7.summary of boiler perf
TRANSCRIPT
-
8/8/2019 7.Summary of Boiler Perf
1/46
Conditions causing Poor
Performance of Boiler
Non-Optimum Reheat or Superheat
steam temperatures.
Higher than design economizer exit gas
temperature or furnace exit gas
temperature caused by poor combustion.
Higher than design Re heater or Super
heater De-Superheating spray flows.
-
8/8/2019 7.Summary of Boiler Perf
2/46
Conditions causing Poor
Performance of Boiler
Fly ash Unburned Carbon or Loss on
Ignition greater than 5% for Eastern
Bituminous Coals or greater than 1% for
Western or Lignite Coals.
High Bottom Ash Loss on Ignition.
Non-Optimum utilization or distribution
of primary air, secondary air and over
fire air, if applicable.
-
8/8/2019 7.Summary of Boiler Perf
3/46
Conditions causing Poor
Performance of Boiler
Increased auxiliary horsepower
consumption by coal pulverizers and fans
Reductions in capacity factors due to
excessive furnace or convection passslagging or fouling.
Excessive boiler setting air in-leakage.
Excessive air heater leakage.
Increased cycle losses with increased
sootblowing due to non-optimum
combustion.
-
8/8/2019 7.Summary of Boiler Perf
4/46
Conditions causing Poor
Performance of Boiler
Excessive pulverizer spillage on vertical
spindle, roll and race and ball bearing
type pulverizers. Reductions in capacity
factors due to pulverizer or fan capacitylimitations.
Reductions in capacity factors due to
Superheater or Reheater tubeoverheating and/or coal-ash corrosion.
-
8/8/2019 7.Summary of Boiler Perf
5/46
Requirements For Achieving
Optimum Conditions
Furnace exit must be oxidizing,
preferably 3% excess O2.
Minimal air in-leakage between thefurnace exit and economizer exit.
Pulverizer fineness of >75% passing
200 Mesh and
-
8/8/2019 7.Summary of Boiler Perf
6/46
Requirements For Achieving
Optimum Conditions
Optimum windbox to furnace
differential, typically 100mm w.c. at
full load. Optimum Pulverizer Primary Air to
Fuel Ratio. In most cases, air to fuel
ratio of 1.8 to 1 on roll and race and
ball bearing type pulverizers, and 1.4
to 1 on attrition and ball tube
pulverizers.
-
8/8/2019 7.Summary of Boiler Perf
7/46
Requirements For Achieving
Optimum Conditions
Fuel balanced between each
pulverizers fuel lines to within 10%
deviation from the mean. Pulverized coal line dirty airflow
balanced between each pulverizers
fuel lines within 5%.
Pulverized coal line clean air
velocities balanced to 2% of the
mean.
-
8/8/2019 7.Summary of Boiler Perf
8/46
Requirements For Achieving
Optimum Conditions
Coal line minimum velocities of 17
Mps.
Burner mechanical tolerances with6mm (circular burners), burner
buckets stroked and synchronized to
within 2 (tangentially fired).
Primary airflow metered and
controlled to 3% accuracy.
-
8/8/2019 7.Summary of Boiler Perf
9/46
Requirements For Combustion
Optimisation Programme
Boiler testing to identify opportunities for
improved unit heat rate.
Comprehensive inspections of the boiler,
burners, pulverizers and auxiliaries to
identify and address opportunities related to
mechanical tolerances.
Technical direction of outage repairs toensure mechanical tolerances are optimized
as well as training of maintenance personnel
in achieving optimum mechanical tolerances.
-
8/8/2019 7.Summary of Boiler Perf
10/46
Requirements For Combustion
Optimisation Programme
Design new or calibration of existing air
flow measurement elements to facilitate
optimum management and control of
primary air, secondary air and overfire air
(when applicable).
Curtain or boundary air incorporated into
some low NOx burner systems must also
be precisely measured and controlled.
-
8/8/2019 7.Summary of Boiler Perf
11/46
Requirements For Combustion
Optimisation Programme
Modifying existing equipment
(pulverizers, boiler heating surfaces, fans,
burner components) to meet challenges of
switching fuels or changing status of unit
between cyclic and non-cyclic.
Boiler tuning and testing to achieve all
"pre-requisites" for optimum
combustion.
-
8/8/2019 7.Summary of Boiler Perf
12/46
Requirements For Combustion
Optimisation Programme "Awareness" training of boiler
operators, maintenance personnel and
engineering personnel to sustain long
term improvements achieved through
combustion optimization during day to
day operation. Usually termed a"Performance Preservation Program".
-
8/8/2019 7.Summary of Boiler Perf
13/46
-
8/8/2019 7.Summary of Boiler Perf
14/46
-
8/8/2019 7.Summary of Boiler Perf
15/46
COMBUSTION OPTIMIZATIONGUIDELINES -
SUMMARY
Secondary Air Balancing
Burner Tilt Timing
Fuel Balancing
Reduce Air-In-Leakage
Control Primary Air Flow
-
8/8/2019 7.Summary of Boiler Perf
16/46
Unit Generating Capacity Limitations
From Inadequate Fan Performance
Higher ambient temperatures result in less
stack draft.
ID fan capacity limitation may result in load
reduction or inability to maintain desiredexcess air levels.
Low excess air due to fan capacity limitation
can result in
Increased slagging and fouling propensity
High Flyash Loss On Ignition
Superheater and Reheater tube overheating
High boiler exit gas temperature
-
8/8/2019 7.Summary of Boiler Perf
17/46
Common conditions contributing to
inadequate fan capacity
Excessive inlet cone gap & overlap clearance
Excessive boiler setting air in-filtration
Pre-spinning condition at the fan inlet
Non-Optimum damper or pre-spin vane stroke
and/or synchronization
Excessive air heater leakage
High air heater pressure differential due tonon-optimum air heater soot
-
8/8/2019 7.Summary of Boiler Perf
18/46
-
8/8/2019 7.Summary of Boiler Perf
19/46
Ensure the mating surfaces between sections of
the inlet box-scroll interface are tightly sealed
and the interface plate is free of holes.
A 35-50mm
differential in static
pressure between the
fan outlet and inlet is
typical.
Holes or gaps in the
interface plate will
allow circulation
between the outlet or
scroll side and the inlet
reducing fan capacity
-
8/8/2019 7.Summary of Boiler Perf
20/46
Non-optimum damper stroking
Dampers should bestroked with internal
position verification
of full damper
opening.
An external key
stock indicator or
scribe mark should
be present to verify
internal damper
position from the
outside.
-
8/8/2019 7.Summary of Boiler Perf
21/46
Test Procedure For Collecting An
ASME Fineness Sample
Sample locations are
positioned correctly with
regard to bends and
restrictions. Ideally, test
taps should be located in avertical run of piping, 10
diameters upstream and
downstream from the
nearest disturbance. Aminimum of two taps, 90
apart, is required. Taps
should not be located at
the discharge of an
exhauster.
-
8/8/2019 7.Summary of Boiler Perf
22/46
Test Procedure For Collecting An
ASME Fineness Sample
Traverse points collected fromequal area test grid
Traverse points are sampled
for equal time intervals. This is
necessary for calculation of
total recovered sample (A
fineness test is said to be
representative when the sum of
the samples totals between 90 -
110% of the indicated feederflows). Collection of a timed
sample allows for determination
of relative pipe-to-pipe fuel
balance.
-
8/8/2019 7.Summary of Boiler Perf
23/46
Test Procedure For Collecting An
ASME Fineness Sample
Traverse points are sampled for equal time
intervals. This is necessary for calculation of total
recovered sample (A fineness test is said to be
representative when the sum of the samples totalsbetween 90 - 110% of the indicated feeder flows).
Collection of a timed sample allows for
determination of relative pipe-to-pipe fuelbalance. Recovered fuel flow per pipe is
calculated using the following equation:)
-
8/8/2019 7.Summary of Boiler Perf
24/46
Test Procedure For Collecting An
ASME Fineness Sample
Fuel Flow lbs/Hr per burner line
=
gms sampled per pipe 1lb 60min p---------------------------- ---- -------- ---------------
Sample time in min. 453.6 1Hr.
0.0021 sft
-
8/8/2019 7.Summary of Boiler Perf
25/46
-
8/8/2019 7.Summary of Boiler Perf
26/46
Procedure to collect coal samples
using the ASME Coal Sampler :
Insert the sample probe into the dustless
connector, open the ball valve, and slide the
probe in to the first port (probe completely
inserted) with the flag of probe (sample tip) inthe direction of flow. Turn the tip of the probe
into the flow, turn on and adjust the aspirating
air to achieve/maintain 10 psi, and start the
stopwatch. Sample each traverse point for 10seconds (total burner line sample time of 4
minutes, assuming a 24 point traverse grid).
Upon completion of the last traverse point, cut
off the air, and remove the probe. Repeat the
-
8/8/2019 7.Summary of Boiler Perf
27/46
Procedure to collect coal samples
using the ASME Coal Sampler : :
After completing traverses of each test port on a
designated burner line, empty the sampling jug
and the filter canister into a labeled Ziploc bag.
Repeat the process for each burner line on the
pulverizer.
Once all burner lines on the pulverizer have been
tested, weigh the samples and calculate an
individual burner line fuel flow and sum the
results to determine (%) recovery. If thecumulative recovery is not between 90% - 110%
of the feeder indication, then repeat traverse
again increasing and/or decreasing the extraction
diff. Pr. until desired recovery is achieved.
-
8/8/2019 7.Summary of Boiler Perf
28/46
-
8/8/2019 7.Summary of Boiler Perf
29/46
Coal Sieving Procedure
Remove 50 grams of coal from the sample. This
is done by using an ASTM riffler or by
rolling the sample (usually between 200 g
and 800 g).
Shake the sample through a series of 50, 100,140 and 200 Mesh U.S. Standard sieves
Record the weight of coal residue on each
screen and coal in the bottom pan (passing 200
Mesh). Great care should be taken in weighingcoal sample residue on each screen. Residue on
50 Mesh will be very small and must be
weighed accurately to yield representative data.
-
8/8/2019 7.Summary of Boiler Perf
30/46
-
8/8/2019 7.Summary of Boiler Perf
31/46
-
8/8/2019 7.Summary of Boiler Perf
32/46
Coal Sieves and Calculations
Wt of test sample
Wt.of residue on 50 mesh 1g
Wt.of residue on 100 mesh R2g
Wt.of residue on 140 mesh R3g
Wt.of residue on 200 mesh R4g
Wt.of residue in pan 5g
-
8/8/2019 7.Summary of Boiler Perf
33/46
Coal Sieves and Calculations
% Passing 50 mesh ( 50-R1) *100/50
% Passing 100 mesh {50-(R1+R2)} *100/50
% Passing 140 mesh {50-(R1+R2+R3)} *100/50
% Passing 200 mesh {50-(R1+R2+R3+R4)} *100/50
-
8/8/2019 7.Summary of Boiler Perf
34/46
VOLUMETRIC FLYASH SAMPLE
COLLECTION AND ANALYSIS
According to the ASME Test Code PTC 38
Determining the Concentration of Particulate
Matter in a Gas Stream; ideally test tap layout
should be such that sampling access ports and
traverse points are selected to permit sampling inzones of equal areas. The traverse grid should
facilitate a minimum of one traverse point for
every 9 ft of duct area. For example a 12 18
duct with a cross-sectional area of 216 ft will
require a minimum of (24) traverse points.
-
8/8/2019 7.Summary of Boiler Perf
35/46
VOLUMETRIC FLYASH SAMPLE
COLLECTION AND ANALYSIS
The traverse grid should be located in a straightrun of ductwork (constant cross-sectional area),
preferably a vertical run in order to minimize
stratification of the medium. In addition, the
traverse grid should be located a minimum ofeight (8) duct diameters downstream and two (2)
duct diameters upstream from the nearest flow
disturbance. Since these criteria are often
impossible to meet, test taps are generally
located in the best possible location. This isacceptable if all parties involved in the testing
agree. Adequacy of probe access, lighting, power
facilities, etc. should also be considered when
choosing a location
-
8/8/2019 7.Summary of Boiler Perf
36/46
Volumetric Fly ash Sample Collection
and Analysis
Example of Equal Area Sampling Grid
-
8/8/2019 7.Summary of Boiler Perf
37/46
-
8/8/2019 7.Summary of Boiler Perf
38/46
Typical locations for collection of a fly ash sample
-
8/8/2019 7.Summary of Boiler Perf
39/46
Procedure for Sieving a Flyash
Sample
-
8/8/2019 7.Summary of Boiler Perf
40/46
Procedure for Burning a Fly ash
Sample for L.O.I. Determination
Equipment
A small oven capable of maintaining
temperatures between 150 - 815 C
A set of ceramic crucibles for burning the ash
A set of pincers or tongs for handling the
crucibles
A highly accurate scale(balance) for measuring
the ash samples; the scale should have areadability of 0.1 mg with a repeatability of + 0.1
mg.
-
8/8/2019 7.Summary of Boiler Perf
41/46
Procedure for Burning a Flyash
Sample for L.O.I. Determination
Label each of the crucibles.
Preheat the crucibles to 150 C for
approximately 15 minutes.
Weigh each crucible while hot(Wc).
Add one gram of the ash to be burned to
the crucible as it remains on the scale and
record the sample and crucible weight.
-
8/8/2019 7.Summary of Boiler Perf
42/46
Procedure for Burning a Flyash
Sample for L.O.I. Determination
Insert the crucible with the sample into
the oven and leave it for 1 hour at
between 150 - 260 C.
Remove the crucible with sample and
reweigh and record it, comparing the
weight to the initial weight. Any difference in the two is the amount
of water driven off.
-
8/8/2019 7.Summary of Boiler Perf
43/46
Procedure for Burning a Flyash
Sample for L.O.I. Determination
Replace the crucible w/sample in the
oven at 150 - 260 C and leave it for 30
minutes.
Remove, weigh, and record the crucible
w/sample.
Continue this process until the weightremains constant.
RECORD THIS WEIGHT(WCSD).
-
8/8/2019 7.Summary of Boiler Perf
44/46
Procedure for Burning a Flyash
Sample for L.O.I. Determination
Replace the crucible w/sample in the
oven and cook the sample at 815 C for
three (3) hours.
Remove, weigh, and record the crucible
w/sample weight.
Replace the crucible w/sample and cookat 815 C for 30 minutes.
-
8/8/2019 7.Summary of Boiler Perf
45/46
Procedure for Burning a Flyash
Sample for L.O.I. Determination
Remove, weigh, and record the crucible
w/sample weight.
Any difference indicates that there is still
carbon present in the ash.
Continue this procedure until the weight
remains constant(WCSFW).
-
8/8/2019 7.Summary of Boiler Perf
46/46
Procedure for Burning a Flyash
Sample for L.O.I. Determination
Once the weight no longer changes, the flyash
L.O.I. can be calculated using the following
equation:
WCSD = Crucible w/sample (dried) weight
WCSFW = Crucible w/sample (final weight)
WC = Crucible weight
% Flyash L.O.I.
= {[(WCSD - WC) - (WCSFW - WC) 100]}
WCSD