AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831 Melissa Bynum North Slope Borough, Department of Capital Improvement Program Management Walter Heins, PE, CxA Coffman Engineers, Inc. April 26, 2018 CxEnergy 2018 1

Upload: others

Post on 10-Dec-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

AABC Commissioning GroupAIA Provider Number 50111116

Case Study: Re-Commissioning an

Industrial Gas Chiller

Course Number: CXENERGY1831

Melissa BynumNorth Slope Borough, Department of Capital

Improvement Program Management

Walter Heins, PE, CxACoffman Engineers, Inc.

April 26, 2018CxEnergy 2018 1

Page 2: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Credit(s) earned on completion of

this course will be reported to AIA

CES for AIA members.

Certificates of Completion for both

AIA members and non-AIA

members are available upon

request.

This course is registered with AIA

CES for continuing professional

education. As such, it does not

include content that may be

deemed or construed to be an

approval or endorsement by the

AIA of any material of construction

or any method or manner of

handling, using, distributing, or

dealing in any material or product._______________________________________

Questions related to specific materials, methods,

and services will be addressed at the conclusion

of this presentation.

CxEnergy 2018 2

Page 3: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

This presentation is protected by US and International Copyright laws.

Reproduction, distribution, display and use of the presentation without written

permission of the speaker is prohibited.

© Coffman Engineers, Inc. 2018

Copyright Materials

CxEnergy 2018 3

Page 4: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

This case study examines re-starting, re-commissioning, and

optimizing an industrial gas chiller used for drying well-head natural

gas. It validates building commissioning processes in non-building

applications. The project applies building commissioning to a piece

of industrial equipment. The recommissioning led to a new OPR, an

operational hazard analysis, design review, installation verification,

and testing as well as planning, documentation, and training. The

completed project transformed a non-performing investment into a

system that exceeded expectations.

Course

Description

CxEnergy 2018 4

Page 5: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Learning

Objectives

1. Learn the difference between startup processes and commissioning processes, in

this case the recommissioning leading to a new OPR, an operational hazard analysis,

design review, installation verification, and testing as well as planning,

documentation, and training.

2. Learn the importance of using all the steps in the commissioning process and not

cutting corners. Understand that the commissioning process, by design, incorporates

measures that optimize mechanical, electrical, plumbing and fire protection that

provide many benefits beyond immediately apparent operations.

3. Understand how the CxA can apply building commissioning processes to non-

building applications.

4. Understand the importance of including the commissioning requirements properly

in the project specifications so that all benefits to mechanical systems are assured,

documentary requirements are met, and compliance with relevant regulations,

standards, laws and ordinances is met.

At the end of the this course, participants will be able to:

CxEnergy 2018 5

Page 6: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Get the whole story

Page 7: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Today’s Presentation

• Who we are

– Owner and consultant

• What is this thing?

– The Alaska Factor

– The Chiller

• Why ReCommission?

– The Owner’s Perspective

ReCommissioning an Industrial Gas Chiller

CxEnergy 2018 7

Page 8: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Today’s Presentation

• The ReCommissioning process;

– Compare Cx to ReCx

• System challenges

– Initial findings

– Follow-on projects

• Conclusions

– What’s next

CxEnergy 2018 8

ReCommissioning an Industrial Gas Chiller

Page 9: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Who We Are

• Melissa Bynum, Project Manager

for Capital Improvement Program

Management for the North Slope

Borough, AK

– Issued contract solicitation

– Managed contract scope and budget

– Participated in OPR development

CxEnergy 2018 9

ReCommissioning an Industrial Gas Chiller

Page 10: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Who We Are

• Walter Heins, PE, CxA, CCP

Commissioning Consultant

– Developed project approach

– Facilitated OPR

– Developed Cx Plan

– Facilitated all field activities

CxEnergy 2018 10

ReCommissioning an Industrial Gas Chiller

Page 11: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Who We Are

• The Commissioning Team

– Commissioning Consultant

• Mechanical, Electrical

• Manufacturer’s Engineer

– Gas Field Operator

– Subcontractors

• Refrigeration contractor

• PLC Integrator

CxEnergy 2018 11

ReCommissioning an Industrial Gas Chiller

Page 12: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

ReCommissioning an Industrial Gas Chiller

CxEnergy 2018 12

• The Alaska Factor

• Barrow now known as Utqiagvik, is the most Northern City in the United States.

• Located 320 Miles North of the Arctic Circle.

• Utqiagvikpopulation of 4,933.

Page 13: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

640 Miles

Alaska’s North Slope compared to the Gulf Coast

ReCommissioning an Industrial Gas Chiller

CxEnergy 2018 13

•No Road! All freight comes by ship (summer) or air.

640 Miles

Page 14: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 14

– Approximately 94,000 square miles

ReCommissioning an Industrial Gas

Chiller

– Climate ranges from -30 below

in the Winter and 40 to 70

above in the Summer.

– Includes 8 villages that range in

population of 200 to 4,933.

Page 15: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

•Sun sets on Nov. 18 and

doesn’t come up for 65

days.

CxEnergy 2018 15

•Midnight Sun in May

•We have Polar Bears!

ReCommissioning an Industrial Gas Chiller

Page 16: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

• We don’t live in Igloos.

We have real homes.

CxEnergy 2018 16

• Natural Gas is our only fuel

for heat, electricity, and the

water/sewer plant.

• Homes are built on pilings to

preserve the permafrost.

ReCommissioning an Industrial Gas Chiller

Page 17: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

ReCommissioningan Industrial Gas Chiller

CxEnergy 2018 17

Why ReCommission?

• We had a Chiller Skid that didn’t run and we couldn’t figure out why?

• We needed the chiller to dry out our gas so it can be processed and delivered to all the residences in Barrow (Utqiagvik)

Page 18: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

ReCommissioningan Industrial Gas Chiller

CxEnergy 2018 18

Why ReCommission?

• Chiller Skid was constructed and installed in 2009 and ran seasonally

• After the first season Chiller Skid started to fail. Operators left it off and bypassed the Chiller using our Primary building.

Page 19: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

•Contracted with Coffman

to find the problem.

•Discovered missing

lubrication management

components.

•Without these key

components the Chiller

Skid wouldn’t work

properly.

CxEnergy 2018 19

17-Mile Gas Pipeline

ReCommissioning an Industrial Gas Chiller

Page 20: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

•We also needed a way

to transmit operating data to

the operation center.

• Installation of a control

module included a

PLC/HMI and

eventually SCADA.

CxEnergy 2018 20

Local Control Panel

(Gas Line Overhead)

ReCommissioning an Industrial Gas Chiller

Page 21: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

What is this thing?

CxEnergy 2018 21

Natural Gas Chiller

ReCommissioning an Industrial Gas Chiller

Page 22: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Natural Gas Chiller

CxEnergy 2018 22

Compressor

Condenser

Evaporator

Natural Gas

ReCommissioning an Industrial Gas Chiller

Page 23: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Refrigerates Raw Natural Gas

CxEnergy 2018 23

Packaged Air Cooled Condenser with 4 independent

circuits

Packaged Chiller Skid with 4 independent circuits

ReCommissioning an Industrial Gas Chiller

Page 24: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Initial Commissioning

Structure and Plan

– No specification for inspection or testing

– No specification for training

– No specification for O&M Manuals

CxEnergy 2018 24

ReCommissioning an Industrial Gas Chiller

Page 25: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Initial Commissioning

Prefunctional

– Factory witness testing incomplete

– Manufacturer factory checkout report

– No Prefunctional examination recorded

CxEnergy 2018 25

ReCommissioning an Industrial Gas Chiller

Page 26: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 26

The original Prefunctional Factory Checkout Sheets

ReCommissioning an Industrial Gas Chiller

Page 27: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Initial Commissioning

Functional Testing

– Better described as a “Startup”

– Short runtime

– Minimal performance benchmarking

– Brief / poor records

CxEnergy 2018 27

ReCommissioning an Industrial Gas Chiller

Page 28: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 28

The Original Functional Checkout Sheets

ReCommissioning an Industrial Gas Chiller

Page 29: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

– Combination of Scoping, OPR, and Process

– Scoping

CxEnergy 2018 29

ReCommissioning an Industrial Gas Chiller

Page 30: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The ReCommissioning Process:

Cx Plan

– Scoping

• Major refrigeration upgrades

• Complete PLC replacement

30

ReCommissioning an Industrial Gas Chiller

CxEnergy 2018

Page 31: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

Combination of Scoping, OPR, and Process

– Scoping

• Major refrigeration upgrades

• Complete PLC Replacement

• CxA to represent Owner in RFPs

• Develop RFPs & evaluate proposals from

qualified contractors

CxEnergy 2018 31

ReCommissioning an Industrial Gas Chiller

Page 32: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

– Combination of Scoping, OPR, and Process

– Owner’s Project Requirements

• Determine temperature setpoints and

deadbands

-40°F to -35°F

CxEnergy 2018 32

ReCommissioning an Industrial Gas Chiller

Page 33: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

– Combination of Scoping, OPR, and Process

– Owner’s Project Requirements

• Determine temperature minimums allowed

-40°F to -35°F

• Determine summer/winter operations

CxEnergy 2018 33

ReCommissioning an Industrial Gas Chiller

Page 34: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

– Combination of Scoping, OPR, and Process

• Owner’s Project Requirements

Determine PLC shortfalls

CxEnergy 2018 34

ReCommissioning an Industrial Gas Chiller

Page 35: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

• Combination of Scoping, OPR, and Process

• Owner’s Project Requirements

– Determine PLC shortfalls

– Examine Hazards

CxEnergy 2018 35

ReCommissioning an Industrial Gas Chiller

Page 36: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

• Combination of Scoping, OPR, and Process

• Process

– Statement of 5 W’s and 1 H

CxEnergy 2018 36

ReCommissioning an Industrial Gas Chiller

Page 37: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

• Combination of Scoping, OPR, and Process

• Process

– Statement of 5 W’s and 1 H

– Issue Prefunctional checksheets

CxEnergy 2018 37

ReCommissioning an Industrial Gas Chiller

Page 38: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 38

Refrigeration Upgrades

ReCommissioning an Industrial Gas Chiller

Page 39: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Prefunctional Checksheets

CxEnergy 2018 39

Prefunctional Checksheets, Compressor

ReCommissioning an Industrial Gas Chiller

Page 40: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Prefunctional Checksheets

CxEnergy 2018 40

Prefunctional Checksheets, Refrigerant System

ReCommissioning an Industrial Gas Chiller

Page 41: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 41

Programmable Logic Controller Replacement

ReCommissioning an Industrial Gas Chiller

Page 42: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 42

Class 1 Div 2, 500 PSI Oil Level Monitors

ReCommissioning an Industrial Gas Chiller

Page 43: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Cx Plan

• Combination of Scoping, OPR, and Process

• Process

– Statement of 5 W’s and 1 H

– Issue Prefunctional checksheets

– Issue Functional Performance Tests

CxEnergy 2018 43

ReCommissioning an Industrial Gas Chiller

Page 44: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 44

Gas Pre-Heater

ReCommissioning an Industrial Gas Chiller

Page 45: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 45

Functional Performance TestsFunctional Performance Tests

Page 46: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 46

Programmable Logic

Controller Replacement

ReCommissioningan Industrial Gas Chiller

Page 47: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 47

Programmable Logic Controller Replacement

ReCommissioning an Industrial Gas Chiller

Page 48: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

Functional Performance TestsFunctional Performance Tests

CxEnergy 2018 48

Functional Performance Tests

Page 49: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 49

Oil Management Systems

ReCommissioning an Industrial Gas Chiller

Page 50: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 50

Oil Management Systems

ReCommissioning an Industrial Gas Chiller

Page 51: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Project Closeout

– Training

• Develop content

• Engage videographer

• Schedule trainees

CxEnergy 2018 51

ReCommissioning an Industrial Gas Chiller

Page 52: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 52

Training VideoTraining Video

ReCommissioning an Industrial Gas Chiller

Page 53: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

The Process: ReCommissioning

Project Closeout

– Training

• Develop content

• Engage videographer

• Schedule trainees

CxEnergy 2018 53

ReCommissioning an Industrial Gas Chiller

– O&M Manual

Page 54: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 54

O&M ManualO&M Manual

Page 55: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 55

– Equipment was examined

– Owner’s Project Requirements were compiled

– Project specifications were developed

• Plans and Specs

• Testing, Training, and O&Ms

The Building Commissioning Process

ReCommissioning an Industrial Gas Chiller

Page 56: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 56

– Owner was represented by qualified engineers

during upgrades

– System underwent rigorous FCO over a wide

operating range

– Project accepted based on verifiable criteria

The Building Commissioning Process

ReCommissioning an Industrial Gas Chiller

Page 57: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 57

The Building Commissioning Process

Job Complete!

ReCommissioning an Industrial Gas Chiller

Page 58: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

CxEnergy 2018 58

– The building commissioning processes are

adaptable to commissioning any project

– Get the Whole Story!!!

• Work with the Owners to develop the OPR

– Owners can only expect thorough commissioning

if they specify it

Lessons Learned

ReCommissioning an Industrial Gas Chiller

Page 59: AABC Commissioning Group 2018... · 2019. 1. 16. · AABC Commissioning Group AIA Provider Number 50111116 Case Study: Re-Commissioning an Industrial Gas Chiller Course Number: CXENERGY1831

This concludes The American Institute of Architects

Continuing Education Systems Course

Walter K Heins, PE, CxA, [email protected]

9907) 267.6664

ReCommissioning an Industrial

Gas Chiller

Melissa Bynum, PM

CIPM Department

North Slope Borough, Alaska