a46 link road phase 1 (stoneleigh junction)

91
Project: A46 Link Stoneleigh Junction Phase 1 Construction Environment Management Plan (CEMP) Page | 1 ` A46 Link Road Phase 1 (Stoneleigh Junction) Construction Environmental Management Plan (CEMP) Document Number: WCC: 9.2-A46-083-REP-007 CS: FBC005-CSL-C-HSE-PL-0002 Rev02 Prepared CC Checked NS Approved NS Date 08-11-19 Date 08.11-19 Date 11.11-19

Upload: others

Post on 18-May-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan (CEMP)

Page | 1

`

A46 Link Road Phase 1

(Stoneleigh Junction )

Construction Environmental Management Plan (CEMP)

Document Number: • WCC: 9.2-A46-083-REP-007 • CS: FBC005-CSL-C-HSE-PL-0002 Rev02

Prepared CC Checked NS Approved NS

Date 08-11-19 Date 08.11-19 Date 11.11-19

Page 2: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

Revision History

Issue no.

Issue date Prepared by Amendments to the previous i ssue

00 08/11/2019 CC N/A (first issue)

01 24/02/2020 Susana Sa Document Number updated

Table 3 updated with Principal Contractor’s Contact Details

Table 4 updated

Topics 3.6; 3.7; 3.8; 3.9; 3.11; 3.12; 3.13; 13.1.5; 15.1.5; 17.2.3; 17.2.4; 18; 20.1.5; 24.1.3; 24.1.4; 24.1.5 and 30.1.6 updated

Appendices updated

02 29/04/2020 Susana Sa WCC’s comments addressed

New Appendices added

03 13/05/2020 Graeme Wasilew Final Draft Completed. All appendices added

04 04/09/2020 Andy Bond References to Kier amended in Table 4 (cl. 3.12)

Page 3: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

TABLE OF CONTENTS

PART 1 – INTRODUCTION AND PROJECT STRUCTURE .................................................................... 2

1. Introduction .............................................................................................................................. 3

1.1 Background and Context ......................................................................................................... 3

1.2 Objectives and Purpose of the CEMP ..................................................................................... 4

1.3 Structure of the CEMP ............................................................................................................ 5

2. Regulatory Framework & Planning Conditions ....................................................................... 5

2.1 Relevant Legislation ................................................................................................................ 5

2.2 Planning Consent .................................................................................................................... 6

3. Project team roles and responsibilities .................................................................................. 11

3.1 Employer and Principal Contractor ....................................................................................... 11

3.2 Employer’s Representative ................................................................................................... 12

3.3 Design Manager .................................................................................................................... 12

3.4 NEC3 Project Manager .......................................................................................................... 12

3.5 NEC3 Supervisor .................................................................................................................... 12

3.6 Project Ecologist .................................................................................................................... 12

3.7 Archeaologist ........................................................................................................................ 13

3.8 Construction Project Manager .............................................................................................. 13

3.9 Site Management .................................................................................................................. 13

3.10 Site Personnel ....................................................................................................................... 14

3.11 SHEQ Manager and Site Environmental Advisor................................................................... 14

3.12 Sub-Principal Contractors and Third Parties ......................................................................... 15

3.13 Sub Contractor Works Managers .......................................................................................... 17

3.14 Third Party Visitors ................................................................................................................ 17

3.15 Environmental Training and Briefing Procedures ................................................................. 18

PART 2 – EXISTING SITE INFORMATION AND BASELINE CONDITIONS ......................................... 19

4. Site Location and Existing Site Conditions............................................................................ 20

5. Existing Site – Nearby Features ............................................................................................ 21

6. Ecological Baseline Conditions ............................................................................................. 22

7. Existing Ground Conditions ................................................................................................... 22

8. Area In and Around Finham Brook ........................................................................................ 22

9. Existing Trees ........................................................................................................................ 23

PART 3 – ACTIVE MEASURES – CEMP SITE SPECIFIC CONTROLS ............................................... 24

10. General .................................................................................................................................. 25

Page 4: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

11. ENVIROMENTAL Risk Assessments ................................................................................... 25

12. Method Statements ............................................................................................................... 25

13. Air Quality - Dust & EmiSsions .............................................................................................. 26

14. Archaeology & cultural heritage ............................................................................................ 27

15. Construction Lighting ............................................................................................................. 28

16. Ecology .................................................................................................................................. 29

17. Geology, Soils and Contaminated Ground............................................................................ 29

17.2 Treatment of Himalayan Balsam ........................................................................................... 29

17.3 Suitability of Ground Materials ............................................................................................. 30

18. Housekeeping ....................................................................................................................... 34

19. Landscaping and Land Use .................................................................................................. 34

19.1 Protection of Existing Trees .................................................................................................. 34

19.2 Landscaping Installation and Maintenance .......................................................................... 35

20. Noise and Vibration ............................................................................................................... 35

21. Waste .................................................................................................................................... 37

22. Water Environment ................................................................................................................ 37

23. Water Consumption ............................................................................................................... 39

24. Pollution Prevention and Hazardous Material Storage ......................................................... 41

25. Monitoring and amendments to the cemp ............................................................................. 42

26. Internal Communication & Training ....................................................................................... 43

27. External Communications ..................................................................................................... 44

28. Environmental Actions and Commitments ............................................................................ 45

PART 4 – REACTIVE MEASURES – INCIDENT RESPONSE PROCEDURES .................................... 46

29. Incident Response – General ................................................................................................ 47

29.1 Definitions ............................................................................................................................. 47

29.2 Responsibilities...................................................................................................................... 47

29.3 Immediate Impact Control Measures – All Incidents ............................................................ 47

29.4 Reporting ............................................................................................................................... 47

29.5 Incident Classification ........................................................................................................... 48

29.6 Investigation and Corrective Action ...................................................................................... 49

29.7 Incident Review ..................................................................................................................... 49

30. Incident Response - Spillage ................................................................................................ 50

31. Incident Response – Emissions to Air ................................................................................... 53

32. Incident Response – Contaminated Ground ......................................................................... 53

33. Incident Response – Water Bodies ....................................................................................... 55

APPENDIX A – Planning Conditions summary ....................................................................................... 56

APPENDIX B – E-CEMP ......................................................................................................................... 57

APPENDIX C – Environmental Risks in and around Finham Broo ......................................................... 58

APPENDIX D – RIVER NETWORK LOCATION PLAN .......................................................................... 60

Page 5: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

APPENDIX E - Site Waste Management Plan ........................................................................................ 61

APPENDIX F – Quantities of Recycled and Secondary Materials used in the Works ............................ 62

APPENDIX G – Waste management ...................................................................................................... 63

APPENDIX H – Risk Assessments and Method Statements .................................................................. 78

APPENDIX I – Site Archaelogical Investigations .................................................................................... 79

APPENDIX J – LEMP .............................................................................................................................. 80

APPENDIX K – Tree Protection Plan ...................................................................................................... 81

APPENDIX L – Environmental Action and Commitment Register (REAC) ............................................. 82

A46 Stoneleigh Junction – environmental action and commitment register (REAC) ................................ 1

LIST OF FIGURES AND TABLES

Table 1: Relevant Legislation .................................................................................................................. 5

Table 2: Key Environmental Planning Conditions ................................................................................ 7

Table 3: Employer and Principal Contractor Key Personnel ............................................................ 11

Table 4: Third Parties, Sub Contractors and Suppliers Key Personnel .......................................... 15

Figure 5: Aerial Image of Existing Junction circa 2018 ..................................................................... 21

Table 6: Soil Leachate Limiting Values ............................................................................................... 31

Table 7: Soil Limiting Values (mg/kg) .................................................................................................. 32

Table 8: Petroleum Hydrocarbons Soil Limiting Values (mg/kg) ..................................................... 33

Table 9: Schedule of Maximum Noise Levels Permitted .................................................................. 36

Table 10: Site Working Hours ............................................................................................................... 36

Table 11: List of Key External Consultees .......................................................................................... 45

Page 6: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan (CEMP)

GLOSSARY

CEMP Construction Environmental Management Plan (this document)

CPP Construction Phase Plan

COSHH Control of Substances Hazardous to Health

DEFRA Department for Environment, Food and Rural Affairs

EA Environment Agency

E-CEMP Ecological – Construction Environmental Management Plan

EIFR Environmental Incident Frequency Rate

EcIA Ecological Impact Assessment

EMS Environmental Management System

FRA Flood Risk Assessment

HSEQ/SHEQ Health, Safety and Environment Quality or Safety, Health, Environment Quality

HS2 High Speed 2 Railway

IAN Interim Advice Note

IAQM Institute of Air Quality Management

LEMP Landscape Ecological Management Plan

MCERTS Monitoring Certification Scheme (EA’s monitoring scheme for Emissions to Air, Land and Water)

NAEC National Agriculture and Exhibition Centre

NEC3 New Engineering Contract Version 3

PROW Public Right of Way

REAC Register of Environmental Actions and Commitments (Appendix L)

RAMS Risk and Method Statements

RIDDOR Reporting of Injuries, Diseases and Dangerous Occurances

SHE Safety, Health and Environment

SRN Strategic Road Network (Mainline A46 and slip roads)

SWMP Site Waste Management Plan

UKAS UK Accreditation Service

WBRC Warwickshire Biological Records Centre

WCC Warwickshire County Council

Page 7: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 2

PART 1 – INTRODUCTION AND PROJECT STRUCTURE

Page 8: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 3

1. INTRODUCTION

1.1 Background and Context

1.1.1 This Construction and Environmental Management Plan (CEMP) has been prepared for Warwickshire County Council (hereinafter referred to as the ‘Employer’) for use on the A46 Stoneleigh Road Project.

1.1.2 It sets out the strategy for how the Principal Contractor will meet and manage the Construction and Environmental Requirements associated with the project and reports on how the construction activities associated with the junction improvement works are undertaken. This Plan shall only be for the works associated with the A46 Stoneleigh Road junction in Warwickshire (hereafter referred to as the ‘Site’), located at Ordnance Survey Grid Ref SP320734.

1.1.3 The existing junction comprises of a single carriageway bridge carrying the C32 Stoneleigh Road above the three lane A46 dual carriageway. Two slip roads allow unrestricted access north and south from the C32 onto and off from the A46. At the point where the slip roads meet the C32, there are two priority crossroads.

1.1.4 The C32 continues from the A46 bridge north west towards the University of Warwick and approximately 300m from the bridge, there is an existing roundabout at the junction of Stoneleigh Road and Dalehouse Lane. Stoneleigh Road then continues to the north west, crossing Finham Brook and heads towards Coventry.

1.1.5 The project will seek to deliver major improvements in the operation of the A46Stoneleigh Road junction, through the introduction of an elevated gyratory and improved junction approaches. This would improve highway safety, highway capacity, accesses to local businesses and reduce journey times. The project would also help address existing congestion and safety issues at the junction, whilst also improving access to the University of Warwick and Stoneleigh Park.

1.1.6 The project proposals (hereinafter referred to as the ‘Works’) include the installation of a new bridge over the A46 to the north-east of the existing junction, thereby creating a new grade separated gyratory roundabout over the A46. This roundabout will be partially signal controlled to help the flow of traffic around the gyratory and local roads. The existing bridge will be retained, but reconfigured to create an additional lane added within the bridge deck.

1.1.7 The Works will also involve constructing a new Stoneleigh Road/Dalehouse Lane roundabout and a new bridge over Finham Brook. Comprehensive shared footway/cycleway facilities will be provided throughout the scheme and this will include four signalised toucan crossings on all four slip roads.

1.1.8 The permanent speed limits on the local roads will all be amended to be a proposed 50mph throughout. The main A46 and slip roads will be retained as national speed limit.

1.1.9 The construction process will comprise extensive disturbance throughout most of the Site footprint lying within the application boundary, not only for the new bridges and road and road junctions but also in relation to the construction of access roads and any areas required for storage of materials.

1.1.10 The production of a Construction and Environmental Management Plan (CEMP) is required by Condition 20 of the Planning Permission Decision Notice (dated 17th July 2018) Application Number WDC / 17CC015. This is discussed in more detail in Section

Page 9: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 4

1.2 Objectives and Purpose of the CEMP

1.2.1 This CEMP has been drafted to document the procedures and working practices that shall be employed on this project to deliver the Works whilst also mitigating any potential adverse impacts on the environment that may arise due to the construction operations.

1.2.2 It is intended to focus on the targeted pre-commencement checks and appropriate communication lines to ensure all who are required to know are familiar with the information and processes contained within this document.

1.2.3 The CEMP will largely follow the requirements outlined in ISO 14001, the guidance contained within the Institute of Environmental Management and Assessment's “Best Practice Series Volume 12, December 2008 "Environmental Management Plans" and CIRIA guidance C692 "Environmental Good Practice on Site (Third Edition)" as well as Interim Advice Note (IAN) 183/14.

1.2.4 As such the objectives of this CEMP are to:

i. Registering all applicable environmental aspects (effects of the Works);

ii. Establish Project Team roles and responsibilities and assign a line of communication that extends to other parties involved in the Contract, e.g. sub-Principal Contractors;

iii. Outline and document all key environmental risks and the measures for addressing them;

iv. Describing the key consents, approvals and permissions for environmental aspects of the works;

v. Documenting the methodology for dealing with changes on site that may require the methodologies and working practices outlined in this document to be changed added to or removed;

vi. Determining the methods by which the appropriate environmental data required for handover and maintenance will be captured;

vii. Instituting procedures for the periodic review and monitoring compliance with the measures described in this CEMP; and

viii. Establishing emergency procedures in the event of an environmental emergency.

1.2.5 The CEMP is a practical working document which shall be monitored and updated during the life of the project. Adherence to the CEMP does not substitute any legal or planning obligations on the Employer or Principal Contractor, or the need for an on-going appraisal of site activities to determine unforeseen events and the design of any appropriate remediation measures. However, the CEMP provides a set framework against which to manage and monitor activities on the site.

1.2.6 All records required and associated with this plan will be maintained in a suitably referenced filing structure and shall be accessible for any user and subsequent archiving.

Page 10: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 5

1.3 Structure of the CEMP

1.3.1 This CEMP has been split into four parts as follows:

i. Part 1 – Introduction and Project Structure;

ii. Part 2 – Existing Site Information and Baseline Conditions;

iii. Part 3 – Active Measures – CEMP Site Specific Controls; and

iv. Part 4 – Reactive Measures – Incident Procedures

1.3.2 The project and this CEMP acknowledges that there needs to be a distinction made between different type of procedures and monitoring during the construction of the Works. Therefore, Part 3 details Active Measures which are controls that are put in place designed to stop an environmental incident occurring whereas Part 4 details the Reactive Measures which are to be implemented in case of an incident occurring.

2. REGULATORY FRAMEWORK & PLANNING CONDITIONS

2.1 Relevant Legislation

2.1.1 There are a number of legislations in place that govern how the environment is monitored and to ensure it is not adversely affected. The key Legislation believed to be applicable to this CEMP are outlined in Table 1 below.

Table 1: Relevant Legislation

Aspect Legislation Impact Risk

Dust/Air Quality

Environmental Protection Act 1990

Clean Air Act 1993

A reduction in air quality and harm to human health and the environment

Legal action,

Complaints,

Clean Up Costs,

Reputational damage if problem persists

Noise & Vibration

Environmental Protection Act 1990

Clean Neighbourhoods and Environment Act 2005

Control of Pollution Act 1974

Anti-Social Behaviour Act 2002

Disturbance of residents or damage to environmentally sensitive receptors

Legal action,

Complaints,

Delay to works,

Reputational damage if problem persists

Water/Pollution Control of Pollution Act 1974

Pollution Prevention and Control Act 1999

Water Industry Act 1991

Water Resources Act 2003

Groundwater Regulations 1995

Environmental Permitting Regulations 2016

Oil Storage Regulations 2001

Reduction in surface water/groundwater qualities

Pollution to water bodies

Damage to ecological habitats

Working on or near water bodies with the potential to cause localized flooding

Legal action,

Clean up costs

Failure to meet consents

Enforcement action

Page 11: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 6

Aspect Legislation Impact Risk

Waste Environmental Protection Act 1990

Control of Pollution Act 1974

Environment Act 1995

Waste Regulations

Hazardous Waste Regulations

Clean Neighbourhoods and Environment Act 2005

Environmental Permitting Regulations 2016

Fly tipping, waste not correctly identified or later found to be hazardous leading to contamination

Waste removed to unauthorized disposal points.

Costs relating to disposal and to transporting the waste

Landfill capacities

Breach in Duty of Care

Legal action

Clean up costs

Prosecutions

Ecology Wildlife 7 Countryside Act 1981

Environment Act 1995

Wild Mammals (Protection) Act 1996

Protection of Badgers Act 1992

Countryside and Rights of Way Act 2000

National Planning Policy Framework

Hedgerow Regulations 1997

Natural Environment and Rural Communities Act 2006

Conservation of Habitats and Species Regulations 2010

Loss of or damage to ecological habitats

Death of wildlife

Spreading of noxious or invasive species

Legal action

Reputational damage

Reinstatement costs

Unnecessary suffering to wildlife

Failure to meet consent/ license

Delay to construction operations

Traffic Road Traffic (Vehicle Emission) Regulations

National Planning Policy Framework

Traffic disruption and dust and airborne pollution

Damage to human health and ecology

Complaints

Legal action

Cultural Heritage

National Planning Policy Framework

Historic Buildings and Ancients Monuments Act

Damage to cultural heritage and site of historic interest

Legal action

Complaints

Delay to construction operations

2.1.2 In addition to the above, the Principal Contractor will refer to the CIRIA Environmental Good Practice on Site (C502) and Environment Agency Pollution Prevention Guidance Notes.

2.1.3 The Principal Contractor will maintain the register of relevant environmental legislation and other commitments/permits with Environmental Authorities. The register will be updated throughout the project.

2.2 Planning Consent

2.2.1 The primary environmental requirements of the planning consent are the production of various documents to record how environmental controls will be established and with due consideration of environmental legislation. The CEMP is the core record in this

Page 12: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 7

regard and brings together the various environmental disciplines and their control under a single reference document.

2.2.2 The complete Planning Consent Conditions are listed in Appendix A for reference but the key environmental ones are listed in Table 2 below. The table also highlights the environmental discipline applicable to the condition.

Table 2: Key Environmental Planning Conditions

Planning Condition Number

Planning Condition Text Environmental Discipline Affected

3 Work which is likely to give rise to noise levels that are above 34dBA where background noise levels are no more than 24dBA, or 10dBA above the background noise level if this is more than 24dBA shall be restricted to the following hours:

Mon-Fri 0700 – 1900, Sat 0730 – 1300

Piling and activities such as hydro demolition shall be restricted to Monday – Friday between the hours of 0800 and 1700.

No construction operations shall take place on Sundays or Public Holidays unless otherwise agreed in writing with the County Planning Authority.

Noise

5 In the event that contamination is found at any time when carrying out the approved development that was not previously identified, it must be reported in writing immediately to the County Planning Authority. An investigation and risk assessment must be undertaken, and, where remediation is necessary, a remediation strategy must be submitted to and approved in writing by the County Planning Authority. Following completion of measures identified in the approved remediation scheme, a verification report must be prepared and approved in writing by the County Planning Authority.

Contaminated Ground

6 Prior to the commencement of development, a construction management plan shall be submitted to and approved in writing by the County Planning Authority. The construction management plan shall include details of:

• Any temporary measures required to manage traffic during construction

• Plans and details of haul roads within the site and for the turning and unloading and loading of vehicles within the site during construction

• Dust management and suppression measures – level of mitigation determined using IAQM guidance

• Wheel washing

• Noise assessment and mitigation method statements for the construction activities in accordance with the provisions of BS 5228:2009 Code of Practice for Noise and Vibration Control on Construction and Open Sites – Parts 1 and 2

• Concrete crusher if required or alternative procedure

• Site lighting

Noise, Dust, Non-motorised users

Page 13: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 8

Planning Condition Number

Planning Condition Text Environmental Discipline Affected

• Access and protection arrangements around the site for pedestrians, cyclists and other road users

• Restrictions on burning and details of all temporary Principal Contractors’ buildings

• Plant and storage of materials associated with the development process

• External safety and information signing notices

• Complaints procedures, including complaints response procedures and dedicated points of contact

Construction activities shall be carried out in accordance with the approved scheme.

7 A landscape and ecological management plan (LEMP) shall have been submitted to and approved in writing by the County Planning Authority prior to the commencement of the development. The content of the LEMP shall include the following:

• Description and evaluation of features to be managed

• Ecological trends and constraints on site that might influence management

• Aims and objectives of management

• Appropriate management options for achieving aims and objectives

• Prescriptions for management actions

• Preparation of a work schedule (including an annual work plan capable of being rolled forward over a five-year period)

• Details of the body or organisation responsible for implementation of the plan

• Ongoing monitoring and remedial measures

The LEMP shall also include details of the legal and funding mechanism(s) by which long term implementation of the plan will be secured by the developer with the management body(ies) responsible for its delivery. The plan shall also set out (where results from monitoring show that conservation aims and objectives of the LEMP are not being met) how contingencies and/or remedial action will be identified, agreed and implemented so that the development still delivers the fully functioning biodiversity objectives of the originally approved scheme. The approved plan shall be implemented in accordance with the approved details.

Landscaping, Ecology

8 No development shall commence unless and until a scheme ("the scheme") to ensure that there is no net biodiversity loss as a result of the development has been submitted to and agreed in writing by the County Planning Authority. The net biodiversity impact of the development shall be measured in accordance

Landscaping, Ecology

Page 14: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 9

Planning Condition Number

Planning Condition Text Environmental Discipline Affected

with the DEFRA biodiversity offsetting metric as applied in the area in which the site is situated at the relevant time and the scheme shall include:

• proposals for on-site mitigation (full details of which will be provided in relation to each phase of development in accordance with Condition 7 of these conditions)

• if and to the extent that a net biodiversity loss cannot be avoided by on-site mitigation alone, proposals for off-site offsetting

• a methodology for the identification of any receptor site(s) for off-site offsetting measures;

• the identification of any such receptor site(s);

• the provision of arrangements to secure the delivery of any off-site offsetting measures (including a timetable for their delivery); and

• a management and monitoring plan (to include arrangements for the provision and maintenance of any off-site offsetting measures in perpetuity).

The written approval of the County Planning Authority shall not be issued before the arrangements necessary to secure the delivery of any off-site offsetting measures have been executed. The scheme shall be implemented in full accordance with the requirements of the scheme or any variation so approved.

9 The development hereby permitted shall not commence until a Construction and Ecological Management Plan has been submitted to and approved in writing by the County Planning Authority. The Plan shall include details of monitoring of the otter couch and any otter nesting sites prior to and during works, pre-commencement checks for badgers, bats, breeding birds, otters, reptiles and amphibians, and appropriate working practices and safeguards for wildlife and habitats plus any mitigation required that is to be employed whilst works are taking place on site. The agreed Construction and Ecological Management Plan shall thereafter be implemented in full.

Ecology

10 The development hereby permitted shall not commence until a qualified ecologist has been appointed by the applicant to inspect the structures and vegetation to be cleared on site for evidence of nesting birds immediately prior to works. If evidence of nesting birds is found works may not proceed in that area until either the nesting bird season (March to September inclusive) has ended or until after the young have fledged, as advised by the ecologist.

Ecology

12 No part of the development hereby permitted shall be commenced and no equipment, machinery or materials shall be brought onto the site until a scheme for the protection of all existing trees and hedges to be retained on site has been submitted to and approved in writing by the County Planning Authority and has been put in place. The scheme must include details of the erection of stout protective fencing and be in accordance with British Standard BS5837:2012, Trees in relation to design, demolition and construction. Nothing shall be stored or placed in those areas fenced in accordance with this condition and nor shall the ground levels be altered or any excavation take place in those areas without the prior consent in writing of the County Planning Authority. The approved scheme shall be kept in place until all parts of the

Aboriculture

Page 15: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 10

Planning Condition Number

Planning Condition Text Environmental Discipline Affected

development have been completed and all equipment and machinery and surplus materials have been removed.

13 No development shall take place until a programme of archaeological survey work has been implemented in accordance with a written scheme of investigation which has been submitted by the applicant and approved in writing by the County Planning Authority.

Cultural Heritage

14 The development permitted by this planning permission shall be carried out in accordance with the approved Flood Risk Assessment (FRA) and associated Flood Risk Assessment Report - Addendum 06/03/2018 and in particular flood plain compensation will be created upstream of the bridge.

Flood Risk

20 No development shall commence until a Construction Environmental Management Plan for the development has been submitted to, and approved in writing by, the County Planning Authority. The approved Plan shall be adhered to throughout each construction phase.

All disciplines

2.2.3 Planning conditions 3 (noise), 5 (contaminated ground) and 14 (flood risk) do not require pre-commencement conditions to be discharged but the conditions need consideration in the CEMP and so will be reported under the appropriate sections of this document.

2.2.4 Planning condition 10 requires an ecologist to be appointed to inspect various items before any site clearance takes place. An application has already been made to the Planning Authority and this condition was discharged on 04th September 2019. However, the mechanisms by which the ecologist will undertake these inspections is documented in the Ecological – Construction Environmental Management Plan (E-CEMP) required under Condition 9.

2.2.5 Condition 13 required a programme of archaeological survey work to be undertaken which has been already been completed and the planning condition was discharged on 29th August 2019.. However, there is a requirement for part of the Works to be carried out under archaeological control and the mechanisms for this brief shall be captured in this CEMP.

2.2.6 Condition 8 requires information for the biodiversity offsetting produced by the scheme proposals. This is considered to be outside the scope of this CEMP and is indirectly related to the long-term landscaping maintenance after the scheme construction is completed. This will be tied into Condition 7 which outlines the need for a long-term landscaping management plan (LEMP), the first year of which will fall under the Works.

2.2.7 Conditions 6 (Construction Management Plan), 7 (LEMP), 9 (E-CEMP), 12 (Tree Protection Plan), 20 (Production of the CEMP) are conditions that require discharge pre-commencement of the works. As these individual conditions will be collected under the umbrella of the CEMP - but still need to be distinctive items to allow for application for condition discharge - it is proposed to have these documents as standalone sections within the CEMP.

Page 16: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 11

3. PROJECT TEAM ROLES AND RESPONSIBILITIES

3.1 Employer and Principal Contractor

3.1.1 The key individuals responsible for monitoring, updating of and for ensuring compliance to, the CEMP for the Employer and Principal Contractor are listed in Table 3.

3.1.2 To ensure that the above ecological standards are maintained, it is necessary that every person working on the Site shall be made aware of their responsibilities. The Principal Contractor shall have overall responsibility for implementation of the CEMP on site. The Principal Contractor shall also detail roles and responsibilities in Method Statements and Plans of Work for each activity. A summary of key responsibilities for each position listed in Table 3 follows after the table.

Table 3: Employer and Principal Contractor Key Personnel

Name Contact Details Role on Project

Employer (Warwickshire County Council)

Tristan Hall [email protected]

01926 412 675

Employer’s Representative

Neil Spencer [email protected]

01926 412 406

Design Manager – Highways

(also Highways Principal

Designer under CDM

Regulations)

Peter O’Connor [email protected]

01926 412 025

Design Manager – Structures

(also Structures Principal

Designer under CDM

Regulations)

TBC TBC NEC3 Project Manager

Graeme Wasilew [email protected]

07715 677 044

NEC3 Supervisor

Gary Hillier [email protected]

01926 418 060

Project Ecologist

Caroline Rann [email protected]

01926 416 936

Archaeologist

Principal Contractor (Colas SIAC)

Nicholas Dobbie [email protected]

07747 237 752

Project Director

Andy Bond [email protected]

07912 970 104

Construction Project

Manager

Jason Hayter [email protected]

07760 163 146

Planner

Page 17: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 12

Name Contact Details Role on Project

Kevin Nevin [email protected]

07791 718 436

Works Manager

Russell Threadgold [email protected]

07852 269 716

Site Agent 1

Susana Sa [email protected]

07342 073 348

Site Engineer

Zeshan Hussain [email protected] Site Engineer

Jake Swinburn [email protected]

07502 790 335

Apprentice Engineer

Darren Weston [email protected]

07760 175 733

SHEQ Manager

Middlemarch

Environmental

01676 498 038 Site Environmental Advisor

3.2 Employer’s Representative

3.2.1 Key person involved in the management of the project on behalf of the Employer, and who monitors the overall progress of the project in terms of cost, time and quality. This person shall be responsible for ensuring that suitably appointed people will be issuing instructions to the Principal Contractor and NEC 3 Project Manager as necessary.

3.3 Design Manager

3.3.1 Person involved in the technical design of the project on behalf of the Employer, and who addresses design and technical issues surrounding the Works. This person shall be responsible for ensuring that any design or technical issues requiring the Employer input shall consider the requirements of the CEMP’s and the procedures/processes contained therein.

3.4 NEC3 Project Manager

3.4.1 This person is responsible for the administration of the Contract on behalf of the Employer and will ensure that the parts of the CEMP that are required to be actioned by the Employer will be done so in a timely fashion.

3.5 NEC3 Supervisor

3.5.1 The Supervisor will be based full time on site to make sure that the quality requirements of the Works will be undertaken in line with the procedures/processes outlined in the CEMP.

3.6 Project Ecologist

3.6.1 The Project Ecologist will be based on site part time. A more detailed description of the

Page 18: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 13

Project Ecologist’s role and responsibility is contained in the E-CEMP in Appendix B.

3.7 Archeaologist

3.7.1 The Archeaologist will not be based on site full time but will visit site should the need arise to address any archaeological issue encountered.

3.8 Construction Project Manager

3.8.1 Assumes overall responsibility for ensuring that the requirements of this CEMP are always adhered to and liaising with the Employer where necessary. Makes certain that all Site staff and Sub-Principal Contractors undertake their activities in accordance with the CEMP and that appropriate monitoring of applying the CEMP’s requirements is being undertaken.

3.8.2 Assumes overall responsibility for ensuring that unacceptable levels of environmental pollution such as water and soil pollution, noise, vibration and dust do not arise from their activities on the Site. This includes making sure that:

i. statutory environmental requirements are met;

ii. environmental best practice and control is employed;

iii. producing environmental project specific procedures for all significant risks identified and implementing control measures to minimise the risk of damage to the environment;

iv. when completed, that the relevant procedures are followed;

v. resources (personnel and financial) are available to meet the environmental management requirements;

vi. corrective actions are implemented; and

vii. records and other relevant documentation are maintained.

viii. Responsible to complete the site waste management plan and ensure it is followed.

ix. Copies of the CEMP are held on site and that it is implemented throughout all phases of the project.

x. Ensuring the CEMP details are updated as and when relevant information is provided by the stakeholders associated with each section of the CEMP; e.g. further consent conditions, pre-construction surveys, etc.

3.9 Site Management

3.9.1 The Works Manager will implement and oversee the day to day aspects of this CEMP and will be responsible for:

i. Overseeing the security of the site and making sure all materials and chemicals are stored safely and securely;

Page 19: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 14

ii. Ensuring that appropriate signage (e.g. COSHH stores, tree root protection zones, ecological buffers etc) and information relating to this CEMP are displayed throughout the site;

iii. Making sure the site is maintained in a tidy and orderly fashion and that all site procedures outlined in this CEMP are implemented;

iv. Arranging for controlled access arrangements so that in an emergency, those leaving site in the event of a pollution or spillage incident can do so safely;

v. Make sure all emergency arrangements and First Aid facilities (including trained staff) are available;

3.9.2 The Works Manager will make sure that all those that work on the site:

i. Have an appropriate site induction including a briefing on this CEMP and environmental issues pertinent to the project;

ii. Carry out regular and relevant toolbox talks;

iii. Understand and obey the Site Rules;

iv. Are made aware of the Emergency egress arrangements, Muster points, First Aid facilities and First Aiders, spill and clean up procedures;

v. Read and understand the site hazard board;

vi. Have current certification for activities as required;

vii. Are aware of all environmental matters which arise on site;

viii. Have appropriate information on the specific task, including risk assessments and method statements (RAMS), which – where necessary – identify and document any environmental procedure that may be applicable; and

ix. Carry out their tasks and duties in accordance with the RAMS and this CEMP where necessary;

3.10 Site Personnel

3.10.1 All Site staff shall be responsible for adhering to the requirements of the procedures outlined in the CEMP, ensuring that legislative requirements and good environmental practice are met within their job function.

3.10.2 As part of the Site induction, all Site staff shall be made aware of this CEMP and its contents, together with the importance of good environmental control.

3.11 SHEQ Manager and Site Environmental Advisor

3.11.1 The SHEQ Manager and Site Environmental Advisor shall ensure work is carried out:

i. In accordance with legislation & consents, objectives, targets and the CEMP with regards to any Environmental activities on site.

Page 20: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 15

ii. Ensure site staff operates in accordance with agreed Risk Assessments and Method Statement (RAMS) and in accordance with the induction and tool box talk training with regards to environmental risk.

3.11.2 Monitor/Report Environmental Issues by:

i. Ensuring compliance with Environmental legislation & consents, objectives, targets and the CEMP.

ii. Carrying out Inspections, Audits and Non – conformance.

iii. Responsible for delivering environmental training.

iv. Environmental performance data reporting.

v. Ensure work is carried out in accordance with the CEMP

vi. Compliance with environmental legislation, consents, objectives,

vii. Targets and other environmental commitments

3.12 Sub-Principal Contractors and Third Parties

3.12.1 In addition, the key individuals from Third Parties and the supply chain listed in Table 4 will have a duty to ensure compliance with the CEMP. Where necessary, these individuals will be delegated responsibility from either the Employer or Principal Contractor who retain overall responsibility for the correct implementation of the CEMP.

Table 4: Third Parties, Sub Contractors and Suppliers Key Personnel

Name Contact Details Role on Project

Highways England/Kier

Mark Winthorpe [email protected]

07980 809 922

Construction Manager

(Area 9 ASC)

Note - Kier role is 3rd party

(non-contractual) – acting

as Highways England

Watchman (Section 6

agreement)

Katie Owen [email protected]

07467 117 310

Landscape Manager (Area

9)

Note - Kier role is 3rd party

(non-contractual) – acting

as Highways England

Watchman (Section 6

agreement)

Page 21: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 16

Name Contact Details Role on Project

BT Openreach

Christopher Brodie [email protected]

07743 843 254

Project Engineer

British Pipeline Agency Ltd (BPA) Pipelines

Adam Canning [email protected]

07860 260 542

Lands Team Leader

Cadent Gas Ltd (National Grid)

Sarrah Diaby [email protected]

07856 002 841

Designer

Severn Trent Water Mains

Scott Minchin [email protected]

07889 632 727

Project Engineer

Stephen Bramley 07889632727

[email protected]

Programme Manager

Severn Trent Water Sewer

Andy Biggins 02477 716 843 -

Virgin Media

Steve Rourke 07973 246 796 -

Vodafone

Julie Flanagan [email protected]

07803 260 359

Networks Manager

Nick Rigby [email protected]

07717 432716

Diversionary Works

Western Power Distribution (Electric & DNO)

Sally Andreasen [email protected]

01455 232 224

-

Page 22: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 17

Name Contact Details Role on Project

Atkins

Jim Girdis [email protected]

0780 3259696

Senior Ecologist who can

deputise for Project

Ecologist

WSP

Silvia Pensa [email protected] Employer’s Geotechnical

Support

3.13 Sub Contractor Works Managers

3.13.1 Where highlighted in Table 4, Sub Contractor Works Managers shall be responsible for:

i. Ensuring that all staff adhere to statutory ecological requirements and the CEMP.

ii. Ensuring that resources (personnel and financial) are available to meet the necessary ecological mitigation requirements.

iii. Reporting incidents to the Principal Contractor.

iv. Ensuring that corrective actions are implemented.

v. Ensuring that records and other relevant documentation are maintained and reported to the Principal Contractor.

3.14 Third Party Visitors

3.14.1 All visitors to the site will be made aware of the CEMP and the controls applicable to their presence and activities on site including but not limited to:

i. Method statements

ii. Risk Assessments

iii. Site induction which include Environment briefings

iv. Tool box talks.

3.14.2 The Project Manager will be responsible for monitoring communications between all relevant parties to the project ensuring that all environmental matters to the project are discussed and managed and observation of the communications will be documented in the weekly site meetings and sent by e-mail. In addition, a copy of all correspondence will be held on file.

3.14.3 Relevant site layout and location plans/ CDM drawing detailing the location and construction of the site compound, storage locations and car parking are to be displayed on an information board at the site entrance.

Page 23: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 18

3.14.4 Visitors to the project will be responsible for:

i. Ensuring that the control measures identified from environmental surveys are implemented as they are relevant to their work / visit.

ii. Ensuring that the project management team are notified of any non-conformance of control measures or environmental incident where the environment has been put at risk.

3.15 Environmental Training and Briefing Procedures

3.15.1 The Principal Contractor will instigate a series of inductions, training and briefing procedures for all construction staff operating on the site in order to communicate the requirements of the CEMP.

3.15.2 As specified in the Construction Phase Plan (CPP), Colas SIAC Site Team will deliver site inductions to all persons required to enter on site.

3.15.3 All the general Environmental restrictions will be mentioned in all inductions.

3.15.4 All the specific Environmental restrictions related to Site activities will be mentioned in the RAMS and briefed to the Site Staff before the works start.

3.15.5 Colas SIAC will notify the Subcontractors about the Environmental restrictions that could be related to their activities to make sure that all the restrictions are mentioned in their RAMS. All Subcontractor’s RAMS will be reviewed and approved by Colas SIAC and WCC before any works start.

3.15.6 Colas SIAC will perform toolbox talks on a regularly basis to alert all Site Staff about all Environmental restrictions that are present on site.

Page 24: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan (CEMP)

PART 2 – EXISTING SITE INFORMATION AND BASELINE CONDITIONS

Page 25: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 20

4. SITE LOCATION AND EXISTING SITE CONDITIONS

4.1.1 The A46 Stoneleigh Junction is located on the A46 between Coventry and Kenilworth at the junction with the C32 Stoneleigh Road. It provides principal access from the Strategic Road Network (SRN) to Warwick University and the National Agriculture and Exhibition Centre (NAEC) at Stoneleigh.

4.1.2 The existing junction compromises a single carriageway bridge carrying the C32 Stoneleigh road above the three lane A46 dual carriageway. Two Lane slip roads allow unrestricted access north and south from the C32 onto and off from the A46. At the point where the slip roads meet the C32, there are two priority cross roads.

4.1.3 The C32 continues from the bridge north west towards the University of Warwick and approximately 300m on from the bridge, there is an existing roundabout at the junction of Stoneleigh Road and Dalehouse Lane which provides connectivity into Kenilworth from the east. The road crosses Finham Brook to the north west of the Dalehouse Lane Roundabout.

4.1.4 Heading south east from the existing A46, the C32 links into the B4115 which provides onwards connections towards Leamington Spa.

4.1.5 Stoneleigh Road does include for footway provision on the existing A46 overbridge and along a section of the road to the east of the junction. However, there is no other footway access on the main C32 road itself. A public footpath – Centenary Way - passes alongside the A46 northbound off slip and along a section of Stoneleigh Road until the Stoneleigh Road/B4115 junction.

4.1.6 The surrounding land is dominated by arable land with some improved and semi improved grassland, small areas of woodland, hedgerows, scrub and ponds. Finham Brook lies to the west and north of the junction and flows from the southwest to the northeast.

4.1.7 The earliest historical maps dating from 1886 shows the area of the A46 junction was used as agricultural fields. A track along the alignment of Stoneleigh Road is shown to be present at this time. Dalehouse Lane is present on its original alignment close to, and parallel with Finham Brook. Dalehouse Lane has a junction with Stoneleigh Road approximately 50m from Finham Brook.

4.1.8 There was very little change until the construction of the A46, first shown on mapping from 1983. This map also shows the realignment of Dalehouse Lane on the approach to Stoneleigh Road with a new triangular junction. This triangular junction has changed to the current roundabout on 2006 mapping.

4.1.9 An assessment of neighbouring land uses was undertaken in 2018 and identified the current neighbouring land as follows:

i. North – A46 and agricultural fields;

ii. South – A46 and agricultural fields;

iii. East – Agricultural fields; and

iv. West – Agricultural fields and Finham Brook.

An aerial image of the existing junction from 2018 is shown in Figure 5.

Page 26: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 21

Figure 5: Aerial Image of Existing Junction circa 2018

5. EXISTING SITE – NEARBY FEATURES

5.1.1 There are a number of residential properties to the north of Dalehouse Lane, including: Croyde Hoe, Knysna, Finbrook, Barnfield, Westley House, High Lo and the Cottage. There are other farmhouses in the area including Manor Fields Farm, Kingswood House and Kingswood Farmhouse.

5.1.2 An area of land to the south of Stoneleigh Road (between Dalehouse Lane and Finham Brook) is currently used for beekeeping activities. North of Finham Brook (along Stoneleigh Road), is an area of land used for commercial use at Brook Farm. There are a number of agricultural accesses to fields either side of Stoneleigh Road between the A46 and Finham Brook.

5.1.3 Approximately 800m south of the existing A46/Stoneleigh Road junction, there is proposed to be the crossing of the High Speed 2 (HS2) railway line. Traffic associated with the HS2 works is expected to use the Stoneleigh junction as a haulage route, thereby increasing traffic flows (particularly lorries) in the area for a number of years.

5.1.4 In the field to the north of Stoneleigh Road east, there is a proposal to construct the Rugby Farmers’ Market which is a new development.

5.1.5 In the fields to the south of Dalehouse Lane, there is an existing Public Right of Way (PROW), route K29. The PROW crosses over the field before running along the boundary of the A46 northbound off slip road before finally providing a stepped access to the road at the top of the northbound off slip.

Page 27: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 22

6. ECOLOGICAL BASELINE CONDITIONS

6.1.1 An Ecological Impact Assessment (EcIA) was completed by the Employer in December 2017 and was used to support the planning application. This EcIA document formed the basis of a baseline assessment of ecological conditions and more detail can be found in the Ecological – Construction Environmental Management Plan (E-CEMP) contained in Appendix B.

6.1.2 The E-CEMP document is to be read in conjunction with this CEMP. To provide a distinction between the Construction Environmental Management Plan and the Construction Ecological Management Plan, the former is abbreviated to CEMP (and is this document), whereas the latter is abbreviated to CEMP with the E prefix (e.g. E-CEMP) and is contained in Appendix B.

7. EXISTING GROUND CONDITIONS

7.1.1 Ground investigation work has been undertaken during the development of the scheme which outlines that the ground largely comprises Kenilworth Sandstone Formation which comprises both sandstone and mudstone. The Formation was typically described as a medium dense silt/gravel sand which may in areas be cohesive.

7.1.2 Made ground is present close to the A46 as part of the northbound off-slip which is to be constructed on an embankment. Further made ground is located near Finham Brook and there are also alluvial and river terrace deposits in proximity to the Brook and these extend to depths of 3, to 4m below existing ground level.

7.1.3 No areas of contamination were noted during any ground investigation testing undertaken during the design development. However, it is expected that the ground in the area around Finham Brook is contaminated with the seed for Himilayan Balsam and this is documented further in the next section.

7.1.4 No mines or mineral deposits were identified within 500m of the site and no recorded landfills are present within 1km of the site.

7.1.5 Information from the Environment Agency revealed that the bedrock of the site is a Principal aquifer and the superficial deposits are a Secondary A aquifer. The site lies entirely within Zone 3 of a groundwater source protection zone.

7.1.6 An archaeological evaluation was undertaken between January and February 2017. This revealed no features were recorded to the west of the A46. An undated ditch parallel to the existing boundary was recorded to the east of the A46. No archaeological finds were made.

8. AREA IN AND AROUND FINHAM BROOK

8.1.1 The Works are required to take place in and around Finham Brook. Finham Brook is a salmonid river and there are risks to the environment of the river during any construction operations. The main environmental issues when working in the vicinity of the Brook are as follows:

i. Finham Brook is located in a flood zone;

ii. It is a salmonid watercourse; and

Page 28: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 23

iii. Areas around the river contain Himalayan Balsam.

8.1.2 Following discussions with the Environment Agency, the risks to the river are deemed to be as follows:

iv. The construction operations create a flood risk;

v. Damage to the ecology of the river through construction operations; and

vi. The construction operations allow the spread of Himalayan Balsam which is in the area.

8.1.3 A summary of the environmental risks in this area is shown on drawing 9.2-A46-083-190 which is contained in Appendix C.

9. EXISTING TREES

9.1.1 A survey of existing trees has been undertaken which has identified a number of critical mature trees to be retained in and around the site. These trees are to be retained during the Works and a Tree Protection Plan has been put in place which outlines the methods by which this shall be done. A copy of this plan is contained in Appendix K.

Page 29: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 24

PART 3 – ACTIVE MEASURES – CEMP SITE SPECIFIC CONTROLS

Page 30: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 25

10. GENERAL

10.1.1 The following control measures have been developed to best reflect the actual methods of working during the construction period.

10.1.2 The environmental standards for the site have been determined and detail the minimum measures that will be applied for general operations that fall outside the risk assessment and/or method statements.

10.1.3 Where necessary, these are outlined in the relevant sections below.

11. ENVIROMENTAL RISK ASSESSMENTS

11.1.1 All activities to be undertaken on site have had an Environmental Risk Assessment carried out by the Principal Contractor. The Risk Assessment has been undertaken by trained staff following an approved procedure. The assessment has:

i. Identified the significant environmental impacts that can be anticipated;

ii. Assessed the risks from these impacts;

iii. Identified the control measures to be taken and re-calculate the risk; and,

iv. Report where an inappropriate level of residual risk is identified so that action can be taken through design changes, re-scheduling of work or alternative methods of working to reduce the risk to an acceptable level.

11.1.2 The results of a risk assessment and their residual risks are only considered acceptable if:

i. the severity of outcome is reduced to the lowest practical level;

ii. the number of risk exposures are minimised;

iii. all reasonably practical mitigating measures have been taken and the residual risk rating is reduced to a minimum.

11.1.3 The findings of the risk assessment and the necessary controls will be explained to all operatives before the commencement of the relevant tasks using an agreed instruction format.

11.1.4 The Risk Assessments are contained in Appendix H.

12. METHOD STATEMENTS

12.1.1 Method Statements have been prepared by the Principal Contractor (or, where necessary by Sub Contractor or Suppliers) by competent, trained experienced personnel. These documents have been prepared in consultation with on-site environmental staff and, where necessary, environmental specialists.

12.1.2 Their production has included a review of the environmental risks and commitments, (as identified in the risk assessment outlined in the previous section), so that appropriate control measures are developed and included within the construction processes.

Page 31: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 26

12.1.3 Method Statements have been reviewed by the SHEQ Manager, and, where necessary, by an appropriate environmental specialist. Where necessary, Method Statements will be submitted to the enforcement agencies (Environment Agency, Natural England, Environmental Health Officer etc) as appropriate.

12.1.4 The Method Statements are contained in Appendix H.

13. AIR QUALITY - DUST & EMISSIONS

13.1.1 Dust deposition can harm vegetation and cause potential habitat loss, particularly if present in significant quantities. There is potential for dust to reach both on-Site and adjacent designated sites and habitats as a result of construction activity.

13.1.2 Dust levels during construction are not expected to be problematic, although dust suppression will be required during dry conditions. Care will be required to maintain dust emissions at a practicable minimum when working in the vicinity of residential properties and environmentally sensitive areas. Best practice mitigation will be required during dry conditions.

13.1.3 The site will adopt a control of dust at source approach by limiting where possible the materials and operations that will produce dust. The following protocols will be adopted for this site:

Site Vehicle Usage

i. Reuse or construction of new road surfaces to limit the dust arisings that may occur from moving vehicles across the site. Where necessary, this will be in the form of a haul road constructed from suitably compacted material to prevent dust arising;

ii. The implementation of a site wide policy to not have idling engines for vehicles not in use. These shall be switched off;

iii. Routing all site vehicles aware from sensitive environmental and ecological features where possible;

iv. Limiting the fall distance for materials onto lorries or into the Works; and

v. Ensuring that all vehicles are suitably well maintained so that exhaust emissions do not breach statutory limits.

Equipment and Material Usage

vi. Restrict cutting or grinding operations (such as cutting concrete or any cutting activity likely to result in a lot of dust arising) to certain locations and away from environmentally sensitive areas;

vii. Wherever possible, fitting equipment likely to produce a lot of dust with suppression equipment, e.g. vacuums or water sprays;

viii. Limiting the fall distance for materials onto lorries or into the Works;

Other Measures

ix. Stockpiling and storing materials in an appropriate manner to ensure that dust particles are prevented from becoming airborne. This may include sealing and seeding of the stockpiles;

Page 32: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 27

x. Where necessary, damping down construction operations – particularly bulk earthworks – during dry weather to minimise dust particles becoming airborne;

xi. Erecting fencing and/or hoarding to limit dust dispersion and prevent any unauthorised access from wildlife;

xii. Banning the use of fires or any form of burning on site; and

xiii. Regularly sweeping all roads, footways and/or hard standing areas.

13.1.4 Construction operations will be monitored for dust. Colas SIAC site staff will visually monitor activities which can be reponsible for production of dust. Preventative measures will be implemented to prevent production of dust. Colas SIAC control methods are presented in point 3.8.2 of the CPP.

13.1.5 The Construction Project Manager will ensure that the source of any identified air quality problem is determined and immediately implement the appropriate mitigation action to address the issue. The action taken shall be recorded and shall include for a period of monitoring whereby the effectiveness of the mitigation action shall be determined.

13.1.6 Where the mitigation action successfully controls the spread of dust, this shall be recorded and no further action is necessary. Where it does not, the Construction Project Manager will work up an action plan to address the issue and implement it as soon as possible. If necessary, this may include suspending the operation until appropriate control measures can be put in place.

13.1.7 All records shall be kept and made available as part of the regular review of the effectiveness of the CEMP.

14. ARCHAEOLOGY & CULTURAL HERITAGE

14.1.1 In 2017, the Employer undertook a series of on site archaeological investigations that formed part of the planning application. The work was carried out in accordance with the Chartered Institute for Archaeologists Standards and Guidance for Field Evaluation 2014.

14.1.2 Twenty-eight trial trenches were excavated across the site and locations of the trenches can be seen in the plan in Appendix I. The single feature found was a shallow and undated ditch. No archaeological remains of national significance were found as part of the investigations.

14.1.3 However, there remains a requirement for archaeological control and potential investigation on any other area within the Works that has not already been subjected to any assessment.

14.1.4 Drawing 9.2-A46-083-6110D in Appendix I outlines the areas within the Works which shall be carried out under archaeological control . The project archaeologist will be present on site for any topsoil strip and early excavations for material up to a 1m deep in the first instance.

14.1.5 The scheme archaeologist will be as listed in Table 3 of this document.

14.1.6 The Principal Contractor shall provide no less than five working days notice of the plan to carry out topsoil strip/excavation works in each of the locations identified on Drawing 9.2-A46-083-60. This is to allow sufficient time for the scheme

Page 33: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 28

archaeologist to make arrangments to attend site.

14.1.7 Before any excavation works take place, the scheme archaeologist will prepare a Written Scheme of Investigation (WSI) and submit it for approval by the Planning Archaeologist. The WSI should include the following information:

i. A description of the proposed methods of excavation and recording system;

ii. An explanation of the sampling strategies to be used;

iii. A project timetable for the work on site, including numbers of staff and machines (and for post excavation work, including staff numbers and specialist sub-Principal Contractors); and

iv. Any significant variations to the proposal by the Planning Archaeologist.

14.1.8 The areas will be stripped under the supervision of the scheme archaeologist up to a depth of circa 1.0m initially. The Principal Contractor will use a toothless ditching bucket to undertake the excavation and will work in spits based on the direction of the archaeologist. Excavation will continue until the top of any archaeological remains are reached, or the geological natural ground is encountered or the required dig level – whichever is first. The scheme archaeologist will make the assessment on site as to the point where excavation ceases.

14.1.9 If no archaeological features are found, the scheme archaeologist will record this and work shall continue. No excavation shall continue until the scheme archaeologist has reviewed, documented everything they require and confirmed that it can proceed.

14.1.10 If archaeological features are discovered, excavation shall be halted and time will be allowed in the programme for the scheme archaeologist (with assistance from other archaeologists as required) to excavate and record the features exposed. This may require additional excavation to clarify the character or extent of any archaeological feature exposed.

14.1.11 The scheme archaeologist will have the authority to halt any excavation works if necessary on the identification of possible areas of archaeological interest. Excavation work shall not recommence until the scheme archaeologist has documented what they require and then confirmed it can proceed.

14.1.12 Any human remains which are encountered must initially be left in situ until confirmed by the scheme archaeologist who will consult with the Planning Archaeologist as required.

14.1.13 Any areas of exposed archaeological remains will not be available for any form of construction work or for plant/vehicle crossing until permission is granted by the Planning Archaeologist. The scheme archaeologist will arrange for all necessary information to be provided to the Planning Archaeologist to enable that permission to be granted.

15. CONSTRUCTION LIGHTING

15.1.1 In determining the lighting arrangement on site, consideration will be given to residents and other environmental sensitive receptors that may experience a nuisance by light. Where appropriate, measures will be implemented to reduce obtrusive light.

Page 34: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 29

15.1.2 Where possible, a daylight only construction schedule will be adopted to minimise adverse lighting. It is unavoidable that construction work may require work during the hours of darkness in consideration of shorter daylight availability during winter months.

15.1.3 Where appropriate the following measures will be adopted for implementation:

i. Dim or switch off lights (including flashing beacons) where it is safe to do so

ii. Use specifically designed equipment

iii. Position lights sensibly and pointing away from boundary edges, residents and other environmental sensitive receptors.

15.1.4 Habitats on site including the linear scrub/trees and hedgerows on both phases are suitable for commuting and foraging bats. Further information on lighting and ecology can be found in the E-CEMP.

15.1.5 No night working is to be undertaken with working hours restricted to 1900 and 0700, as approved by the Overseeing Organisation. Should the use of lighting be required during these hours, (due to reduced daylight during winter and spring months), all lighting equipment will be directed away from habitats of value to faunal species such as trees, hedgerows and watercourses.

16. ECOLOGY

16.1.1 All matters pertaining to ecology are contained in the Ecological – Construction Environmental Management Plan (E-CEMP) which is contained in Appendix B.

16.1.2 Detailed habitat management descriptions for retained habitats and ecological enhancement measures are proposed via the production of a Landscape and Ecological Management Plan (LEMP), which is contained in Appendix J. The procedures for the LEMP will largely apply after the construction works have concluded and the landscape maintenance is underway.

17. GEOLOGY, SOILS AND CONTAMINATED GROUND

17.1.1 The permanent Works are to be constructed on a granular core of Class 1 acceptable material laid to a slope gradient averaging 1 in 2.5. Site won materials will be incorporated into the works providing that the necessary grading and materials specifications are met.

17.1.2 No contaminated ground was encountered during the ground investigation works and so is not anticipated to be discovered during routine earthworks operations. Should contaminated ground be detected, the procedure for dealing with it is outlined in Part 4.

17.1.3 The area around Finham Brook has been identified as having the presence of Himalayan Balsam. The design includes for a strategy for dealing with this plant in order to prevent its spread. This is outlined in more detail in the next section.

17.2 Treatment of Himalayan Balsam

17.2.1 The approximate extent of the Himalayan Balsam that is known is shown on drawing 9.2-A46-083-190 contained in Appendix C. It is not known the depths of soil that the plant spores may contaminate but the working assumption is that the

Page 35: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 30

top 500mm will be affected.

Finham Brook Flood Compensation Area

17.2.2 The Works requires the creation of a new permanent flood area to compensate for the construction of Westley Bridge. The work consists of reducing the existing ground level down to a lower level by removing some material from the area.

17.2.3 The strategy for addressing the Himalayan Balsam is as follows:

i. The top 500mm of material (assumed topsoil) will be excavated with care and under archaeological control and stored within the site area with appropriate measures in place to prevent the spread of the seeds. Colas SIAC are aware about the risks related to Himalayan Balsam and will make sure that all RAMS related to the works that will take place in the area(s) affected by Himalayan Balsam will outline the requirements of the Environment Agency Code of Practice.

ii. The remaining earth will then be removed down to the final required levels plus a further 500mm using conventional excavation techniques and bearing in mind the requirements of working near a watercourse outlined in the E-CEMP.

iii. All excavated earth will then be removed from the area. The topsoil containing the Himalayan Balsam seeds will then be reinstated to the final finished levels.

iv. All the RAMS will be approved by Colas SIAC and WCC before works start. During the performance of the works, visual inspections will be carried out by Colas SIAC to control the excavation, ensure that the topsoil contaminated with Himalayan balsam seeds remains on site and doesn’t enter into Finham Brook and control any other requirements stated in the RAMS.

Construction of New Westley Bridge

17.2.4 The construction of the new bridge will be within an area containing Himalayan Balsam. The proposed strategy for addressing the Himalayan Balsam in this area is as follows:

i. As outlined in the CPP, Colas SIAC will carry out a visual inspection during the pre-construction stage to determine the geographical area of Himalayan Balsam that is likely to be affected by bridge construction works.

ii. A method statement will be submitted to WCC and approved by WCC and the Environment Agency before the works related to the construction of the new Westley bridge start.

iii. As outlined in the project CPP, a method statement will be produced, stating that the top 500mm layer of soil (where the Hymalayan Balsam is present as seeds) will be excavated for the bridge works will be buried underneath a mound in the centre of the Dalehouse Lane roundabout. If there is insufficient room within the Dalehouse Lane mound for the aforementioned storage method, the remaining material will be safely removed from site in accordance with the Environmental Protection Act Sections 33 and 34.

17.3 Suitability of Ground Materials

17.3.1 All soil materials that are to be used on site (whether that is reuse of existing

Page 36: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 31

materials won from site or material imported into site), will be assessed for whether or not it is environmentally acceptable.

17.3.2 The first stage of this assessment will be to determine whether the material poses a risk in terms of polluting sensitive controlled waters and/or a risk in terms of harm to human health or the environment.

Polluting Sensitive Controlled Waters

17.3.3 During planning of the earthworks operations, the Principal Contractor will make an assessment of where on Site the potentially sensitive controlled waters are located. A ‘controlled water sensitive area’ is defined as:

i. Any area within 500m of a surface water body;

ii. In an area underlain by an aquifer designated as any of the following:

• Principal or Secondary A aquifer;

• Having intermediate or high aquifer vulnerability;

• A groundwater Source Protection Zone – total catchment (for a potable extraction); or

• Groundwater (Drinking Water) Safeguard Zone

17.3.4 The ground investigation works identified that the Site lies within 500m of a

surface water body (Finham Brook) and is in Zone 3 of a source protection zone. It was also noted that the bedrock is a Principal aquifer and some of the superficial deposits are Secondary A aquifers. Therefore, the entire site is classed as a controlled water sensitive area. A copy of the groundwater source protection zone is shown in Ground Investigation Report produced by WSP for WCC.

17.3.5 As a result of this, all material to be used will be chemically tested to demonstrate suitability for use. It will be tested at a frequency of one sample per 500m3 (subject to a minimum of three for each material stream from any distinct source). The samples will be submitted for soil leachability analysis to UKAS/MCERTS accredited laboratories. The SHEQ Manager will be responsible for ensuring this testing is carried out.

17.3.6 The samples will not exceed the Limiting Values as set out in Table 6 or else the material will not be used and an alternative compliant material sourced. The Limiting Values have been set in order to protect surface water quality and are based on available environmental quality standards.

Table 6: Soil Leachate Limiting Values

Analysis Limiting Value Criteria Source

pH ≥ 6.5 to ≤ 9 pH units The Water Supply (Water Quality) Regulations 2016

Arsenic 10 µg/l The Water Supply (Water Quality) Regulations 2016

Cadmium 5 µg/l The Water Supply (Water Quality) Regulations 2016

Mercury 1 µg/l The Water Supply (Water Quality) Regulations 2016

Iron 0.2 mg/l The Water Supply (Water Quality) Regulations 2016

Lead 10 µg/l The Water Supply (Water Quality) Regulations 2016

Page 37: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 32

Analysis Limiting Value Criteria Source

Copper 2,000 µg/l The Water Supply (Water Quality) Regulations 2016

Manganese 50 µg/l The Water Supply (Water Quality) Regulations 2016

Nickel 20 µg/l The Water Supply (Water Quality) Regulations 2016

Selenium 10 µg/l The Water Supply (Water Quality) Regulations 2016

Benzo(a)pyrene 0.01 µg/l The Water Supply (Water Quality) Regulations 2016

Benzene 1 µg/l The Water Supply (Water Quality) Regulations 2016

Toluene 700 µg/l The Water Supply (Water Quality) Regulations 2016

Cyanide 0.05 mg/1 The Water Supply (Water Quality) Regulations 2016

PAHs (sum of four)*

0.01 µg/l The Water Supply (Water Quality) Regulations 2016

* sum of benzo(b)fluoranthene, benzo(g,h,i)perylene, indeno(1,2,3-cd)pyrene & benzo(k)fluoranthene

Harm to Human Health and the Environment

17.3.7 As well as making an assessment to potential pollution of sensitive waters, all material must be tested to ensure it does not have the potential to cause harm to human health and other flora and fauna.

17.3.8 Similarly to the pollution assessment, all material to be used will be chemically tested to demonstrate suitability for use. It will be tested at a frequency of one sample per 500m3 (subject to a minimum of three for each material stream from any distinct source). The samples will be submitted for soil leachability analysis to UKAS/MCERTS accredited laboratories. The SHEQ Manager will be responsible for ensuring this testing is carried out.

17.3.9 The samples will not exceed the Limiting Values as set out in Tables 7 and 8 or else the material will not be used and either:

i. an alternative compliant material sourced; and/or

ii. a programme of treatment considered and applied which is then re-assessed for its suitability.

Table 7: Soil Limiting Values (mg/kg)

Determinand Human Health (Commercial/Industrial exposure scenario)

Origin of Value

Inorganics

Arsenic 640 C4SL (Defra 2014)

Cadmium 410 C4SL (Defra 2014)

Chromium (total) 8600 LQM/CIEH 2014

Copper 68,000 LQM/CIEH 2014

Lead 2330 C4SL (Defra 2014)

Mercury (methyl) 290 LQM/CIEH 2014

Nickel 980 LQM/CIEH 2014

Selenium 12,000 LQM/CIEH 2014

Page 38: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 33

Determinand Human Health (Commercial/Industrial exposure scenario)

Origin of Value

Zinc 730,000 LQM/CIEH 2014

Organics

Phenol 380[1] LQM/CIEH 2014

Toluene 33,000 LQM/CIEH 2014

Ethylbenzene 32,000 LQM/CIEH 2014

Polycyclic Aromatic Hydrocarbons (PAH):

Acenaphthene 75,000 LQM/CIEH 2014

Acenaphthylene 76,000 LQM/CIEH 2014

Anthracene 520,000 LQM/CIEH 2014

Benzo(a)anthracene 170[2] LQM/CIEH 2014

Benzo(b)fluoranthene 45[2] LQM/CIEH 2014

Benzo(k)fluoranthene 1200[2] LQM/CIEH 2014

Benzo(a)pyrene 76 C4SL (Defra 2014)

Benzo(ghi)perylene 3900 LQM/CIEH 2014

Chrysene 350[2] LQM/CIEH 2014

Dibenzo(ah)anthracene 3.5[2] LQM/CIEH 2014

Fluoranthene 23,000 LQM/CIEH 2014

Fluorene 60,000 LQM/CIEH 2014

Indeno(123-cd)pyrene 510[2] LQM/CIEH 2014

Naphthalene 100 LQM/CIEH 2014

Phenanthrene Pyrene 22,000 LQM/CIEH 2014

NOTES TO ACCOMPANY TABLE:

1. Phenols capped based on EA approach to limit Phenol to 1% by weight in soil solution (Phenol SGV Report).

2. Benzo(a)pyrene may be used as a surrogate marker for these compounds in the assessment of carcinogenic risks posed by PAHs in soils where the PAH profile in the soils is sufficiently similar to that of coal tar as defined by Culp et al. (1998). If the PAH profile is not sufficiently similar to coal tar then speciated assessment thresholds should be adopted.

Table 8: Petroleum Hydrocarbons Soil Limiting Values (mg/kg)

Determinand Human Health (Commercial/Industrial exposure scenario)

Origin of Value

Total Petroleum Hydrocarbons

TPH ALIPHATIC C5-C6 24,000 LQM/CIEH 2014

TPH ALIPHATIC C6-C8 5,300 LQM/CIEH 2014

TPH ALIPHATIC C8-C10 1,300 LQM/CIEH 2014

TPH ALIPHATIC C10-C12 6,100 LQM/CIEH 2014

TPH ALIPHATIC C12-C16 43,000 LQM/CIEH 2014

TPH Aliphatic C16-C35 1,000,000 LQM/CIEH 2014

TPH Aliphatic C35-C44 1,000,000 LQM/CIEH 2014

Page 39: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 34

TPH Aromatic C8-C10 122,000 LQM/CIEH 2014

TPH Aromatic C10-C12 11,000 LQM/CIEH 2014

TPH Aromatic C12-C16 35,000 LQM/CIEH 2014

TPH Aromatic C16-C21 29,000 LQM/CIEH 2014

TPH Aromatic C21-C35 29,000 LQM/CIEH 2014

TPH Aromatic C35-C44 29,000 LQM/CIEH 2014

18. HOUSEKEEPING

18.1.1 The Compound for the main works will be located at Stoneleigh Road. The Compound will comprised Offices, Canteen, Drying Room, Storage Room, Waste Areas and Toilet Facilities (refer to the CPP for more details).

18.1.2 To make sure that the Site will be Environmentally friendly, Colas SIAC will make available segregated waste skips, COSHH bins, recycle containers, spill kits and granules, concrete washout and bunded tanks for fuel storage.

18.1.3 Road sweepers and a wheel wash facilities will be available on site to keep the roads and vehicles clean during construction activities.

19. LANDSCAPING AND LAND USE

19.1 Protection of Existing Trees

19.1.1 There are numerous trees that are required to be protected for the duration of the works. Prior to works commencing in the area of the trees, and in accordance with planning condition No12, tree protection measures shall be put in place to prevent the trees being damaged during the construction of the works. The measures to be applied will be in accordance with the Tree Protection Plan (Appendix K).

19.1.2 The Construction Project Manager is to arrange for the weekly inspection of the tree protection fencing. These inspections are to be documented to evidence the ongoing surveillance and the records kept on file.

19.1.3 Should the fencing be found to be damaged in any way, the Construction Project Manager will:

i. Immediately stop works in the area;

ii. Arrange for remedial works to be carried out to the fencing;

iii. Investigate the reason for the damage to prevent re-occurrence; and

iv. Arrange for inspection of the tree and, where required, arrange for a trained arboriculturalist to carry out appropriate measures to minimise the impact on the tree

19.1.4 After any remedial measures to the tree have been undertaken, the Construction Project Manager will recommence the programme of weekly inspections which will now include a review of the mitigation measures undertaken.

Page 40: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 35

19.2 Landscaping Installation and Maintenance

19.2.1 A Site specific Method Statement and Risk Assessment for this activity will be prepared by Colas/SIAC before the works starts and a copy kept on the site file.

20. NOISE AND VIBRATION

20.1.1 Noise and vibration nuisances are controlled under the Environmental Protection Act 1990 as it has the potential to affect human health and habitats within and adjacent to the Site.

20.1.2 Noise and vibration shall be managed according to the best practicable means. The following mitigation measures will be implemented by the Contractor at all times to minimise noise and vibration generated from Site activities and disruption to any sensitive receptors:

i. Erecting noise protecting hoarding/sheeting to any boundaries adjacent to a receptor as outlined by the Ecologist or consider the use of constructing noise mitigation bunds;

ii. Control vehicle (especially lorry) movements in and around areas adjacent to receptors as well as ensuring vehicles are not stood with engines idling in the same areas;

iii. All plant, equipment and machinery used on site (including vehicular traffic), shall be designed and maintained to reduce noise levels to a minimum in order to meet the requirements of relevant EU directives and UK Statutory Instruments that limit noise emissions from construction plant, such as: Council Directive 79/113/EEC, Council Directive 86/662/EEC, Council Directive 86/662/EEC, Council Directive 95/27/EC and the Construction Plant and Equipment (Harmonisation of Noise Emission Standards) Regulations, 1988 SI 361;

iv. All plant equipment and machinery used on site, including vehicular traffic to and from the site, which is capable of being fitted with the appropriate silencers, baffles, cladding and rubber linings will be so fitted and maintained;

v. All plant will be sited so that the noise impact at nearby noise sensitive properties is minimized and will be switched off when not in use;

vi. Regular maintenance of plant in accordance with manufactures instructions;

vii. Noise and vibration monitoring on the Site, where necessary, which will assist in controlling levels at sensitive receptors. This will particularly apply when changes in processes are required for whatever reason; and

viii. Delivery vehicles will not be permitted to arrive on site before 07:30 or after 18:30 Monday to Friday, before 08:00 or after 13:00 on Saturday or at any time on Sundays or Public Holidays nor will they be permitted to wait on the Public Highways outside of these timescales. Care will be taken when unloading vehicles to minimise noise. Delivery vehicles will be routed to minimise disturbance to local residents. Delivery vehicles will be prohibited from waiting within the site with their engines running;

ix. Working hours would be restricted to the hours indicated in Table 10 below.

Page 41: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 36

20.1.3 Noise levels shall be monitored in an around the boundaries of the site adjacent to sensitive receptor sites. The ambient noise level (Leq) from all sources when measured 2.0m above the ground and 1.0m from the boundary of any receptor site shall either not exceed the appropriate level outlined in Table 9 or not exceed by more than 3dB(A), the existing ambient noise level (Leq).

20.1.4 Colas SIAC subcontractor will undertake background noise surveys at various times and locations around the Site before the main works start to establish the normal noise levels and monitor when the works’ performance exceed them.

20.1.5 When comparing the noise levels during the construction against the ambient level (Leq), the monitoring shall take place at the same location and over the same period as that which was used to determine the ambient level (Leq).

20.1.6 Should the construction noise levels consistently exceed those of the ambient levels (Leq), all construction work in the area shall cease until the source of the high noise level can be determined and rectified. Where necessary, the Contractor shall amend the method of working to minimise the impact of the noise operations.

20.1.7 Any such change to the working methodology or other noise mitigation procedures shall be recorded in the CEMP and distributed to the site staff by means of a Toolbox Talk.

Table 9: Schedule of Maximum Noise Levels Permitted

Total Noise Level Measured

Work which is likely to give rise to noise levels that are above 34dBA where background noise levels are no more than 24dBA (or 10dBA above the background noise level if this is more than 24dBA) shall be restricted to the following hours:

Mon-Fri 07:00 – 19:00, Sat 07:30 – 13:00.

Piling and activities such as hydro demolition shall be restricted to between the hours of 08:00 – 17:00.

No construction operations shall take place on Sundays or Public Holidays.

Restrictions outlined above are based on Planning Permission Condition 3 and shall not be changed unless otherwise agreed in writing with the County Planning Authority

Table 10: Site Working Hours

Normal Working Hours

0730 – 1830 Monday to Friday 0800 – 1300 Saturday No construction works to occur on Sunday or Public Holidays.

Special Exemptions Variations from the above would only occur with the prior written consent of the Warwickshire Council Environmental Health Officer and County Planning Authority

Page 42: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 37

21. WASTE

21.1.1 The Site will operate a Site Waste Management Plan (SWMP), broadly in line with the Site Waste Management Plan Regulations 2008 and required by the Employer under the Contract under Clause 175AR.

21.1.2 The SWMP is contained in Appendix E of this document. It shall be maintained and regularly reviewed by the Construction Project Manager and will be made available to all personnel on site as appropriate.

21.1.3 The SWMP will also be made available for inspection at all times by the Employer or any key stakeholder (e.g. Highways England) where required.

21.1.4 In accordance with Clause 174AR of the Contract, the quantities of recycled and secondary materials shall be recorded in an excel spreadsheet similar to the one presented in Appendix F.

21.1.5 For waste management details, please refer to the Colas Waste Management document presented in Appendix G and the draft shown in the Site Setup contained in the CPP.

21.1.6 All data sheets contained within the SWMP (documenting the usage and destination of all waste materials) shall be supplied to the Employer (and where necessary Highways England) within one month of completion of the Works.

22. WATER ENVIRONMENT

22.1.1 The majority of the Works lie within the natural catchment of Finham Brook. Only the most south-eastern part of Stoneleigh Road is located within the natural catchment of the River Sowe. The locations of the two watercourses in relation to the scheme are shown on the River Network Location Plan, drawing number drawing 9.2-A46-083-079 in Appendix D.

22.1.2 Both Finham Brook and the River Sowe are classified by the Environment Agency as having overall Moderate status (as per the 2015 cycle).

22.1.3 The drainage strategy for the Works is to reuse existing drainage outfalls to Finham Brook and the existing drainage system on Stoneleigh Road that ultimately ends in the River Sowe. Where necessary, treatment and attenuation of the permanent water has been encompassed into the design through the use of soakaways, swale and attenuation ponds.

22.1.4 During construction, water pollution has the potential to significantly alter environmental conditions on Site which can subsequently impact the viability of ecological habitats in those areas affected as well as cause a risk to human health. In particular, pollutants which can enter soil and water can change the chemical composition of growing substrates and water bodies which can damage the biodiversity of the watercourse.

22.1.5 It is considered that certain construction elements of the Works have the potential to contravene the Salmond and Freshwaters Fishery Act 1975 i.e. cause a pollution or silt incident associated with Finham Brook, which is classified as a Salmonid River. As such, in addition to those mitigation measures with regards to air, water and soil pollution as detailed elsewhere in the CEMP, further mitigation procedures will be applied during construction activities.

Page 43: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 38

Works Affecting Finham Brook

22.1.6 Works around Finham Brook will be subject to a defined method which as been approved by the Environment Agency (EA). A copy of that method and Environmental permit is contained in Appendix A of the E-CEMP. It is expected that there will be minimal amount of impact on biodiversity in the brook. The Works shall be carried out in accordance with the E-CEMP recommendations which describe a precautionary approach to the construction activities.

22.1.7 Water and soil pollution have the potential to significantly alter environmental conditions on Site which can subsequently impact the viability of habitats in those areas affected. In particular, pollutants that enter soil and water can change the chemical composition of growing substrates and water bodies which can significantly impact species growth, composition and diversity.

22.1.8 When working within 10m of Finham Brook, special considerations and working methods will be adopted. These were outlined in the Technical Note for Salmonid Rivers and are reproduced below:

i. No groundworks will occur during wet of forecasted to be wet conditions within the subsequent 24 hours that are within:

10m of the brook edge;

5m from the top of a slope that leads to the brook where precipitation may cause silt to be washed into the brook;

5m of a ditch, channel or drain that leads to the brook.

ii. Unless or until the following preventative measures have been put into place at an appropriate time:

Anti-pollution barriers are placed to prevent silt from entering the brook or a watercourse/pathway leading to the brook; and

Soft ground is compacted or covered to prevent silt from entering the brook or watercourse/pathway leading to the brook.

22.1.9 The Principal Contractor will ensure that the site is registered with the Environment Agency’s (EA) Floodline Warnings Direct Service, so that any flood warning information issued by the EA is automatically received.

22.1.10 As required by the Environmental Permit, the Principal Contractor will ensure the EA is notified of the intention to carry out works no more than 7 working days before its commencement. The EA will also be notified no more than 7 days after the works have been completed.

22.1.11 Under no circumstances shall waste chemicals, fuels, silt or sediments be discharged or allowed to discharge into the Finham Brook watercourse.

22.1.12 Prior to works taking place around Finham Brook, silt trap devices, booms and blankets will be installed immediately downstream of the works to intercept suspended sediment, concrete and any accidental spillages. In addition, spill kits and mats will be readily available alongside the works which will be used to mop up or contain any material/liquid in the event of a spillage.

22.1.13 A suitable number of spill kits shall be kept on the Site in the vicinity of the Works in progress, which as a minimum shall contain absorbent granules, sand bags and

Page 44: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 39

drain covers. Absorbent pads and booms shall preferably be used instead of granules and sand bags where possible. Used spill kits shall be disposed of appropriately, for example as hazardous waste, where relevant and the appropriate environmental regulator immediately notified by the Principal Contractor.

22.1.14 During the initial phases of the Works, pre-earthworks drainage with inline silt protection is to be established. Where inline silt protection measures are not possible, silt busters or similar are to be employed to de-silt surface water.

22.1.15 An emergency response plan with the EA’s contact details will be in place in the event of a major incident/spillage and/or flooding. All workers will be made aware of the emergency response plan and boards erected detailing the emergency response procedure with contact details of site supervisor, general foreman etc. This site procedure will be located adjacent at the work face, site offices and designated phone areas.

22.1.16 All staff and workforce shall be made aware of the procedures and trained in the use of spill equipment and how to manage and dispose of waste materials legally. As part of the communication processes outlined in this CEMP any Induction and/or Toolbox talk shall cover these specific mitigation measures required to be implemented for the Salmonid species.

Flooding Contingency Plans

22.1.17 In order to mitigate any flood situations, close consultation will be maintained with WCC and the EA using up to date weather forecasts and flood alerts, which will give some warning and allow the Principal Contractor to prepare for a flood event through the MET Office forecasts.

22.1.18 The weather forecast for the week ahead will be regularly checked and if it predicts that a flood event is likely then measures will be taken to remove any hazardous materials from the site and store them in a safe location so that if the site floods no pollutants contaminate Finham Brook, any other drainage or the groundwater.

22.1.19 If there is an enforced shutdown for any other reason, hazardous material will again be removed from site and stored in a safe location.

Discharging Water

22.1.20 Before any work commences in either the Works, or a specific area of the Works in accordance with the construction phasing, the Construction Project Manager will arrange for an inspection of the immediate area in order to ascertain the likely water discharge points. This inspection will consider whether discharge of water is likely to impact flooding, any ecology or impact human health. Any such point identified will be documented along with the reasons for selection.

22.1.21 Once identified, the discharge point will be written into the Method Statement for the specific construction operations to which they apply. The Construction Project Manager will then ensure that the method documented will be applied while the works are undertaken.

23. WATER CONSUMPTION

23.1.1 Effective construction management can deliver major savings in water use and the associated costs of energy, water supply and wastewater treatment. This can be achieved without compromising the performance and user acceptability of the

Page 45: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 40

project.

23.1.2 Typically, the use of water will take place in the following areas:

i. Dust suppression for construction operations and at stockpiles of soil;

ii. Cleaning for vehicles and across the site;

iii. Domestic and Welfare facilities including toilets, drinking water and food preparation areas; and

iv. As part of construction operations, e.g. mortar or cement mixing.

23.1.3 The project will where appropriate utilize the following examples of best practice, or equivalent:

i. Enable monitoring of water use: e.g. install meters which are easy to read; ensure all areas of site water consumption are quantified; consider splitting welfare and “site-based” water consumption; record site water consumption on a regular basis for review at project progress meetings; and regular meter readings should be taken from all meters, sub-meters and metered standpipes (weekly is recommended);

ii. Reduce the risk of uncontrolled water use: e.g. sensor-actuated devices (such as infra-red actuated taps and occupancy sensors);

iii. Minimise the risk of leakage: leak detection equipment (including pulsed meters for regular monitoring); ensure valves and overflows are visible for early detection of water loss and easy to access for maintenance; and

iv. Influence user behaviour: Creating a culture that changes attitude and behaviour to accepting ownership of water efficiency is fundamental to improving the use of water in an efficient manner.

23.1.4 Good housekeeping (e.g. reporting/repairing leaks, turning off taps which are not in use, and generally using water in an efficient manner) can assist the site reduce its overall water use.

23.1.5 The provision of information on appropriate use of fittings and appliances; raising awareness of the costs and environmental importance of water efficiency will be conducted via Tool Box Talks. The talks will also cover guidance on processes for identifying and reporting water leakage / poorly-performing fittings and the method for providing feedback.

Works Affecting Finham Brook

23.1.6 Works within Finham Brook will be subject to a defined method which has been Soil Pollution Control.

23.1.7 The area of the works has been kept as small as possible to ensure there is not significant impact on the adjacent habitats or wildlife. The works only extend a small distance away from the construction activities.

23.1.8 All waste material will be carefully excavated and transported on site. Storage of materials at the work face will be limited and hence materials will be distributed as they arise.

Page 46: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 41

Flooding Contingency Plans

23.1.9 In order to mitigate any flood situations, close consultation will be maintained with WCC and the EA using up to date weather forecasts and flood alerts, which will give some warning and allow the Principal Contractor to prepare for a flood event through the MET Office forecasts.

23.1.10 The weather forecast for the week ahead will be regularly checked and if it predicts that a flood event is likely then measures will be taken to remove any hazardous materials from the site and store them in a safe location so that if the site floods no pollutants contaminate Finham Brook, any other drainage or the groundwater.

23.1.11 If there is an enforced shutdown for any other reason, hazardous material will again be removed from site and stored in a safe location.

24. POLLUTION PREVENTION AND HAZARDOUS MATERIAL STORAGE

24.1.1 Chemicals and hazardous materials such as fuels and lubricants are to be stored on site during the construction of the project. Such materials include (but are not limited to) the following:

i. Fuels

ii. Oils

iii. Lubricants

iv. Paint and Coating

v. Adhesives and resins

vi. Solvents

vii. Compressed gases

viii. Cements and binders

24.1.2 The Site Setup presentend in the CPP shows the storage location of fuelling facilities and storage areas for chemicals and materials.

24.1.3 All materials and liquids that have the potential to pollute any water body shall be stored in COSHH stores. All necessary COSHH paperwork associated with any such material shall be made available on the COSHH register.

24.1.4 The detailed storage and handling procedures for hazardous materials will be contained within the COSHH Data Sheet, as briefed out to Site personnel.

24.1.5 The Pollution Prevention procedures shall be cascaded to the Site Operation Teams via frequent Toollbox Talks. A Toolbox Talk Register shall be maintained and recorded in the Principal Contractor’s electronic system.

24.1.6 All oil or other potential contaminants stored on the site will be controlled in accordance with the Control of Substances Hazardous to Health Regulations (COSHH) (HSE, 2002). These will be isolated, placed on drip trays or bunded such that no oil or other contaminants could reach watercourses or groundwater.

Page 47: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 42

24.1.7 Storage of such materials will be located in a secure area, at least 10m away from any watercourses and 50m from any spring, well or borehole and watercourse with any flood zones.

24.1.8 All static plant such as generators will contain appropriate secondary containment or be placed on drip trays at all times.

24.1.9 Relevant spill kits will be located at strategic locations and personnel trained in their use.

24.1.10 Cement, concrete and grouts are highly alkaline and corrosive and could cause serious pollution to the ground and watercourses. The measures to prevent pollution from these substances is as detailed below:

i. Concrete mixed on site will be carried out on an impermeable designated area located at least 10m from any watercourse or surface water drain to reduce risk of run-off entering a watercourse;

ii. Surplus dry concrete and grout will be used elsewhere on site if suitable, or as inert rubble. Where this is not possible it will be disposed of off-site at a suitable facility and transported using a registered waste carrier;

iii. All equipment used for working with cement will be washed out in a designated washout area that had been specifically designed to contain wet concrete/ wash water. The concrete washout area will be located well away from any watercourses, drain or other elements sensitive to contamination;

iv. Wash waters will be stored to allow solids to settle out and will be recirculated to minimise the risk of pollution and reduce water usage. Contaminated wash water will be collected for authorised disposal off-site;

v. Concrete mixing and delivery lorries will return to the batching plant for washout; and

vi. Silt fences will be set up at the edge of the construction site near watercourses to protect water quality. Mitigation such as straw bales will be on standby to prevent sediment entering the water channels.

25. MONITORING AND AMENDMENTS TO THE CEMP

25.1.1 The Construction Project Manager shall arrange for a coordinate a periodic CEMP Review to assess whether the procedures and processes outlined in the CEMP are being operated effectively, are meeting the environmental requirements of the project and statutory legislation and, where necessary, recommending improvements. Where necessary, the Construction Project Manager shall appoint a delegated person(s) to undertake this review.

25.1.2 The review shall be required by the timescales of the project but shall not be greater than quarterly. The reviewer shall gather, collate, analyse and interpret the following input information:

i. The status of any actions from previous CEMP Reviews;

ii. The status of any actions from any other audits on the CEMP or its activities (whether external or internal);

iii. Appropriateness and effectiveness of the mechanisms for communicating

Page 48: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 43

the contents of the CEMP to all personnel working on site;

iv. Trends in the application of the procedures and requirements of the CEMP when used to construct the Works (by all parties that are required to adhere to it e.g. Sub-Principal Contractors);

v. Assessing whether there has been any change to on-site conditions that may affect the restrictions and/or procedures outlined in the CEMP;

vi. Reviewing any environmental incidents (and any investigation thereof) that may have occurred since the last review; and

vii. Considering where the CEMP feeds into other control documentation (e.g. quality procedures, risk and method statements) and assessing whether these documents are still fit for purpose or are required to be revised.

25.1.3 Once the review is complete, a report shall be produced that will be issued to the Employer and kept on file if further scrutiny is required. The report will be tailored to suit the findings of the assessment, but will likely cover such things as:

i. Recommendations/actions for any issue identified. This may include changes to the actions/procedures listed in the CEMP (or any associated documents such as the E-CEMP), in which case, the CEMP or other required document will then be updated;

ii. Statements relating to the suitability and effectiveness of the CEMP and physical application of the CEMP’s principles on site;

iii. Statements relating to the effectiveness of any corrective actions employed from previous audits, management reviews or response to an environmental incident.

25.1.4 Where the outcome of any review requires the update of the CEMP, the document shall be amended as required and then formally issued to supersede the previous revision in line with the project’s document control procedures.

26. INTERNAL COMMUNICATION & TRAINING

26.1.1 “Internal” communication shall cover communications between individuals and parties working on the Site or are affiliated to the Site as part of the wider project team.

26.1.2 The CEMP will be distributed to the project team, including Sub-Contractors, to ensure that the environmental requirements are communicated effectively. Key activities and environmentally sensitive operations will also be briefed to staff through the Site Induction and regular Toolbox Talks. An environmental register must be signed and updated to confirm toolbox talks, training and weekly meetings by the environmental team. The SHEQ Manager will be responsible for ensuring that the requirements of the CEMP are communicated to the project team.

26.1.3 Environmental awareness and training shall be achieved by:

i. All managers and supervisors being briefed on the CEMP. All site staff and operators are to undergo an environmental induction and toolbox talks and the CEMP will be signed and updated on the Environmental Register.

Page 49: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 44

ii. Site inductions, including relevant environmental issues, such as waste management, working near watercourses, noise & dust management and ecological risks;

iii. Emergency preparedness and response briefings, including communication and reporting of incidents, use of spill kits and other equipment, learning lessons;

iv. Method statement and risk assessment briefings including reference to environmental risk;

v. Toolbox talks to cover specific task related matters of environmental risk; and

vi. Key project specific environmental issues and briefings where required.

26.1.4 A schedule of meetings will be developed to include weekly Safety, Health and

Environment (SHE) meetings, where any issues or incidents will be raised for the attention of the Employer, along with proposed remedial action and additional control if required. An environmental register must be signed and updated to confirm toolbox talks, training and weekly meetings by the environmental team.

26.1.5 During the construction phase, internal communication will include reporting on the following: Inspections, audits and non-conformance, Environmental performance data including any incidents, near misses and progress on reaching targets. Group HSEQ and the account director will be informed of any visits by external bodies and the outcome or feedback from them.

27. EXTERNAL COMMUNICATIONS

27.1.1 “External” communications shall relate to all communications with individuals and/or bodies who are not directly affiliated to the Site or the wider project team. These may include (but not be limited to):

i. Natural England;

ii. Environment Agency;

iii. Highways England and/or their Area 9 Asset Support Contractor, Kier;

iv. Parties working on behalf of HS2;

v. Private Landowners;

vi. Local Authority Environmental Health Officer;

vii. Local Planning Authority; and

viii. Members of the Public.

27.1.2 All complaints or information requests will be made aware to the Construction Project Manager and will be logged within 24 hours of the complaint being made. Any complaints received shall record details of the location of the affected party, time and nature of the disturbance and the impact it is having. This is to assist with managing the works to reduce the likelihood of further complaints.

Page 50: A46 Link Road Phase 1 (Stoneleigh Junction)

Project: A46 Link Stoneleigh Junction Phase 1

Construction Environment Management Plan

(CEMP)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 45

27.1.3 The Construction Project Manager will arrange for an investigation to be undertaken into any complaint, arrange for requested information to be sourced and for any positive feedback to be fed back to the Project Team. Formal responses will will be provided to the person who raised it within 7 days of the enquiry date. The response will be logged along with any action taken to change procedures or processes outlined in this CEMP as a result of the complaint.

27.1.4 The Construction Project Manager will arrange for monthly reviews of the complaints received, how they have been addressed and how working practices have had to change as a result.

27.1.5 Table 11 lists the contact details of key external consultees.

Table 11: List of Key External Consultees

Organisation Location Contact Details Role

Natural England 2nd Floor, Parkside Court, Hall Park Way, Telford, Shropshire TF3 4LR

0300 060 3900 Permits and advice on the natural environment

Environment Agency Sentinel House, 9 Wellington Court, Fradley Park, Lichfield, Staffordshire, WS13 8RR

03708 506 506 Permits and advice on Environmental Regulation

Highways England The Cube, 199 Wharfside Street, Birmingham, B1 1RN

0300 123 5000 Owners of A46 Mainline (including slip roads) – Area 9

Kier McLaren Building, 2nd Floor, 46 Priory Queensway, Birmingham, B4 7LR

0121 435 7860 Highways England Area 9 Maintaining Agents

HS2 Two Snowhill, Snowhill Queensway Birmingham, B4 6GA

0808 143 4434 Nearby scheme of national interest

Warwick District Council

Riverside House, Milverton Hill, Leamington Spa CV32 5HZ

01926 456 725 Local Authority Environmental Health Officer

28. ENVIRONMENTAL ACTIONS AND COMMITMENTS

28.1.1 An Environmental Actions and Commitments Register has been developed for the scheme which is contained in Appendix L.

Page 51: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 46

PART 4 – REACTIVE MEASURES – INCIDENT RESPONSE PROCEDURES

Page 52: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 47

29. INCIDENT RESPONSE – GENERAL

29.1.1 Any and all environmental incidents (including ecological incidents and those that could lead to regulatory enforcement, public complaint or media attention), will be immediately reported to the Construction Project Manager who will immediately report the incident to the Environment Agency Incident Hotline – 0800 80 70 60. Following this, any other relevant individuals and organisations shall also be informed.

29.1 Definitions

29.1.1 An environmental incident (or event) can be defined as an uncontrolled or unplanned event which impacts, or has the potential to impact, on the environment, event types include:

i. Spillage – unplanned loss of substances with potential for environmental damage, impacting on land and / or water dependent on the location, drainage, etc.

ii. Emissions to air – uncontrolled or unplanned emission of particulates, smoke, odours, etc which cause a nuisance and / or environmental hazard.

iii. Breach of legislation – breaches identified by a regulatory authority or internally, for example during monitoring or inspection routines.

iv. Complaints – from the public or any third party, often relating to a nuisance issue such as dust, fumes or noise.

29.1.2 Further guidance on incident classification can be found in the appropriate section below.

29.2 Responsibilities

29.2.1 All employees shall be responsible for minimising the impact their activity has on the environment. In the event of an incident, all employees have a responsibility to react immediately to minimise the effects with due regard for the safety of themselves and others.

29.2.2 Activity managers shall be responsible for ensuring adequate emergency actions are implemented to minimise the impact of an environmental incident and thereafter undertake the necessary investigation and implement effective corrective actions to reduce the likelihood of recurrence.

29.3 Immediate Impact Control Measures – All Incide nts

29.3.1 The first priority with all environmental incidents shall be to minimise the impact on the environment by initiating immediate control and containment actions wherever possible. The type of actions required will be dependent on the incident, but the primary response must be to Stop the Source and Contain the Released Material where relevant.

29.4 Reporting

29.4.1 All environmental incidents must be reported using the Colas AIRSweb HSEQ reporting system. Events which are classified as a Near Miss may be recorded on AIRSweb or the Colas Near Miss Reporting Card system. However when the card system is used, the additional corrective actions may be requested by the SHEQ Manager, additional actions will be raised and managed using the AIRSweb system.

Page 53: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 48

29.4.2 Significant events, including breaches of operating permits must also be reported to the relevant Enforcing Authority e.g. Environment Agency or SEPA for spillages entering surface water drains or a controlled water and Local Authorities for events relating to Permitted Processes such as asphalt plants. An overview of reporting requirements can be found on the Colas Incident Reporting Guide – copies of which are available from the SHEQ Manager.

29.4.3 Copies of correspondence from third parties should also be uploaded to AIRSweb and attached to the incident report, together with photographs, maps, plans, etc.

29.4.4 When reporting an environmental incident or event, the following points should be detailed (as relevant):

i. The type of incident e.g. spillage, emissions to air, etc

ii. Type and quantity of material lost

iii. Name, address and contact details of complaina nt

iv. Notifications made to Enforcing Authority, name , time, etc

v. Immediate actions taken to minimise pollution ri sk

vi. Weather conditions

29.4.5 All environmental incidents and near misses must be reported within 24hrs using either the AIRSweb system or Near Miss Reporting Cards. AIRSweb allows for just the initial event details to be recorded with corrective actions to be added following the investigation.

29.5 Incident Classification

29.5.1 Environmental events are classified in accordance with the following guidance:

i. Incident – this classification should be used wherever an event has an environmental impact, this includes but is not limited to:

− release of material to an external drainage system or controlled water (river, stream, lake, groundwaters, coastal water, etc)

− release of material to ground where material infiltrates substrate. Spillages that are completely contained and cleared with no impact on the ground below shall be recorded as ‘near miss’

− any breach of operating permits e.g. emissions to air, stack test failure on asphalt plant, exceeding blast vibration limits during quarry operations

− noise, dust or nuisance complaints from third parties or regulators where Colas SIAC are found liable

Page 54: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 49

ii. Near Miss – shall be used for minor events where the occurrence has the potential for environmental impact but early identification and/or actions have prevented an actual incident e.g. spillage contained within bund or hardstanding

iii. Reporting Purposes Only – used for events that Colas SIAC does not have direct control or responsibility over or for unjustified complaints from Third Parties, etc.

29.6 Investigation and Corrective Action

29.6.1 Investigation of environmental incidents shall be conducted by the activity manager, the depth of investigation shall be commensurate with the scale of the incident; details of the investigation shall be documented on the Colas AIRSweb HSEQ Reporting system with supporting information uploaded as required.

29.6.2 Investigations should conclude the following:

i. Exact details / facts of event

ii. Root cause of event

29.6.3 Corrective actions need to be commensurate with the severity of the incident and the associated pollution risk; actions may include but not be limited to:

i. Training / retraining of personnel

ii. Revision and amendment of EMS and local environ mental procedures

iii. Revision and amendment of maintenance and / or calibration routines

iv. Amendment / implementation of monitoring routin es

v. Review of relevant Environmental Risk Assessment s and Controls

29.7 Incident Review

29.7.1 Environmental incidents not classified as Near Miss or Reporting Purposes only shall be counted towards the Company’s Environmental Incident Frequency Rate (EIFR). This rate is calculated using the same methodology as Safety LTIFR.

29.7.2 Incident analysis and statistics shall also be produced each month by Safety Services and distributed to Colas SIAC managers; these reports shall also be published on the Colas EMS accessible to all computer users through the Company’s intranet.

29.7.3 Environmental incidents and associated corrective actions shall be reviewed as part of the EMS Management Review Process.

Page 55: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 50

30. INCIDENT RESPONSE - SPILLAGE

30.1.1 The most common type of incident requiring immediate action are spillages; the greatest risk posed to the environment is the release of substances into controlled waters (rivers, streams, lakes, etc). It should be noted that most surface water drainage systems will discharge to a watercourse and therefore spillages must be prevented from entering surface (storm) water drainage systems.

30.1.2 Controlled waters also include groundwaters such as aquifers, spillages can result in pollutants seeping through soil and contaminating groundwaters which are often used as a source of drinking water.

30.1.3 Although spillage incidents are normally associated with liquids, loss of dry materials can be an issue if they are washed away by rainwater.

30.1.4 The basic principles of Spill Management shall be communicated to all operational personnel, particularly where a spill risk has been identified; this may be supplemented by a site or activity-specific spill procedure in which personnel shall be trained.

30.1.5 Fire water run-off can also pose a significant risk to controlled waters and wherever possible should be contained for example through use of pollution control valves or bunding.

30.1.6 The Spillage Procedure shall be as outlined on the flow charts on the following two pages.

Page 56: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 51

Page 57: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 52

Page 58: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 53

31. INCIDENT RESPONSE – EMISSIONS TO AIR

31.1.1 Incidents involving emissions to air may require immediate action for example loss of materials (e.g. fines) during transfers or failure of dust control systems. The first priority will be to stop the activity i.e. cease material transfer or shut-down plant to prevent further release.

31.1.2 Emission incidents will also include release of odours and fumes, particularly relevant to manufacturing plants sited near to residential or commercial premises, in which case the incident may be identified through a complaint from a Third Party e.g. Enforcing Authority, neighbouring business or residential property. This type of incident may require detailed investigation unless the source is immediately obvious e.g. following a plant malfunction.

32. INCIDENT RESPONSE – CONTAMINATED GROUND

32.1.1 All ground investigation carried out on the site to date have highlighted that there are no areas of contamination identified. The exception of this is Himalayan Balsam but there is an active measure for dealing with this outlined in Part 3.

32.1.2 Despite this, a working method which promotes vigilance will be adopted on the project with respect to encountering contaminated material. Such materials may be (but not limited to) the following:

i. Visible suspected asbestos;

ii. Material with strong or obvious odours;

iii. Material with bright or unnatural colouring;

iv. Encountering unexpected liquids or perched groundwater.

Encountering Contaminated Material

32.1.3 Should potentially unacceptable or contaminated land be encountered, the Principal Contractor shall notify the Employer immediately with the aim of establishing a watching brief on the area by a suitable qualified and experienced contaminated land professional who shall be in attendance.

32.1.4 Condition 5 of the Planning Approval requires the County Planning Authority to be notified immediately in writing if contaminated material is encountered during the works. The Employer shall notify the County Planning Authority based on information provided by the Principal Contractor.

32.1.5 Upon identification, the material will be capped and left in situ (where soil porosity is low enough not to present a risk of migration of contaminants) The affected area will be fenced off and signs posted to warn of the presence of the contaminated material. All personnel on site will be made aware of the special arrangements regarding the suspected material.

32.1.6 If the material presents an immediate Health and Safety or Environmental hazard, it shall be carefully excavated and stockpiled separately from other arisings. Any such excavation would be under the supervision of the contaminated land professional.

32.1.7 Storage of any such material shall be within a secure area with contained drainage, provided with an impermeable base to prevent seepage of contaminated water and covered to prevent rainwater mobilising contaminants.

Page 59: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 54

32.1.8 Once the immediate actions regarding the material have been undertaken (i.e. left in situ or else moved if it poses a H&S or Environmental risk), a detailed Method Statement and Risk Assessment for treatment of said material would cover such things as:

i. Keeping records on locations, extents, volumes, movements and any test results undertaken;

ii. Sampling and testing (including type and frequency) of the suspected material by suitably qualified and experienced professionals;

iii. Recording treatment of material (including removal and disposal arrangements if required);

iv. Handling and stockpiling of the material;

v. Management of environmental issues such as pollution of ground water and/or surface water or release of gases;

vi. Preventing cross contamination of the material on other aspects of the Site and/or surroundings;

vii. Health & Safety and Environmental practices when working with or near the material.

32.1.9 Any risk assessment or method statement will need to be submitted to the County Planning Authority in accordance with Condition 5 of the Planning Approval. No remedial work will take place until approval of the submitted documents is provided from the Planning Authority.

32.1.10 To derive the Method Statement, samples of the contaminated material shall be taken and analysed to determine the chemical constituents and an appropriate disposal method chosen. Determining the appropriate method of disposal would be carried out in consultation with the Environment Agency and the Employer. Any chemical testing undertaken on material samples shall be carried out by approved specialist laboratory that has UKAS accreditation and MCERTS accreditation for soils testing.

32.1.11 Unless otherwise agreed in writing by the Local Planning Authority, the approved Method Statement will be either fully implemented prior to the recommencement of construction or concurrently with construction and fully implemented prior to completion of construction and first use of any part of the site.

32.1.12 The investigation, assessment and disposal of any unacceptable or contaminated materials shall be undertaken in accordance with:

i. Control of Substances Hazardous to Health (COSHH) Regulations;

ii. CIRIA C733 Asbestos in soil and made ground: a guide to understanding and managing risks;

iii. CIRIA C765 Asbestos in soil and made ground good practice guide;

iv. If required – Reporting of Injuries, Diseases and Dangerous Occurrences Regulations (RIDDOR);

32.1.13 Treatment shall not include for mixing/lending of contaminated material with other material in order to “reduce” the contamination levels unless specific permission has been applied for and granted by the Environment Agency, Local Health Authority and the Employer.

Page 60: A46 Link Road Phase 1 (Stoneleigh Junction)

FBCM005-CSL-C-HSE-PL-0002 Rev02 Page | 55

32.1.14 Once the Method Statement has been approved and its actions carried out on site, a verification report will be prepared by the Construction Project Manager and provided to the Employer. The Employer will then submit it to the County Planning Authority in order to comply with Condition 5 of the Planning Approval.

33. INCIDENT RESPONSE – WATER BODIES

33.1.1 If the weather forecast predicts that a flood event is likely then measures can be taken to remove any hazardous materials from site and store them in a safe location so that if the site floods no pollutants contaminate the watercourse. If there is an enforced shutdown, hazardous material will again be removed from site and stored in a safe location.

33.1.2 The following is a list of possible accident scenarios:

i. Hydraulic pipes on excavator burst with possible leak of hydraulic oil.

The risk is considered low. All hydraulic systems will be fitted with shut off valves that will restrict the amount of hydraulic oil that will escape during a pipe or coupling burst. Biodegradable hydraulic oil to be used and the site will have spill kits and drip trays that can be put in place in a few minutes. There is potential for oil to escape but these should be minimal and will be very carefully cleaned up using proprietary materials. All contaminated materials will be removed from site and disposed of in an appropriate way.

ii. Breakdown of excavator during excavation.

It is possible that an excavator could breakdown part way through the excavation for the earthworks and channels which if there is a flood could pollute the adjacent watercourses. However no work will be started if there is concern that a flood event is imminent and the machine is likely to be a standard machine that would be easily and quickly replaced.

iii. Fires.

It is considered that fires are a very low risk on this site where no flammable materials will be stored.

iv. Vandalism

v. The Construction Project Manager will ensure that the working area is securely fenced off to prevent unauthorised access. During non-working hours the site will be monitored with CCTV cameras and or security staff visiting.

Page 61: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX A – PLANNING CONDITIONS SUMMARY

Page 62: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX B – E-CEMP This plan will be discharged with Planning Conditio n 9. The approved plan will be availiable in the Colas SIAC Health, Safety, Wellbeing and Env ironmental file and cross referred to this document. The approved E-CEMP will be used as a reference for developing methodologies for any associated works activities.

Page 63: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX C – ENVIRONMENTAL RISKS IN AND AROUND FINHAM BROOK

Page 64: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 65: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX D – RIVER NETWORK LOCATION PLAN

Page 66: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX E - SITE WASTE MANAGEMEN T PLAN The following table is the Summary & Review that is presented at the last tab of the Colas SIAC SWMP. All the details of the calculations will be shown in the SWMP excel spread sheet and it will be always available for review up on request.

Page 67: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX F – QUANTITIES OF RECYCLED AND SECONDA RY MATERIALS USED IN THE WORKS

Page 68: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX G – WASTE MANA GEMENT

Page 69: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 70: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 71: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 72: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 73: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 74: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 75: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 76: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 77: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 78: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 79: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 80: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 81: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 82: A46 Link Road Phase 1 (Stoneleigh Junction)
Page 83: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX H – RISK ASSESSMENTS AND METHOD STATEMENTS All the Risk Assessments and Method Statement that will be created for the performance of all Site activities will be avalaible in the Colas SIAC RAMS file and cross referred to this document.

Page 84: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX I – SITE ARCHAELOGICAL INVESTIGATIONS

Page 85: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX J – LEMP This plan will be discharged with Planning Conditio n 7.

Page 86: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX K – TREE PROTECTION PLA N This plan will be discharged with Planning Conditio n 12. The approved plan will be availiable in the Colas SIAC Health, Safety, Wellbe ing and Environmental file. The approved TPP will be used as a reference for developing meth odologies for any associated works activities.

Page 87: A46 Link Road Phase 1 (Stoneleigh Junction)

APPENDIX L – ENVIRONMENTAL ACTION AND COMMITMENT REGISTER (REAC)

Page 88: A46 Link Road Phase 1 (Stoneleigh Junction)

A46 Stoneleigh Junction

Environmental Action and Commitment Register

Page | 1

A46 STONELEIGH JUNCTION – ENVIRONMENTAL ACTION AND COMMITMENT REGISTER (REAC)

Revision No: A

Date of Revision: 14/05/2020

No. Action/Commitment Description

Action/Commitment Assumptions (if

applicable)

Action Objective How will Action be Implemented/ Achieved?

Action Source Responsible Person

Achievement Criteria

Estimated Date of Implementation

Action Monitoring

Requirements

1 Air Quality (Dust)

Ensuring dust levels

are not excessive

during construction so

as to present a risk to

human and

vegetation/ecology.

None Required by the

Environmental Protection

Act and Clear Air Act as

outlined in Table 1 of the

CEMP.

Also required by

Condition 6 of the

Planning Permission

which requires

assessment against IAQM

guidance.

As outlined in Section 13 of the

CEMP and Section 3.8.2 of the

CPP.

• Cutting, grinding

operations.

• Vehicle emissions.

• Earthworks movement

operations

Contractor Successful

controlling of dust

and air quality

At the

commencement of

construction works

and throughout

construction

operations.

As outlined in

Section 13 of the

CEMP

2 Cultural Heritage

(Archaeology)

Ensuring remaining

areas not previously

subjected to

archaeological

investigation are

verified as being

acceptable

A written Scheme of

Investigation (WSI)

prepared for works in

the Flood Alleviation

Area and main site

compound and a

watching brief during

on site operations.

Maintain archeological

control of excvations in

the flood alleviation area

and site compound.

Required by the National

Planning Policy

Framework and Historic

Buildings Act as outlined

in Table 1 of the CEMP

As outlined in Section 14 of the

CEMP

• Commitment from

planning application

archeological

investigation

Contractor

Project

Archaeologist

Successful topsoil

strip/excavation in

flood alleviation area

and main compound

area.

During the early part

of the on site

construction

operations until such

time as the main

works compound is

established and the

flood alleviation area

constructed.

On site watching

brief required as

outlined in

Section 14 of the

CEMP

3 Contaminated Ground

Making sure an

incident response plan

is in place in the

unlikely event that

contaminated ground

is encountered and

present a hazard to

humans and

ecology/vegetation.

No contaminated

ground was

encountered during

site investigation.

However, contingency

plan required for

incident response in

the unlikely event that

it is encountered

during construction

operations.

Monitoring of all earth

movement operations

and/or excavations and

report any suspected

contaminated ground.

Incident response

procedure then to be

followed.

As outlined in Section 32 of the

CEMP

• Requirement from

Planning Condition 5

• Industry Best Practice

Contractor

All Site

Personnel

Efficient dealing with

any contaminated

ground should it be

encountered.

At the

commencement of

the construction

works and throughout

construction

operations.

On site vigilance

in spotting

contaminated

ground.

4 Ecology – General

ecological measures.

Ongoing monitoring of

ecological features and

receptors during

operations to ensure

there is no impact

Baseline ecological

surveys and impact

assessment (as

outlined in Section 3 of

the E-CEMP)

Ongoing monitoring

during construction

operations to ensure

compliance with various

ecological Acts and

Regulations such as the

Wildlife & Countryside

Act and the Environment

Act (the full list is in Table

Regular monitoring of ecological

features and general area

during construction as outlined

in Section 4 of the E-CEMP)

• Requirement from

Planning Condition 9

• Legal Requirement

• Baseline Ecological

Surveys and Impact

Assessment

Project

Ecologist

Contractor

No impact on

ecological species

(such as Great

Crested Newts,

amphibions or

reptiles) recorded

throughout the

construction period.

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Regular

monitoring

required as

outlined in

Section 5.5 of the

E-CEMP.

Page 89: A46 Link Road Phase 1 (Stoneleigh Junction)

A46 Stoneleigh Junction

Environmental Action and Commitment Register

Page | 2

No. Action/Commitment Description

Action/Commitment Assumptions (if

applicable)

Action Objective How will Action be Implemented/ Achieved?

Action Source Responsible Person

Achievement Criteria

Estimated Date of Implementation

Action Monitoring

Requirements

1 of the CEMP)

5 Ecology – Badger

Activity and Working

around Badger Setts to

ensure there is no

impact due to the

construction.

All known badger setts

have been closed. This

assumes new setts are

discovered on the lead

up to or during the

main works

construction

operations.

Ensure any newly

discovered badger activity

is recorded and dealt with

in accordance with the

various ecological Acts

and Regulations listed in

Table 1 of the CEMP.

Regular surveys of the site and

general mitigation principles

outlined in Section 5.5 (for

badgers) adopted.

Any new activity will be

addressed using the incident

response process outlined in

Appendix G of the E-CEMP.

• Requirement from

Planning Condition 9

• Legal Requirement

• Baseline Ecological

Surveys and Impact

Assessment

Project

Ecologist

Contractor

No impact on Badger

activity recorded

throughout the

construction period.

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Regular

monitoring

required as

outlined in

Section 5.5 (for

Badgers) of the E-

CEMP.

6 Ecology – Otter

Activity and Working

around Otter Holts to

ensure there is no

impact due to the

construction.

Known Otter Holt to be

retained and a suitable

exclusion zone to be

erected around it. This

also assumes new

otter holts are

discovered on the lead

up to or during the

main works

construction

operations.

Ensure any newly

discovered otter activity is

recorded and dealt with

in accordance with the

various ecological Acts

and Regulations listed in

Table 1 of the CEMP.

Screening off of the otter

exclusion zone which is

maintained during the main

construction works.

Regular surveys of the site and

general mitigation principles

outlined in Section 5.5 (for

otters) adopted.

Any new activity will be

addressed using the incident

response process outlined in

Appendix G of the E-CEMP.

• Requirement from

Planning Condition 9

• Legal Requirement

• Baseline Ecological

Surveys and Impact

Assessment

Project

Ecologist

Contractor

No impact on Otter

activity recorded

throughout the

construction period.

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Regular

monitoring

required as

outlined in

Section 5.5 (for

Otters) of the E-

CEMP.

7 Ecology – working in

Finham Brook and

impact on salmonid

species.

Finham Brook

identified as a

salmonid river as part

of the baseline

ecological surveys.

Ensure any works in

Finham Brook do not

impact on any salmonid

species present in the

watercourse in

accordance with the

Salmonid and

Freshwaters Fisherys Act

Methodology as outlined in

Section 5.6 of the E-CEMP along

with information in the EA

permit for working in Finham

Brook to be applied.

• Requirement from

Planning Condition 9

• Legal Requirement

• Requirement of EA

Permit for working in

Finham Brook

• Baseline Ecological

Surveys and Impact

Assessment

Project

Ecologist

Contractor

No impact on

salmonid activity in

Finham Brook

through a pollution

or water

contamination

incident

At the

commencement of

construction works

and throughout

construction

operations.

Regular

monitoring

required as

outlined in

Section 5.6 of the

E-CEMP.

8 Ecology – Bird Activity

and Nesting.

Vegetation clearance

and ensuring there is

no impact due to

construction.

None Avoid impact on bird

activity or nesting

through construction

activities such as

vegetation clearance

Wherever possible, all

vegetation clearance works will

take place outside of bird

nesting season.

Methodology as outlined in

Section 5.5 (Breeding Birds) in

the E-CEMP.

• Requirement from

Planning Condition 9

• Legal Requirement

• Baseline Ecological

Surveys and Impact

Assessment

Project

Ecologist

Contractor

No impact on bird or

bird nesting activity

recorded throughout

the construction

period.

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Regular

monitoring

required as

outlined in

Section 5.5. of the

E-CEMP.

9 Ecology – Bat Roosting Bat Roosting potential

identified on the

existing bridge over

the A46.

Ensure any works to

structures or other

ecological feature does

not impact on any bat

roosts.

Methodology as outlined in

Section 5.5 (Bats) in the E-

CEMP.

• Requirement from

Planning Condition 9

• Legal Requirement

• Baseline Ecological

Surveys and Impact

Assessment

Project

Ecologist

Contractor

No impact on bat

roosting recording

throughout the

construction period.

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Further surveys

planned before

works to

structures or

features with bat

roost potential

commences. As

outlined in

Page 90: A46 Link Road Phase 1 (Stoneleigh Junction)

A46 Stoneleigh Junction

Environmental Action and Commitment Register

Page | 3

No. Action/Commitment Description

Action/Commitment Assumptions (if

applicable)

Action Objective How will Action be Implemented/ Achieved?

Action Source Responsible Person

Achievement Criteria

Estimated Date of Implementation

Action Monitoring

Requirements

Section 5.5 (Bats)

of the E-CEMP.

10 Ecology – Monitoring

of Artificial Badger

Setts and Otter Holt

Ongoing requirement

to monitor artificial

habitats created in

advance of the

construction works

To help mitigate Badger

and Otter impact of the

works by providing a

dedicated facility away

from the construction

works. Monitoring

required to ensure the

artificial habitats are

being used.

Regular monitoring of the

habitats throughout the

construction period in line with

Section 4.3 of the E-CEMP

• This requirement

arose out of the

findings of the

Ecological Impact

Assessment

Project

Ecologist

No impact recorded

on Badger and Otter

activity in the

artificial habitats

throughout the

construction

operations

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Regular

monitoring

required as

outlined in

Section 4.3 of the

E-CEMP.

11 Flood Risk – risk of

flooding from Finham

Brook to nearby

properties and/or

ecological features.

Risk of flooding occurs

in both the permanent

(as constructed)

arrangement and

temporarily (during

construction).

Ensure that flooding does

not occur and/or is not

exacerbated by the

proposed works in the

long term and floods

properties or ecological

features.

Permanent Flood Alleviation

Area will be created as part of

the works to cater for

permanent flooding.

Methodology as outlined in

Section 22 of the CEMP.

• Legal Requirement

• Flood zones as

identified by the EA

Employer

Contractor

No recorded

flooding incidents

during the

construction period

(temporary

situation) or after

the project is built

(permanent

situation)

During the

construction works

and for the design life

of the flood alleviation

area afterwards

On site vigilance

in spotting flood

events.

Close eye on

weather

forecasts.

12 Himalayan Balsam

Contamination –

preventing the spread

of an invasive plant

species

None To limit the spread of

Himalayan Balsam plant

which according to

Schedule 9 of the Wildlife

and Countryside Act is

considered an invasive

species

Permanent strategy for dealing

with this plant is outlined in

Section 17.2 of the CEMP.

• Existing site condition

• Schedule 9 of Wildlife

and Countryside Act

Contractor No spread of the

plant through

construction

operations

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

No specific

monitoring

required before

works. After

works,

assessment that

plant has not

spread required.

13 Landscaping – Tree

Protection – protecting

existing trees to be

retained on site.

Existing trees to be

retained have been

identified.

To retain good quality

trees within the site

which helps mitigate the

biodiversity impact

caused by the scheme.

Methodology as outlined in

Section 19.1 and Appendix K of

CEMP.

• Baseline Arboricultural

Survey

• Scheme biodiversity

offsetting

Contractor All identified trees to

be retained are

successfully

retained.

January 2020 and

leading up to the

commencement of

and during the main

works construction

operations.

Once tree

protection

measures are put

in place, regular

inspections as

outlined in

Section 19.1 of

the CEMP

14 Noise and Vibration –

Limiting noise and

vibrations to minimize

impact on human and

ecology

Baseline noise

monitoring an

ecological receptor

sites not required.

Minimise noise and

vibration nuisance on

neighbouring properties

and nearby ecological

features

Methodology as outlined in

Section 20 of the CEMP.

• Planning Conditions 3

and 4

• Environmental

Protecton Act

Contractor Noise and vibration

levels will not be

recorded as being

sufficient to cause

disturbance

At the

commencement of

construction works

and throughout

construction

operations.

Monitoring as

outlined in

Section 20 of the

CEMP.

15 Site Waste

Management – ensure

waste from

construction

operations do not

present an

None To limit the amount of

waste produced the site,

but where waste is

produced, document a

full audit trail to its

eventual location

Methodology as outlined in

Section 21 of the CEMP. The

Waste Management Plan is

located in Appendix E of the

CEMP.

• All site operations may

produce waste as a

byproduct.

• Legal Requirements as

outlined in Table 1 of

Contractor All waste produced

by the site

accounted for in site

records at the end of

the construction

operations.

At the

commencement of

construction works

and throughout

construction

operations.

As outlined in the

Management

Plan in Appendix

E.

Page 91: A46 Link Road Phase 1 (Stoneleigh Junction)

A46 Stoneleigh Junction

Environmental Action and Commitment Register

Page | 4

No. Action/Commitment Description

Action/Commitment Assumptions (if

applicable)

Action Objective How will Action be Implemented/ Achieved?

Action Source Responsible Person

Achievement Criteria

Estimated Date of Implementation

Action Monitoring

Requirements

environmental hazard the CEMP

16 Water Quality – ensure

construction

operations do not

impact on water

quality (both in

watercourses and

groundwater) and

create a risk on the

health of humans or

ecology/biodiversity

Work takes place

around Finham Brook

watercourse but also

includes extensive

excavation and earth

movement operations

which will affect

ground water.

Limit any operation to

ensure water quality does

not exceed the pollution

control thresholds

outlined in Section 17.3 of

the CEMP.

Entire site designinated a

controlled water sensitive area.

Testing will be undertaken to

measure compliance with the

Tables in Section 17.3 of the

CEMP.

• Earthworks operations

and work in and

around Finham Brook

• Legal Requirements as

outlined in Table 1 of

the CEMP

Contractor Testing regime

shows that the

Limiting Values for

water quality have

been met

throughout the

scheme.

At the

commencement of

construction works

and throughout

construction

operations.

As outlined in

Sections 17.3 and

22 of the CEMP