6.1.16 city council meeting presentation- local projects update
TRANSCRIPT
![Page 1: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/1.jpg)
1Local Project Updates
Nelson D. NelsonPublic Works Director
June 1, 2016
City Council Meeting
![Page 2: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/2.jpg)
2
Southwest Quadrant of Grand Boulevard Waterline Project Construction anticipated to be complete in June
![Page 3: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/3.jpg)
3
2015-2016 CDBG Sidewalk ImprovementsConstruction continues through June
![Page 4: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/4.jpg)
4
SAWPA
![Page 5: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/5.jpg)
5
Northbound lane between Tom Barnes Street and Tuscany Street.
Southbound lane just north of Blue Springs Drive.
Within the median between Pronio Drive and Lakeshore Drive. Requires one northbound lane closure.
Testing is necessary to ensure the new pipe meets the national standard for cured-in-place pipe.
![Page 6: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/6.jpg)
69
SR-91 CLOSURES2-WEEK LOOK AHEAD AT A GLANCE
![Page 7: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/7.jpg)
7
Westbound SR-91: 2-Week Look Ahead
![Page 8: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/8.jpg)
8
Eastbound SR-91: 2-Week Look AheadMain Street EB on-ramp scheduled to open June 22nd
![Page 9: 6.1.16 City Council Meeting Presentation- Local Projects Update](https://reader035.vdocuments.site/reader035/viewer/2022062523/58ec411a1a28abbd4b8b4747/html5/thumbnails/9.jpg)
9Local Project Updates
June 1, 2016
City Council Meeting