1 विजय शमा vkbZvkj,lb Vijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar, 2019. 1. Highlights of the month of Mar, 2019. 1.1 Progress during the month has been adversely affected due to continuous rainfall causing heavy damage to all the approach roads which has affected the movement of diesel and construction materials at all working fronts. Situation was further aggravated due to Law & Order conditions. However, during this month tunneling of 1967 m was done, this comprises of 1063m of Main Tunnel and 904m of Escape Tunnel and also 26276m of tunnelling has been completed in this financial year. 1.2 Tender for design of Broad Gauge blast less track including supply, installation, testing and commissioning between Banihal and Arpinchala (Approx. 16 Km) was opened on 26.03.2019 and finalization is under progress. 1.3 Progress of tunneling work (Main tunnel) between Katra- Banihal Section : S/No Agency Scope (m) Progress (m) Progress during the month (m) 1 KRCL 46101 33855 381 2 IRCON 48761 28958 682 3 NR 2456 2456 Work Completed 4 Total 97318 65269 1063 1.4 Progress of tunneling work (Escape tunnel) between Katra- Banihal Section : S/No Agency Scope (m) Progress (m) Progress during the month (m) 1 KRCL 23541 11914 325 2 IRCON 42927 25578 579 3 NR 0 0 Work Completed 4 Total 66468 37492 904

Upload: others

Post on 26-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

1

विजय शर्मा

vkbZvkj,lb

Vijay Sharma

IRSE

No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019

Sub: PCDO for the Month of Mar, 2019.

1. Highlights of the month of Mar, 2019.

1.1 Progress during the month has been adversely affected due to continuous rainfall

causing heavy damage to all the approach roads which has affected the movement

of diesel and construction materials at all working fronts. Situation was further

aggravated due to Law & Order conditions. However, during this month tunneling of

1967 m was done, this comprises of 1063m of Main Tunnel and 904m of Escape

Tunnel and also 26276m of tunnelling has been completed in this financial year.

1.2 Tender for design of Broad Gauge blast less track including supply, installation,

testing and commissioning between Banihal and Arpinchala (Approx. 16 Km) was

opened on 26.03.2019 and finalization is under progress.

1.3 Progress of tunneling work (Main tunnel) between Katra- Banihal Section :

S/No Agency Scope (m) Progress (m) Progress during the month (m)

1 KRCL 46101 33855 381

2 IRCON 48761 28958 682

3 NR 2456 2456 Work Completed

4 Total 97318 65269 1063

1.4 Progress of tunneling work (Escape tunnel) between Katra- Banihal Section :

S/No Agency Scope (m) Progress (m) Progress during the month (m)

1 KRCL 23541 11914 325

2 IRCON 42927 25578 579

3 NR 0 0 Work Completed

4 Total 66468 37492 904

Page 2: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

2

1.5 Status of Bridges between Katra- Banihal Section.

Agency KRCL IRCON NR

Major 15 10 1

Minor 7 1 3

Total 22 11 4

Work in progress 10 6 0

Work completed 4 Major +7 Minor 3 (Major) 1 Major + 3 Minor

Work yet to start 1 (Br.60)

2 (Br. 61 & Br. 4)

0

Total bridges in Katra-Banihal section : 37 (26 Major + 11 Minor)

2. Important achievements during the month

2.1 Earth Work:

2.1.1 Earth work and protection work is in progress in Sangaldan station yard, out of

23,60,000 Cum of total quantity 22,67,183 Cum has been done so far.

2.1.2 Earthwork for excavation of Bridges foundation is in progress for Katra

Banihal section, out of 16,38,639 cum quantity (i.e. except Chenab bridge)

13,81,370 cum has been completed.

2.1.3 Earthwork for excavation of Chenab Bridge foundations & slope

protection is in progress, out of 10,08,545 cum quantity 9,75,697 has

been completed (i.e. 97% completed).

2.2 Tunneling

i. Progress of underground excavation achieved in various tunnels are as follows.

Sr.

No. Tunnel

Progress of Main Tunnels (m) Progress of Escape Tunnels (m)

Scope During this

Month Cumulative Scope

During this

Month Cumulative

1 T-1 3159 0 2850 - - -

2 T-2 5093 122 3224 5072 103 3303

3 T-5 5959 51 5777 5959 57 5799

4 T-13 9368 208 2624 9368 165 2812

5 T-14 6284 36 199 6284 33 465

5 T-15 9829 202 2788 9829 201 3433

6 T-48 10186 203 6807 9788 232 6652

7 T-49 12758 135 8090 12755 92 8180

8 T-74R 8600 38 7918 7413 21 6848

9 T-77D 1863 68 773 - - -

10 Total 73099 1063 41050 66468 904 37492

Page 3: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

3

ii. Progress of lining achieved during this month is as follows

Sr.

No. Tunnel

Progress of Main Tunnel Lining

(m)

Progress of Escape Tunnel Lining

(m)

Scope During this

Month Cumulative Scope

During this

Month Cumulative

1 T-1 3159 6 2386 - - -

2 T-2 5093 63 113 5072 0 0

3 T-5 5959 107 4703 5959 27 3779

4 T-13 9368 0 0 9368 0 0

5 T-14 6284 0 0 6284 0 0

5 T-15 9829 37 112 9829 0 0

6 T-48 10186 99 1350 9788 84 612

7 T-49 12758 262 1876 12755 130 350

8 T-74R 8600 0 6327 7413 0 5393

9 T-77D 1863 0 0 - - -

10 Total 73099 574 16867 66468 241 10134

iii. Progress of tunnel works/agency wise is as follows,

Main Tunnel

S/No Agency Scope (m) Progress (m) Balance (m) Progress (%)

1 KRCL 46101 33855 12246 73

2 IRCON 48761 28958 19803 59

3 NR 2456 2456 0 100

4 Total 97318 65269 32049 67

Escape Tunnel

S/No Agency Scope (m) Progress (m) Balance (m) Progress (%)

1 KRCL 23541 11914 11627 51

2 IRCON 42927 25578 17349 60

3 NR No scope

4 Total 66468 37492 28976 56

Page 4: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

4

iv. Month wise Tunneling progress (2018-19)

Tunnel Progress (2018-19)

Month Main Tunnel (m) Escape Tunnel (m)

KRCL IRCON Total KRCL IRCON Total

Apr-18 295 566 861 259 569 828

May-18 335 503 838 262 477 739

Jun-18 389 500 889 374 498 872

Jul-18 459 615 1074 444 646 1090

Aug-18 510 580 1090 436 550 986

Sep-18 515 669 1184 522 738 1260

Oct-18 486 740 1226 531 934 1465

Nov-18 506 709 1215 535 878 1413

Dec-18 504 802 1306 572 836 1408

Jan-19 580 815 1395 620 761 1381

Feb-19 391 488 879 396 513 909

Mar-19 381 682 1063 325 579 904

Total 5351 7669 13020 5276 7979 13255

v. Linear progress of tunnel excavation (main +escape) for 2018-19

295

566

335

503

389

500459

615

510

580

515

669

486

740

506

709

504

802

580

815

391

488

381

682

KRCL IRCON

Tunnel Excavation (Main Tunnel)2018-19

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

Page 5: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

5

Tunnel Lining Progress (2018-19)

Month Main Tunnel Lining (m) Escape Tunnel Lining (m)

KRCL IRCON Total KRCL IRCON Total

Apr-18 324 356 680 122 165 287

May-18 269 376 645 116 111 227

Jun-18 345 337 682 181 121 302

Jul-18 238 336 574 235 293 528

Aug-18 347 300 647 223 190 413

Sep-18 295 268 563 211 244 455

Oct-18 237 223 460 151 226 377

Nov-18 115 314 429 150 358 508

Dec-18 175 274 449 164 234 398

Jan-19 202 289 491 136 372 508

Feb-19 158 152 310 32 143 175

Mar-19 176 398 574 27 214 241

Total 2881 3623 6504 1748 2671 4419

259

569

262

477

374

498444

646

436

550522

738

531

934

535

878

572

836

620

761

396

513

325

579

KRCL IRCON

Tunnel Excavation (Escape Tunnel)2018-19

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

Page 6: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

6

324356

269

376345 337

238

336347

300295268

237 223

115

314

175

274

202

289

158 152176

398

KRCL IRCON

(Main Tunnel Lining)2018-19

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18

Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

122

165

116 111

181

121

235

293

223

190211

244

151

226

150

358

164

234

136

372

32

143

27

214

KRCL IRCON

(Escape Tunnel Lining)2018-19

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18

Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

Page 7: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

7

Tunnel wise last Three Month progress (2018-19)

S/No. Tunnel December January February March Total Progress

(2018-19)

1 T-1 Main (m) 0 0 0 0 0 0 0 0 0

8 T-2 Main (m) 152

301 125

264 92

184 122

225 1804

Escape (m) 149 139 92 103 1817

2 T-5 Main (m) 66

174 65

178 46

94 51

108 1097

Escape (m) 108 113 48 57 1102

9 T-13 Main (m) 286

601 390

758 253

509 208

373 2450

Escape (m) 315 368 256 165 2357

11 T-14 Main (m) 58

131 58

117 25

51 36

69 199

Escape (m) 73 59 26 33 465

7 T-15 Main (m) 261

541 247

497 138

297 202

403 1808

Escape (m) 280 250 159 201 2361

3 T-48 Main (m) 187

444 217

443 152

409 203

435 2295

Escape (m) 257 226 257 232 2560

4 T-49 Main (m) 145

311 169

354 117

183 135

227 2035

Escape (m) 166 185 66 92 2009

6 T-

74R Main (m) 63

132 69

110 21

26 38

59 701

Escape (m) 69 41 5 21 593

10 T-

77D Main (m) 80 80 55 55 35 35

68 68 623

12 Total (MT+ET)

2715 2776 1788 1967

Total (2018-19):26276m

Ballast-less Track (BLT)

2.2.1 Tender for design of Broad Gauge BLT (Ballast less track) including supply,

installation, testing and commissioning between Banihal - Arpinchalla (Approx.

16 Km.) was opened on 26.03.2019 and finalization is under progress.

2.2.2 Tender for design of Broad Gauge BLT (Ballast less track) including supply,

installation, testing and commissioning between Km. 25.00 to Km. 70.742 and

Km. 92.398 to Km. 101.632 on Katra-Dharam Section of USBRL was invited by

M/s KRCL on 22.02.2019 and is to be opened on 22.04.2019.

Page 8: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

8

2.3 Bridges

Progress of bridges between Katra- Banihal section has been shown in Table 3.

2.4 Miscellaneous:

2.4.1 ESP of Kata Banihal Section:

a) ESP of Sumber and Arpinchala have been approved on 28.12.2018.

b) ESP of Sangaldan, Basindadhar and Salal-A have been approved on 25.02.2019.

c) ESP of Reasi has been approved by Ferozepur division and submitted at

HQ/Baroda House on 30.01.2019.

d) ESP of Dugga has been approved by Ferozepur division and submitted at

HQ/Baroda House on 26.03.2019.

2.4.2 Tender for Transportation of DEMU Power and Trailer Coaches 17 no’s and

Two WDS6 Locos by Road, duly conducting feasibility study, from Udhampur

Railway Station to Budgam Railway Station has been awarded to SAAR Frights

Corporation on 12.01.2019.

2.4.3 E&M (Electro and Mechanical Works) for Tunnels:

a) Tender for Integrated Sub-Station (ISS) at Sangaldan is awarded to M/S

Hightech Erectors Pvt. Ltd. on 25.03.2019.

b) Tender for Integrated Sub-Station (ISS) at Reasi is under finalization.

c) E&M Tender for package-I (tunnel No-6 to T-12) has been opened on

26.02.2019 and tender is under evaluation.

2.5 Chenab Bridge

Progress of Chenab Bridge has been summarized in table below:

Progress of Chenab Bridge: 2018-19 (KRCL)

Item Unit Total

Quantity

Achieved up to

31/03/18

Balance on 1/4/18

Target for

2018-19

Monthly Progress

Mar 2019

Progress for F.Y. 2018-19

Balance of

2018-19

Earth Work in Excavation

Cum 1008545 968164 40381 4000 0 4283 36098

Fabrication of Deck Segments

Nos/MT 164/12697 67/7238 97/5459 20/2650 0/0 21/2716 76/2743

Fabrication of Main Arch, Piers & Trestles

MT 13784 12415 1369 1350 0 1369 -

Launching and Erection of Superstructure Deck Segments

Nos 164 59 105 0 0 0 59

Launching of Main Arch, Piers & Trestles

Nos. 429 +

Trestles 120

309+ Trestles

80 0 82 202

Financial Progress Cr. 1198 1071.68 126.32 110 0* 97 13

Total expenditure (Mar 2019) : 1168.68 Cr.

* M/s CBPU has suspended the work from 20.10.2018 due to contractual dispute with KRCL.

Page 9: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

9

2.6 Major Contract Awarded

All major contract awarded.

2.7 Tender Invited/Under Finalisation/Under process

2.7.1 Tender for design of Broad Gauge BLT (Ballast less track) including supply,

installation, testing and commissioning between Banihal - Arpinchalla (Approx.

16 Km.) was invited by M/s IROCN on 12/02/2019 and was opened on

26.03.2019 and finalization is under progress.

2.7.2 Tender for design of Broad Gauge BLT (Ballast less track) including supply,

installation, testing and commissioning between Km. 25.00 to Km. 70.742 and

Km. 92.398 to Km. 101.632 on Katra-Dharam Section of USBRL was invited by

M/s KRCL on 22.02.2019 and is to be opened on 22.04.2019.

2.7.3 Tender for Manufacture, Supply, Transportation and delivery of prime quality

of UIC 60 Kg 1080 Grade Head Hardened Class A Rails as per Indian Railway

Standard Specification for Flat Bottom Rails IRS-T-12-2009 (With latest A&C

Slips) at Banihal site for Katra-Banihal section of USBRL Project in J&K, India was

awarded to M/S Voestalpine Schienen, GmbH on 26.03.2019.

2.7.4 Financial Bid for the Tender for “Construction of prposed all buildings

including station building, RPF & GRP Posts, RPF Barrack & GRP Barracks,

Equipment Control Rooms for Tunnels, 33 KV Switch Yard, Electrical Sub-

Station (ESS), Portal Sub Stations for Arpinchala Station Yard of USBRL Project

has been finalized and awarded to M/s N.S. Associates Pvt. Ltd., New Delhi on

14.02.2019.

2.8 Budget and Expenditure

2.8.1 Abstract Cost = 19565 Cr

2.8.2 Last Sanctioned Cost = 27,949 Cr

2.8.3 Latest anticipated Cost = 27,949 Cr

2.8.4 Budget out lay for 2018-19 (USBRL Project) = 1880 Cr (Revised)

2.8.5 Up to date expenditure = Rs. 17999 Cr. (Since inception)

2.8.6 Break up of expenditure under major Plan heads is detailed as under :

SN Plan Head

Total Expenditure up to March

2018 (Cr.)

Year 2018-19

Outlay (Cr.)

Revised

Booking upto March'2019 (Cr.)

Expenditure up to March

2019 (Cr.)

% Expenditure

Total Net (after ROC

from PSU)

1 New Line

(8300) 16120.09 1880 1987.3 1879.2 2587 138

Page 10: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

10

Booking details as shown by USBRL finance:

S/No. Section Cost (As per

detailed estimate) Booking up to March-2019

1 Udhampur- Katra 1111.43 1119

2 Katra- Banihal 21652.33 11880

3 Banihal-Quazigund 1691.88 1687

4 Quazigund- Baraumulla 3493 3314

5 Total 27948.6 17999

Expenditure incurred by IRCON and KRCL (2018-19)

Financial/Actual Expenditure during (2018-19)

Month (2018-19)

IRCON KRCL NR

Target (Cr.) Achieved (Cr.) Target (Cr.) Achieved

(Cr.)

April 50 57.1 65 73.54 13.97

May 60 72.66 75 86.53 4.68

June 65 82.72 80 95.67 22.71

July 80 90.98 90 99.41 31.85

August 90 92.03 90 106.92 23.04

September 100 95.66 105 117.06 3.71

October 110 86.43 110 120.45 8.01

November 110 105.29 110 119.34 5.01

December 110 107.3 110 126.12 4.09

January 120 95.78 110 126.79 8.64

February 120 99.86 110 114.6 3.17

March 120 166.26 110 116.57 3.25

Total 1135 1152.07 1165 1303 132.13

Annual planning of Expenditure during 2018-19 for IRCON =1150 Cr

Annual planning of Expenditure during 2018-19 for KRCL =1100 Cr.

Annual planning of Expenditure during 2018-19 for NR =150 Cr.

Page 11: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

11

3. Katra-Banihal Section (Progress in Details)

3.1 For construction convenience and monitoring, this section has been divided into

following legs:

A. Katra – Banganga (km. 25 - 30): Executed by Northern Railway and works are

completed.

B. Km. 30 - 100 (KRCL, except 73.78 to 91 as transferred to IRCON): Progress

of underground excavation for various tunnels being executed by KRCL are

shown in Table 1.

C. Km 100 – 136: Executed by M/s IRCON. Progress of underground excavation

for various tunnels being executed by IRCON are shown in Table 2.

3.2 Chenab Bridge, Br. No. 44 (KRCL)

Chenab Bridge has been divided in four parts for construction point of view, these

are

A. Construction of Arch Portion (S-10 to S-70)

B. Construction of Viaduct Portion (S-70 to S-180)

C. Slope Stabilization - Bakkal end and

D. Slope Stabilization - Kauri end

A. Progress on Arch Portion (S10 to S70) :

a. Progress of the Arch:

(i) RCC work: Concreting of S10 (Except 234 Cum), S20, S30, S40, S50, S60

and S70 (Except Pier Cap) has been completed.

(ii) Workshop: Main span deck fabrication at S180 & Bakkal is under progress.

Arch fabrication work at wheels India Ltd., Wardha & Trestle fabrication at

AIML, Raipur has been completed.

iii) Progress on Viaduct Portion (S-70 to S-180): Launching of viaduct portion

from S-80 to S-180, Segment AS34 to AS35 and AS36 to AS07 completed.

a. Progress:

(i) RCC Work: All completed except the pier cap of S-70.

B. Slope stabilization – Kauri end: In progress. C. Slope stabilization - Bakkal end: In progress.

4. Progress of bridges between Katra- Banihal section has been shown in Table 3.

Page 12: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

12

Table 1: Tunnel Details: KRCL

KRCL Portion

S/No. Tunnel No Length

(m) Award of Contract

Progress this

month

Cumulative Progress

Remarks Balance

(m)

Target 2018-

19

Achieved (2018-19)

Lining

Scope Progress this

month Cumulative

Progress Balance

(m) Target

2018-19 Achieved (2018-19)

1 T-1 3159 Jul-14 0 2850 Tunnel Excavation in

progress 309 45 0 3159 6 2386 773 1300 1197

2

T-2 5093 Mar-16 122 3224 Tunnel Excavation in

progress

1869 1320 1804 5093 63 113 4980 0 113

T-2 5072 Mar-16 103 3303 1769 1320 1817 5072 0 0 5072 0 0

3 T-3 3009 Nov-10 3009 Work Completed 0 Completed 3009 0 3009 - -

4 T-5 5959 Oct-10 51 5777 Tunnel Excavation in

progress.

182 800 1097 5959 107 4703 1256 1800 1571

4A T-5

(Escape) 5959 41922 57 5799 160 800 1102 5959 27 3779 2180 1900 1748

5 T-6 3493 Sep-10 3493 Completed. 0

Completed

3493 0 3493 0 0

6 T-9 470 Sep-10 470 Completed 0 470 0 470 0 0

7 T-10 1010 Sep-10 1010 Completed 0 1010 0 1010 0 0

8 T-11 830 Sep-10 830 Completed 0 830 0 830 0

9 T-12 2123 Sep-10 2123 Excavation completed.

Lining in progress. 0 2123 0 1971 152 0

10 T-13 9368 Jul-16

208 2624 Work awarded to M/s HCC on 25/7/16. Work

Transferred to KRCL

6744 1690 2450 9368 0 0 9368 0

10A T-13

(Escape) 9368 165 2812 6556 1810 2357 9368 0 0 9368 0

11 T-14 3142 Jul-16

Reflect the part that is

clubbed with T-13

3142 0 3142

11A T-14

(Escape) 3142 0 3142

12 T-40/41 1346 Oct'05 1346 Work Completed 0 1346 1346

13 T- 42/43 2732 Oct'05 2732 Work Completed 0 2732 2732

14 T-44/45 1483 Oct'05 1483 Work Completed 0 1483 1483

15 T-46 654 Oct'05 654 Work Completed 0 654 654

16 T-47 2230 Oct'05 2230 Work Completed 0 2230 2230

17 Total (Main

Tunnel) 46101 381 33855 73% 12246 3855 5351 46101 176 26430 19671 3100 2881

18 Total

(Escape) 23541 325 11914 51% 11627 3930 5276 23541 27 3779 19762 1900 1748

Page 13: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

13

Table 2: Tunnel Details: IRCON

IRCON Portion

Sr. No Tunnel No Length

(m) Award of Contract

Progress this

month

Cumulative Progress

Remarks Balance

(m) Target

2018-19 Achieved (2018-19)

Lining

Scope Progress

this month

Cumulative Progress

Balance (m)

Target 2018-19

Achieved (2018-19)

1 T-14 3142 - 36 199 Tender clubbed with that of T-13 and

T-15. Part clubbed with T-13 transferred to KRCL

2943 180 199 3142 0 3142 0

1A T-14

(Escape) 3142 33 465 2677 360 463 3142 0 3142 0

2 T-15 9829 Mar-16 202 2788 Work in progress.

7041 2280 1807 9829 37 112 9717 0 112

2A T-15

(Escape) 9829 Mar-16 201 3433 6396 2520 2409 9829 0 9829 0

3 T-48 10186 Sept,2012 203 6807 Work in progress

3379 2463 2295 10186 99 1350 8836 3100 765

3A T-48

(Escape) 9788 Sept,2012 232 6652 3136 2290 2560 9788 84 612 9176 2400 612

4 T-49 12758 Dec,2013 135 8090 Work in progress

4668 2445 2035 12758 262 1876 10882 2150 1724

4A T-49

(Escape) 12755 Dec,2013 92 8180 4575 2220 2009 12758 130 350 12408 300 350

5 T-50 255 June,2014 255 Completed 0 0 0 255 0 188 67 255 188

6 T-74 R 8600 Oct,2011 38 7918 Work in progress 682 828 701 8600 0 6327 2273 1247 871

6A T-74 R Escape

Tunnel 7413 Oct,2011 21 6848 Work in progress 565 720 593 7413 0 5393 2020 1010 1708

7 T-77 335 335 Completed Completed

0 335 335 Completed

8 T-77 A 873 873 Completed 0 873 873 Completed

9 T-77D 1863 July,2016 68 773 Work in progress 1090 1040 623 1863 0 1863 0

10 T-78 920 920 Completed Completed 0 920 920 Completed

13 Total (Main

Tunnel) 48761 682 28958 59% 19803 9236 7660 48761 398 11981 36780 6752 3660

14 Total

(Escape Tunnel)

42927 579 25578 60% 17349 8110 8034 42930 214 6355 36575 3710 2670

Page 14: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

14

Table 3: Status of bridge works between Katra-Banihal Section

BRIDGES IN KATRA-BANIHAL SECTION (111 KM)

S. No.

Br. No. Chainage

C/L Span Arrangement Type of Bridge Bridge Category Status

Position of bridges from Km 25 to 30 (N.R.)

1 32 28.138 1x34+1x64+1x92+1x64m PSC Girder Major Completed

2 33 29.403 3x3m RCC Box Minor Completed

3 33A 29.512 5.2x5.585m RCC Box Minor Completed

4 34 33.180 3x3m RCC Box Minor Completed

i. Bridges with KRCL ( Km 30-100)

1 34 33.186 1x24.4 =24.4m Steel open web

girder Major In progress

2 35 (Anji Khad)

38.670 Main Bridge : 1x290+ 1x80+ 1x75+ 1x28.25

=(473.25m) Viaduct : 1x25 +2x35 + 1x25 (120m)

Cable Stayed Important

(Mega) In progress

3 38 42.270 1x24.4+1x61+1x45.7 = 131.1m Composite

plate Girder Major

Sub structure completed.

4 39 42.460 1x53.15+6x64+1x53.15= 490.25m Composite

plate Girder Important

(Mega) In progress

5 40 42.900 1x4x3 =12m RCC BOX minor Completed

6 41 48.980 1*5*5=25m RCC BOX minor Completed

7 42 49.240 3x5x5=75m RCC BOX minor Completed

8 43 50.000 1x35+1x53+10x64+1x49 = 777m Girder Bridge Important(Mega) In progress

Page 15: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

15

9 44(Chenab

bridge) 51.057

1x55+2x65+10x48+1x65+1x55+1x40+9x50+1x40 = 1315

Girder and arch bridge

Important (Mega)

In progress

10 53 55.490 3x30.5 = 91.5m Composite

Plate Girder Major Completed

11 55 56.260 1x24.4 =24.4m Composite

Plate Girder Major Completed

12 56 57.590 1x24.4=24.4m Composite

Plate Girder Major Completed

13 57 58.042 1x24.4=24.4m Composite

Plate Girder Major Completed

S. No.

Br. No. Chainage

C/L Span Arrangement Type of Bridge Bridge Category Status

14 58 60.725 3x30.5= 91.5 m Composite

Plate Girder Major

Sub structure completed.

15 59 60.930 1x30.5+1x45.7+1x30.5 = 106.7 m Composite

Plate Girder Major

Sub structure completed

16 60 70.509 2x30.5(CPG)+2x61(CT)+1x30.5 (CPG)+1X18.3(CPG)m=231.8m,

Composite Plate Girder

(CPG) +composite

truss (CT)

Major

GT investigation completed, work

awarded. GAD under finalization.

17 81 92.470 2x3x2m =12m RCC BOX minor Completed

18 82 93.080 2x(3x3) =18m RCC BOX minor Completed

19 85 96.443 1x45.7+3x61+1x45.7 =274.4m STEEL GIRDER Major In progress

20 85A 96.693 1x(3x3) m=9m RCC BOX minor Completed

21 87 98.440 3x61.0 m+1x45.7=228.7m COMPOSITE

GIRDER Major In progress

22 87A 98.540 1x3x3m=9m RCC BOX minor Completed

23 88 99.361 1X45.7=45.7m THROUGH

GIRDER Major

Sub structure completed.

Page 16: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

16

ii. Bridges with IRCON

24 61 76.971 1x18.3+1x24.4+x30.5m=73.2m Composite Plate

Girder Major

GT investigation completed, work awarded. GAD finalised.

25 1 99.98 1x30=30m Steel Girder/Composit

Girder Major In progress

26 2 110.6955 11x39= 429m Composite Steel

Girder Important In progress

27 3 111.300 8x39= 312m Composite Steel

Girder Important In progress

28 4 124.2975 1x35=35m RCC Box for rock

protection Major In progress

29 5 124.782 1x5 =5m RCC Box minor In progress

30 121 125.2525 1x30.5+1x45.7+2x30.5 =

137.2m Steel Girder (OWG) Major Completed

31 138 147.952 3x30.5= 91.5 m Composite Girder Major In progress

32 142 148.439 3x30.48=91.44m Steel Girder Major Completed

33 144 149.48 2x25.51.2m Steel Girder Major Completed

Page 17: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

17

5. Progress of land acquisition in various stretches of Udhampur - Srinagar-

Baramulla New Line is enclosed as, Annexure-I.

6. Land Plans: Preparation of Land Plans authentication are under process, the

progress of same for each Dy.CEs jurisdiction wise is tabulated below:

SN Field unit Total

no.’s of

cases

Plans

authentic-

cated

Plan

Scanned

Balance work

Under

Preparation

Records

compilation

1. Dy.CE/ Banihal 36 30 30 5 1

2. Dy.CE/Chenab 3 - - 3 -

3. Dy.CE/Sangaldan 73 20 - 16 37

4. Dy.CE/Reasi 80 - - 25 55

5. Dy.CE/Anji 03 - - 2 1

7. Assistance Required:

Land Management System (LMS) portal, requires to update the facility/option

for upload of Land Plans for Construction Organisation.

भवदीय

(ववजय शर्मा)

Shri Vishwesh Chaube Member Engineering Ministry of Railways Railway Board New Delhi

Copy to

1. The Addl. Member Works, Railway Board, New Delhi.

2. The Executive Director Works, Railway Board, New Delhi.

3. The Director Works, Railway Board, New Delhi.

Page 18: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

18

Annexure-1: Details of land acquisition upto the month of Mar 2019 for USBRL Project

A) Land Acquisition details for Jurisdiction of Dy. CE’s

S.No Jurisdiction

Revenue Land Diversion Forest Land

Already Acquired

Under Process

Total Already Acquired

Under Process

Total

1

Dy.CE/Banihal (Banihal- Dharam) 299.36 13.39 312.75 144.56 0.00 144.56

(Banihal- Baramulla) 857.50 0.00 857.50 0.00 0.00 0.00

2 Dy.CE/Sang 129.25 12.00 141.25 81.04 20.00 101.04

3 Dy.Ce/Reasi 200.34 43.25 243.59 240.89 0.00 240.89

4 Dy.CE/UHP 268.92 1.23 270.15 12.31 0.00 12.31

5 Dy.CE/Anji 5.96 0.75 6.71 19.87 0.00 19.87

6 Dy.CE/Chenab 13.24 0.00 13.24 12.39 0.61 13.00

Total 1774.57 70.62 1845.19 511.06 20.61 531.67

B) Abstract of Land Acquisition Status of USBRL:

Description Total Land Required (Hectare)

Already Acquired (Hectare)

Balance (Hectare) Percentage

Balance

Revenue/ Private Land 1845 1775 71 4%

Diversion of Forest Land 532 511 21 4%

Total 2377 2377 91 4%

Page 19: विजय शर्मा vkbZvkj,lb Vijay Sharma IRSEusbrl.org/PCDO-March2019.pdfVijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 08/04/2019 Sub: PCDO for the Month of Mar,

19

Annexure-II

Financials- USBRL

Year Estimate Cost (Rs. Crore)

1994-95 Pink Book 1500

1998-99 DPR 3077

2010 CCEA Approved Cost 19565

Latest Estimate

S/No. Section Estimated

Cost (Cr.)

Remarks

1 UHP- Katra 927.61 2nd Revised-2012

1111.43 Completion cost (with associate finance)

2 Katra (Km 25)-Km 30 183.51 Detailed estimate of 2012

3 Banihal- Quazigund 1691.88 Detailed estimate of 2012

4 Quazigund- Baramulla 3493 Completion Estimate 3376.22 Cr.

submitted to Rly.Board

5 Katra (Km 30)- Banihal 21468.82 Detailed estimate of 2015

6 USBRL Project Cost 27949 Crores

Booking up to March-2019

S/No. Section Cost (As per

detailed estimate)

Booking up to March-2019

1 Udhampur- Katra 1111.43 1119

2 Katra- Banihal 21652.33 11880

3 Banihal-Quazigund 1691.88 1687

4 Quazigund- Baraumulla 3493 3314

5 Total 27948.6 17999