1 2000, QualityToolBox.com, LLC, all rights reserved
A STRATEGY FOR
PERFORMANCE
EXCELLENCE
2 2000, QualityToolBox.com, LLC, all rights reserved
Executive Overview
Participant manual
Tools WorkbookKnowledge Breakthrough
Lecture notes Lecture notes
Performance Excellence Series
Training Module Elements
3 2000, QualityToolBox.com, LLC, all rights reserved
Session 1.0 Introduction…….……...……………………. 3
Session 2.0 Waste Management ……………………….. 14
Session 3.0 5S Implementation…………………………. 20
Element 3.1 Systematic Organization…………………... 31
Element 3.1.1 Red Tag System……………………………. 47
Element 3.2 Sorting Visual Placement………………….. 33
Element 3.2.1 Visual Sign System………………………….. 66
Element 3.2.2 Visual Color System………………………... 76
Element 3.3 Scrubbing Clean……………………………. 40
Element 3.4 Standardizing Control……………………... 45
Element 3.5 Self Discipline Control……………………... 48
4 2000, QualityToolBox.com, LLC, all rights reserved
What is 5S ?
An essential step required for Waste Elimination
An integral step in Kaizen A required element to achieve Lean-site
Manufacturing.
Systematic Organization
“Seiri”
Orderliness
“Seiton”
Cleanliness
“Seiso”
Cleanup
“Seiketsu”
Cleanup
“Seiketsu”
Standardization/Perseverance
“Shitsuke”
5 2000, QualityToolBox.com, LLC, all rights reserved
5S Performance Excellence Model
Systematic-Systematic Organization
Scrubbing clean
Self-Discipline-
Control
Customer Expectations
Sorting Visual Placement
Standardizing Control
Improved Quality
Improved Safety
Reduced costs
Consistent Deliveries
Improved Product/ Service Options
6 2000, QualityToolBox.com, LLC, all rights reserved
The Five Elements of 5SSystematic Systematic Organization- Identifying what items are required and which are not.
Sorting Visual Placement- Items should be easily retrievable, easy to get, and visual-easy to see.
Self-Discipline/Control-Ensuring that Systematic Organization, Visual Placement & Cleanliness are maintained.
Scrubbing Clean-Keep the area free from debris, dirt, oil, items not needed.
Standardizing Control- Maintain and continually improve the previous improvements.
7 2000, QualityToolBox.com, LLC, all rights reserved
Major CPITools (6) Kaizen Lean Description
Cp/Cpk Process capability assessmentDOE Design of experimentsSPC Process control based on statistics and data analysisFMEA Risk assessment toolRegression Correlate effect one variable has on anotherProcess Map Map process steps to communicate and identify opportunities5 whys /2 hows Determination methods for root cause discoveryPareto Column chart ranking items highest to lowestFishbone Cause / Effect Diagram5S Elimination wasteVisual Mgmt Emphasis on visual techniques to manage processPoka-Yoke Error proofing techniquesSpagetti Chart Kanban Material storage technique used to control processTakt Time Determine pace or beat of a processStd Work Evaluate tasks done during a processSMED Single minute exchange of dies - Quick machine set upTPM Integrate maintenance strategy with processCellular Flow Reduce inventory & cycle time thru process layout and pull
production techniques
Expand Process Improvement Program to Utilize Kaizen Tool Kit Expand Process Improvement Program to Utilize Kaizen Tool Kit
Tool Kit Comparison
8 2000, QualityToolBox.com, LLC, all rights reserved
6 Sigma• Disciplined Methodology• Technical Approach
(Quantitative)• Data Driven - Statistical• Customer Focus• Reduce Variation• Focus on Large Impact• Larger/Longer Projects
Kaizen • Philosophical Approach• Common Sense Approach
(Qualitative)• Data Driven - Observation• Operational Focus• Waste Elimination 5S• Incremental Change• Smaller/Shorter Projects
Complimentary Tools Driving Continuous ImprovementComplimentary Tools Driving Continuous Improvement
Expanding the Strategy
Performance Excellence
9 2000, QualityToolBox.com, LLC, all rights reserved
Comparative AnalysisImprovement Methodologies• Similar in Structure• Improvements measured against
established process• Team oriented
• Similar improvement tools• Measure effectiveness of improvements• Maintain new performance level• Standardize & Proceduralize
Results• More Efficient Processes
Comparison• Both are Effective Improvement Mechanisms• CPI/6s best applied to large complex problems• Kaizen/Lean best applied to achieve incremental changes and eliminate wastes.
Measure- Data Collection- Determine Process Potential / Goals
Evaluate- Root Cause / Vital Few- Statistical Analysis
Improve & Verify- Implement Improvement- Validate Improvement
Standardize- Standardize / Leverage- SPC- Update Procedures
Evaluate- Baseline Process Performance- Establish Target
Decide-Compare solutions- Choose
Act-Communicate - Implement improvement- Control
Measure- Validate improvement- Standardize - Update Procedures
Focus- Reduce Process Variation- Identify Critical Cause and Focus Resources for Maximum Impact
Focus- Eliminate Waste 5S- Seek Incremental Process Changes
Kaizen/Lean 6
Summary- Technical Approach based on Statistical Analysis- Requires Significant Data Collection- Best applied to Manufacturing Processes- Typical Projects 1-3 Months
Summary- Common Sense Approach based on Observation- Applicable to all types of processes- Defined improvement strategy- Typical Projects 1 week
10 2000, QualityToolBox.com, LLC, all rights reserved
Why 5S
•To eliminate the wastes that result from“uncontrolled” processes.• To gain control on equipment, material & inventory placement and position.• Apply Control Techniques to Eliminate Erosion of Improvements.• Standardize Improvements for Maintenance of Critical Process Parameters.
Look Familiar?
11 2000, QualityToolBox.com, LLC, all rights reserved
Overproduction Delays (waiting time) Transportation Process Inventories Motions Defective products Untapped Resources Mis-used Resources
9 Wastes
The Nine types of wastes.
12 2000, QualityToolBox.com, LLC, all rights reserved
Overproduction ______________________________ Delays (waiting time)__________________________ Transportation _______________________________ Process_____________________________________ Inventories__________________________________ Motions ____________________________________ Defective products ____________________________ Untapped Resources __________________________ Mis-used Resources ___________________________
9 Wastes
Give an example of each type of waste.
The Nine types of wastesThink Break
13 2000, QualityToolBox.com, LLC, all rights reserved
5 S Element Waste/ Improvement Item Deliverable
SystematicOrganization
Elimination of finding.Reduction of part selection errors.
Reduced CostsImproved QualityIncreased Product Options
Sorting-VisualPlacement
Elimination of finding.Elimination of nonconformances.Elimination of motion.Reduction of part selection errors.
Reduced CostsIncreased SafetyImproved QualityIncreased Product Options.
Scrubbing Clean Increased safety.Preventive maintenance.Increased equipment knowledge.
Increased SafetyImproved Quality
StandardizationControl
Increased equipment life.Higher morale.Clean environment.Increased visibility of nonconformances.
Improved QualityConsistent DeliveryImproved Safety
Elimination of Waste
14 2000, QualityToolBox.com, LLC, all rights reserved
Systematic
Organization
CleanlinessVisual Placement
Standardization
5 S Implementation
Plan
Progressive
Enhancements
Step 1
Establish 5 S
Implementation Team
Step 2
Develop Specific
Implementation Plan
Step 3
Develop Communication
Plan
Step 4
Develop 5 S Training PlanStep 5
Implement 5 S
Step 6
Verification of Effectiveness
15 2000, QualityToolBox.com, LLC, all rights reserved
Removing “Red Tagged” stuff
What Stuff would you “Red Tag” in these pictures ?
Picture A__________________________________________________________
Picture B _________________________________________________________
Think Break
16 2000, QualityToolBox.com, LLC, all rights reserved
In the following pictures, identify some of the “finding wastes “ ( assume you work in a distribution center and you have to fill an order with product located in the following pictures).
___________________ ___________________ _________________
___________________ ___________________ _________________
___________________ ___________________ _________________
___________________ ___________________ _________________
Everything has a useable place
Think Break
Finding Wastes
17 2000, QualityToolBox.com, LLC, all rights reserved
Some evidence of standardized work areas
•Clear, shiny aisle ways
•Color coded areas
•Slogans, banners
•No work-in-process ( WIP )
•One-Piece Flow
•Standardized Work Sheets
18 2000, QualityToolBox.com, LLC, all rights reserved
Visual Color System Implementation
• Develop a map identifying the “access ways”(aisles, entrances, walkways etc.) and the “action” areas.
• Perform any necessary realignment of walkways, isles, entrances.
• Assign an address to each of the major action areas.
• Mark off the Walkways, Aisles & entrances from the action areas Table 1.0
• Apply flow-direction arrows to aisles & walkways Table 1.0
• Perform any necessary realignment of action areas.
• Mark-off the inventory locations Table 1.0.
• Mark-off equipment/machine locations Table 1.0
• Mark-off storage locations( Cabinets,shelves,tables) Table 1.0
• Color-code the floors and respective action areas per Table 1.0.
19 2000, QualityToolBox.com, LLC, all rights reserved
Cleanliness involves cleaning every aspect of the Organization and the removal of dirt,
dust,oil, scraps on the floor, & garbage.
Key Deliverables
A clean Systematic Organization results in increased safety and efficiency.
Increased Safety
Increased Efficiency
20 2000, QualityToolBox.com, LLC, all rights reserved
Step 2: Allocation:
Assign resources to the specific tasks required to make 3S a habit.
5S “To Do” Plan Date: Page of
5S Team Members Company/Division Name: Person Preparing This Sheet
Item#
DateStarted
5S element 5S Task - Action PersonResponsible
Location/Department
PercentComplete
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
100 25
75 50
5S for the WorkplaceTraining andSourcebookfor5S Worksheets
How to Use This Manual
The continuous improvement tools that are presented in Sections1-10 of this manual are shown in order of use. These formsMUST be completed in the order presented in this manual. Eachsection contains a brief description of the tool, its purpose, whento use it, who should use it, how to use it, and the expectedresults.
Remember to focus on the elimination of waste.Strive to maximize yields and obtain cost reductionsfrom existing machinery and equipment before“buying solutions”. Improve current systems andtechniques before automation. Automating a systemor practices without first having an understanding ofthe process will not solve underlying processproblems.
Perhaps the most important point to remember is thatwe must understand a process before we make anyattempt in changing it. “No Tampering” is the first ruleof continuous improvement. We can not tamper witha process without understanding it.
By using these tools, we will all share a common andsystematic approach for questioning, analyzing,proposing solutions, experimenting, and finally,implementing proven changes.
“The problems that exist in the worldtodaycannot be solved by the same level ofthinkingthat created them.”
Improvement
Identify waste
Measurement
5STemplate
Table of Contents
Section 1 Development of 5S “To Do” Plan: Establishment of the 5S team focused onthe development, training, and implementation of the company’s 5S program.Deliverable includes action plan and associated tasks with the 5Simplementation. ………………………………………………………………………… 4
Section 2 Waste Identification Map: Identification of the 9 wastes associated withproduction of products and services. A detailed map of each major work area isdeveloped describing the major types of wastes in each area. These wastes arethe improvement opportunities that exist prior to5S………………………………...
The overall wastes is calculated for all the work areas and identified on the 9Waste Radar Chart
7
Section 3 5S Action sheet: Establishing baseline key performance metrics in terms ofkey deliverables, photographs, and current conditions of the “before” 5Simplementation phase. Deliverable includes the 5S actionsheet………………….
11
Red Tag Strategy: The utilization of “Red Tags” to visually identify items whichare not needed or used infrequently…………………………………………………..
14
Section 5 Visual Color Sheets: Utilization of colors to identify specific work actions,inventory locations, access areas within the work environment. Initializationbegins with development of Visual ColorSheets…………………………………….
17
Section 6 Visual Sign Sheets: Utilization of signs to identify machine, equipment, tooling,inventory, safety, hazard and work center locations. Sample SignSheets……….
20
Section 7 Standard Cleaning Work Sheet: A cleaning matrix identifying the work arearesponsibilities, supplies, and schedules for cleaning. …………………………….. 23
Section 8 Cleaning “To Do List”: A action list identifying specific cleaning tasks for eachwork area identified on the Standard Cleaning Work Sheet……………………….. 27
Section 9 5S Status Report: A report identifying implementation effectiveness of each 5Ssteps applied. A variable metric ranging from 0-5 is established for each stepimplemented…………………………………………………………………………….. 30
Section 10 Waste Identification Map: Identification of the 9 wastes associated withproduction of products and services. A detailed map of each major work area isdeveloped describing the major types of wastes in each area. These wastes arethe improvement opportunities that exist prior to 5S……………………………
9 Wastes Radar Chart: After the completion of 5S, the results of the waste reductionis recorded, charted and compared to the initial 9 Waste Radar Chart.
33
Section 2
Waste Identification Map
Manager or Team Leader (Section A) Area or Process Name (Section B) Person Preparing This Sheet (Section C)
Over production Delays
Transportation
Process
Inventory
Motion
Defective Product
Defective
Untapped
Resources Mis-used
Resources
Waste Identification Map
9 Waste Radar Chart
% of Waste Before 5S
% of Waste After 5S
0
Defective Product
Transportation
Delays
ResourcesMis-used
Process
10
Motion
Inventory
UntappedResources
90
70
2030
4050
60
80
100Over production
Overproduction Delays Transportation Inventory Motion Processes DefectiveProducts
UntappedResources
Mis- UsedResources
Before After Before After Before After Before After Before After Before After Before After Before After Before After
100
90
80
70
60
50
40
30
20
10
0
The Nine WastesP
erce
nta
ge o
f W
aste
Waste Identification Map
Purpose Used to create a visual picture of a work area to assess waste in work placeorganization, office/cell layout and crewing. Shows the type of each waste insection/division of the organization. Also utilized to indicate equipment type,size, and distances within each work area.
When To Use The Waste Identification Map should be used after the 5S “To Do” plan iscompleted. A map should be developed for each department or focus areaof the 5S program. Do not attempt to develop a single Map for an entireorganization, it will become too busy to be effective.
Who Should Use It The Waste Identification Map can be used by anyone involved in continuousprocess improvement.
Expected Benefits The Waste Identification Map will provide information about work waste ineach department, work sequence, equipment layout and distances. TheWaste Identification Map not only provides actual waste, but also provides avisual layout of the interrelationship of the waste.
How To Use It 1. Referring to the 5S “To Do” Plan, identify each respective area 5S willbe implemented. Develop a Waste Identification Map for each area ordepartment and complete sections A, B, C, with the necessaryinformation. Note you may have multiple Maps for the entire 5Simplementation program.
2. For each work department, fill in the equipment, access areas,storage areas, inventory locations etc. on the Map. It is best to drawthese to scale.
3. Next identify the processes for each area on the Map.
4. Next, list the products and services at each applicable workstation.
5. Next, identify the product/service flow through the respectiveprocesses & work stations.
6. Establish time trials for each major activity and when completeddocument the time for each major activity within the department.
7. Document the type of waste and time associated with each waste ateach activity, process, equipment, inventory, storage, and officelocation.
8. For each type of waste identified, complete the waste matrix section onthe bottom of the 9 Waste Radar Chart in the “before” column. Note:The y-axis list % of waste, use whatever metric makes sense i.e.time, $, labor hours, productivity etc. Remember that your goal isto reduce these wastes as a result of the 5S Program.
Chart the % waste value for each type of waste on the Radar Chart.Connect each of the values on the radar chart. This is extremely important,this is your baseline metric and will be used to determine the magnitude ofyour improvements.
Next Step You are now ready to move to the next step, the Action Sheet.