Work Charting Methods
![Page 2: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/2.jpg)
April 14, 2023
Objective
• Objectively document the work task or process for analysis
• Many methods are available
• New ones are invented regularly
• Break down the job into sub-components or tasks
• Describe the tasks in a meaningful way King Saud University
College of Engineering Department of Industrial Engineering
2
![Page 3: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/3.jpg)
April 14, 2023
Pareto Chart
• Items of interest are identified and measured on a common scale
• Then ordered in ascending order, creating a cumulative distribution
King Saud University College of Engineering
Department of Industrial Engineering 3
![Page 4: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/4.jpg)
April 14, 2023
Pareto Chart
• Pareto principle: 80% of the total activity can be found in the first 20% of the items.
• Goal is to identify the appropriate 20% for analysis.– 80% of inventory is associated with 20%
of the parts.– 80% of the injuries are associated with
20% of the jobs.King Saud University
College of Engineering Department of Industrial Engineering
4
![Page 5: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/5.jpg)
April 14, 2023
Fishbone Diagram (Cause-Effect)
• Identifies components lead to undesirable (desirable) event in a process
• Principle event is identified at the fish head
• Associated contributing factors are identified using a tree type structure.
• Closely related to many different charts used in safety analysis (Fault-Tree method)
King Saud University College of Engineering
Department of Industrial Engineering 5
![Page 6: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/6.jpg)
April 14, 2023
Example
King Saud University College of Engineering
Department of Industrial Engineering 6
![Page 7: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/7.jpg)
April 14, 2023
Operations Process Charts
• Represents the chronological sequence of: – operations, – Inspections, – Time allowances, and – materials used in a process
• from the arrival of raw material to the packaging of the finished product.
King Saud University College of Engineering
Department of Industrial Engineering 7
![Page 8: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/8.jpg)
April 14, 2023
Operations Process Charts
• Focuses on products and/or facilities
• Two symbols are used in the chart:– Operations are denoted using a
small circle– Inspections are denoted using a
small square
King Saud University College of Engineering
Department of Industrial Engineering 8
![Page 9: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/9.jpg)
April 14, 2023
Operations Process Charts
• Vertical lines indicate general flow of the process as work is completed
• Horizontal lines feeding into vertical lines are for parts or subassemblies.
• Lines should not cross in the chart.
• Time values are assigned to operations and inspections on the chart.
King Saud University College of Engineering
Department of Industrial Engineering 9
![Page 10: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/10.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
10
![Page 11: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/11.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
11
![Page 12: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/12.jpg)
April 14, 2023
Flow Process Charts
• Identify operations, inspections, materials, moves, storages, and delays involved in making a part or completing a process.
• Show all events in the correct sequence.
• Show the relationship between parts and fabrication complexity.
• used for workers, components, or sub-assemblies.
King Saud University College of Engineering
Department of Industrial Engineering 12
![Page 13: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/13.jpg)
April 14, 2023
Flow Process Charts
• Distinguish between produced and purchased parts.
• Provide information on the number of employees utilized and the time required to perform each operation and inspection.
• More details than operations process charts
King Saud University College of Engineering
Department of Industrial Engineering 13
![Page 14: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/14.jpg)
April 14, 2023
Flow Process Charts
• Two types are commonly used:– Product or material– Operative or person
• Help identify nonproduction hidden costs such as distances traveled, delays, and temporary storage.
King Saud University College of Engineering
Department of Industrial Engineering 14
![Page 15: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/15.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
15
![Page 16: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/16.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
16
![Page 17: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/17.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
17
![Page 18: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/18.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
18
![Page 19: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/19.jpg)
April 14, 2023
Flow Diagrams
• Supplement to Flow process charts to indicate process flow
• Overhead pictorial plan of the facility.
King Saud University College of Engineering
Department of Industrial Engineering 19
![Page 20: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/20.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
20
![Page 21: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/21.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
21
![Page 22: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/22.jpg)
April 14, 2023
Worker and Machine Process Charts
• Show time relationship between the working cycle of a person and the operating cycle of a machine(s) at a single workstation.
• Machine times and operator times must be known for each element
• Chart drawn vertically to scale.
King Saud University College of Engineering
Department of Industrial Engineering 22
![Page 23: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/23.jpg)
April 14, 2023
Worker and Machine Process Charts
• Solid lines represent productive time,
• Breaks indicate idle time,
• Dotted lines represent non-productive time.
King Saud University College of Engineering
Department of Industrial Engineering 23
![Page 24: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/24.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
24
![Page 25: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/25.jpg)
April 14, 2023
Gang Process Charts
• Worker and Machine Process charts showing many workers are called Gang Process Charts.
King Saud University College of Engineering
Department of Industrial Engineering 25
![Page 26: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/26.jpg)
April 14, 2023
Gang Process Charts
King Saud University College of Engineering
Department of Industrial Engineering 26
![Page 27: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/27.jpg)
April 14, 2023
Gang Process Charts
King Saud University College of Engineering
Department of Industrial Engineering 27
![Page 28: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/28.jpg)
April 14, 2023
Two-Handed Process Chart
• Left-hand / right-hand chart
• Operator process chart.
• Is a flow process chart directed at an operator
• Each hand is documented separately.
• Useful when doing work methods analysis.King Saud University
College of Engineering Department of Industrial Engineering
28
![Page 29: 3 work charting_methods](https://reader031.vdocuments.site/reader031/viewer/2022032715/55b1522cbb61eb73258b463a/html5/thumbnails/29.jpg)
April 14, 2023King Saud University
College of Engineering Department of Industrial Engineering
29