319 Fleming Creek FINISHED Project
2018
District 5 and Fleming Creek Road
Project Location
Breaking Ground November 26, 2018 Culvert #1 BEFORE
Spring 2018 Breaking Ground!
Culvert #1 District 5 Road
Before (Inlet)
Culvert #1 Finished Inlet
Culvert #1
Before (Outlet)
After
Culvert #1 Outlet Finished
Culvert # 2 Fleming Creek Road- Before
Spring 2018- Inlet Spring 2018- Outlet
Culvert # 2 Work Begins!!!
Breaking Ground Inlet Diversion
Making Progress!!!
Working Hard!!!
Finished Culvert #2
Finished Inlet
Outlet Culvert #2 Fleming Creek Road
Spring 2018 Finished Outlet
Cross Drain Installed
CULVERTS: $15,930.77* WILLOWS: $100.00* R&B EQUIPMENT COSTS: $16,075.50* R&B LABOR: $15,536.56 MATERIALS: $6,223.40 SWCC: MATCH $3,287.16 BSCD: MATCH $1680.00 ADMIN: $3530.00
TOTAL PROJECT COST: $62,363.39 60% $37,418.03 40% $24,945.36
$5311.76 TOWARDS LABOR AND MATERIALS
Biggest Highlight
• Thank you to Boundary County Road and Bridge and all of your hard
work!