companypay Rise
Promotion!
Rate Tables are selected in the task usage view by
double clicking on the resource name against the task
to be charged
-
8/8/2019 Abridged MS Project Guide
38/53
Assigning Resources
When Resources are assigned MS Project calculates the Work, andcosts generated by that resource(s) and applies the formula
Work=Duration x Units
Total Costs are calculated according to the rate tables Cost =Work xrate specific Information of the resources assigned
It is assumed that a resource works evenly across the task unless youspecify otherwise
The next time you change either the Calendar, resource units, or timebased information, MS project will calculate. either a new duration,amount of work.. or number of units
When we fixed duration and made tasks not effort driven in setting upthe project..we retained control Now adding or removing resourcewill only change the amount of Work and thus the cost. The PMthen decides what affect those changes has on duration and modifiesthem accordingly
-
8/8/2019 Abridged MS Project Guide
39/53
Assigning Resource
Select the task or tasks in the Gantt chart andclick the resource icon
Select a resource or resources and .click
assign
You can assign resources how you like as
long as it is consistent.25% = 1 engineer
of their time.2 % = two engineers.or 4
engineers at timeyou decide
Material is assigned as a decimal with the
label you entered
You could even use it to suggest skillFred at
8%, John at 8 % as he is less skilled..butthis is probably too advanced for first use!
If you wish to change a resource use Replace
rather than Removeit prevents recalculation
occurring
R/D is Requested or
Demanded and is used
for group working
-
8/8/2019 Abridged MS Project Guide
40/53
Modifying a Resource on a Task
Sometimes the situation you are trying to simulate is not representedcorrectly by the standard assignment
In these cases go to.View..Task Usage. And Double click on aresource assigned to a task
You can change the amountof work donehere theManager only does 1halthough assigned at 1 %all day
You can also change the ratetable for alternate costs
Work Contouring can bechanged but avoid this untilexperiencedKISS Keep itSimple.S
-
8/8/2019 Abridged MS Project Guide
41/53
Levelling Resources
-
8/8/2019 Abridged MS Project Guide
42/53
There are never enough resources
With a finite pool of resource, conflicts are bound to ariseMS Project tells youwhen there is a conflict by showing that a resource is over allocated..in otherwords you have used the same resource on more than one task at the sametime..
Without using MS Project we know how to resolve this.Replace the resourcewith another. Reschedule so that the tasks no longer overlap.. reduce the
allocation to 5 % on each task.the list is endlessits just called management MS Project can only help you with rescheduling the tasks.this is called
Resource levelling.
Resource Levelling can be Time Constrained or Resource Constrained.Whatdoes that mean?.
Time Constrained is when you do not wish to extend the project but work withthe available slack and if necessary add or change resources to shorten theschedule
Resource constrained is when there is No more resource available and thus theduration of the project will have to be extended to resolve conflicts
MS Project will suggest possible solutions.it will not unravel a bad plan
-
8/8/2019 Abridged MS Project Guide
43/53
Levelling Resources
Here the resource Tech head has been assigned to both Installingthe UPS and the Workstation on the same day.so there is aconflict.
We choose first to Level resourceswithin the available slackyoucan see that both tasks have slack showing.MS project worksouts how much slack is available and Delays the start of InstallWorkstation by 1 day
You can check out what has been applied.Go to
ViewTables.More tables and select the Delay Table.You canmanually change the delay or even remove it as you wishso evenif it all went horribly wrong you can simply set the delays back toZeroID Task
ame Duration
1. .1 onfigure S 0. days
1. . Install UPS 1 day
1. . onfigure
pps
days
1. .
onfig omplete 0 days
1. . Install Workstation 1 day
3rd
tyContractor,
anager
ech Head
05
06
Tech Head
W T S S M T W T S S M T W T S S M
May '0 0 Jun '0 09 J
ID Task ame Duration
1.
.1 onfigure ! S 0."
days#
"
1.
.
Install UPS 1 day#
$
1.
.%
onfigure&
pps
days
' 1.
.
onfig omplete 0 days(
1.
."
Install Workstation 1 day#
3rd
tyContractor,
anager
Tech Head
05
06
Tech Head
W T ) S S M T W T ) S S M T W T ) S S M
$
May '0%
0
Jun '0%
09 J
Project has moved the task along
the slack line by1 day..if you dont
agree..put it back.. by clearing thelevelling or changing the table
-
8/8/2019 Abridged MS Project Guide
44/53
Levelling Resources (contd)
Use Manual it iseasier to see what
happens
Leave these uncheckeduntil you are more
experienced!
Time Constrained..only movesnon critical tasks..uncheck it and
project will move Critical tasks aswell..providing there are no
constraints set
Takes into accounttask priorities if used
Set this to your timehorizonthere is generallyno point in levelling things
six months away
Over allocationsDayby day..Week by week
Clear all levelling..orbetween
dates.this is theOh No Im a PMget
me out of here
button!
hoose. Tools.Resource Levelling
-
8/8/2019 Abridged MS Project Guide
45/53
When Levelling Messages start to appear
This is NOT a disaster..MS Project is just telling you that you master piece of
resource planning is not greatit means that within the time and constraints
currently set there is no solution that project can offer you
Back to your planyou need either more time..more resources.less
tasks..again its up to you.MS project has done its 25% and told you that you
have a problemNow you employ your 75% and figure out the
solution.modify your plan and let MS project work it out againthis time if you
resource plan is better MS project may be able to fine tune it for you
Remember..MS Project applies delays when Levelling.there is no Magic!
-
8/8/2019 Abridged MS Project Guide
46/53
Tracking
-
8/8/2019 Abridged MS Project Guide
47/53
Base lining
Before we can effectively track our project we mustbaseline itThis simply records a copy ofyou plans.dates costs. durations and otherdata for comparison later
You can Baseline either the whole project orselected tasks.
In a long project you may not want to baselineactivity until it falls within your time horizon
Select Tools.Tracking.Save Baseline
Save all or part of the projectand if you need tosave up to interim plans that reflect changes to the
original baseline
Now save a copy of your plan in case youaccidentally save the baseline again
Big Tip!
Do a Save Asevery time
you make major changes to
your plan..and put it in a safe
place in case you mess up the
current file..
-
8/8/2019 Abridged MS Project Guide
48/53
Basic Tracking
Task Update box
Select a task and Mark it
,25,5 ,75,1 %dont bother with
63.56% who can judge exactly?
These 5 boxes are interrelatedChange
one at a time..to show actual progress
Select a task and Mark it
,25,5 ,75,1 %dont bother with
63.56% who can judge exactly?
Update all tasks up to the
time line
ID Task Name Leveling Delay
1 1 Server Install 0 edays
2 1.1 Install Server 0 edays
3 1.2 Configure Server 0 edays
4 1.2.1 Configure OS 0 edays
5 1.2.2 Install UPS 0 edays
Tech1
ead
3rd pty Contractor,Manager
Tech1
ead
W T F S S M T W T F S S M T W T F S S M
26 May ' 0 3 0 2 Jun ' 0 3 0 2 Ju
Today
Tasks completed to the right of the time line are Early,
Not completed to the left are Late
The Tracking Toolbar
-
8/8/2019 Abridged MS Project Guide
49/53
Tables & Views to help you track
Variance Tablegives you schedulevariance against the baselinePositivevariance is a slippageStart variance isgreater than Finish variance shows animprovement..
Summary Table shows % complete and totalcost
Tracking Gantt shows variance againstbaseline.. shown as grey bars below each
taskI3 Task 4 ame
5 Ser6
er Install
7 Install Server
8 ConfigureSer6
er9
@ onfigure A S
B Install UPS
C @onfigure
D
pps
E @onfig @ omplete
FInstall
G
orkstation
5 B
5 00%
0
0%
0%
0%
09
0%
HT
G
T F S SH
TG
T F S SH
7 C H ay '0 8 0 7 Jun '0 8 09 Ju
-
8/8/2019 Abridged MS Project Guide
50/53
Costs
-
8/8/2019 Abridged MS Project Guide
51/53
Cost Basics
Costs are Planned in two ways.when resources are assigned totasks.and as fixed costs against a task
Costs are generated as work is performed..as you mark tasks% complete so the costs are recorded
Costs are ChargedAt the startat the endor prorated overthe duration of a task according to the resource that has beenassigned
When you save the baseline you record in effectyour budget
-
8/8/2019 Abridged MS Project Guide
52/53
Cost Table
Cost not associatedwith resources
Your Budget
Planned work x resource
rates assigned..thischanges with your plan
Actual cost is derived from % completebutyou can edit it once task has been 1 %
completed
Not yet Spent
Install Server final cost was2 over budget, adjusted
actual after 1 % complete
Task 75% completeyoucannot edit the actual
cost....change the amountof work performed and this
figure will change
Unplanned fixed cost
creates 2 overbudget
Summary tasks roll upvariances and totals
Total Cost = Fixed costs + resource based costs
-
8/8/2019 Abridged MS Project Guide
53/53
Cash Flow Views
In the Task usage view ..right click and show just coststhen a cash flow view isimmediately availableuse the zoom controls to zoom out to weekly, monthly orquarterly costsSummary tasks roll up the costs..
If you want to show revenues create tasks to concur with customer paymentsand enter a Negative Fixed cost for the task.