650 api field erected tanks prequalification criteria

23
BLUE GRASS CHEMICAL AGENT DESTRUCTION PILOT PLANT (BGCAPP) PRE-QUALIFICATION CRITERIA & RESPONSE FIELD-ERECTED STORAGE TANKS (EPC) SUBCONTRACT DUE DATE: 28 SEPTEMBER 2009 1.0 Introduction Bechtel National, Inc., (BNI) intends to issue a Request for Proposal (RFP) for an Engineer, Procure & Construction (EPC) subcontract for a fifteen (15) API 650 field-erected storage tanks, ranging in size from 16,500 gallons to 300,000 gallons and associated equipment at the Blue Grass Army Depot for the Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) Project in Richmond, KY. Companies must be pre-qualified by BNI to be included on the bid list. To support the prequalification evaluation process, the prime potential Offeror (1 st tier Subcontractor) must provide the requested information, respond to questions within this document. The Experience Statement should include relevant information for both the Prime Offeror and any subtier contractors. Additional supporting documentation such as brochures and company profiles may be submitted. In-depth supporting documentation will be required as part of your proposal. If it does not support your pre-qualification responses, your proposal may be deemed unacceptable and excluded from consideration. 2.0 Scope of Work Provide design, fabrication, supervision, labor, installation and testing of outdoor storage tanks and associated equipment. All tanks are to be field-erected at the BGCAPP Project, located in Richmond, Kentucky. Work included and excluded from the scope of this Subcontract can be found in sections 2.1 and 2.2. 2.1 Work Included in Scope The tank fabricator shall be responsible for the following: 1. Design, fabricate, deliver material, field erect, inspect and test in accordance with the purchase documents and engineering specifications and data sheets and applicable referenced codes and standards. 2. Provide materials, labor, transportation, staging and tools to complete the erection of the tank. 3. Submit plot layout of hoisting equipment, when used. 4. Provide anchor bolt requirements. 5. Design, fabricate and install `stairways, ladders, cages, platforms, handrails and pipe guides and pipe supports when indicated in the tank data sheets. 6. Perform external painting and internal lining when indicated in the tank data sheets. 18 Sept. 2009 Page 1 of 23 Field-Erected Storage Tanks Subcontract

Upload: berkay-guener

Post on 16-Dec-2015

103 views

Category:

Documents


5 download

DESCRIPTION

Tank Manufacturers Pre-qualification Questionnaires

TRANSCRIPT

BJC Prequalification

BLUE GRASS CHEMICAL AGENT DESTRUCTION PILOT PLANT (BGCAPP)

PRE-QUALIFICATION CRITERIA & RESPONSE

FIELD-ERECTED STORAGE TANKS (EPC) SUBCONTRACTDUE DATE: 28 SEPTEMBER 2009BLUE GRASS CHEMICAL AGENT DESTRUCTION PILOT PLANT (BGCAPP)

PRE-QUALIFICATION CRITERIA & RESPONSE

FIELD-ERECTED STORAGE TANKS (EPC) SUBCONTRACTDUE DATE: 28 SEPTEMBER 2009

1.0 Introduction

Bechtel National, Inc., (BNI) intends to issue a Request for Proposal (RFP) for an Engineer, Procure & Construction (EPC) subcontract for a fifteen (15) API 650 field-erected storage tanks, ranging in size from 16,500 gallons to 300,000 gallons and associated equipment at the Blue Grass Army Depot for the Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) Project in Richmond, KY. Companies must be pre-qualified by BNI to be included on the bid list. To support the prequalification evaluation process, the prime potential Offeror (1st tier Subcontractor) must provide the requested information, respond to questions within this document. The Experience Statement should include relevant information for both the Prime Offeror and any subtier contractors. Additional supporting documentation such as brochures and company profiles may be submitted. In-depth supporting documentation will be required as part of your proposal. If it does not support your pre-qualification responses, your proposal may be deemed unacceptable and excluded from consideration.

2.0 Scope of WorkProvide design, fabrication, supervision, labor, installation and testing of outdoor storage tanks and associated equipment. All tanks are to be field-erected at the BGCAPP Project, located in Richmond, Kentucky. Work included and excluded from the scope of this Subcontract can be found in sections 2.1 and 2.2.2.1Work Included in Scope

The tank fabricator shall be responsible for the following:1. Design, fabricate, deliver material, field erect, inspect and test in accordance with the purchase documents and engineering specifications and data sheets and applicable referenced codes and standards.

2. Provide materials, labor, transportation, staging and tools to complete the erection of the tank.

3. Submit plot layout of hoisting equipment, when used.

4. Provide anchor bolt requirements.

5. Design, fabricate and install `stairways, ladders, cages, platforms, handrails and pipe guides and pipe supports when indicated in the tank data sheets.

6. Perform external painting and internal lining when indicated in the tank data sheets.

7. Provide agitator supports when indicated in the tank data sheets.

8. Design and fabricate tank internals as indicated in the tank data sheets.

9. Provide insulation supports when insulation is required in the tank data sheets.

10. Provide fabrication drawings in accordance with this specification.

11. Provide water, equipment and temporary pipes, supports and valves required to perform hydrostatic testing.

12. Perform nondestructive examination of welds.

13. Provide preventive maintenance instructions for the erected tank and items supplied with the tank that performs a mechanical function.

14. Confirm the sizing of agitators as required in the tank data sheets.

15. Purchase, test and install agitators as required in the tank data sheets, including vibration detectors.

16. Tank insulation and heat tracing (both may be included with the requisition).

2.2Work Excluded from Scope

1. Buyer will provide site preparation foundation design and construction, including anchor bolts as specified by the Supplier.

2. Instrumentation. 3. Variable frequency drives (VFD) for agitators.3.0 Response Submittal

3.1 Electronic response (e-mail w/ attachments) is the preferred method of response and must be submitted no later than 28 September, 2009. The address for electronic submittal is [email protected].

3.2 When an electronic response is not possible, your response may be sent via U.S. Mail or Priority Mail (e.g. Fed-X, UPS, DHL) in time to meet the due date. The mailing address is:Bechtel Parsons Blue Grass

830 Eastern Bypass, Suite 106Richmond, KY 40475

Attention: Subcontracts Manager

Pre-Qualification No.: 24915- H23-SRA-AKBP-00001

3.3Pre-Qualification Document Checklist

Companies are encouraged to use this checklist to ensure their submittals are complete.

FORMCHECKBOX

ITAR Certification FORMCHECKBOX

Prequalification Criteria and Response pages 4 through 15 FORMCHECKBOX

OSHA Form 300 & 300A logs and data for past three calendar years

FORMCHECKBOX

Letter from insurance provider confirming Experience Modification Rate (EMR) for past three calendar years

FORMCHECKBOX

Copy of Safety Program Table of Contents

FORMCHECKBOX

Explanation of violation of environmental regulatory requirements and fines or penalties FORMCHECKBOX

QA Program Table of Contents and summary or copy of QA Plan FORMCHECKBOX

Description of directly relevant experience4.0 Pre-Selection CriteriaThe successful bidder will not be required to be signatory to the Project National Labor Agreement for this RFP if they meet the following criteria: Local Contractor (Clark, Estill, Fayette, Garrard, Jackson, Jessamine, Madison, Rockcastle County), Small Business, Small Disadvantaged business, Woman-Owned business, HUBZone Business, Veteran-Owned Business, Service Disabled Veteran Owned Business.

5.0 Company ResponsePrime Subcontractor Company Name:

Address:

Pre-qualification Contact Name:

Phone Number:

Facsimile Number:

E-mail Address:

DUNS No. (Dun & Bradstreet):

Business Size Classification (according to U.S. Small Business Administration Criteria) below $33.5 million annual revenue is a small business FORMCHECKBOX Small

FORMCHECKBOX Small Disadvantaged Business

FORMCHECKBOX Woman Owned Small Business

FORMCHECKBOX HUBZone Business

FORMCHECKBOX Veteran-Owned Small Business Concern

FORMCHECKBOX Service-Disabled Veteran-Owned Small Business Concern.

5.1 Commercial Data

Potential offerors are required to register on the Bechtel Supplier and Contractor Portal in order to be considered. What was the date your company registered or updated its information on the Portal?Date Updated:

5.2 Safety & Health RequirementsA. Definitions:

B. Safety Rating Status: Rating given to a potential Offeror after review of the potential Offerors EMR, Incident Rate (IR), and Lost Time Incident Rate (LTIR). The EMR, IR and LTIR Hurdle Rates are as follows:

Category A - Preferred. Best subcontractor, Acceptable to bid.

Category B - Conditional. Average subcontractor, BNI S&H Supervisor to review safety program prior to acceptance as a qualified bidder.

Category C - Probationary. Poor subcontractor, Not acceptable to bid without overriding factor and with concurrence of the BNI S&H Supervisor.

These categories are based on the following safety performance statistics:CategoryExperience Modification Rate (EMR*)Lost Time Incident Rate

(LTIR)Incident Rate

(IR)

A.88 or less2.503.50

B1.00 or less4.007.50

C1.00 or more5.6013.50

*These cutoff levels apply to the Interstate EMR. Hurdle rates may vary for state EMRs and must be provided by the ES&H Supervisor. The state rate overrides the Interstate EMR and will determine the bidders category rating.(i) Experience Modification Rate (EMR): An adjustment to the Workers' Compensation experience. An experience modifier of 1.00 is the expected average for a given company and reflects the cost of losses expected for a contractor that employs the various trades.(ii) Hurdle Rates: A number that is set for the upper limits of each evaluation item.(iii) Evaluation Items: EMR, IR (recordable Incident Rate), LTIR (Lost Time Incident Rate)(iv) Incident Rate: The number of injuries, illnesses, or lost workday cases related to a common exposure base enables one to make accurate industry comparisons, trend analysis, overtime, or comparisons among firms regardless of size.This rate is calculated as: N x 200,000

EHWhere:

N = number of recordable injuries and/or illnesses or lost workday cases;

EH = total hours worked by all employees during calendar year;

200,000= base for 100 full-time equivalent employees (working 40 hours per week, 50 weeks per year)C. All potential offerors, lower-tier subcontractors, and teaming partners proposing to work on the BGCAPP project site must fall in one of the three Safety Rating Categories defined above. Companies failing to meet this requirement will not receive a RFP.D. Based on definitions in preceding Section 2.A, which Safety Rating Category does your Company fall in?

FORMCHECKBOX A FORMCHECKBOX B FORMCHECKBOX C

E. All data and information required by the following Safety and Health History must be submitted for the potential offeror, each lower-tier subcontractor, and teaming partner proposed to perform any portion of the Work on-site.SAFETY AND HEALTH HISTORY

1.Check your type of work (use NAICS code to determine):

FORMCHECKBOX

Non-Residential Building

FORMCHECKBOX

Heavy (Non-Highway) Construction

FORMCHECKBOX

Mechanical

FORMCHECKBOX

Electrical

FORMCHECKBOX

Other (State Types):

2.EMR (Provide letter from Insurance Carrier)

2A.List your firms Interstate Experience Modification Rate (EMR) for the three most recent years and total hours worked.

FORMDROPDOWN

FORMDROPDOWN

FORMDROPDOWN

a.EMR (last three completed calendar years)

b.Hours Worked (last three completed calendar years)

2B.If the State where the jobsite was located has an EMR rating system, provide the State EMR for the three most recent years and total hours worked.

FORMDROPDOWN

FORMDROPDOWN

FORMDROPDOWN

a.EMR (last three completed calendar years)

b.Hours Worked (last three completed calendar years)

3.OCCUPATIONAL SAFETY & HEALTH PERFORMANCE (Use OSHA Form 300 & 300A to complete)

3A.Fatality: Provide a brief description of each fatality your firm has incurred in the three most recent years (Refer to OSHA Form 300, Categories F and G):

Years & brief description (Cat. F)

FORMDROPDOWN

FORMDROPDOWN

FORMDROPDOWN

3B.Use information from your OSHA Form 300 categories to fill in the three most recent years. Submit a copy of your completed OSHA form 300 and summary page for the last three calendar years .

FORMDROPDOWN

FORMDROPDOWN

FORMDROPDOWN

a.Number of lost workday cases. (Cat. H 300 log)

b.Number of restricted workday cases. (Cat. I 300 log total)

Last three completed calendar years.

c.Number of cases with medical treatment beyond first aid only. (Cat. J 300 log total)

d.Number of fatalities. (Cat. G 300 log total)

e.Number of hours worked by Company.

4.Are accident reports or OSHA form 300A summary of work-related injuries and illness sent to the following and how often?

NoYesMonthlyQuarterlyAnnually

a.Project Superintendent/Site Manager. FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

b.Vice President/Manager of Construction FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

c.Safety Director / Manager FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

d.President / CEO of Firm FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

5.How are accident records and accident summaries kept? How often are they reported?

NoYesMonthlyAnnually

a.Accidents totaled for the entire company FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

b.Accidents totaled by project FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

(1)Subtotaled by superintendent FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

(2)Subtotaled by foreman FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

6.How are costs of individual accidents kept? How often are they reported?

NoYesMonthlyAnnually

a.Costs totaled for the entire company FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

b.Costs totaled by project FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

(1)Subtotaled by superintendent FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

(2)Subtotaled by foreman FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

7.Do you hold site safety meetings for field employees both Manual and Non-Manual?

Yes FORMCHECKBOX

No FORMCHECKBOX

How Often?

Weekly FORMCHECKBOX

Bi-Weekly FORMCHECKBOX

Monthly FORMCHECKBOX

Less Often, As needed FORMCHECKBOX

8.Do you conduct project safety audits / inspections / assessments?

Yes FORMCHECKBOX

No FORMCHECKBOX

If yes, who conducts them?

TITLE / POSITION:HOW OFTEN?

9.List key Safety and Health personnel planned for this project. Please list name, expected position or title. When a project has not been specified, list key company personnel.

NAMEPOSITIONPROJECT

10.Do you have a written safety program?

Yes FORMCHECKBOX

No FORMCHECKBOX

If yes, submit a copy of the table of contents for evaluation.

11.Do you have an orientation program for new hires?

Yes FORMCHECKBOX

No FORMCHECKBOX

Does it include instruction on the following?

YesNoYesNo

a.Head protection FORMCHECKBOX

FORMCHECKBOX

i.Fire protection / prevention FORMCHECKBOX

FORMCHECKBOX

b.Eye protection FORMCHECKBOX

FORMCHECKBOX

j.First aid facilities FORMCHECKBOX

FORMCHECKBOX

c.Hearing protection FORMCHECKBOX

FORMCHECKBOX

k.Emergency procedures FORMCHECKBOX

FORMCHECKBOX

d.Respiratory protection FORMCHECKBOX

FORMCHECKBOX

l.Toxic substances FORMCHECKBOX

FORMCHECKBOX

e.Safety harness and lanyard FORMCHECKBOX

FORMCHECKBOX

m.Trenching and excavation FORMCHECKBOX

FORMCHECKBOX

f.Scaffolding FORMCHECKBOX

FORMCHECKBOX

n.Signs, barricades, flagging FORMCHECKBOX

FORMCHECKBOX

g.Perimeter guarding FORMCHECKBOX

FORMCHECKBOX

o.Electrical safety FORMCHECKBOX

FORMCHECKBOX

h.Housekeeping FORMCHECKBOX

FORMCHECKBOX

p.Rigging and crane safety FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

FORMCHECKBOX

q.Vehicle / Road Safety (Driving) FORMCHECKBOX

FORMCHECKBOX

12.Do you have a program for newly hired or promoted foremen?

Yes FORMCHECKBOX

No FORMCHECKBOX

Does it include the following?

YesNoYesNo

a.Safe work practices FORMCHECKBOX

FORMCHECKBOX

e.First aid procedures FORMCHECKBOX

FORMCHECKBOX

b.Safety supervision FORMCHECKBOX

FORMCHECKBOX

f.Accident investigation FORMCHECKBOX

FORMCHECKBOX

c.Toolbox meetings FORMCHECKBOX

FORMCHECKBOX

g.Fire protection and prevention FORMCHECKBOX

FORMCHECKBOX

d.Emergency procedures FORMCHECKBOX

FORMCHECKBOX

h.New worker orientation FORMCHECKBOX

FORMCHECKBOX

13.Do you hold craft toolbox meetings?

Yes FORMCHECKBOX

No FORMCHECKBOX

How Often?

Weekly FORMCHECKBOX

Bi-Weekly FORMCHECKBOX

Monthly FORMCHECKBOX

Less Often, As needed FORMCHECKBOX

14.Do you have a written Hazard Communication program?

Yes FORMCHECKBOX

No FORMCHECKBOX

If yes, please provide an outline below.

15.Do you have/require Material Safety Data Sheets (MSDS) for material/chemicals?

Yes FORMCHECKBOX

No FORMCHECKBOX

If yes, explain process how they are used to inform craft workers about potential exposure / hazards to chemicals:

16.List three (3) client references that we may contact to discuss the effectiveness of your safety program.

NameAddressPhone No.

a.

b.

c.

5.3 Environmental

Has your company worked the previous three (3) years without receiving any citations by a Federal or State agency for violations of an environmental regulatory requirement?

FORMCHECKBOX Yes FORMCHECKBOX No

If No, were any fines or penalties levied? FORMCHECKBOX Yes FORMCHECKBOX No

If yes, provide explanation (use continuation page if necessary).

5.4 Quality Assurance Program

A. Does your Company have a written Quality Assurance Program?

FORMCHECKBOX Yes FORMCHECKBOX No

B. Potential Offeror shall furnish a copy of its QA Program Table of Contents and a brief summary identifying each of the requirements listed below. The level of rigor applied to the elements shall be commensurate with the risks associated with the Work. A description of the organizational structure, functional responsibilities, levels of authority, and interfaces for those managing, performing, and assessing the Work. Personnel Training and Qualifications Quality Improvement

Control of Documents and Records

Work Processes

Design

Procurement

Product Identification and Traceability

Inspection and Acceptance Testing

Control of the Testing Equipment

Control of Non-Conforming Product

Corrective and Preventative Actions

Handling, Storage and Shipping Procedures

Management Assessment

Independent Assessment

C. The Potential Offer has the option to submit their full Quality Assurance Plan with this proposal.5.5 Technical Criteria

A. Does the potential Offeror have direct relevant experience in planning, managing, and executing work involving design, fabrication, installation and testing of API 650 storage tanks and components? (Note: This criterion must be answered ONLY for the prime potential Offeror not the potential Offerors team.)

FORMCHECKBOX Yes FORMCHECKBOX NoB. Do the potential Offeror and/or agitator manufacturer have experience required to design, fabricate, procure, transport, install and test agitators and related components?

FORMCHECKBOX Yes FORMCHECKBOX NoC. Do the potential Offeror and/or its coating contractor have direct relevant experience in applying internal epoxy coatings to storage tanks?

FORMCHECKBOX Yes FORMCHECKBOX NoD. Do the potential Offeror and/or its coating contractor have direct relevant experience in applying coatings to the exteriors of storage tanks? FORMCHECKBOX Yes FORMCHECKBOX NoE. Does the potential Offeror have direct relevant experience in constructing double-bottoms for storage tanks per API 650 Appendix I?

FORMCHECKBOX Yes FORMCHECKBOX NoF. Does the potential Offeror and/or its team members have experience in designing and installing an internal tank eductor into a storage tank of this type?

FORMCHECKBOX Yes FORMCHECKBOX NoG. Does the potential Offeror and/or its team members have experience in designing and installing heat tracing systems for storage tanks of this type?

FORMCHECKBOX Yes FORMCHECKBOX NoH. Does the potential Offeror and/or its team members have experience in installing installation on storage tanks of this type?

FORMCHECKBOX Yes FORMCHECKBOX NoI. Do the potential Offeror and/or its team members have experience in the government contracting environment coordinating the timely submittal of design documentation, calculations and product submittals for client review, and the revision of these documents based on client feedback?

FORMCHECKBOX Yes FORMCHECKBOX NoJ. Direct Relevant Experience Documentation: If the Respondent has answered yes to the foregoing questions, provide a reference list of example projects over the last ten years, on the included Experience Statement (Page 14), that demonstrates direct relevant project experience to support each yes response. Example projects should be detailed as to both the technical scope of the project and your participation in the project. Column completion notes for the following page, Experience Statement, to be completed by the Prime subcontractor and each associated team member:

A. Customer Name, Address, Contact Name and Phone No.- So that we may contact as a reference as needed.

B. Work Description and Location- Describe work scope and location, and then indicate if prime or subcontract.

C. Original/ Final Contract Value- Original award value and final closeout contract value.

D. Commencement/ Completion Dates- Provide starting date and actual completion (or forecast if still in progress) by month/year format (e.g., Jan 2006/ Sept 2007)

EXPERIENCE STATEMENT PRIME SUBCONTRACTORCOMPANY NAME:

EXPECTED ROLE IN THIS PROJECT:

Customer Name, Address, Contact Name and Phone No.Work Description and LocationOriginal/Final Contract ValuesCommence/ Complete Dates

EXPERIENCE STATEMENT AGITATOR MANUFACTURER/COATING CONTRACTORCOMPANY NAME:

EXPECTED ROLE IN THIS PROJECT:

Customer Name, Address, Contact Name and Phone No.Work Description and LocationOriginal/Final Contract ValuesCommence/ Complete Dates

Potential Bidder ITAR CertificationI, ______________, an authorized corporate representative of __________________, do hereby certify to the best of my knowledge and belief, that:

1. Technical data subject to U.S. export control laws and regulations shall be used for purposes of this procurement only. Such data shall not be disseminated elsewhere outside my company, either domestically or abroad, without the express written consent of Bechtel National Inc. (BNI) or Parsons Infrastructure and Technology Group, Inc (Parsons). My company will implement safeguards to ensure that such dissemination does not occur.

2. Prior to disseminating any technical data to foreign nationals in my company who are not permanent resident aliens (green card holders) or asylees, my company agrees to ascertain whether a government license - or other procedures or safeguards are required.

3. My company, including its parent or sister companies, corporations or firms, its affiliates or subsidiaries, and all employees of any such entities, FORMCHECKBOX have FORMCHECKBOX have not been convicted of or had a civil judgment rendered and against them for, and FORMCHECKBOX are FORMCHECKBOX are not presently indicted f or, or otherwise criminally or civilly charged by a Government entity with violations of any U.S. statutes or regulations regarding export controls, including but not limited to the Department of States International Traffic in Arms Regulation and the Department of Commerces Export Administration Regulations, as well as laws involving and regulations promulgated by the Departments of Energy and Treasury. (Check the appropriate boxes).

4. My company, including its parent or sister companies, corporations or firms, its affiliates or subsidiaries, and all employees of any such entities, FORMCHECKBOX are not FORMCHECKBOX are presently included on any U.S. government restricted parties list relating to export controls or economic sanctions. (check one)

5.My company FORMCHECKBOX is FORMCHECKBOX is not subject to Foreign Ownership, Control or Influence. Foreign Ownership, Control or Influence means a situation where the degree of ownership, control or influence of an offeror or a contractor by a foreign interest is such that a reasonable basis exists for concluding that the compromise of export control information may result. A foreign interest means any of the following: 1) a foreign government or foreign government agency or instrumentality thereof; 2) any form of business enterprise organized under the laws of any country other than the U.S. or its possessions; 3) any form of business enterprise organized or incorporated under the laws of the U.S. or a State or other jurisdiction with the U.S. which is owned, controlled, or influenced by a foreign government, agency, firm, corporation, or person, or 4) any person who is not a U.S. Citizen.

Signature:

Date: _____________

Typed Name and Title:

The BGCAPP Small Business Advocate determined that the NAICS (North American Industry Classification System code for this work is 236220 Construction Management, Commercial and Institutional Building-. The SBA size standard for this code is annual revenue of $33.5 million. For pre-qualification purposes, you are a small business if your companys revenues to not exceed $33.5 million.

18 Sept. 2009Page 1 of 16Field-Erected Storage Tanks Subcontract18 Sept. 2009Page 13 of 16Field-Erected Storage Tanks Subcontract