42378-016: power system expansion and efficiency ... · this semiannual environmental monitoring...

119
Semiannual Environmental Monitoring Report Project No: 42378-016 Loan No- BAN: 3087 December 2018 Power System Expansion and Efficiency Improvement Investment Program - Tranche 2 Augmentation and rehabilitation of Distribution system in DESCO

Upload: others

Post on 19-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Semiannual Environmental Monitoring Report

Project No: 42378-016 Loan No- BAN: 3087 December 2018

Power System Expansion and Efficiency Improvement Investment Program - Tranche 2

Augmentation and rehabilitation of Distribution system in DESCO

Page 2: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgments as to the legal or other status

of any territory or area.

Page 3: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily
Page 4: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily
Page 5: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

4th Environmental Monitoring Report

on

Augmentation and Rehabilitation of Distribution System in

DESCO Area

Period: July to December 2018

Page 6: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily
Page 7: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

i

Table of Content

List of Tables ............................................................................................. iii

List of Figures ............................................................................................ iv

Unit of Measurement ................................................................................... v

Abbreviations and Acronyms ..................................................................... vii

Executive Summary ................................................................................... ix

1. Introduction .......................................................................................... 1

1.1 Background ......................................................................................... 1

1.2 Objectives ........................................................................................... 1

1.2.1 Main Objective .............................................................................. 1

1.2.2 Specific Objectives ......................................................................... 1

1.3 Project Locations .................................................................................. 2

1.4 Scope of Studies .................................................................................. 6

1.5 Monitoring Law and Policy Standard ........................................................ 7

1.5.1 Compliance with National Environmental Laws ................................... 8

1.5.2 Bangladesh Government Regulation and Compliance Monitoring ........... 8

1.5.3 Compliance with DoE’s Guidelines .................................................. 10

1.5.4 ADB Loan Covenants with the DESCO ............................................. 11

2. Approach and Methodology ................................................................. 14

2.1 Overall Approach ................................................................................ 14

2.2 Study Mobilization .............................................................................. 14

2.3 Study Team Mobilization ...................................................................... 14

2.4 Methodology ...................................................................................... 15

2.4.1 Physical Environment ................................................................... 15

2.4.2 Biological Environment ................................................................. 16

3. Monitoring Results .............................................................................. 18

3.1 Introduction....................................................................................... 18

3.2 Physical Environment .......................................................................... 18

3.2.1 Ambient Air Quality...................................................................... 18

3.2.2 Noise Level ................................................................................. 23

3.2.3 Waste Management and Sanitation System ..................................... 24

3.2.4 Soil Quality ................................................................................. 26

3.3 Biological Environment ........................................................................ 47

Page 8: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

ii

4. Institutional Arrangement and Grievance Redress Mechanism ............. 51

4.1 Institutional Arrangement .................................................................... 51

4.2 Grievance Redress Mechanism .............................................................. 51

5. Specific Environmental Management Plan............................................ 54

6. Conclusions and Recommendations ..................................................... 58

6.1 Conclusions ....................................................................................... 58

6.2 Recommendations .............................................................................. 58

Reference ................................................................................................. 60

Appendix-A: Field Photos .......................................................................... 62

Appendix-B: Monitoring Checklist (Physical and Biological Components) .. 64

Appendix-C: Contract Agreement between DESCO and Siemens India ....... 90

Appendix-D: Environmental Clearance Certificate ..................................... 94

Appendix-E: Laboratory Test Summary Sheet ............................................ 96

Page 9: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

iii

List of Tables

Table 1.1: Twenty Four 33/11kV Substations and Construction Status in DESCO Area

................................................................................................................... 4

Table 1.2: Selected IESCs and Parameters ...................................................... 11

Table 2.1: The Composition of the Main Team .................................................. 14

Table 2.2: The Composition of the Multidisciplinary Field Team ........................... 14

Table 3.1: Test Results of Air Quality Monitoring of DESCO Project Area (Existing) . 20

Table 3.2: Test Results of Air Quality Monitoring of DESCO Project Area (New) ..... 21

Table 3.5: Laboratory Test Summary Sheet for Agragaon .................................. 27

Table 3.6: Laboratory Test Summary Sheet for Mirpur-6 ................................... 28

Table 3.7: Laboratory Test Summary Sheet for ADA ......................................... 29

Table 3.8: Laboratory Test Summary Sheet for Baunia ...................................... 30

Table 3.9: Laboratory Test Summary Sheet for Mirpur DOHS (Augmentation) ...... 31

Table 3.10: Laboratory Test Summary Sheet for Uttar Khan (Promy) .................. 32

Table 3.11: Laboratory Test Summary Sheet for Merul Badda ............................ 34

Table 3.12: Laboratory Test Summary Sheet for Satarkul, Vatara ....................... 35

Table 3.13: Laboratory Test Summary Sheet for Kalshi, Senpara ........................ 36

Table 3.14: Laboratory Test Summary Sheet for Diabari, Uttara ......................... 37

Table 3.15: Laboratory Test Summary Sheet for Swarnali Abason, Barua ............. 38

Table 3.16: Laboratory Test Summary Sheet for Lake City Concord, Khilkhet ....... 39

Table 3.17: Laboratory Test Summary Sheet for Mirpur DOHS-2 ........................ 40

Table 3.18: Laboratory Test Summary Sheet for Swadesh Properties, Satarkul ..... 41

Table 3.19: Laboratory Test Summary Sheet for Tongi-3/Uttara Sector-14 ........... 42

Table 3.20: Laboratory Test Summary Sheet for Tongi-1, BSCIC I/A, Tongi, Gazipur

................................................................................................................. 44

Table 3.21: Laboratory Test Summary Sheet for Tongi-2, Cherag Ali Besides Tongi S

& D Division ................................................................................................ 45

Table 3.22: Laboratory Test Summary Sheet for Tongi BSCIC’S, Near BPDB’s 80 MW

Power Station, Tongi .................................................................................... 46

Table 3.23: Matrix of Monitoring Results ......................................................... 48

Table 3.24: Implementation Plan for Non-Compliance Issues ............................. 49

Table 5.1: Specific Environmental Management Plan (SEMP) .............................. 54

Page 10: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

iv

List of Figures

Figure 1.1: Map of Proposed 24 (Twenty Four) 33/11kV Substations in DESCO Area 3

Figure 3.1: Photographs of Air Quality Monitoring at Different Locations of DESCO

Area .......................................................................................................... 19

Figure 3.2: Summary of Air Quality for Existing Substation areas ........................ 20

Figure 3.3: Summary of Air Quality for New Substation areas............................. 22

Figure 3.4: Sources of dust generation (motor) in during the under construction ... 22

Figure 3.5: Sources of dust generation (stacked chipped stones) in during the under

construction ................................................................................................ 22

Figure 3.6: Sources of dust generation (stacked sand dunes) in during the under

construction ................................................................................................ 22

Figure 3.7: Water Spraysystem to minimize dust during the construction activites at

project sites ................................................................................................ 22

Figure 3.8: Measured Noise Level at Project Sites of DESCO area........................ 23

Figure 3.9: Waste Management and Sanitation system in existing substation area 25

Figure 3.10: Solid waste at Satarkul Project site ............................................... 26

Figure 4.1: Institutional Arrangement of DESCO for Compliance and Monitoring .... 51

Figure A.1: Safety measures and instrument at the substations .......................... 62

Figure A.2: Working environment during project implementation ........................ 62

Figure A.3: Construction activitites at substation sites ....................................... 63

Figure A.4: Monitoring Team on Site with KII ................................................... 63

Page 11: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

v

Unit of Measurement

1 Bigha = 33 Decimals

1 Katha = 1.65 Decimals

1 acre = 0.404686 Hectare

Page 12: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

vi

Page 13: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

vii

Abbreviations and Acronyms

ADB Asian Development Bank

BECA Bangladesh Environmental Conservation Act

BECR Bangladesh Environmental Conservation Rules

BOD Biological Oxygen Demand

BPDB Bangladesh Power Development Board

CAP Corrective Action Plan

CEGIS Center for Environmental and Geographic Information Services

CO Carbon Mono-oxide

DESCO Dhaka Electric Supply Company Limited

DO Dissolved Oxygen

DoE Department of Environment

DOHS Defense Officers Housing Society

DBH Diameter at Breast Height

ECC Environmental Clearance Certificate

ECR Environmental Conservation Rule

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EMR Environmental Monitoring Report

EPC Engineering, Procurement and Construction

ERF Extracting area Rehabilitation Fund

GoB Government of Bangladesh

IEE Initial Environmental Examination

IESCs Important Environmental and Social Components

IUCN International Union for Conservation of Nature

KII Key Informant Interview

NOx Oxides of Nitrogen

Page 14: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

viii

NSO National Survey Organization

PM Particulate Matters

PMU Project Management Unit

SDG Sustainable Development Goal

SOx Oxides of Sulphur

SPM Suspended Particulate Matters

SPS Safeguard Policy Statement

SPT Standard Penetration Test

SSC Site Clearance Certificate

ToR Terms of Reference

Page 15: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

ix

Executive Summary

This is the 4th phase of environmental monitoring commenced on July 2018 and continued

until December 2018 through monthly field visits by the consultant. In this stage, there are

twenty one (22) substations where the construction works are ongoing and this study

covered all these substations. The monitoring team visited and observed all construction

activates and consulted with relevant stakeholders according to the prepared checklist on

physical i.e. air quality, waste management, noise levels and soil quality, ecosystem and

biodiversity i.e. terrestrial vegetation, flora and fauna status at the construction sites applying

both qualitative and quantitative approaches.

Based on the selected parameters of air quality, the results of the air quality were checked

whether it is satisfactory or not regarding the national air quality standard. Besides, how this

construction activities are related with the air quality has been observed through regular field

visit.

The noise levels were measured during day time at different project sites. The recorded

noise levels showed that the minimum levels are at the entrance. The noise readings near

the construction zone were unsteady due to different construction activities. The impact of

this noise level is considered as insignificant as it is more temporary than permament. The

solid waste is maintained by the EPC contractor. The risks for solid waste disposal is very

low as the sites’ waste managements are found to be in satisfactory condition.

During the environmental monitoring, air quality was monitored by an air quality monitoring

machine at the project sites as well as through visual inspection. CEGIS used dust track

aerosol monitor model 8533EP which is an air quality monitoring machine. Based on the air

quality results, air quality were checked to be satisfactory at the project sites, whereas no

external source of air pollution was observed that can deteriorate air quality in the project

areas. During field visit, it was also found that water was sprayed every day to control

fugitive dusts and other particles when earth materials become suspended. The noise levels

were measured during day time at different project sites. Noise showed the minimum level at

and around the project sites. Waste management system, restoration of ecological resources

at different project sites were relatively good.

Most of the cases, compliance status achieved significantly but for the non-compliance

issues several corrective action plans suggested and shared with implementing agency. The

status of non-compliance issues have been addressed in the next phase of environmental

monitoring.

Page 16: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

1

1. Introduction

1.1 Background

1. The Government of Bangladesh (GoB) has set their goal in providing access to

affordable and reliable electricity for all by 2021. In this respect, Bangladesh has scaled

up its priority to strengthen the electricity production, transmission, and distribution for

overall growth and development of the country.

2. Dhaka Electric Supply Company Limited (DESCO) has taken several initiatives to

expand its infrastructure in the distribution system with the construction of the new line,

substations, and renovation of existing substations in order to enhance the electricity

distribution and meeting the increasing demand of Dhaka City North. This project titled:

Augmentation and Rehabilitation of Distribution System in DESCO Area has already

obtained the site clearance certificate (SSC) and environmental clearance certificate

(ECC) from the Department of Environment (DoE) of the GoB. The Siemens India

entrusted as the Engineering, Procurement and Construction (EPC) contractor to

implement this project. In this project, CEGIS is working as environmental consultant to

monitor the compliance status based on Bangladesh National Environmental Policy

Standards, Environmental conservation rules of the Asian Development Bank (ADB) and

loan covenant between the ADB and GoB.

3. In relation to the previous environmental monitorings, this 4th monitoring has been held

(from July 2018 to December 2018) and the compliance status has been checked based

the prepared checklist on physical and biological environment.

4. With the monthly field visit and following the mixed approach this environmental

monitoring has been completed (up to December 2018). The status of non-compliance

issues addressed in this Environmental Monitoring Report (EMR) and provide to upgrade

the status by expert judgement mentioning the Corrective Action Plan (CAP).

1.2 Objectives

1.2.1 Main Objective

5. The main objective of the environmental monitoring is to observe how EMP is being

complied in relation with national and international standard in pre-construction, during

construction and operation and maintenance phase of the project.

1.2.2 Specific Objectives

6. The specific objectives of the environmental monitoring are to:

Analyze the water and air quality in pre-construction and during construction

phases of the Project

Analyze noise in three stages of the Project

Explore land characteristics in the Project sites

Analyze the waste management system of the concerned authority and/ or the

EPC contractor

Page 17: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

2

7. The environmental compliance monitoring would include:

Analyses of Environmental Laws and Policies of Bangladesh

Description of Environmental Management, and Monitoring Plan described in the

Environmental Impact Assessment (EIA) in line with the requirements of ADB

1.3 Project Locations

8. Following Figure 1.1 and Table 1.1 shows the locations of proposed 24 (twenty four)

33/11kV Substations in DESCO area. An A3 size map is shown in the Appendix D. Here,

it is noted that this environmental monitoring consider the construction activities of 21

(twenty one) substation where the construction works are ongoing.

Page 18: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

3

Figure 1.1: Map of Proposed 24 (Twenty Four) 33/11kV Substations in DESCO Area

9. In the EIA report, the substations area and locations were mentioned clearly. But in the

meantime, the DESCO authority has changed/ shifted some of the substation area due

to availability of the land. The final list of the proposed substations area mentioned in the

Table 1.1.

Page 19: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

4

Table 1.1: Twenty Four 33/11kV Substations and Construction Status in DESCO Area

Sl. No.

Name of the substations

Locations Implementation

Status Remarks

1 Kazipara Switching Station

740/B, West Kazipara,Mirpur

(Beside the mosque of west Kazipara Bus station)

Ongoing

Presently, pilling for construction is ongoing which will be finished within the month of December 2018.

2

Mazar Road

Relocated:

Mazar Road shifted to Eastern Housing

Plot: J-82, J-10

Eastern Housing

Mirpur,Dhaka

Ongoing

It is fallow land and suitable for housing and any kind of infrastructure.

Presently, pilling for construction is ongoing which will be finished within the month of December 2018.

3 Kalshi (Shenpara)

Bijoy Rakeen City

Plot: 1/2, Block: D, Section: 15, Mirpur, Dhaka.

Ongoing

Completed the Pilling and Construction Works is ongoing. About 60% work has been completed till December 2018.

4 Mirpur DOHS-2

Road#33, Plot#837, Mirpur 14, Dhaka.

Ongoing

About 90% work has been completed and it will be handed over in the next march-april 2019.

5 Lake City Concord Mouza: Joarsahara, Ward No: 17, Khikhet, Dhaka

Ongoing

The land is not enough that made a complexity to complete this work About 60% work has been completed till December 2018.

6 Uttara Sector 14

Sun Valley Abason, Swadesh Properties Ltd.

Plot#11, Block#E

Road#7, Sector#2

Mauza: Satarkul

Thana: Badda

Ongoing Civil work has already been completed.

7 Satarkul-1

Road# 317,Plot#4, Sect#03,

Dag:1100,1105,1106

United City

Mauza: Satarkul

Thana: Badda

Ongoing Area of Land: 1.0 bigha1.

8 Barua

Plot# 13,Road# 11, Block#A,Sector#1, Swarnali Properties Mauza: Borua,

Thana: Dakshinkhan.

Ongoing

9 Gulshan-03 BRAC university, Merul Ongoing About 75% work has

1 1 bigha = 33 decimals

Page 20: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

5

Sl. No.

Name of the substations

Locations Implementation

Status Remarks

Relocated:

Gulshan-03 shifted to Merul Badda

Badda, Dhaka already been completed. The working progress is good and will be finished within the next April 2019.

10

Basundhara Block G

Relocated:

Basundhara I Block

Bashundhara I block Ongoing

11 Sholahati

Uttara Third Phase (Sector-15, Block-G, Commercial Plot)

Besides Rajuk Apartment Project

Ongoing

12 Mohakhali DOHS Mohakhali DoHs, Dhaka Cantonment, Dhaka

Not started yet

The proposed location is located at Mohakhali DOHS, beside the British American Tobacco industry.

13 Uttarkhan (Promy)

Promy Agro Foods Ltd., Moinertek

Mauza: Gobindapur,

C.S.-305,306. R.S.-538

Ongoing

Area of Land :

22-23 Katha.

About 75% work has already been completed. The working progress is good and will be finished within the next April 2019.

14 Tilargati, Tongi Sataish

S.A.R.S-01, S.A-129, R.S-251, Mauza-Kakil 27, Tilargati, Tongi.

Ongoing

About 60% work has already been completed. The working progress is good and will be finished within the next May to June.

15 Agargaon

Existing 33/11 KV substation

New Colony, Behind BCS Computer City,With Probin Hitoishi Hospital, Opposite to the Agargaon S&D.

Ongoing Almost completed.

16 Mirpur DOHS

Existing 33/11 KV substation

At the end of R#10 , DOHS, Mirpur-12.

Ongoing Civil work has been completed.

17 Mirpur-06

Existing 33/11 KV substation

Near Al-Markajul Mosque & Market of Section-06, Original Mirpur-10.

Ongoing Civil work has been completed.

18 Tongi-01

Existing 33/11 KV substation

BSCIC I/A, Tongi, Gazipur

Ongoing

19 Tongi-2

Existing 33/11 KV substation

Cherag Ali, Beside Tongi S&D Division.

Ongoing

20 Civil Aviation (CAAB)

Left from Jashimuddin, Beside Airport Boundary

Ongoing Civil work has been completed.

Page 21: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

6

Sl. No.

Name of the substations

Locations Implementation

Status Remarks

Existing 33/11 KV substation

& Sector#1)

Kurmitola, Uttara, Dhaka

21 ADA

Existing 33/11 KV substation

Beside Civil Aviation Quarters’, Kaola.

Ongoing Civil work has been completed.

22 Ahsania Mission Not started yet. Will be started soon.

23 Tongi (BSCIC)

Existing 33/11 KV substation

Near BPDB’s 80 MW Power Station, Tongi.

Ongoing About 50% work has already been completed.

24 Baunia (Existing 33/11 Kv substation)

Mouza: Faridabad, Airport, Uttara, Dhaka

Ongoing Civil work has been completed.

Source: PD office, May, 2018.

1.4 Scope of Studies

10. In line with the aforementioned objectives the scope of the services should cover the

following:

i. Monitoring ambient air quality of the project site and its adjoining area before

construction stage;

ii. Review of environmental management and environmental monitoring plan

suggested in the EIA report in line with the action plan proposed by ADB;

iii. Upgrade (if required) the environmental monitoring framework and work plan

specifying the indicators, method, location, time, frequency of monitoring

provided in the EIA that shall be followed by the EPC contractor;

iv. Monthly monitoring of construction activities to see their compliance with national

environmental and social regulations, and ADB’s performance standards on

social and environmental sustainability;

v. Physical observation (monthly) to assess that all mitigation measures are carried

out or in place in conformity with the EMP and action plan;

vi. Monthly monitoring of implementation of environmental monitoring activities as

specified in the environmental monitoring plan;

vii. Monthly monitoring of different activities of EPC contractor regarding analysis of

air quality, water quality, soil texture and quality, soil and land erosion, noise

measurement, waste management, etc. in connection with the environmental

monitoring plan;

viii. Monthly monitoring of socio-economic issues like community safeguard due to

pollution, hazards and employment opportunity;

ix. Suggestion of pollution prevention and mitigation measures to ensure

environmental safeguard, to ensure compliance with national environmental and

social regulations;

Page 22: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

7

x. Keep close liaison with the project implementation office (Project Director), and

EPC contractor;

xi. Provide an interim monitoring report at the end of every three (3) months in line

with the reporting requirement of DESCO/ ADB satisfying equator principles;

xii. Provide a monitoring report at the end of every six (6) months in line with the

reporting requirement of ADB satisfying equator principles.

1.5 Monitoring Law and Policy Standard

11. The Environment Conservation Rules place construction of power plant into the Red

category. The site clearances based on Initial Environmental Examination (IEE) and

Environmental Clearance Certificate have been obtained from the DoE. As per the GoB

policy standard, environmental compliance monitoring is one of the important part need

to be initiated following the Environmental compliance monitoring guidelines by DoE and

the agreement between ADB and GoB (based on the ADB loan covenants). DESCO has

taken initiatives to expand its infrastructure of the distribution system through

construction of new lines, installation of new substations and rehabilitation of existing

substation in order to provide new connections to the incoming consumers. In this

regard, during carrying out the EIA study for the proposed twenty four 33/11kV

Substations, Environmental Management Plan (EMP) was prepared following the

national guidelines of Bangladesh and policies of the ADB. Now, the purpose of the

environmental monitoring is to monitor whether the construction activities are performed

or not considering the EMP prepared in the EIA stage.

Page 23: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

8

1.5.1 Compliance with National Environmental Laws

12. The environmental legislation of GOB gives importance to reduce the negative impacts

of infrastructure development projects, and give priority for the enhancement of positive

impacts due to the project implementation. It conforms the National Environmental Policy

1992 based on the Agenda 21 of Rio Conference and subsequent enactments of the

Bangladesh Environmental Conservation Act (BECA) 1995 and Bangladesh

Environmental Conservation Rules (BECR) 1997.

National Environmental Laws Compliance Requirement Performance of DESCO

Bangladesh Environmental

Conservation Act (BECA) 1995

and Bangladesh Environmental

Conservation Rules (BECR)

1997

The Construction of Twenty

Four 33/11kv Substations in

DESCO Area requires

environmental clearance

certificate (EC)

The environmental clearance (valid for 1 year) for the project was obtained from the DoE on 25.06.15. The processing for renewal is ongoing as per the Government rules.

3 (three) sites under this project have been relocated that require Environmental clearance certificate. The completion of EIA for these relocated sites is in under process.

1.5.2 Bangladesh Government Regulation and Compliance Monitoring

13. The Bangladesh Environment Conservation Act of 1995 (ECA, 1995) is the key

legislation in relation to environment protection in Bangladesh. This Act is promulgated

for environment conservation, standards, development, pollution control, and abatement.

It has repealed the Environment Pollution Control Ordinance of 1977. The Act has been

amended in 2000, 2002, 2007 and 2010.

14. The main objectives of the Act are:

Conservation and improvement of the environment; and

Control and mitigation of pollution of the environment.

15. The main strategies of the Act can be summarized as:

Declaration of ecologically critical areas and restriction on the operations and

processes, which can or cannot be carried/initiated in the ecologically critical

areas;

Regulations in respect of vehicles emitting smoke harmful for the environment;

Environmental clearance;

Regulation of the industries and other development activities’ discharge permits;

Promulgation of standards for quality of air, water, noise and soil for different

areas for different purposes;

Promulgation of a standard limit for discharging and emitting waste; and

Formulation and declaration of environmental guidelines.

Page 24: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

9

16. The ECA, 1995 specified that no industrial unit or project shall be established or

undertaken without obtaining Environmental Clearance from Director General in a

manner prescribed by the Rules. The project promoter must obtain Environmental

Clearance from the Director General of Department of Environment (DoE). An appeal

procedure does exist for those promoters who fail to obtain clearance. Failure to comply

with any part of this Act may result in punishment of imprisonment or fine or both. The

DoE executes the Act under the leadership of the Director General.

17. The Bangladesh Environment Conservation Act (Amendment), 2000 focuses on: (1)

ascertaining responsibility for Compensation in cases of damage to ecosystems, (2)

increased provision of punitive measures both for fines and imprisonment and (3) fixing

authority on cognizance of offences.

18. The Bangladesh Environment Conservation Act (Amendment), 2002 elaborates on:

(1) restriction on polluting automobiles, (2) restriction on the sale and production of

environmentally harmful items like polythene bags, (3) assistance from law enforcement

agencies for environmental actions, (4) break up of punitive measures and (5) authority

to try environmental cases.

19. The Bangladesh Environment Conservation Act (Amendment), 2010 introduces new

rules & restriction on: a) Ensure proper management of hazardous wastes to prevent

environmental pollution and Health Risk, b) No remarked water body cannot be filled

up/changed; in case of national interest; it can be done after getting clearance from the

respective department; and c) Emitter of any activities/incident will be bound to control

emission of environmental pollutants that exceeds the existing emission standards (d)

Government may declare any ecosystem as “Ecologically critical area” if it appears to be

degraded or expected to be degraded and take all precaution measures to protect that

ecosystem. In addition, government shall stop any ongoing activities and will not allow

any new developments in the ecosystem after declaration of “Ecologically Critical Area”.

20. The Bangladesh Environment Conservation Rules, 1997 is the first set of rules,

promulgated under the ECA 95 (so far there have been three amendments to this set of

rules – February and August 2002 and April 2003). The Environment Conservation Rules

of 1997 has provided categorization of industries and projects and identified types of

environmental assessments needed against respective categories of industries or

projects.

21. Among other things, these rules set (i) the National Environmental Quality Standards for

ambient air, various types of water, industrial effluent, emission, noise, vehicular exhaust

etc., (ii) the requirement for and procedures to obtain environmental clearance, and (iii)

the requirement for IEE and EIA’s according to categories of industrial and other

development interventions.

22. The proposed project, according to the DoE, was under the “Red” category according to

the Environmental Conservation Rules, 1997 but recent amendment in 2018 made this

project as orange B category.

23. Noise Pollution (Control) Rules, 2006 gives the authority to all the Union Councils,

Paurasabhas, City Corporations, City Development Authority (i.e. RAJUK, CDA, KDA,

RDA etc.) to mark off the areas under their jurisdiction as silent, residential, mixed,

commercial or industrial. They should also put signs to mark those areas. The act also

describes the approved standard limit of sound in the added schedule 1 and 2. In the

Page 25: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

10

schedule 1, silent area means area up-to a radius of 100 meters around hospitals or

educational institutions or special institutions/ establishments identified/to be identified by

the government. In the silent area, it is prohibited to use any kind of horns of vehicles,

audio signals and loudspeakers. According to this act, daytime is counted from 6am to

9pm whereas night-time is counted from 9pm to 6am.

24. The Motor Vehicle Ordinance, 1983 stated to impose a penalty of maximum two

hundred taka for those vehicles that are emitting smokes that poses health hazard in the

public places. It also restricts the passenger from smoking in public service vehicles and

in any other vehicles with notice of not smoking. This ordinance is enforced occasionally

but a regular enforcement would be helpful to reduce air pollution in big cities including

Dhaka. However, it is to be noted that amount of the penalty is very low which may be

revised as well.

25. The Environment Court Act, 2000 provides for the establishment of environment courts

and matters incidental thereto. This act also provides the jurisdictions of environment

court, penalty for violating court’s order, trial procedure in special magistrate’s court,

power of entry and search, procedure for investigation, procedure and power of

environment court, authority of environment court to inspect, appeal procedure and

formation of environment appeal court.

1.5.3 Compliance with DoE’s Guidelines

26. As mentioned above, the project activities fall under the ‘red’ category according to the

Environment Conservation Rules, 1997. For projects under this category, it is mandatory

to carry out IEE and subsequently EIA including Environmental Management Plan (EMP)

and where necessary develop a Resettlement Plan for getting environmental clearance

from the DoE. The DoE has issued EIA Guidelines for Industries and addresses the IEE

and EIA for several industrial sectors and activities. Each Project Proponent shall

conduct an IEE or EIA and is expected to consult and follow the DoE guidelines. The

provisions of the environment legislations and the EIA guidelines of the DoE have been

reviewed under this study. The DoE has issued application procedure for obtaining

site/environmental clearance.

27. Environmental quality standards for air quality, noise, odour, sewage discharge,

industrial effluents, and industrial project emissions for Bangladesh

28. The Environment Conservation Act, 1995 and the Environment Conservation Rules,

1997 are the main legislative base in Bangladesh for protection and conservation of

natural environment. The Environment Conservation Rules (1997) places activities of

power plant into the Red category during the time of EIA study but the with the

amendment held in 2018 made all substations project as ‘Orange B’ category. In this

study, all compliance addressed regarding the policy standard set during the EIA stage

and monitoring of this project completed following this way.

29. However, the Safeguard Policy Statement (SPS) of the ADB has also been reviewed

since ADB is financing the project in partnership with the GoB. As per the ADB

categorization, the substation construction activities are under the ‘Category B’

considering the significance of the project’s potential environmental impacts. Therefore,

the EMP is prepared based on the combination of both the national and the ADB.

Page 26: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

11

30. The environmental standards are determined in the Environmental Conservation Rules.

The standards for air, water, sound, odour and other components of the environment is

started to monitor in accordance with the standards specified in Schedules - 2, 3, 4, 5, 6,

7 and 8. The Bangladesh standards, in general, are less stringent compared to the

developed countries. This is in view to promote and encourage industrialization in the

country. The Bangladesh standards are not for any specific period of time. There is no

provision for partial compliance too. For this reason, monitoring is based on the national

standards unless there is absence of clear standards; only then ADB’s standard is being

considered.

31. Following IESCs and parameters are selected for monitoring in DESCO’s 24 substation

areas which have presented in Table 1.2.

Table 1.2: Selected IESCs and Parameters

IESCs Parameters

Air Suspended Particulate Maters (SPM), Sulphur dioxide, Carbon Monoxide,

Oxides Nitrogen

Waste Waste generation and proper waste disposal

Noise dBa unit at both day and night time

Water (if any) Dissolved Oxygen (DO), acidity or basity of water (pH), Biochemical oxygen

demand (BOD), Arsenic (As), whether water is usable for irrigation or by fisheries

Biodiversity Habitat conversion and fragmentation

Health & Safety Risk of electrocution, safety measures within the construction site, emergency

plan.

Resettlement livelihood challenges, restoration process, compensation process, whether any

complaints from affected people

32. The results of the monitoring are needed to compare the established benchmarks/

baseline and compliance status and help to identify the areas where adverse

environmental and social adverse impacts are still occurring. It would be helpful to

formulate the corrective actions accordingly and in a timely manner.

1.5.4 ADB Loan Covenants with the DESCO

33. According to the Loan Covenant Article (II), section 2.01, DESCO should carry out the

project, with the due diligence and efficiency and in conformity with sound administrative,

financial, engineering, environmental and power sector practices. For the execution of

project following criteria should be followed.

Implementation arrangement

34. DESCO should ensure the project implementation in accordance with the detailed

arrangements set forth in the PAM. Besides, it is the responsibility of DESCO to ensure

their project management staff who have the qualification to undertake necessary tasks

of procurement, construction, supervision, inspection, and testing of equipment,

payments to contractors, monitoring, environmental and social safeguards due diligence

and reporting of progress relevant to the components under their responsibility.

Page 27: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

12

Environment

35. DESCO should ensure that the preparation, design, construction, implementation,

operation, and decommissioning of the project and all project facilities comply with;

All applicable laws and regulations of the relating to environment, health and

safety

The environmental safeguard (i.e. Air quality, noise quality, soil quality and waste

management, and conservation of ecological resources)

All measures and requirements set forth in the respective IEE and EMP and any

corrective or preventive actions set forth in a safeguard monitoring report

Project Reviews

The project progress would be reviewed by the ADB with necessary midcourse

corrections

The Assistance should be provided by the Executing Agency (i.e. DESCO).

36. The environmental monitoring will assess the compliance that has been suggested under

the Bangladesh Govt. laws, policies and national standards (i.e. air, noise and water

quality) and ADB loan covenants. As there is no involuntary resettlement and ethnic

minority issues, therefore, this monitoring assess the environmental issues in

accordance with the GoB laws and ADB loan covenants like the above mentioned ways.

Page 28: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Introduction

13

Page 29: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

14

2. Approach and Methodology

2.1 Overall Approach

37. The objective of the Environmental Compliance Monitoring is to identify environmental

issues following the compliance regarding the EMP, National Environmental Acts, Laws

and Policy, ADB’s Environmental Standard and terms of Bangladesh and ADB loan

covenants. During this environmental monitoring, mixed approach has been followed and

collected both quantitative and qualitative data to understand the compliance status of

physical and biological environment regarding the project implementation.

2.2 Study Mobilization

38. Based on a comprehensive checklist this study has been mobilized and consider the

compliance status due to the project implementation. A multidisciplinary team having

with relevant expertise has been selected to conduct this study.

2.3 Study Team Mobilization

39. In line with the previous environmental monitoring, the study team has been mobilized to

conduct the 4th environmental monitoring. A group of highly skilled professionals

mobilized for conducting field observation and collecting both quantitative and qualitative

data. Initiatives have been taken for accomplishment of the study within the expected

time-frame based on the formulated action plan.

40. The consultant (CEGIS) continued the whole works through overall supervision of the

Project Director, and close liaison with DESCO offices (both field and central offices).

Besides, the team Leader supervised and visited the study area to complete the study

based on the study objectives. The progress of the study was reviewed in weekly

progress review meeting. Each report and deliverable was reviewed carefully by the

team members and Team Leader and finally, checked by technical and linguistic editors.

Table 2.1: The Composition of the Main Team

Sl. No. Name of Professional Position Assigned

1 Engr. Jalal Ahmed Chawdhury Environmental Expert/ Transmission Line/ Power Plant Expert

2 Dr. Dilruba Ahmed Sociologist

3 Subrata Kumar Mondal Economist

41. As per commitment the following multidisciplinary team was mobilized for collecting data

from the field.

Table 2.2: The Composition of the Multidisciplinary Field Team

Sl. No. Name of Professional Position Assigned

1 Amith Dutta Anthropologist

2 Rifat Jahan Sadia Water Resource Engineer

3 Tanvir Ahmed Ecologist

Page 30: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

15

2.4 Methodology

2.4.1 Physical Environment

Ambient Air Quality

42. Air quality is an indicator of purity of air for respiration process of human being plants,

and animals. Poor air quality can affect human health and deteriorate surrounding

environment. Air quality was monitored by an air quality monitoring machine at the

project sites as well as through visual inspection as potential pollution sources were from

external air contamination. CEGIS used dust track aerosol monitor model 8533EP which

is an air quality monitoring machine. This is a desktop model with external pump. This

machine is used for outdoor monitoring applications and it can measures mass

concentration such as dust, smoke, fumes and mist. It was applied for fugitive emissions

monitoring. This Dust track monitor is continuous, real time, laser photometer that

measures mass fraction concentrations to PM1, PM2.5, PM10 and other particles that can

be respired. The value is expressed in µg/m3.

43. The machine was calibrated before starting sampling at each time. Clean brush and

isopropyl alcohol was used to clean out side, inside and imp actor plate. Then dry in air

thoroughly and applied 2 drops oil to the imp actor plate. Then pressed Run mode for

sampling mode options. Log mode starts and stops the instrument at specified time, run

for a specified test length, and performs multiple tests of the same length with a specified

time period between tests. The air quality monitoring results are not only been presented

but also have been compared with the national standards.

Noise level

44. Noise level is an important parameter as excessive noise may create disturbance to local

communities, ecosystem and workers at worksite due to project activities. Short-term

noise exposure can be overcome with rest, but if exposure is sustained, it may result in

irreversible long-term damage. Hearing loss in the workplace can lead to safety risks if

workers are unable to hear alarms or critical communications from other workers. Noise

level was perceived from individual acoustics of monitoring team. Noise monitoring is

important for any big construction activity as excessive noise may create disturbance to

the wild life, indigenous species, fragile ecosystems, communal stability in case of

sudden intrusion and workers due to construction activities and subsequent increased

traffic movement.

45. Hence, ambient noise level has been monitored monthly at nearby sensitive receptors

around the construction site (including substation site) of this project. Each time, noise

level has been recorded using portable noise level meter for a 2 (two) minutes time span

at 5 (five) minutes interval depending on the site condition. Noise level has been

recorded at day time only as the construction works held only at daylight hours. A

probable increase in noise level in the same area may provide the tools for assessment

of impact on environment.

Waste Management

46. Infrastructure work for any development, usually generate variable quantities and types

of waste materials which have the potential to cause adverse environmental impacts

during generation, storage, transport and disposal. For this reason, the project aims to

Page 31: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

16

implement waste management procedures immediately after the commencement of the

civil works in order to maintain minimal potential impacts to the environment. The project

sites were observed visually during sites visit to investigate concerns related to waste

disposal.

Soil Quality

47. Sub-soil investigation is very important for proper planning and designing of the structure

which confirm the safety and stability of the structure. Thus, National Survey

Organization has been performed the sub-soil investigation for the construction of

proposed design, supply installation and commissioning of 24 nos. 33/11kV substations.

National Survey Organization (NSO) has executed Standard Penetration Test (SPT),

different field and laboratory tests for investigation of sub-soil. They have evaluated

bearing capacity of soils at different layers. A number of bore holes have been drilled at

particular depths depending on the project sites. We have been reviewed and

incorporated the sub-soil investigation report’s data for understanding the soil condition

of the project sites which are provided by Siemens Bangladesh Ltd.

2.4.2 Biological Environment

48. Different biological indicators have been monitored both through monthly physical

observations and public discussions at the under constructed substation sites. An

ecologist have visited the substation sites and collected the information on vegetation

clearance, plantations, wildlife disturbance, and bird habitat status using a formatted

checklist. Public discussions have been performed mainly through application of Key

Informant Interview (KII). The substation staff, labours and respective officers were

considered as the key informants.

Terrestrial Vegetation

49. Vegetation clearance has been ensured through visual observation of the green

coverage and denuded areas of the construction sites and thus compared in different

monitoring tiers. Status of plantations and the species composition of planted areas also

confirmed through physical observations.

Flora and Fauna

50. Information on wildlife disturbance due to excess lighting, movement path blocking has

been observed by direct observations and through KII with substations officials and

construction workers. Bird nesting and roosting habitat also sighted during field

inspection at the constructed sites and detect the changes by comparing the status in

different regular monitoring visits.

Page 32: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

17

Page 33: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

18

3. Monitoring Results

3.1 Introduction

51. For the commencement of the project implementation, Dhaka Electric Supply Company

Limited (DESCO) has made a Contract Agreement with Siemens India in consortium

with the Siemens Bangladesh to Design, Supply, and Install & Commission 24 (twenty

four) 33/11kV Substations in Turnkey Basis in DESCO area under the Dhaka and

Gazipur districts against Bid No. IFB 01/2016, Package-C1 of Lot-3 under ADB Loan

No.: 3087- BAN: under “Power System Expansion and Efficiency Improvement

Investment Program” (Trench 2). After getting the Topographical Survey report they have

started their construction. Presently, there are twenty two (22) substations where the

construction work is ongoing. The environmental monitoring (4th phase) has been

completed based on the construction activities of these substations and impact due to

the project implementation. All activities 2 related to the construction observed and

findings of social safeguard monitoring compiled following the ADB social safeguard

policy and ADB –Bangladesh loan covenants.

3.2 Physical Environment

3.2.1 Ambient Air Quality

52. Ambient air quality data at the project site were measured to ascertain the current quality

of air. The aim was to develop the baseline air quality data and to compare the same with

the air quality data during project activities to check if there is any high air pollution

developed due to the construction activities and to design adequate mitigation measures,

as applicable. In summer the heavy shower cleans the air to a great extant, but in winter

the pollutant level particularly PM levels increase to a great extant.

53. Dispersal of these pollutants greatly depends upon factors like prevailing wind direction

and other weather conditions, atmospheric stability, height of the source. CEGIS used dust

track aerosol monitor model 8533EP which is an air quality monitoring machine to conduct

air quality test in the project sites. The test was carried out for 1 hour at and around the

project sites (Figure 3.1) from 20 November to 10 December 2018.

54. This Dust track monitor is continuous, real time, laser photometer that measures mass

fraction concentrations to.The parameters were PM1, PM2.5, PM10 and other particles that

can be respired. The weather was mostly sunny during the test period. The average values

of ambient air quality result has been shown in Table 3.1 and Table 3.2. The air quality

analysis of Ahsania Mission Cancer Hospital and Mohakhali DOHS area are in progress

and will be presented in the next report.

2 Piling, Electrical Works (i.e. Earth work),Transformer Foundation, RCC Works, Fellow Casting

Page 34: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

19

Figure 3.1: Photographs of Air Quality Monitoring at Different Locations of DESCO Area

Existing Substation

55. From the monitoring Test Results (Table 3.1 and Figure 3.2) of Air Quality Monitoring at

DESCO project areas, we have found that the concentration of PM2.5 area is higher than

the Bangladesh standard limit. On the other hand, concentration of PM10 have found within

the Bangladesh standard limit except at Kazipara Switching Station which is 191 µg/m3.

56. The air pollution levels have been compared with the Bangladesh Ambient Air Quality

Standard as adopted in 2005. During field visit, no significant internal and external sources

of air pollution was observed in the project sites that would deteriorate air quality. The

overall air condition of Dhaka city is comparatively polluted for which the air qualities of the

adjacent project sites are deteriorated.

Page 35: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

20

Figure 3.2: Summary of Air Quality for Existing Substation areas

Table 3.1: Test Results of Air Quality Monitoring of DESCO Project Area (Existing)

Sl No.

Project Site Name

Concentration Present of DESCO project area (Existing Substation Area)

PM1 (µg/m3) PM2.5

(µg/m3)

PM10

(µg/m3)

Respirable

(µg/m3)

1 Civil Aviation (CAAB) 101 104 110 105

2 DOHS Mirpur 104 102 107 105

3 Mirpur-6 179 180 114 118

4 Agargaon-2 107 110 110 107

5 Baunia 104 109 150 112

6 Tongi (BSCIC) 113 114 123 115

7 ADA 84 88 143 95

8 Tongi-2 104 103 112 106

9 Kazipara Switching Station 154 156 191 161

Bangladesh Standard** ( For 24 hrs)

- 65 150 -

IFC/World Bank Standard ( For 24 hrs)

- 75 150 -

Monitoring Result of CEGIS at Project sites, November- December 2018

** The Bangladesh National Ambient Air Quality Standards have been taken from the Environmental

Conservation Rules, 1997 which was amended on 19thJuly 2005 vide S.R.O. No. 220-Law/2005

New Substation

57. The data presented in this report are based on monitoring results (Table 3.2 and

Figure 3.3) of air quality parameters during the month of November-December, 2018. The data

shows that specific PM2.5 pollutant cross their standards of National Ambient Air Quality limit.

0

50

100

150

200

250

Co

nce

ntr

atio

n (

µg/

m3

)

Project Sites

PM1 PM2.5 PM10 Respirable

Page 36: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

21

On the other hand, inspection of the available data shows that concentration level of PM10

within the Bangladesh standard limit except Tilagati, Tongi Sataish, Kalshi, Merul Badda and

Uttar Khan and the concentrations of these sites are 208 µg/m3 , 222 µg/m3, 215 µg/m3 and

176 µg/m3 accordingly. Due to vehicular movements, heavy construction machineries, digging

of the earth and loose earth materials (e.g. soil, sand), some dust particles were observed in

the project area which is negligible.

58. During field visit it was also found that the EPC contractor is regularly spraying water in

the construction site to maintain the air quality within the standard and no significant internal

and external sources of air pollution was observed in the project sites that would deteriorate air

quality. However, the constructional activities do not cause air pollution of the project sites.

The overall air condition of Dhaka city is comparatively polluted for which the air qualities of

the adjacent project sites are deteriorated. The air quality data of Ahsania Mission Cancer

Hospital and Mohakhali DOHS will be included in the next report as the sites works are in

progress in the project sites.

Table 3.2: Test Results of Air Quality Monitoring of DESCO Project Area (New)

Sl No.

Project Site Name

Concentration Present of DESCO project area (New Substation Area)

PM1 (µg/m3) PM2.5

(µg/m3)

PM10

(µg/m3)

Respirable

(µg/m3)

1 Tilagati Tongi Shataish 188 190 208 192

2 Tongi-1 103 104 112 105

3 Bashundhara Block 108 108 116 109

4 Mirpur DOHS-2 72 73 79 74

5 Kalshi 179 183 222 186

6 Merul Badda 199 201 215 204

7 Eastern Housing 115 109 118 112

8 Lake City Concord 70 74 103 78

9 Satarkul 1 122 122 132 124

10 Uttarakhan 84 85 106 87

11 Barua 107 110 176 116

12 Sholahati, Diabari 79 81 89 83

13 Uttara-14 107 110 124 113

Bangladesh Standard** ( For 24 hrs)

- 65 150 -

IFC/World Bank Standard ( For 24 hrs)

- 75 150 -

Monitoring Result of CEGIS at Project sites, November- December 2018

Page 37: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

22

Figure 3.3: Summary of Air Quality for New Substation areas

Figure 3.4: Sources of dust generation (motor) in during the under construction

Figure 3.5: Sources of dust generation (stacked chipped stones) in during the

under construction

Figure 3.6: Sources of dust generation (stacked sand dunes) in during the under

construction

Figure 3.7: Water Spraysystem to minimize dust during the construction

activites at project sites

050

100150200250

Co

nce

ntr

atio

n (

µg/

m3

)

Project Sites

PM1 PM2.5 PM10 Respirable

Page 38: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

23

3.2.2 Noise Level

59. The noise levels were measured during day time at different project sites. Noise

showed the minimum level at the entrance. On the contrary, the noise reading near the

construction zone was un-steady due to different construction activities. Most of these

activities are limited to day time only. The impact of this noise level is considered as

insignificant as it is temporary.

60. During this visit, it was noticed that most of the workers were not comfortable in using

earmuffs. The contractors were suggested to provide earmuffs to all workers. The labours are

exposed approximately eight hours per day to the loud noise which can cause acute damage

to their hearing system, leading to hearing loss.

61. Though the project sites are within developing residential area where no considerable

human settlement around the project site has yet been set up that could be affected by noise

pollution.

62. Vehicular movements around the project sites were relatively moderate. Hence, noise

generation from external sources was insignificant. The average noise level of the project sites

are shown in the Table 3.3 below and Table 3.4 along with the standards of noise levels for

different zones of Bangladesh.

Figure 3.8: Measured Noise Level at Project Sites of DESCO area

Table 3.3: The measured average noise level of the project sites during the field visit

Sl.

No. Name of the substations

Average Noise

Level (dB) Sub Station Type

1 Civil Aviation (CAAB) 48 Existing

2 DOHS Mirpur 46 Existing

3 Mirpur-6 50 Existing

4 Agargaon-2 47 Existing

5 Baunia 49 Existing

6 Tilagati,Tongi Sataish 57 New

7 Tongi (BSCIC) 56 Existing

Page 39: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

24

Sl.

No. Name of the substations

Average Noise

Level (dB) Sub Station Type

8 Tongi-1 63 New

9 ADA 48 Existing

10 Tongi-2 58 Existing

11 Bashundhora I Block 50 New

12 Mirpur DOHS-2 45 New

13 Kazipara Sitching Station 47 Existing

14 Kalshi (Shenapara)(Rakeen City) 49 New

15 Merul Badda 49 New

16 Eastern Housing 43 New

17 Lake City Concord 48 New

18 Satarkul-1 46 New

19 Uttarakhan 48 New

20 Barua 43 New

21 Sholahati,Diabari 46 New

22 Uttara-14 49 New

Table 3.4: Standards of noise levels for different zones of Bangladesh

Serial No.

Category of areas

Standards determined at dBa unit

Day Night

1 Silent zone 45 35

2 Residential area 50 40

3 Mixed area (mainly residential area, simultaneously used for commercial and industrial purposes)

60 50

4 Commercial area 70 60

5 Industrial area 75 70

Source: E.C.R. ’97

During the field visit, the measured average noise level of the project sites (Table 3.3) shows that the average

noise level are within noise levels for different zones of Bangladesh

3.2.3 Waste Management and Sanitation System

Existing Substation

63. Waste management system at project sites was relatively good. Most of the sites were

good in terms of prevalent solid wastes. Dustbins were present at the project areas for

cooking and other organic disposals. There were separate arrangements of sanitation

facilities for officials and daily workers in the project sites.

64. There overall scenario of the Civil Aviation (CAAB), DOHS Mirpur, Mirpur-6, Agargaon-2,

Baunia, Tongi (BSCIC), ADA, Tongi-2, and Kazipara Switching Station were same. No

form of water stagnation was observed during the monitoring period within the project

side.

Page 40: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

25

Figure 3.9: Waste Management and Sanitation system in existing substation area

New Substation

65. Waste management system at project sites was relatively good. Most of the sites were

good in terms of prevalent solid wastes dustbins were presented at the project areas for

cooking and other organic disposals. But at Satarkul area, the dustbins were present but

it is not use properly. Otherwise, the overall scenario where same. The workers should

be more encouraged and guided properly to use dustbins as they show less interest to

use them properly. It has been advised accordingly to improve the waste management

system.

66. There were separate arrangements of sanitation facilities for officials and daily workers in

the project sites. No form of water stagnation was observed during the monitoring period

within the project sites.

Page 41: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

26

Figure 3.10: Dustbin used for waste management at Uttara Sector 14

3.2.4 Soil Quality

67. Soil is an important component of environment management as well as proper planning

and designing of the structure. We have been reviewed and incorporated the sub-soil

investigation report’s data for understanding the soil condition of the project sites which

are provided by Siemens Bangladesh Ltd. in the following section.

Page 42: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

27

Table 3.5: Laboratory Test Summary Sheet for Agragaon

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D7 D6 D8 D12 UD-1 D2 D3 D7 D8 D9 D11

Depth (ft.) 8 10 15 35 30 40 60 8 10 15 35 40 45 55

Natural moisture content 25 26

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 20 57 62 12 51 53

Fines<0.075 mm 80 43 38 88 49 47

Unconfined

Compression

Test

qu,UD, (Psi) 25.75 24.55

Strain (%) 6.50 6.50

Wrt Density, pcf 119.25 119.45

Dry Density, pcf 95.75 95.85

Atterbarg limit

Liquid Limit 49 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear

Test

Ø (Degree) 30.30 31.75 32.10 30.25 31.50 32.15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index, Cc 0.1090 0.1092

Initial Void Ratio

e0 0.3473 0.3470

Page 43: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

28

Table 3.6: Laboratory Test Summary Sheet for Mirpur-6

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D6 D7 D8 D9 D11 UD-1 D2 D5 D8 D9 D10 D12

Depth (ft.) 8 10 30 35 40 45 55 8 10 25 40 45 50 60

Natural moisture content 28 27

Specific gravity 266 269

Particle Size

Gravel

Sand 14 54 52 10 55 54

Fines<0.075 mm 86 46 48 90 45 46

Unconfined

Compression Test

qu, UD, (Psi) 19.95

Strain (%) 6.50

Wrt Density, pcf 118.75

Dry Density, pcf 95.50

Atterbarg limit

Liquid Limit 48 47

Plastic Limit 25 24

Plasticity index 23 23

Direct Shear Test Ø (Degree) 30.28 31.25 33.50 31.25 31.75 32.55

C (tsf) 0 0 0 0 0 0

Consolidation Test Comp. Index, Cc 0.1088 0.1090

Initial Void Ratio e0 0.3469 0.3471

Page 44: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

29

Table 3.7: Laboratory Test Summary Sheet for ADA

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D7 D6 D8 D12 UD-1 D2 D3 D7 D8 D9 D11

Depth (ft.) 8 10 15 35 30 40 60 8 10 15 35 40 45 55

Natural moisture content 25 26

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 20 57 62 12 51 53

Fines<0.075 mm 80 43 38 88 49 47

Unconfined

Compression

Test

qu, UD, (Psi) 25.75 24.55

Strain (%) 6.50 6.50

Wrt Density, pcf 119.25 119.45

Dry Density, pcf 95.75 95.85

Atterbarg limit

Liquid Limit 49 47

Plastic Limit 25 25

Plasticity index 25 22

Direct Shear

Test

Ø (Degree) 30.30 31.75 32.10 30.25 31.50 32.15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index, Cc 0.1090 0.1092

Initial Void Ratio

e0 0.3472 0.3471

Page 45: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

30

Table 3.8: Laboratory Test Summary Sheet for Baunia

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D6 D7 D8 D13

UD-1 D2 D3 D7 D8 D9 D12

Depth (ft.) 12 10 15 30 35 40 65 12 10 15 35 40 45 60

Natural moisture content 28 27

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 16 52 56 12 51 53

Fines<0.075 mm 84 48 44 88 49 47

Unconfined

Compression

Test

qu, UD, (Psi) 21.25 20.85

Strain (%) 6.50 6.50

Wrt Density, pcf 119.25 119.45

Dry Density, pcf 95.75 95.85

Atterbarg limit

Liquid Limit 48 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear

Test

Ø (Degree) 30.45 31.85 32.25 30.25 31.50 32.15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index, Cc 0.3492 0.3489

Initial Void Ratio e0 0.1073 0.1070

Page 46: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

31

Table 3.9: Laboratory Test Summary Sheet for Mirpur DOHS (Augmentation)

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D6 D6 D7 D12 UD-1 D3 D7 D7 D8 D11

Depth (ft.) 8 10 15 30 30 35 60 8 15 35 35 40 55

Natural moisture content 26 27

Specific gravity

Particle Size

Gravel

Sand 13 19 56 18 17 52

Fines<0.075 mm 87 81 44 82 83 48

Unconfined

Compression Test

qu, UD, (Psi) 25.75 24.55

Strain (%) 6.50 6.50

Wrt Density, pcf 119.25 119.45

Dry Density, pcf 95.75 95.85

Atterbarg limit

Liquid Limit 49 48

Plastic Limit 25 25

Plasticity index 24 23

Direct Shear Test Ø (Degree) 30.25 31.30 30.45 31.55

C (tsf) 0 0 0

Consolidation Test Comp. Index, Cc 0.1091 0.1089

Initial Void Ratio e0 0.3471 0.3470

Page 47: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

32

Table 3.10: Laboratory Test Summary Sheet for Uttar Khan (Promy)

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D3

D7

D8

D18

UD

-1

D3

D8

D10

D12

UD

-1

D2

D10

D12

D18

UD

-1

D3

D9

D10

D17

UD

-1

D2

D13

D19

Depth (ft.)

8

15

35

40

90

8

15

40

50

60

8

10

50

60

90

8

15

45

50

85

8

10

65

95

Natural moisture content

28

27

28

27

27

Specific gravity

2.6

56

2.6

90

2.6

90

2.6

66

2.6

65

Particle Size

Gravel

Sand

16

20

57

11

51

53

14

51

54

18

52

56

14

51

57

Fines<0.075 mm

84

80

43

89

49

47

86

49

46

82

48

44

86

49

43

Unconfined

Compression

Test

qu, UD, (Psi)

21.1

5

19.7

5

20.3

5

21.6

5

20.9

5

Strain (%)

6.5

0

6.5

0

6.5

0

6.5

0

6.5

0

Wrt Density, pcf

119.2

5

118.7

5

119.5

0

119.2

5

119.6

5

Dry Density, pcf

95.7

5

46

95.5

0

95.6

5

95.7

5

69.2

5

Page 48: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

33

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D3

D7

D8

D18

UD

-1

D3

D8

D10

D12

UD

-1

D2

D10

D12

D18

UD

-1

D3

D9

D10

D17

UD

-1

D2

D13

D19

Atterbarg limit

Liquid Limit 24

48

47

46

48

Plastic Limit

22

25

25

24

25

Plasticity index

23

22

22

23

Direct Shear Test Ø (Degree)

30.8

8

31.2

5

33.5

0

31.1

5

30.5

31.2

5

C (tsf) 0

0

0

0

0

0

Consolidation

Test

Comp. Index, Cc

0.3

470

0.3

471

0.3

473

0.3

469

0.3

474

Initial Void Ratio

e0

0.1

088

0.1

089

0.1

09

0.1

092

0.1

091

Page 49: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

34

Table 3.11: Laboratory Test Summary Sheet for Merul Badda B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compressio

n Test

Consolidatio

n Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex

(Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-03 4.50 1944.25 1518.21 30 34 20 14 0.30 7.40 0.14 0.730 27 73 2.62

D-09 13.50 26 NP NP NP 37.49 0 80 20 2.68

2 D-03 4.50 1938.12 1510.50 27 39 23 16 0.98 8 0.19 0.775 39 61 2.64

D-09 13.50 25 NP NP NP 40.24 0 89 11 2.70

3 D-03 4.50 1940.75 1512.10 28 38 2 15 0.90 7.80 0.18 0.760 38 62 2.63

D-09 13.50 27 NP NP NP 39.89 0 85 15 2.69

4 D-03 4.50 1938.20 1510.27 27 39 24 15 0.93 7.90 0.18 0.765 40 60 2.64

D-09 13.50 26 NP NP NP 38.73 0 83 17 2.68

5 D-03 4.50 1941.24 1515.15 29 37 21 16 0.88 7.70 0.16 0.750 37 63 2.63

D-09 13.50 27 NP NP NP 41.97 0 92 8 2.70

Page 50: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

35

Table 3.12: Laboratory Test Summary Sheet for Satarkul, Vatara B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex

(Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-10 15 28 NP NP NP 40 35 25 2.63

D-14 21 26 NP NP NP 40.12 0 87 13 2.68

2 D-10 15 27 NP NP NP 43 32 25 2.64

D-14 21 26 NP NP NP 40.24 0 88 12 2.69

3 D-10 15 28 NP NP NP 41 30 29 2.62

D-14 21 25 NP NP NP 41.50 0 90 10 2.70

4 D-11 16.50 26 NP NP NP 45 35 20 2.65

D-14 21 24 NP NP NP 41.75 0 92 8 2.70

5 D-11 16.50 28 NP NP NP 399 33 28 2.62

D-14 21 25 NP NP NP 40..49 0 89 11 2.69

6 D-11 16.50 27 NP NP NP 41 32 27 2.63

D-14 21 24 NP NP NP 40.89 0 90 10 2.69

Page 51: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

36

Table 3.13: Laboratory Test Summary Sheet for Kalshi, Senpara B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear

Test

Direct

Shear Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-03 7.50 1944.70 1518.60 31 35 20 15 0.50 7.50 0.14 0.735 29 71 2.62

D-09 12 27 NP NP NP 40.89 0 83 17 2.69

2 D-03 7.50 1516.15 30 36 20 16 0.60 8 0.16 0.745 34 66 2.63

D-09 12 27 NP NP NP 40.73 0 81 19 2..68

3 D-03 9 1943 31 36 21 15 0.48 7.45 0.15 0.730

D-09 13.50 26 NP NP NP 40.97 0 85 15 2.69

4 D-03 9 1942.19 30 25 21 14 0.45 7.40 0.14 0.725 29 71 2.63

D-09 13.50 28 NP NP NP 39.73 0 80 20 2.68

5 D-03 9 1940.12 28 37 22 15 0.62 8.20 0.16 0.750 35 65 2.64

D-09 13.50 26 NP NP NP 39.50 0 78 22 2.68

Page 52: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

37

Table 3.14: Laboratory Test Summary Sheet for Diabari, Uttara B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-02 3 1938.60 1513.35 28 37 22 15 0.85 8 0.19 0.760 35 65 2.64

D-20 30 27 16.22 0.60 82 18 2.66

2 D-02 3 1942.47 1517.30 30 35 20 15 0.48 7.50 0.14 0.725 28 72 2.62

D-20 30 27

3 D-02 3 1941.70 1516.75 29 36 20 16 0.60 7.70 0.16 0.750 30 70 2.63

D-20 30 28 14.14 0.46 75 25 2.65

4 D-02 3 1940.25 1515.15 29 37 21 16 0.72 7.90 0.18 0.765 32 68 2.64

D-20 30 26 17.25 0.68 85 15 2.67

5 D-02 3 1939.10 1514.50 28 37 22 15 0.89 8.10 0.20 0.780 38 62 2.65

D-21 31.50 25 NP NP NP 41.89 0 90 10 2.69

Page 53: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

38

Table 3.15: Laboratory Test Summary Sheet for Swarnali Abason, Barua B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct

Shear Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-10 15 27 NP NP NP 29 31 40 2.63

D-16 24 25 NP NP NP 41.50 0 93 7 2.70

2 D-10 15 28 NP NP NP 25 30 45 2.62

D-16 24 26 NP NP NP 40.49 0 90 10 2.68

3 D-10 15 27 NP NP NP 24 29 47 2.62

D-16 24 25 NP NP NP 40.73 0 91 9 2.69

4 D-10 15 31 NP NP NP 24 27 49 2.61

D-16 24 25 NP NP NP 39.50 0 89 11 2.68

5 D-10 15 30 NP NP NP 26 30 44 2.62

D-16 24 26 NP NP NP 39.12 0 88 12 2.68

6 D-10 15 33 NP NP NP 22 35 43 2.61

D-16 24 25 NP NP NP 40.24 0 90 10 2.69

Page 54: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

39

Table 3.16: Laboratory Test Summary Sheet for Lake City Concord, Khilkhet B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression Test

Consolidation

Test

Triaxial

Shear Test

Direct

Shear Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-04 6 29 NP NP NP 28 30 42 2.62

D-08 12 28 NP NP NP 36.89 0 81 19 2.68

2 D-04 6 30 NP NP NP 25 31 44 2.62

D-08 12 27 NP NP NP 37.73 0 83 17 2.69

3 D-04 6 32 NP NP NP 22 29 49 2.61

D-08 12 27 NP NP NP 37.97 0 85 15 2.69

4 D-04 6 32 NP NP NP 20 28 52 2.61

D-08 12 28 NP NP NP 37.49 0 82 18 2.68

5 D-04 6 28 NP NP NP 20 33 47 2.63

D-08 12 25 NP NP NP 40.85 0 90 10 2.70

6 D-04 6 29 NP NP NP 21 35 44 2.62

D-08 12 26 NP NP NP 39.90 0 88 12 2.69

Page 55: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

40

Table 3.17: Laboratory Test Summary Sheet for Mirpur DOHS-2 B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht (k

g/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-02 3 1939.40 15114.60 26 39 24 15 1.20 8.50 0.24 0.800 38 62 2.64

D-14 21 24 NP NP NP 32.25 1.47 35 65 2.69

2 D-02 3 1938.50 1510.30 25 40 24 16 1.35 8.80 0.26 0.815 40 60 2.65

D-16 24 24 NP NP NP 31.30 1.40 30 70 2.68

3 D-02 3 1940.10 1514.90 27 38 23 15 1.15 8.60 0.25 0.810 37 63 2.36

D-16 24 25 NP NP NP 31.62 1.38 32 68 2.68

4 D-02 3 1941.25 1515.21 28 37 22 15 0.95 8.10 0.225 0.780 35 65 2.62

D-16 24 26 NP NP NP 32.56 1.51 38 62 2.70

5 D-02 3 1940.75 1514.65 27 37 21 16 1 8.20 0.23 0.790 36 64 2.63

D-16 24 26 NP NP NP 32.10 1.40 34 66 2.69

6 D-02 3 1939.20 1513.45 28 38 23 15 1.08 8.30 0.23 0.785 37 63 2.63

D-16 24 26 NP NP NP 31.94 1.33 30 70 2.68

Page 56: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

41

Table 3.18: Laboratory Test Summary Sheet for Swadesh Properties, Satarkul B

ore

Hole

Sam

ple

No.

Depth

(ft.)

Wet

Unit W

eig

ht (k

g/m

3 )

Dry

Unit W

eig

ht

(kg/m

3 )

Natu

ral M

ois

ture

conte

nt (%

)

Liq

uid

Lim

it (

%)

Pla

stic L

imit (

%)

Pla

sticity In

dex (

%)

Unconfined

Compression

Test

Consolidation

Test

Triaxial

Shear Test

Direct Shear

Test Grain Size Test

Str

en

gth

(kg/m

3 )

Str

ain

at

failu

re (

%)

Com

pre

ssio

n I

ndex (

Cc)

Void

(e0)

Ø0

Cohesio

n (

kg/m

3 )

0

Ø0

Cohesio

n (

kg/m

3 )

0

San

d (

%)

Silt

(%

)

Cla

y (

%)

S.P

. G

ravity

1 D-05 7.50 1940.47 1515.11 30 36 21 15 0.80 8 0.19 0.785 32 68 2.63

D-10 15 28 NP NP NP 31.42 0 30 70 2.68

2 D-05 7.50 1939.97 1514.45 30 35 20 16 0.82 8.10 0.19 0.790 35 65 2.64

D-10 15 NP NP NP 35.73 0 41 59 2.69

3 D-05 7.50 1942.19 1518.13 32 34 20 14 0.50 7.50 0.15 0.745 28 72 2.62

D-10 27 NP NP NP 34.97 0 36 64 2.68

4 D-06 9 1941.21 1517.75 31 35 21 14 0.60 7.70 0.16 0.750 30 70 2.63

D-10 15 28 NP NP NP 34.45 0 34 66 2.68

5 D-05 7.50 1944.15 1521.15 33 34 19 15 0.35 7.40 0.14 0.730 25 75 2.62

D-9 13.50 28 NP NP NP 35.97 0 30 70 2.68

6 D-05 7.50 1944.80 1521.78 33 33 18 15 0.37 7.50 0.14 0.735 20 80 2.62

D-10 15 27 NP NP NP 30.73 0 26 74 2.68

7 D-06 9 1939.15 1515.15 30 37 22 15 0.70 8 0.19 0.790 31 69 2.63

D-24 36 27 NP NP NP 41.89 0 90 10 2.70

Page 57: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

42

Table 3.19: Laboratory Test Summary Sheet for Tongi-3/Uttara Sector-14

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D2

D6

D5

D11

UD

-1

D2

D5

D7

D12

UD

-1

D2

D4

D6

D12

UD

-1

D3

D6

D7

D12

UD

-1

D3

D7

D7

D12

Depth (ft.)

8

10

30

25

55

8

10

25

35

60

8

10

20

30

60

8

15

30

35

60

8

15

35

35

60

Natural moisture content

28

27

28

27

27

27

Specific gravity

2.6

6

2.6

9

2.6

9

2.6

7

2.6

7

Particle Size

Gravel

Sand

14

54

52

10

55

54

21

52

58

20

52

57

9

54

58

Fines<0.075 mm 86

46

48

90

45

46

79

48

42

80

48

43

91

46

42

Unconfined

Compression Test

qu, UD, (Psi)

21.2

5

19.9

5

20.2

5

21.5

5

20.7

5

Strain (%)

6.5

0

6.5

0

6.5

0

6.5

0

6.5

0

Wrt Density, pcf

119.2

5

118.7

5

119.5

0

119.2

5

119.6

5

Dry Density, pcf

95.7

5

95.5

0

95.6

5

95.7

5

96.2

5

Atterbarg limit Liquid Limit

48

47

46

47

48

Page 58: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

43

Bore Hole BH-1 BH-2 BH-3 BH-4 BH-5

Sample No.

UD

-1

D2

D6

D5

D11

UD

-1

D2

D5

D7

D12

UD

-1

D2

D4

D6

D12

UD

-1

D3

D6

D7

D12

UD

-1

D3

D7

D7

D12

Plastic Limit 25

24

24

25

25

Plasticity index

23

23

22

22

23

Direct Shear Test Ø (Degree)

32.1

0

31.2

5

32.4

5

30.8

8

32.4

5

C (tsf) 0

0

0

0

0

Consolidation Test

Comp. Index,Cc

0.3

469

0.3

471

0.3

468

0.3

470

0.3

472

Initial Void Ratio e0

0.1

088

0.1

090

0.1

093

0.1

089

0.1

031

Page 59: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

44

Table 3.20: Laboratory Test Summary Sheet for Tongi-1, BSCIC I/A, Tongi, Gazipur

Bore Hole BH-4 BH-5 BH-6

Sample No. UD-1 D3 D6 D7 D12 UD-1 D3 D7 D7 D12 UD-1 D3 D7 D3 D13

Depth (ft) 8 15 30 35 60 8 15 35 35 60 8 15 35 65 65

Natural moisture content 27 27 27

Specific gravity 2.67 2.67 2.67

Particle Size

Gravel

Sand 20 52 57 9 54 58 20 24 55

Fines<0.075 mm 80 48 43 91 46 42 80 76 45

Unconfined

Compression

Test

qu,UD, (Psi) 21.55 22.25 20.85

Starin (%) 6.50 6.30 6.50

Wrt Density,pcf 119.25 119.95 119.55

Dry Density,pcf 95.75 96.35 95.65

Atterbag limit

Liquid Limit 47 48 47

Plastic Limit 25 25 25

Plasticity index 22 23 22

Direct Shear

Test

Ø (Degree) 30.88 32.45 32.75

C (tsf) 0 0 0

Consolidation

Test

Comp. Index,Cc 0.1089 0.1091 0.1092

Initial Void Ratio

e0 0.3470 0.3472 0.3474

Page 60: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

45

Table 3.21: Laboratory Test Summary Sheet for Tongi-2, Cherag Ali Besides Tongi S & D Division

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D6 D7 D8 D13 UD-1 D2 D3 D7 D8 D9 D12

Depth (ft) 8 10 15 30 35 40 65 8 10 15 35 40 45 60

Natural Moisture Content 28 27

Specific Gravity 2.666 2.656

Particle Size

Gravel 51 53

Sand 16 52 56 12 49 47

Fines<0.075 mm 84 48 44 88

Unconfined

Compression

Test

qu,UD, (Psi) 21.25 20.85

Strain (%) 6.50 6.50

Wrt Density, pcf 139.25 119.45

Dry Density, pcf 95.75 95.85

Atterbarg limit

Liquid Limit 48 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear

Test

Ø (Degree) 30.45 31.85 52.25 30.25 31.50 32

15

C (tsf) 0 0 0 0 0 0

Consolidation

Test

Comp. Index, Cc 0.347 0.347

Initial Void Ratio

e0 0.109 0.109

Page 61: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

46

Table 3.22: Laboratory Test Summary Sheet for Tongi BSCIC’S, Near BPDB’s 80 MW Power Station, Tongi

Bore Hole BH-1 BH-2

Sample No. UD-1 D2 D3 D7 D6 D8 D11 UD-1 D2 D7 D8 D9 D12

Depth (ft) 8 10 15 35 30 40 55 8 8 15 35 40 45

Natural moisture content 28 27

Specific gravity 2.666 2.656

Particle Size

Gravel

Sand 16 54 59 12 51 53

Fines<0.075 mm 84 46 41 88 49 47

Unconfined

Compression Test

qu,UD, (Psi) 20.25 19.350

Strain (%) 6.50 6.50

Wrt Density, pcf 119.25 119.45

Dry Density, pcf 95.75 95.85

Atterbarg limit

Liquid Limit 48 47

Plastic Limit 25 25

Plasticity index 23 22

Direct Shear Test Ø (Degree) 30.30 31.75 32.10 30.25 31.25 32.15

C (tsf) 0 0 0 0 0 0

Consolidation Test Comp. Index, Cc 0.1091 .1093

Initial Void Ratio e0 0.3471 0.33474

Page 62: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

47

3.3 Biological Environment

68. The existing 9 (nine) substations have some distinct features and almost same

ecological scenario. Each of the sites has tiny scope of growing vegetation as most of

the lands are paved by civil structures. Hence the sites contain mere vegetation with

seasonally grown herbs and shrubs. Depending on the vegetation, the wildlife

occurrences is limited and mainly observe some local birds and rodents like mouse and

mongoose. Considering the above overall situation, the compliance of ecosystem and

biodiversity conservation status is followed through last monitoring visit.

69. Out of 9 (nine) sites, 7 (seven) sites limiting the vegetation clearance within the

development footprint and no additional clearing for construction have took place for

avoiding the ancillary facilities expansion outside the footprint area. Uttara section-14

and Tongi-2 area have been subjected to cut down of 3 (three) mango trees.

70. Any of the sites followed/ informed disturbances to wildlife movement and the entire sites

construction footprint have clearly demarked by boundary fences for limiting construction

activities within the site. All the sites have limited the use of night lights which have

minimized the disturbance to nocturnal wildlife. No one site observed any bird nest or

core habitat of any rodents. None of the sites have started plantation activities in them

yet and Mirpur-6 and Agargaon-2 sites have no available space for plantation.

71. The proposed new substation sites featured with bushy vegetation with low densities of

herbs and shrubs. Only the Barura site developed within the agricultural land most of the

sites have already been developed for the construction of civil structures and then after

assembling the mechanical equipment. The observations on ecosystem and biodiversity

conservations are satisfactory most of the sites which revealed from last monitoring tier.

No one sites violate the vegetation conservation protocol outside the development

footprint area or eventually done the additional vegetation clearance outside the footprint

area for ancillary facilities.

72. Only the Lake City Concord site had no clear demarcation of footprint area and some

sites like Basundhara I Block, Sholhati and Barura sites observed no fence surround the

footprint boundaries. Therefore additional vegetation clearance had occurred due to

placing of construction materials dumping outside of the area. Some tall trees will be cut

in Lake City Concord area due to space limitation. However, none of these above four

sites, no threatened species was recorded. Except the above, occurrence of Bengal fox

have been informed in Satarkul and Barua sites and may be interrupted their movement

due to construction works. Local birds are rarely roamed among most of the proposed

substation sites and some small mammals like mouse and shrew have been relocated at

the nearer places. All the sites properly compiled to limiting night light using. Native

plantation yet not been started in the area

73. Considering the overall situation, there were no significant negative impacts on the

existing vegetation and wildlife. The monitoring indicators regarding ecological resources

and their complaince status are presented in Appendix B.

Page 63: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

48

Table 3.23: Matrix of Monitoring Results

Environmental and

social components

Potential impacts Monitoring Measures Status Corrective Action Plan (CAP)

Ambient air quality Emission of fugitive dusts due

to construction activities can

accelerate the air pollution.

Spraying water in the

construction site to control

fugitive dusts

Water spraying is

carried out twice or

three times in a day

Water spraying is carried out

three or more than three times in

a day.

Construction materials

(sand/soil) to be kept covered

Complied in most of the

all sites

Construction materials (sand/soil)

should have to kept covered by

polythene or mulches during dry

weather so that strong wind

cannot blow away

Introducing vehicle speed limit N/A

Using new/good engine quality

machines/vehicles to avoid

incomplete combustion.

Complied in all sites

Noise level Disturbance to local

communities, ecosystem and

workers at worksite due to

construction activities of the

proposed project site.

Using modern machineries for

production of low noise

Complied in all sites

Providing hearing protection for

the workers

Complied in all sites.

The contractor has

mentioned that they

arrange tool box

training for the workers

every day.

Waste management An inefficient municipal solid

waste engagement system may

create serious negative impacts

like spread of infectious

diseases, land and water,

pollution, obstruction of drains

and loss of bio diversity.

Earmarking specific sites for

waste disposal

Complied in all sites

Source: CEGIS, EMR, July to December, 2018

Page 64: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Monitoring Results

49

74. During the monitoring it is found that here have some non-compliance issues which would be complied in the next phase of monitoring. The

implementation plan has been suggested through the consultation with the EPC contractor and PMU. In this following table provides an

implementation with action plan of such non-compliance found during this phase of monitoring. Based on this implementation plan,

implementation performance would be reported in the next monitoring report.

Table 3.24: Implementation Plan for Non-Compliance Issues

Corrective Action Plans Action Plan Implementing Period Responsible Agency Remarks

Water can be sprayed three or

more than three times in a day

for better controlling fugitive

dusts.

Consulted with PMU and

ensured to monitor the

status which would be

incorporated in the next

monitoring report

At the next phase, the

result will be incorporated EPC contractor and PMU

- Due to the project

activities, it is suggested

to spray water sprayed

three or more than three

times in a day for better

controlling fugitive dusts.

- If the next monitoring

result shows

unsatisfactory result

frequency of water

spraying will be increased

to comply (100%) within

the next phase of the

monitoring.

Construction materials

(sand/soil) should be kept

covered by polythene or

mulches during dry weather so

that strong wind cannot blow

away.away.

The EPC contractor will

consider the mitigation

and will cover loose soil

by polythene or sacks.

It will be compiled at the

construction phase EPC contractor and PMU

PMU ensured that all will be

complied (100%) in the next

phase of the monitoring and

would be reported at the next

report.

The boundary will be fenced and

the area cleared in such a way

that the footprint shall not be

extended during clearing works.

Consulted with PMU and

EPC contractor for ensuring

this compliance.

It will be compiled as early

as possible EPC contractor

The performance of this non-

compliance issue will be

reported in the next monitoring

report.

Page 65: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Approach and Methodology

50

Corrective Action Plans Action Plan Implementing Period Responsible Agency Remarks

If the area is to be re-vegetated,

preference should be given to

naturally occurring species that

are recognized as non-invasive

species.

It would be consider after the

complete the work and its

depending on available

space of the area

After the completion of

construction EPC contractor and PMU

PMU will ensure the

compliance status.

Source: Monitoring field visit and consultation with PMU, July – December 2018

Page 66: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

51

4. Institutional Arrangement and Grievance Redress

Mechanism

4.1 Institutional Arrangement

75. The organogram (provided by the DESCO) is responsible to monitor environmental

compliance and monitoring during the project construction. The assistant engineer

(electrical), assistant manager, and sub-assistant engineer are working under the

supervision of the deputy project director for monitoring of augmentation, rehabilitation of

distribution system in DESCO area. The project director is responsible to supervise and

guide the whole work following the prepared checklist on the compliance status. The

following Figure 4.1 shows the institutional arrangement those who are responsible to

ensure monitoring and compliance in accordance with Govt. laws, rules regulations and

ADB’s loan covenants.

Project Director

Deputy project

Director

Assistant EngineerAssistant Engineer

Sub assistant

Engineer

Manager

Sub assistant

Engineer

Figure 4.1: Institutional Arrangement of DESCO for Compliance and Monitoring

4.2 Grievance Redress Mechanism

76. At this stage, there is no Grievance Redress Committee (GRC) to address the grievance

redress but the EA will assist the grievance redress mechanism through their institutional

arrangement. But there is some complaint box where people can submit their complain

based on the project activities. The team working for GRC made their concern and open

the complain box, but there is no complain still found at this stage of environmental

monitoring.

77. Presently, with the starting of construction activities, a sub-assistant engineer is playing

the key role to understand the people’s problems (if any related to the project activity)

and visited all ongoing constructed sites. In addition, there are phone numbers attached

in each station to get compliant and emergency response during the construction

activities.

Page 67: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Institutional Arrangement and Grivence Redress Mechanism

52

Page 68: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Institutional Arrangement and Grivence Redress Mechanism

53

Page 69: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

54

5. Specific Environmental Management Plan

78. The site specific Environmental Management plan is suggested by the EPC contractor

(i.e. Siemens India). In their plan, Siemens have the plans to manage environmental

issues during the construction phase of the project. Based on the following Table 5.1,

Siemens India started the construction work at the three locations whereas the

construction activities continued based on this specific environmental management plan.

All construction activities, the Simmens India (EPC contractor) is trying to maintain the

following SEMP plan for the successful completion of this project.

Table 5.1: Specific Environmental Management Plan (SEMP)

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

1.

Top soil

Ensure the topsoil excavated from the proposed construction site not be dumped or stockpiled anywhere.

We will label all uneven land and excavated topsoil will immediately spread in between site working area.

Confirm the sediment-laden runoff must be prevented from entering into nearby water courses, if erosion occurs from stockpiles due to their location in drainage paths.

Stockpiles will be planed and located such way (away from water courses) so that sediment-laden cannot runoff into nearby water courses.

2.

Fauna (Wildlife)

Make sure that project workers and employees should not disturb, catch, fish, hunt, kill, trade and consumption of birds and wild animals available in natural environment around the project site.

We will provide official instruction (written, verbal and signboard) to all workers and employees to do not disturb wildlife. Also from management sites we will keep monitoring it throughout projects.

Establish and enforce daily site clean-up procedures, including maintenance of adequate disposal facilities for construction debris.

One clear system under waste management will be established for daily clean of construction area.

3.

Solid Waste

Establish daily cleaning through adequate collection and storage of solid waste produces at project site because of various activities throughout the work site, construction yard and labour camp.

Sufficient number of workers will be trained on cleaning to maintain cleaning activities of site areas. Besides this separate waste bin with color code and labeling would be provided to collect and segregate different types of waste.

Ensure adequately safe handling and transportation, with no dropping from waste carrier, of the solid wastes to the disposal sites.

Under waste management training all site personnel and assigned cleaner would be instructed and trained on handling and transporting of waste. Standard tools will also provide to carry and transport waste.

Establish an order that under no

circumstances dispose any materials in environmentally

Buckets, places and area will be placed or allocated far away from any environmentally sensitive’s area.

Page 70: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Specific Environmental Management Plan

55

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

sensitive area (example: designated forest area, area of endanger/rear flora, natural drainage course).

Proper barricade will be provided along with billboard or signage to restricted waste and create awareness.

4.

Drainage Congestion

Confirm an effective system for smooth draining of storm and rain water, and resulting no water logging (for rain and flood water in the monsoon).

Proper drainage system includes rain water drain, water pits sloping in the surface will be constructed/provided for smooth draining of storm and rain water and ensuring no water logging during monsoon.

Ensure no congestion in the

drain(s) resulting blockage of water passing.

To avoid blockage drain would be clean periodically.

5.

Noise level

Control sound pollution from construction equipment and machineries installed in the construction site.

Sound level for several heavy equipment and machineries and generator will be measured individual during their operation and record will be maintained properly.

Maintain noise levels associated with all machineries and equipment at or below 90 decibel (dB), in particular for nearby community facilities.

Air plug will provide all site personnel who are working near the noisy area.

Fully avoid use of hydraulic

horns to project vehicles.

Hydraulic horn (if any exist) of each and every project vehicle will be replaced by non-hydraulic horn.

Control sound pollution from

generation.

We will ensure Installation of soundless generator. If not, generators will be placed in the closed room having barricaded from all sides, which will restrict sound level.

Regulate use of horns of

project vehicles as much as minimum, especially in night.

Strict instruction will be given to the flagman and drivers of project vehicles (motor cycle, car, truck, etc.) for use of horns as much as minimum.

6.

Air quality & Dust

Ensure use of dust-masks by all personnel in areas prone to dust emissions throughout the period of construction.

Proper dust mask will be provided and monitored by site management and EHS officer in the construction area.

Ensure minimum dust emission

in places where earth and cement works is done.

We will prepare and maintain proper HIRA (Hazard Identification & Risk Assessments) and implement SWMS (Standard work method system) to ensure minimum dust emission during earth and cement work. Also regular water will be sprayed all over those area to restrict dust emission.

7. Setting of Ensure health facilities for the

workers and employees at camp Standard camp along with proper sanitation and fresh drinking water

Page 71: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Specific Environmental Management Plan

56

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

construction camp

site. and safe area will be provided to ensure proper health facilities for workers.

Ensure safe disposal of wastewater from the labor camp and causing no pollution of nearby ponds and watercourses.

Proper drainage system including a temporary septic tank will be setup to avoid any pollution of nearby ponds and watercourses.

Confirm maintenance of all camp facilities in a safe clean and/or appropriate condition throughout the constructed period.

A routine cleaning would be ensured to maintain safe, clean and appropriate labor camp.

Ensure hygienic toilet facility (with constant water supply system) at residence of the workers in the camp area.

At least one water closet toilet will be constructed and provided to each 25 workers.

Ensure hygienic urinal facility (with constant water supply system) at residence of the workers in the camp area and its usage.

At least one urinal facility will be constructed and provided to each 25 workers.

Confirm appropriate usage of

the toilet and urinal facilities for all workers and personnel.

Signage and billboard will be provided to create awareness and also site management will strictly monitor of using it.

Ensure safe water supply system for bath, cook and other essential use in camp and their usage by workers.

Tube well, submergible pump (if necessary) will be provided to ensure safe water supply.

Ensure no accident from fire at

camp, residence/quarter. Fire extinguisher will be setup in camp and other important areas.

Ensure immediate

troubleshooting and maintenance of facilities.

Maintenance of all facilities will be done in time as scheduled for keeping the things in a safe, clean and appropriate condition throughout the constructed period.

Page 72: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Specific Environmental Management Plan

57

Sl. Environmental

Issue Proposed Mitigation Measures Implementation Plan by Siemens

i. 8 Cutting Trees3

Avoid tree cutting as many as possible.

SIEMENS will not involve in any kinds of cutting trees and activities which will cause of it.

Confirm replantation of double number of trees against tree cutting.

N/A

Ensure additionally replantation of 107 4 numbers of trees along the access road slopes.

N/A

Strictly prohibit collection of any kind of construction material from within the natural habitat.

No materials for construction, cook, fire, etc. will be collected from within the natural habitat.

When removing vegetation from right of ways, workspaces etc. featheredge the cut to ensure that line of site and cover (both security and thermal protection) issues are addressed.

N/A

9 Natural Habitat5

Prohibit disposal of construction

waste within the natural habitat.

It will be strictly monitored and

controlled by supervising and raising

awareness through training and

meeting.

Restrict any disturbance to

water resource within the

natural habitats.

All site personnel will be clearly

instructed to avoid any disturbance

to water resources within the natural

habitats.

Prevent human disturbance and

ecosystem impacts on sensitive

areas adjacent to projects by

using temporary fencing or flag

off area to restrict travel to

construction zones, RoW and

workplace.

Temporary fencing or flag will be

provided to avoid any disturbance of

human by traveling or moving inside

construction zones, RoW and

workplace. Also at least one security

guard will be placed to ensure

unauthorized personnel movement

on sites and maintain site security

during project execution.

3 1) The species shall be identified in consultation with officials of forest department and/or local

community, giving due importance to local flora, preferably same species as cut.

2) Recommended to plant mixed species in case of both avenue or cluster plantation.

3) Plantation must follow availability of water during dry season.

4) Plants must be protected at initial stage of growth.

4 The EIA/EMP report suggested for planting 107 trees along the access road slops commonly for

each of six specific substations.

5 1) The species shall be identified in consultation with officials of forest department and/or local community, giving due importance to local flora, preferably same species as cut.

2) Recommended to plant mixed species in case of both avenue or cluster plantation. 3) Plantation must follow availability of water during dry season.

3) Plants must be protected at initial stage of growth.

Page 73: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

58

6. Conclusions and Recommendations

6.1 Conclusions

79. This monitoring is conducted on twenty four (24) substations and analysed the

compliance status based on ADB safeguard policy, EMP provided in the EIA, the GoB

and ADB loan covenant. The compliance status on Environmental and Biological

compoents addressed based on the prepared checklist. Therefore, the findings of

environmental monitoring has been compiled and suggested the corrective action plan

for further improvement on non-compliance status. Finally, an implementation plan

based on Corrective Action Plan (CAP) has been recommended in this environmental

report.

6.2 Recommendations

80. For the effective compliance status, following recommendations are proposed by the

study team to be followed during the construction phase of these projects:

Though construction materials like sand and soil were not covered with polythene

at all project sites. This might cause dust pollution in dry condition. Thus, it is

required to cover the construction materials properly.

The noise level should be limited during the construction especially the pilling

stage of the project implementation.

Earmuffs should be available in adequate numbers for all labors working during

construction.

Separate Dustbins for both disposal and non-disposal waste should be set within

the project during implementation.

The use of PPE should be ensured through regular monitoring by the monitoring

team of PMU to avoid the risks for further accidental case.

More awareness is to be created among the workers and community dwellers

regarding the health and safety risks associated with the construction phase of

the project.

One paramedic doctors, and an ambulance need to be made available for the

labors in case of any injury and accident.

Feedbacks from the labors taken to understand their problems during the weekly

toolbox meetings on health and safety, as well as the other governing

environmental and social issues should be initiated.

All addressed Non-Complaince Issues mentioned during the field visit should be

addressed

All newly built substation areas should fenced with high boundary wall during the

construction

Page 74: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Conclusions and Recommendations

59

.

Page 75: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

60

Reference

ADB (2009). Safeguard Policy Statement, Policy Paper

Page 76: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Reference

61

Page 77: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

62

Appendix-A: Field Photos

Figure A.1: Safety measures and instrument at the substations

Figure A.2: Working environment during project implementation

Page 78: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-A

63

Figure A.3: Construction activitites at substation sites

Figure A.4: Monitoring Team on Site with KII

Page 79: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

64

Appendix-B: Monitoring Checklist (Physical and Biological Components)

Category Description of potential impact

Measures/Indicators

CAAB

Co

mp

lied

No

t C

om

plied

Rem

ark

s

Monitoring Component: Physical Environment

Noise Level

Disturbance to local communities, ecosystem and workers at worksite due to construction activities of the proposed plant site.

Use modern low noise producing machineries.

Partially Complied 50%

Rest of the percentage would be complied and incorporated with

the next monitoring report.

Switching off machines which are not in use.

Develop temporary corrugated/ Tarja fencing around the project boundary

Provide hearing protection for the workers

Follow mandatory regulations in case of night shift operations.

Not Applicable

Maintaining noise level 45 dBA at the residential area and 55 dBA at day light hour

Partially Complied 5%

Rest of the percentage would be complied and incorporated with

the next monitoring report.

Page 80: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

65

Category Description of potential impact

Measures/Indicators

CAAB

Co

mp

lied

No

t C

om

plied

Rem

ark

s

Maximize the offset distance between noisy plant items and nearby sensitive receivers

Not Applicable

Employ effective silencing measures for equipment and other abatement techniques to minimize construction site noise.

Ensure that all equipment is in good repair and operated in the correct manner.

Consult with local people /residents and building owners to address community concerns

Air Quality

Emission of particulate matter, SOx and NOx due to construction activity and from construction machineries.

Water spraying system to control fugitive dusts

Restricting excavation activities such as top soil removal during period of high winds

Locating stockpiles away from the sensitive receptors

Carrying out progressive rehabilitation of cleared land

Locating contractor’s compounds away from residential areas

Page 81: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

66

Category Description of potential impact

Measures/Indicators

CAAB

Co

mp

lied

No

t C

om

plied

Rem

ark

s

restricting the burning of waste ✓

minimize exhaust emissions from construction equipment through the regular maintenance of all construction machinery and vehicles

Construction materials (sand/soil) to be kept covered with polythene

X

Provide broad fence/ barrier to restrict wind current

Introduce vehicle speed limit Not applicable

Use good engine quality machines/vehicles

Ensure that emissions from on-road and off-road vehicles should comply with Schedule 6 (Standards for emissions from motor vehicles) of ECR 1997

Soil Characteristics

The soils of the project areas have clay loam/ silty loam to loamy texture. The area under the project would be filled up with external soils having sandy materials. Then the existing soil might

Topsoil that is to be removed should be stockpiled for site rehabilitation and landscaping works.

Soil-erosion and sedimentation-control measures should be undertaken in stages to minimize the area of unstable or unprotected soil surfaces

Not applicable

Page 82: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

67

Category Description of potential impact

Measures/Indicators

CAAB

Co

mp

lied

No

t C

om

plied

Rem

ark

s

turn into sandy soil in the proposed Substation sites.

Wherever possible, vegetation is to be left undisturbed and retained as soil cover. If vegetation cover is not available, spread mulches over the surface to reduce dust and rainfall impact.

Not applicable for

the project site

Undertake the progressive re-vegetation of excavated areas as quickly as possible. Revegetation may include grassing or planting the area with trees or shrubs. The selection of species should be compatible with the local conditions and use requirements.

Partially

50%

Rest of the percentage would be complied and incorporated with

the next monitoring report.

All fuel storage areas and refueling vehicles are to be provided with spill –containment kits

An emergency Spill Contingency plan shall be prepared by the contractor as part of the SEMP

Proper deposition of loose soil and construction materials to avoid water logging

An efficient municipal solid Specific sites for waste disposal ✓

Page 83: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

68

Category Description of potential impact

Measures/Indicators

CAAB

Co

mp

lied

No

t C

om

plied

Rem

ark

s

Waste Management waste management system may create serious negative impacts like infectious diseases, land and water, pollution, obstruction of drains and loss of bio diversity.

Quantification of solid wastes

Not Applicable

Sanitation system

Location of backfilling stockpile in safe area

Measures to control odor problems

Excavated material unsuitable for fill should be disposed in an environmentally safe manner.

Ensure that the waste management measures (collection, sorting, and disposal) are correctly implemented on the project site

Ensure that correctly signed waste containers are available at convenient locations for the disposal of wastes Partially

50%

Rest of the percentage would be complied and incorporated with

the next monitoring report.

Dispose of all used oil and fuel filters in a secure landfill, unless they can be recycled

Ensure that an adequately sized area is ✓

Page 84: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

69

Category Description of potential impact

Measures/Indicators

CAAB

Co

mp

lied

No

t C

om

plied

Rem

ark

s

made available for the safe storage of wastes prior to collection

Ensure that all on-site wastes are suitably contained and prevented from escaping into Partially

60%

Rest of the percentage would be complied and incorporated with

the next monitoring report.

Neighboring fields, properties, and waterways, and that the waste contained does not contaminate soil, surface, or groundwater, or create unpleasant odors for neighbors or workers

Ensure the site is regularly cleaned and waste material appropriately removed, i.e., to a landfill in accordance with regulations

Page 85: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

70

Category Descriptio

n of

Potential

Impact

Measures/Indicator

s

Due diligence

CAAB DOHS Mirpur Mirpur-06

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Biological Environment

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No disturbance on

wildlife movement

✓ ✓ ✓

Limiting the use of

night light

✓ ✓ ✓

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

clearing vegetation

✓ ✓

Page 86: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

71

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

✓ ✓ ✓

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

✓ ✓ ✓

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

✓ ✓ ✓

Page 87: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

72

extended during

clearing works.

If the area is to be

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

Existion

station

Area,

Not yet

started

related

work

Existing

substatio

n ground,

Not yet

started

related

work

Not

available

space for

Plantatio

n

Category Description

of Potential

Impact

Measures/Indicators Due diligence

Agargaon-2 Baunia Tongi-27

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

No disturbance on

wildlife movement

✓ ✓ ✓

Limiting the use of

night light

✓ ✓ ✓

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

✓ ✓

Page 88: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

73

and

biodiversity

due to

constructio

n works.

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

clearing vegetation

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

✓ ✓ ✓

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

✓ ✓ ✓

Page 89: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

74

to minimize

disturbance to

adjacent areas

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

extended during

clearing works.

✓ ✓ ✓

If the area is to be

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

Existing

station,

Not

availabl

e space

Not yet

started

related

initiative

Not yet

started

related

initiative

Category Description

of Potential

Measures/Indicators Due diligence

Tongi(BSCIC) Tongi-01 ADA

Page 90: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

75

Impact

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No disturbance on

wildlife movement

✓ ✓ ✓

Limiting the use of

night light

✓ ✓ ✓

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

clearing vegetation

✓ ✓

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

✓ ✓ ✓

Page 91: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

76

footprint shall be

avoided

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

✓ ✓ ✓

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

extended during

clearing works.

✓ ✓ ✓

If the area is to be

revegetated,

preference should

be given to naturally

Not yet

started

related

initiative

Not yet

started

related

initiative

Not yet

started

related

initiative

Page 92: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

77

occurring species

that are recognized

as non-invasive

species.

Category Description

of Potential

Impact

Measures/Indicators Due diligence

Tongi-02 Bashundhra I block Mirpur DOHS-2

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No disturbance on

wildlife movement

✓ ✓ ✓

Limiting the use of

night light

✓ ✓ ✓

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

✓ ✓

Page 93: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

78

clearing vegetation

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

✓ ✓ ✓

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

✓ ✓ ✓

The boundary will be

fenced and the area

cleared in such a

✓ x

Page 94: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

79

way that the footprint

shall not be

extended during

clearing works.

If the area is to be

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

Not yet

started

related

initiative

Not yet

started

related

initiative

Not yet

started

related

initiative

Category Description

of Potential

Impact

Measures/Indicators Due diligence

Kazipara Switching

station

Kalshi(Rakeen City) Merul Badda C

om

pile

d

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

Bird’s

habitat

loss,

damages of

No disturbance on

wildlife movement

✓ ✓ ✓

Limiting the use of

night light

✓ ✓ ✓

Page 95: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

80

n herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

clearing vegetation

✓ ✓

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

✓ ✓ ✓

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

✓ ✓ ✓

Page 96: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

81

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

extended during

clearing works.

✓ ✓ ✓

If the area is to be

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

Not yet

started

related

initiative

Not yet

started

related

initiative

Not yet

started

related

initiative

Page 97: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

82

Category Description

of Potential

Impact

Measures/Indicators Due diligence

Eastern Housing Lake city Concord Satarkul

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Co

mp

iled

No

t C

om

pile

d

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No disturbance on

wildlife movement

✓ ✓ ✓

Limiting the use of

night light

✓ ✓ ✓

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

clearing vegetation

✓ ✓

Any additional

clearing for

construction will

✓ ✓ ✓

Page 98: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

83

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

30%

compile

d

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

extended during

clearing works.

✓ ✓ ✓

If the area is to be Not yet Not yet Not yet

Page 99: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

84

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

started

related

initiative

started

related

initiative

started

related

initiative

Category Description

of Potential

Impact

Measures/Indicators Due diligence

Uttarkhan (Promy ) Barura Sholahati

Co

mp

iled

No

t

Co

mp

iled

Re

ma

rks

Co

mp

iled

No

t

Co

mp

iled

Re

ma

rks

Co

mp

iled

No

t

Co

mp

iled

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No disturbance on

wildlife movement

✓ ✓ ✓

Page 100: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

85

Limiting the use of

night light

✓ ✓ ✓

No plantation of non-

native species

✓ ✓ ✓

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

areas that are

already relatively

disturbed in

preference to

clearing vegetation

✓ ✓

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

✓ ✓ ✓

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

✓ ✓ ✓

Page 101: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

86

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

extended during

clearing works.

✓ ✓

50%

compile

d

x

If the area is to be

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

Not yet

started

related

initiative

Not yet

started

related

initiative

Not yet

started

related

initiative

Category Description

of Potential

Measures/Indicators Due diligence

Uttara-14

Page 102: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

87

Impact

Co

mp

iled

No

t

Co

mp

iled

Re

ma

rks

Co

mp

iled

No

t

Co

mp

iled

Re

ma

rks

Co

mp

iled

No

t

Co

mp

iled

Re

ma

rks

Ecosystem

and

Biodiversity

Conservatio

n

Bird’s

habitat

loss,

damages of

herbs,

shrubs and

degradation

of

ecosystem

and

biodiversity

due to

constructio

n works.

No disturbance on

wildlife movement

Limiting the use of

night light

No plantation of non-

native species

The removal of

vegetation shall be

restricted to the

development

footprint, which

should encompass

Page 103: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

88

areas that are

already relatively

disturbed in

preference to

clearing vegetation

Any additional

clearing for

construction will

compound the

impacts, so ancillary

facilities outside the

footprint shall be

avoided

The construction

footprint shall be

clearly demarcated.

The clearing

boundaries are to be

shown to machinery

operators with the

instruction that

machinery is not

allowed to operate

outside the

boundaries. The

area is then cleared

to minimize

disturbance to

adjacent areas

Page 104: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-B

89

Legend:

Complied = ✓ Partially complied= (%)✓ Not complied= X

The boundary will be

fenced and the area

cleared in such a

way that the footprint

shall not be

extended during

clearing works.

If the area is to be

revegetated,

preference should

be given to naturally

occurring species

that are recognized

as non-invasive

species.

Not yet

started

related

initiative

Page 105: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

90

Appendix-C: Contract Agreement between DESCO and

Siemens India

Page 106: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-C

91

Page 107: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-C

92

Page 108: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-C

93

Page 109: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-C

94

Appendix-D: Environmental Clearance Certificate

Page 110: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

95

Page 111: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

96

Appendix-E: Laboratory Test Summary Sheet

Table 1: Laboratory Test summary sheet for ADA

Table 2: Laboratory Test summary sheet for Agargaon

Page 112: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

97

Table 3: Laboratory Test summary sheet for Baunia

Table 4: Laboratory Test summary sheet for Mirpur -6

Page 113: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

98

Table 5: Laboratory Test summary sheet for Uttar Khan

Table 6: Laboratory Test summary sheet for Barua

Page 114: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

99

Table 7: Laboratory Test summary sheet for Kalshi

Table 8: Laboratory Test summary sheet for Lake City Concord

Page 115: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

100

Table 9: Laboratory Test summary sheet for Marul Badda

Table 10: Laboratory Test summary sheet for Mirpur DOHS-2

Page 116: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

101

Table 11: Laboratory Test summary sheet for Mirpur DOHS

Table 12: Laboratory Test summary sheet for Satarkul-1

Page 117: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

102

Table 13: Laboratory Test summary sheet for Satarkul-2

Table 14: Laboratory Test summary sheet for Sholahati

Page 118: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

103

Table 15: Laboratory Test summary sheet for Tongi-1

Table 16: Laboratory Test summary sheet for Tongi -2

Page 119: 42378-016: Power System Expansion and Efficiency ... · This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily

Appendix-E

104

Table 17: Laboratory Test summary sheet for Tongi BSCIC

Table 18: Laboratory Test summary sheet for Uttara-14