Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines 1 Monthly Report of PMIC for April 2016 CAMBODIA: Uplands Irrigation and Water Resources Management Sector Project ADB Loan 3289 – CAM PRIMEX (Philippines) in association with OCG (Japan) and CADTIS (Cambodia) May 2016

Upload: others

Post on 26-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

1

Monthly Report of PMIC

for April 2016

CAMBODIA: Uplands Irrigation and Water Resources Management Sector Project

ADB Loan 3289 – CAM

PRIMEX (Philippines) in association with OCG (Japan) and CADTIS (Cambodia)

May 2016

Page 2: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

2

Ministry of Water Resources and Meteorology Uplands Irrigation and Water Resources Management Sector Project

ADB Loan 3289 – CAM [SF]

Monthly Report of PMIC For April 2016

1. This report relates the activities and accomplishments of the Team of PMIC for the month of April 2016. It also discusses the issues and concerns encountered and suggested solutions. A. Consultants’ Mobilization 2. The initial mobilization of PMIC was on 15 February 2016 following the request of the Executing Agency (EA) during the signing of the consultancy services contract on 29 January 2016. For the month of April, the composition of consultants on board was as below:

Name Position Mobilization Date International Consultants 1. Dr. Jose A. Galvez Team Leader 15 February 2016 2. Mr. Bienvenido Gilles M & E Specialist 20 March 2016 National Consultants 3. Mr. Srey Socheat 1/ Deputy Team Leader 18 April 2016 4. Mr. Cheng Saroeun Hydraulic Structures Engineer 1 March 2016 5. Mr. Roeun Sophanna Procurement Specialist 15 February 2016 6. Mr. Fuch Pouk FM/ Accountant Specialist 1 March 2016 7. Mr. Ouk Daren M & E Specialist 1 March 2016 8. Mr. Chhit Kimhor Hydrologist 1 March 2016 9. Mr Prack Sokha Gender Specialist 1 March 2016 10. Mr. Vong Dara Construction Management Engineer,

KTh 15 February 2016

11. Mr. Vuth Sivorng Construction Management Engineer, Batt.

15 February 2016

12. Ms. Heng Thavy Assistant Engineer, Batt. 1 March 2016 13. Mr. Sok Piseth Materials/QC Engineer, Batt. 1 March 2016 14. Mr.Doeur Davuth Materials/QC Engineer, KTh 2 March 2016 15. Mr. Sar Samath Assistant Engineer, KTh 7 March 2016 1/ Mr. Srey Socheat as Deputy Team Leader in place of Mr. Lim Dalika was mobilized on 18 April

2016 based on an email of the PD to put him on probation for 2 months from April. B. Activities of the Consultants for April 2016 3. On Project Management – The consultants carry-out the following: (i) assisted in the finalization of bid evaluation report of the hydromet/automatic weather stations including in the review of PRC and contract document; (ii) continue assistance on financial management (FM) system including the Imprest Account, chart of accounts, FM forms and report format; (iii) assisted in the preparation of documents for the interim payment claims of contractors; (iv) assisted in the inspection of delivery of equipment and vehicles particularly in preparing asset inventory record; (v) prepared the M&E framework and the PPMS manual of procedures; (vi) conducted field work preparatory social assessment and baseline data establishment in O Kra Nhak subproject; (vii) undertake site inspection of TK and PC; (vi) prepare back-to-office report after each site visit; (viii) prepare draft quarterly progress report

Page 3: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

3

no. 1 and monthly reports for March; (ix) assisted in the review and assessment of bill of quantities resulting from the joint survey.

4. On TK and PC – Main activities include; (i) continue conduct of joint survey with contractor to firm-up bill of quantities and scope of work of TK and PC main canals and head works; (ii) assess and identify the proposed secondary and tertiary canals; (iii) review the proposed construction drawings of the TK and PC; (iv) identify and locate all benchmarks on the main canals and location of secondary canals; (v) review and evaluate all test results of materials submitted by contractors; (vi) review and evaluate the work plan and program submitted by contractors; (vii) supervise construction of contractors on the main canal and head works; (viii) carry out spot survey of elevation of invert and top of existing structures, canal embankment and prepared line-diagram comparing this on design elevation of canal bed, water level and embankment crest; (ix) inspection of construction site to resolve identified problems; (x) collect, compile and test hydrology and meteorology data; (xi) prepare terms of reference for the hydrographic and topographic survey of the reservoirs for the study; (xii) prepare program for the computation of water duty for secondary canals and assess design discharges for the design of drainage structures; and (xiii) prepare data requirements for FS, DD and joint reservoir operation study. C. Accomplishments for April 2016 5. On Project Management the Consultants accomplishments are: (i) bid evaluation report for the bidding for the supply and installation of hydro-met and automatic weather stations and minutes of review of by the PRC submitted to ADB on 23 April, (ii) financial management system including forms and Imprest Account establishment, (iii) withdrawal application for the advance payment of TK, procured vehicles, office equipment and furniture, office renovation, advance payment of PC, (iv) quarterly progress report submitted on 19 April, (v) draft PPMS framework and procedures for finalization and submission to ADB, (vi) back to office reports on field inspections on 19-21 April (Annex A) and 20-22 April 2016 (Annex B), and (vii) back to office reports on Focus Group Discussions (FGDs) conducted in O Kra Nhak subproject (Annex C). 6. On TK and PC subprojects the accomplishments are: (i) completed joint survey of the main canal but firmed-up quantities are still being computed; (ii) in TK completed the revision of the main canal and bill of quantities from 0+000 to 16+040; (iii) acceptance of tested materials for construction; (iv) revised design of TK main canal Ch. 17+300 to 18+542 to avoid resettlement problems; (v) proposed solutions to problems identified on headwork and spillway of TK including drawing and BOQ; (vi) identified location and technical descriptions of bench marks along main canals; (vii) staked out locations of secondary canals; (viii) design coded location and bed level of existing and new structures along main canals; (ix) revised work program of contractors to give priority to headwork and spillway during the dry season months of March and April, (x) start revision of works in Prek Chik to address excessive quantity estimates on excavation and embankment fill. The monthly progress reports for April for TK and PC core subprojects are attached as Annexes D and E, respectively. D. Issues and Concerns 7. The proposed rehabilitation of the TK headwork (structure constructed during Pol Pot time) missed to address the weak sections of the structure. This was discussed in the previous report. PMIC is now working on the construction drawings and cost estimates of the headwork, spillway, and other structures that require revision because of extended crest width of main canal.

Page 4: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

4

8. In Prek Chik, the issues are discussed in detail in the BTOR and include (i) design water level could not be attained because of flappy gates crest lower than elevation of spillway, (ii) BOQ of joint survey is extremely large compared to contract quantity, (iii) proposed embankment crest would excavate existing embankment, (iv) excavation of proposed canal bed would expose foundation of existing structures. Field inspection carried out in April results to some revisions of canal elements and new BOQ and drawings are being worked out. The outcome of this activity would require mutual agreement with the contractor. Also it is anticipated that there would be some amendment because of increase in quantities of some work items, particularly on the earthworks of the main canal. 9. The activities for next month are the following:

a. Continue collecting and reviewing project data and relevant information undertaken

during the PPTA; b. Mobilize additional consultants, particularly the engineers, to strengthen the

construction administration and the design of proposed secondary and tertiary canals; c. Carry out the joint survey on the civil works contracts of TK and PC and finalize the

bill of quantities and civil works contract price; d. Continue construction supervision activities of the contractors for TK and PC; e. Initiate the data collection, particularly the topographical survey of the proposed

secondary and tertiary canals in TK and PC; f. Together with the safeguards specialists, assess and categorize the status of the

secondary canals on resettlement, environment, and gender issues; g. Initiate collection of data and relevant information on hydrology for the joint reservoir

operation studies for TK and PC and the feasibility study of non-core subproject; h. Establish the financial management system, and the project performance

management system; i. Determine the design water duty to be used for the DD of secondary and tertiary

canals; j. Finalize the draft inception report; k. Prepare corresponding monthly report of the PMIC and establish the data system for

the project performance monitoring system; and l. Carry out other activities that PMU may require from time to time.

Prepared by Jose A. Galvez, Ph D Team Leader, PMIC

Page 5: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

5

ANNEX A: Back to Office Report on field inspection of 19-21 April 2016

Ministry of Water Resources and Meteorology Uplands Irrigation and Water Resources Management Sector Project

ADB Loan 3289 – CAM [SF]

Field Inspection of PC Subprojects 19-21 April 2016

Respectfully submitted to the Deputy Director General of Technical Affairs and Project Director, Ministry of Water Resources and Meteorology: The field inspection of the Prek Chik subproject was successfully completed and I am pleased to inform the Project Director about the findings, observations and recommendations of the Project Management and Implementation Consultants Team. Objectives of the inspection:

1. Review of the results of the Joint-Survey of Contract No. MOWRAM-CW06, “Upgrading, modernization and rehabilitation of Prek Chik (PC) Irrigation canal in Battambang province”;

2. Meeting with Contractor and CME Team about the joint survey outcome; 3. Field inspection of the main canal and sections where there are major departure from

the contract BOQ; and 4. Agree on activities to be undertaken as next steps to immediately come up with final

BOQ.. Participants: A. From PMIC:

1. Jose A. Galvez – Team Leader 2. Srey Socheat – Deputy Team Leader 3. Cheng Saroeun – Hydraulic Structures Engineer 4. Vuth Sivorng – Construction Management Engineer, Battambang 5. Heng Thavy – Assistant Engineer, Batt 6. Sok Piseth – Materials/QC Engineer, Batt 7. Sear Sokhoang – CAD Operator, Batt

B. From MOWRAM/ PDWRAM

8. Im Soursdey – Technical Assistant, PMU 9. Assistant to Mr Soursdey

C. From Contractor:

10. Ong Kotaro – Project Manager, KBH Construction Co., Ltd. 11. Chhoeun Naro – Deputy Director, KBH Construction Co., Ltd.

Activities and schedule:

1. 19 April – Travel to PC and conduct meeting with Team and Contractor representatives. Field inspection of spillway and flappy gates and portion of MC.

Page 6: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

6

2. 20 April – Field inspection of other section of MC. Discussion on the activities to be carried out. Prepare line diagram of main canal elevation and chainage.

3. 21 April – Travel back to Phnom Penh. Findings, observations and recommendations: Joint survey result for the main canal

The bill of quantities (BOQ) for the main canal rehabilitation as estimated and submitted by the Contractor and CME1 Team compared to the contract BOQ is summarized below.

These quantities were obtained using the present canal cross-section at interval of 50 m compared with the PPTA-design canal cross section. The design cross-section is based on water level elevation of 22.30 m and embankment crest elevation of 25.00 m at Ch. 0+000. The results of the joint survey are staggeringly high compared to the BOQ on items no. 3.02 and 3.05 (excavation and embankment fill). The problems associated with the joint-survey results are: (i) the quantities of excavation and embankment fill are extremely large compared to contract, it is almost unbelievable; (ii) the unit rate for excavation at $20 per m3 is also extremely high; the engineers’ estimate was $2.0 per m3 and the present rate at TK is only $1.30 per m3; ; (iii) the joint-survey results have no data on the other BOQ items. The field inspection on the spillway and flappy gates The elevation of the spillway crest is at 21.10 m while the flappy gate crest is at 21.08 m. The PPTA design will increase the height of the spillway by 1.2 m to a crest elevation of 22.30 m. The crest of the flappy gate, on the other hand, will remain at 21.08 m as the proposed improvement on the gate and structure is confined on the lifting mechnism, that is, by installing hand-cranked gear box to lift the steel gate. In effect, the crest of the flappy gates would be lower than the final crest of the spillway by 1.22 m after the rehabilitation of the structures. This will make the spillway useless as long as the water level is below elevation 22.30 m and all these flood discharges would pass through the flappy gate. Also, the design water level on the main canal at elevation 22.30 m could not be attained as the water would simply escape through the flappy gates. The line diagram shown in Annex A gives an idea why the BOQ on excavation and embankment backfill resulted to extremely large quantities. The proposed embankment crest would require excavation of the existing embankment from Ch. 1+200 to Ch. 20+000. Also,

1 CME = Construction Management Engineer

Contract Contractor CME Team Contractor CME Team

3.01Provide clearing and grubbing work 

with overall width and the whole 

length of the main canal m2 0.30 552,000.00

No data No data

3.02Excavation to form the main canal 

section, no haul m3 20.00 276.00210,059.68 209,082.60

209,783.68 208,806.60

3.05Embankment fill from borrow area 

or stockpile with haulage distance 

not exceeding 2,000 m m3 5.00 44,629.20

352,126.43 347,545.70

307,497.23 302,916.50

3.07

Supply and placing approved 

laterite on top of new embankment 

to form as road, with 150 mm 

thickness, and 5 m width m3 28.00 2,625.04

No data No data

Quantity Estimate Difference Rate, $UnitItem DescriptionNo.

Page 7: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

7

the backfill is necessary from Ch. 21+425 to Ch. 27+600. On the canal bed, there are also large quantities of excavation and backfill. Recommendations and Next Steps The first item for resolution is the final elevation of the crest of the spillway and the flappy gates. The crest elevation of the two structures must be the same to make sure these structures function in unison or at the same time. This situation will ensure that the structures are synchronized and more efficient. The existing condition in the field is such that the crest of the flappy gates cannot be raised to elevation 22.30 m, the proposed crest elevation of the spillway. The beam of the bridge supporting the flappy gates structure is only 0.85 m higher than the crest (see picture of the flappy gate). We could not even raise the crest by 0.85 m as flow would be suppressed. We could however set the crest of the flappy gates at elevation 21.50 m and adopt this as the crest elevation of the spillway, hence the water level elevation would be 21.50 m rather than 22.30 m.

If this elevation of the spillway crest is acceptable, then the final canal embankment crest height could be set. With that new computation of the earthwork could be done. This would result to lower quantities both for excavation and embankment backfill. The computation of embankment backfill should consider (i) certain percentage of excavation to be used as backfill, usually 50-60%, (ii) avoid excavating the existing embankment if the crest elevation is equal or higher than the required elevation. In cases such as this, the works would be only leveling and supply and placing of approved laterite on top of embankment. The bill of quantities involved in the improvement of the spillway and flappy gates would also be re-estimated and any un-used allocation could be allocated for additional erosion protection on the downstream section of the spillway and flappy gates outlets. The other items that should be resolved are the unit rates of Item 3.02 and Item 3.05. On Item 3.02 at $20 per cubic meter, the Contractor agreed to use the existing unit rate of Item 7b.01 “structural excavation with leveling and compaction for structure” at $3.50 per cubic meter. On Item 3.05, the Contractor proposed to retain the bid rate of $5.00 per cubic meter. During the meeting on 19 April 2016 at the field office, we did not decide on the acceptable rate. The main reason is that this will eventually depend on the final bill of quantities and the

0.85 m

Page 8: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

8

additional fund that would be required to pursue the execution of the entire contract. As also mentioned during the meeting, depending on the percentage of price increase, prior approval by ADB may be necessary. The agreed next steps are:

(i) Set the water level elevation at 21.50 m, adjust the embankment crest elevation, and canal bed elevation taking into consideration the existing elevation of canal bed and structure inverts;

(ii) Check the hydraulic integrity of the main canal after the adjustments in item (i) and finalize the appropriate elevation of corresponding canal elements such as embankment crest, canal bed, etc. as necessary;

(iii) Re-draw the line diagram at Annex A using the adjusted elevations and identify canal sections where excavation and backfill would be almost uniform and minimal;

(iv) Develop the longitudinal profile of the main canal considering the adjusted water level, embankment crest and canal bed and existing paddy field elevation;

(v) Re-compute the required earthworks considering the following; (a) avoid excavation of the existing embankment if it is equal or higher than the required elevation or where the embankment crest is paved, (b) avoid excavation of canal bed to expose foundation of existing structures, (c) avoid backfill of embankment if adjacent residential houses will be lower than canal embankment such as at Ch. 0+000 to Ch. 1+000, (d) avoid backfill to cover invert of existing structures, (e) consider the invert and top elevations of new structures, and (f) more importantly attempt to balance excavation and fill as a good practice in canal design.

(vi) Review and prepare the estimates for the spillway and flappy gates considering the new crest elevation;

(vii) Review and prepare the estimates for the other structures as the Contractor has submitted revised estimates for the cross drains/regulators on 22 April 2016;

(viii) Summarize all BOQ, including all the drawings, for agreement by PMU and Contractor.

Prepared by J A Galvez, Team Leader

Page 9: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

9

ANNEX B: Back to Office Report on field inspection of 20-22 April 2016

Ministry of Water Resources and Meteorology Uplands Irrigation and Water Resources Management Sector Project

ADB Loan 3289 – CAM [SF]

Field Visit O’ Kra Nhak Irrigation System 20-22 April 2016

The PMIC team has successfully conducted the three days field visit at O’ Kra Nhak Irrigation System project. The purposes and findings of the field visit are described as below: I- Objectives:

To make an overview on OKN irrigation system, the agriculture status, crop types & cultivation, flood & drought issues, farmers’ livelihoods based on OKN project.

To consult and interview with key persons for the present conditions on genders, socio-economy, poverty and FWUCs.

To collect time series data for meteorology and hydrology

II- Participants: A. PMIC experts:

1. Bienvenido Gilles – International M&E specialist 2. Ouk Daren – M&E Specialist 3. Prak Sokha – Gender Specialist 4. Chhit Kimhor – Hydrologist

B. Local participants at Sandan district center:

5. Long Kisoeung – Sandan District Governor 6. Vannak Sorpeanith- Deputy Sandan District Governor 7. Chhork Sim Heang- Officer of Sandan District Office of Agriculture, Forestry and

Fisheries 8. Mil Samay- Chief office 9. Heng Sokoeung- Sandan commune secretary 10. Lak Saochann- Deputy chief of Sandann District Administrative Office 11. Keo Sang- Officer of Sandann District Office of Land Management 12. Ban Heng- Sandann Commune Chief 13. Ou Eang- Chheour Teal Commune Chief 14. Seour Yort- Second Deputy chief of Chheour Teal Commune 15. Srey Siek- Deputy chief of Mean Rith Commune

C. PDWRAM

16. You Lay- Head of PDWRAM 17. Hak Puthy- Deputy chief of PDWRAM

D. Sandan District Agriculture Office of Agriculture, Forestry, and Fisheries

18. Mok Youthnea- Deputy Chief Provincial Dept. of Agriculture, Forestry and Fisheries 19. San Sithan- Chief Office of Planning Office of DPAFF 20. Chhoeung Kimhy- Chief Office of Sandan District Office of Agriculture, Forestry and

Fisheries 21. Hun Kotal- Officer of Agronomy Office

Page 10: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

10

III- Activities and Schedule

1. 20 April (7:30 AM- 12:00 PM)– Travel to Kampong Thom province 2. 20 April (2:30 PM- 4:00 PM)- Courtesy call and meeting with District Governor, Chief

communes, District Office of Agriculture, Forestry and Fisheries, and other officers, to ask for relevant data on socio-economic condition, gender and poverty and hydrologic data and also history of OKN irrigation system…etc.

3. 21 April: Meeting with Deputy Chief of Mean Rith Commune to ask for further data regarding landholding, commune population…etc and also meeting with a few members of FWUC in Mean Rith commune to brief understanding of the current situation of the FWUC and its management. And the PMIC team accompanied by Officer of District Office of Agriculture, Forestry and Fisheries to visit O’ Kra Nhak Reservoir and uses GPS to measure the project land area covered by the irrigation system and also to oversee the situation of OKN irrigation system as a whole.

4. 21 April (2:30 PM- 4:00 PM): Courtesy call and meeting with Deputy Chief of Agriculture, Forestry and Fisheries and his team to discuss on agriculture situation in the O’ Kra Nhak Irrigation System and PMIC team request for relevant data and make recommendation for enhancing cooperation.

5. 22 April– Courtesy call and meeting with Director, PDWRAM Director and PDWRAM team to discuss on current situation of OKN Irrigation System and how to improve and some technical issues especially hydrologic aspect. And both parties have made recommendation to enhance the cooperation for development of OKN irrigation system.

6. 22 April – Returned to Phnom Penh but on the way, the PMIC team visited Taing Krasaing head office and went to see the Taing Krasaing main canal and meeting with women workers who are working in the construction works and also meeting with contractor manager to submit and explain the M&E forms for fulfill at every end of months.

IV- Findings with schedule:

Date Locations Data-Information Participants

20-April, PM Sandan District - Hard copies for Monthly rainfalls, and partly daily water level

- Hard copies of Village Data Book for Chheu Teal Commune and Sandan Commune.

- Relevant data: Project common

area=700ha Socio-economic data Gender Data Agriculture situation Major Problem of

farmers. Sources of income Cropped calendar 1 FWUC located in

Mean Rith commune Commune challenges Others

15 person (PMIC=4 person + Districts and Commune=11person)

21-April, AM Sandan District and O’ Kra Nhak

- Data on socio-economic condition at Mean Rith

6 persons (PMIC=4 person + 1 Mean Rith

Page 11: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

11

Date Locations Data-Information Participants

Irrigation System Commune - Data on OKN Irrigation system:

It was built in 1976 It was damaged in 1990 It was first rehabilitated

in 1995 and second rehabilitated in 2005-2006.

Dame of OKN Irrigation system is 3 Km.

Others

commune +1 Officer of Sandan District Offices of Agriculture, Forestry and Fisheries

21-April -PM Provincial Dept. of Agriculture, Forestry and Fisheries

- Sources of farmers’ income 85%- 90% derived from

paddy, 5 % from plantation and 5% from selling labor out in their community and outside

Rice yield is 3- 4 ton/ha - No written data is available but

the PD of Agriculture promised to send us by email if any

22- April, AM Provincial Department of Water Resources and Meteorology

- Hard copies for Monthly rainfalls, and partly daily water level

8 persons (PMIC=4 person + 4 persons of District Office of Agriculture, Forestry and Fisheries )

Return to PP - Visit Taing Krasaing main canal - There are about 20% of women

working in construction works

Phnom Penh 25 April 2016 Prepared by PMIC Team

Page 12: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

12

List of Participants 1. PMIC team No. Name Position Telephone No. 1 Bien Gilles International M&E Specialist 2 Ouk Daren National M&E Specialist 012 322 782 3 Prak Sokha Gender Specialist 012 605 462 4 Chhit Kimhor Hydrologist 012 714 627 2. District Office and Commune Counsel

N0. Name Position Telephone No.

1 Long Kisoeung Sandann District governor 012 456 706

2 Vannak Sorpeanith Deputy Chief of Sandann district governor

012 228 268

3 Chhork Sim Heang

Officer of Sandann District Office of Agriculture, Forestry and Fisheries

092 714 004

4 Mil Samay Chief office 097 580 7100

5 Heng Sokoeung Sandann commune secretary 092 678 243

6 Lak Saochann Deputy chief of Sandann District Administrative Office

092 621 252

7 Keo Sang

Officer of Sandann District Office of Land Management District Office

092 496 601

8 Ban Heng Sandann Commune Chief 097 5555531

9 Ou Eang Chheour Teal Commune Chief 099 457 473

10 Seour Yort Second Deputy chief of Chheour Teal Commune

097 514 3172

11 Srey Siek Deputy chief of Mean Rith Commune

097 333 9935

3. Provincial Department of Agriculture, Forestry and Fisheries No. Name Position Telephone No.

1 Mok Youthnea Deputy Chief Provincial Dept. of Agriculture, Forestry and Fisheries

095 858 596

2 San Sithan

Chief Office of Planning Office of DPAFF

012 783 732

3 Chhoeung Kimhy Head of District Office of Agriculture, Forestry and Fisheries

092 918 018

4 Hun Kotal Officer of Agronomy Office 012 783 963

4. Provincial Department of Water Resources and Meteorology

Page 13: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

13

No. Name Position Telephone No.

1 You La Head of Provincial Dept. of Water Resources and Meteorology

077 666 886

2 Hak Puthy Deputy Chief of DPWRAM 012 834 286

Page 14: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

14

ANNEX C: Back to Office Report on Focus Group Discussions of 20-22 April 2016

Ministry of Water Resources and Meteorology Uplands Irrigation and Water Resources Management Sector Project

ADB Loan 3289 – CAM [SF]

Field Visit To O’ Kra Nhak Irrigation System 27-29 April 2016

The PMIC team has conducted the three days field trip at O’ Kra Nhak Irrigation System project. The purposes and fact findings of the field visit are described as below: I- Objectives:

To meet & consult with the commune councils, village chiefs, FWUCs for Gender Group discussion To meet and consult with the key person to get the relevant data, socio economic condition,

poverty….. To identify the status of hydrology and irrigation facilities: head work, canals and zone of water

irrigation & present operation

II- Participants: A. PMIC experts:

1. Bienvenido Gilles – International M&E specialist 2. Ouk Daren – M&E Specialist 3. Prak Sokha – Gender Specialist 4. Chhit Kimhor – Hydrologist

B. Local participants at Sandan district center:

5. Ban Heng – Sandann Commune Chief 6. Ou Eang – Chheour Teal Commune Chief 7. Chheum Khon – MeanRitth Commune Chief

C. PDWRAM

8. Tang Rotha – Meteo-Hydro officer of PDWRAM III- Activities with schedule:

Date Locations Data-Information Participants 27-April, PM Sandan District - General dialogues for crop cultivations,

issues, irrigation system and group discussion concepts

- Obtained partly time series data in hard copies from vice director of PDWRAM, Mr. Hak Puthy

- Check and verify data obtained from previous field trip and ask for more data regarding land area, cropped area, existing irrigated area.

- Discus with the chiefs of 3 communes to find the methods to successfully conduct Focus Group Discussion.

At PM, the afternoon 7 persons (4,PMIC + 3 Commune Chiefs)

28-April AM and PM

Sandan District and the site of O’ Kra

- Identified marks for flood issue, existing canals, proposed flood

At AM , in the morning 32 persons ( 4,PMIC

Page 15: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

15

Date Locations Data-Information Participants Nhak Irrigation System Project

measures and canal extensions - Identify the current conditions of the

project, reservoir spillway and natural stream, existing longest main canal and reservoir and nearly non-functioning of the irrigation facilities

- Focus group discussion (FGD)with key person of Commune Chiefs, commune councils, Village chiefs, FWUCs members

- To collect the relevant data of Gender issues in Okranhak irrigation scheme related to 3 communes in Sandan district.

- To identify the FWUCs constraint, and suggestions within Okranhak irrigation scheme.

- 3 FGD has been setup to response to questionnaires regarding farmers’ income, average of rice yields, land ownership, varieties of rice crop cultivation in both dry and rainy seasons and challenges in farming livelihood encountered in their families.

+ 28, Commune chiefs, Commune councils, Village chiefs and FWUCs members) ----------------------------------- At PM , the afternoon 4 persons, PMIC.

29-April -AM Stung Chinit Stung TangKrasaing And PDWRAM Office

- Visited the locations of Hydrological and Meteorological Stations

At AM, in the morning 4 persons, PMIC

Phnom Penh 03 March 2016 Prepared by PMIC Team

Page 16: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Subprojects Kampong Thom Provinces Report April 2016.

ANNEX D: Monthly Progress Report – Taing Krasaing Core Subproject, April 2016

Kingdom of Cambodia Ministry of Water Resource and Meteorology

Uplands Irrigation and Water Resource

Management Sector Project ADB Loan 3289-CAM

ASIAN DEVELOPMENT BANK

TAING KRASAING CORE SUBPROJECT

M O N T H L Y P R O G R E S S R E P O R T

A P R I L 2 0 1 6

APRIL 2016

Page 17: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Subprojects Kampong Thom Provinces Report April 2016.

Project Location 

Page 18: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Subprojects Kampong Thom Provinces Report April 2016.

TABLE OF CONTENTS

I. Progress Activities Work I.1 Summary I.2 Progress Work I.3. Activities Works I.3.1 Earth Works I.3.2 Structures I.4 Other Works Activities I.4.1 Join survey on structures I.4.2 Cooperation with Authority Activities II Problem Face: III Solutions: IV Conclusions:

Page 19: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

I. Progress Activities Work I.1 Summary:

The Taing Krasaing core subproject is located in the Tipo, Chroab and Korkoah Commune, Santuk district, Kampong Thom Province in the upland part of the Kampong Thom province in approximate distance of 17 km east of the Kampong Thom municipality.

The contractor has successfully bid competition, UNG SIM SIA Construction Co., Ltd. The schedule of implementation work activities a whole project according to contract 18 months and starting from March 2016 – August 2017. The contractor has mobilized materials and staff on site 15 Feb 2016.

I.2 Progress Work: The contractor have continued activities works and starting some more works locations on a long Main Canal including earthworks and structures.

1. Earthworks: -Clearing and Grubbing: Pk:0+000 - 6+400 -Remove Topsoil: PK0+000-PK:2+000, PK:8+000-PK:17+300 -Excavation: PK: 13+000 – PK:15+600, PK:17+300 – PK:18+000 -Backfill: PK:0+000-PK:2+000, PK: 8+000 – 17+300, 17+300-PK:18+000 2. Structures: -Main Canal Linking concrete PK:16+300 – 17+300 .Lean concrete class ‘’D’’ on slope .Casting concrete class ‘’B’’ both side on beam and slop - Head Regulator PK:0+000 .Continue lean concrete .Continue stone masonry -Spillway: PK:0-778 .Excavation and backfill .Lean concrete .Casting concrete class B on beams - Under Sluice PK:0-867 .Excavation and backfill -Cross Drainage: PK:8+950 . Excavation and backfill .Lean concrete .Casting concrete class B on beam -New Cross Regulator PK:13+050 .Excavation and backfill .Lean concrete .Casting concrete class B on beam All the progress in this month both Earth Works and Structures are 12.77% if compare to the progress plan is more than 9.19% of a total progress plan 3.58% for April 2016. The result of progress works has shown in S-Curve table.

Page 20: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

I.3 Activities Works: I.3.1. Earth Works:

Page 21: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Materials Simple Testing from borrow pit activities:

Page 22: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Field Density Testing Concrete Class B and Back fill Embankment Activities:

Page 23: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Clearing, Grubbing and Remove Top Soil Activities:

Page 24: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Excavation Both Side Embankment on Main Canal Activities:

Page 25: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Backfill Both Side Embankment on Main Canal Activities:

Page 26: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

I.3.2. Structures:

Main Canal Lining Concrete on Lean Concrete and Casting Beam Activities:

Page 27: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Spillway on Back fill and Lean Concrete Activities:

Page 28: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

Cross Drainage on Lean Concrete class D and Casting concrete class B Activities:

Page 29: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

1.4. Other Works Activities: I.4.1. Join survey on structures: The existing structures are on Main Canal and some cross structures will be revised.

I.4.2. Cooperation with Authority Activities: The Survey Location and Situation Activities:

Field works to fine out location for install new structures with village leader

and council commune and PDRAM, MOWRAM staff. Field visit on location construction site

Page 30: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

Taing Krasaing Core Sub Project Kampong Thom Province

II. Problem Face: 1. The contractor difficult to fine materials from borrow pit for backfill embankment

because the land all rice field and low land, any way the contractor can not Excavate depth 2.5m water come out.

2. Nowadays. raining season nearly come, it is problems for contractor to do the works.. III. Solutions: 1. The contractor face to fine source of materials and borrow area location very

far from site works. 2. The contractor should be improve their schedule of works at site in during

raining season. IV. Conclusions: In total, the implement constructions on site are available condition to conduct construction activities and getting result 12.77% of all progress work, if we compare to work plan schedule plan 9.19%. However, we face a little problems related to resettlement issue on the end of main canal.

KPH,Date: 02 April 2016 Prepared By: Vong Dara

CME-KPH

Page 31: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

Pacific Rim Innovation and Management Exponents, Inc. (PRIMEX) 502 Manila Luxury Condominium, 30 Pearl Drive, Ortigas Center Pasig City, 1600 Philippines

ANNEX E: Monthly Progress Report – Prek Chik Core Subproject, April 2016

Kingdom of Cambodia Ministry of Water Resource and Meteorology

Uplands Irrigation and Water Resource

Management Sector Project ADB Loan 3289-CAM

ASIAN DEVELOPMENT BANK

PREK CHIK CORE

SUBPROJECT M O N T H L Y P R O G R E S S R E P O R T

April 2016

Page 32: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

1

TableofContents 1. SUB-PROJECT LOCATION ............................................................................................. 2 2. INTRODUCTION.............................................................................................................. 3 3. PROJECT BACKGROUND ............................................................................................... 3 4. PROJECT DESCRIPTION................................................................................................. 3 5. CONSTRUCTION AND REHABILITATION ACTIVITIES .................................................... 3 5.1 Main Canal Rehabilitation ....................................................................................... 3 5.2 Improvement of Existing Structure ......................................................................... 4 5.3 New Construction Work ........................................................................................... 4

6. DETAIL DESIGN OF SECONDARY AND TERTIARY CANAL ............................................ 5 7. THE ISSUE ...................................................................................................................... 5 8. SOLUTIONS .................................................................................................................... 5 9. NEXT PLAN .................................................................................................................... 5 10. LIST OF CORRESPONDENCES ......................................................................................... 5 11. APPENDIXES .................................................................................................................. 5 Appendix 1- Contractors’ personnel .................................................................................... 5 Appendix 2- Contractor’ equipment .................................................................................... 6 Appendix 3- Contractor’ Work Program for 1st Tree Month ........................................... 7 Appendix 4- Work Progresses .............................................................................................. 8 Appendix 5- Photographs ...................................................................................................... 8

   

Page 33: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

2

1. Sub‐Project Location 

   

Core Subproject Project Location 

Page 34: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

3

2. Introduction  This progress report summarizes the work accomplished ending 30 April, 2016.

3. Project Background The system Prek Chik in Battambang province is located some 250 km from the capital city of Phnom Penh, south of the provincial capital Battambang. It is accessible through National Road No. 5. Between Pursat and Battambang at the municipality of Muong. The distance from Battambang city to Prek Chik headworks is some 50 km.

The total irrigable area of Prek Chik is 20,800 ha. The system is supplied from Bassac reservoir – 14 km away to south-west – at present empty and whose dam at present is undergoing repair to replace 3 missing gates out of 7. This repair is to be completed by March 2016. The Secondaries and Tertiaries system is basically non-existing. All area is rainfed, with 90% on left side, and only some 10% on right side, as system slope right-to-left from main canal flow viewpoint.

4. Project Description Rehabilitation and improvement of Prek Chik include:

a) Rehabilitation of head works (including raising of spillway by 0.5 meters) b) Rehabilitation of 27.6 kms Main Canal and installation of all structures for water control and

distribution, and provision of all drainage works c) Secondary and Tertiary Canals - Part 1 – for a length of 70.2 km, to be able to cover 10,400

ha of net irrigated lands in Phase I. d) Increased focus and associated training in Joint Reservoir Operations for Bassac reservoir, to

improve on water sharing and water scheduling arrangements between linked systems. e) Supply and installation of Hydro-Met stations for water resources monitoring (assisted by the

ADB Flood and Drought Management Project. f) Provision of training to the PDWRAM, FWUCs and the appropriate government agencies on

Water Management, including planning for implementation. g) Organization, mobilization and training of FWUCs in the command area. h) Provision of Project Implementation Management Consultants to manage all activities under

the the project and provide on-the-job capacity building for PMU and MOWRAM personnel.

5. Construction and Rehabilitation activities 

5.1   Main Canal Rehabilitation 

5.1.1 Joint Survey and Firm up the Quantity

‐ Running the Existing Cross Sections drawing (50m of Each) of Existing ground level ‐ Design main canal by (Cross section 50m of Each) ‐ Setting out locations of New Structures ‐ Redesign the code water level at head work by reducing from EL:22.30 to 21.50 at PK:0+000

to 1+400 ‐ Redesign the code Bottom and Top level of new structures ‐ Field visit (Field visit from PMIC PMU, Contractor and Construction Team on 19 April to 21

April go through the Firm up the quantity of MC and Structures). ‐ Back fill on existing Embankment where broken to accessible

Page 35: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

4

‐ Firm up the Quantity (Attach-BoQ Joint Survey Result). There are two parts of Firm up the Quantity of Earth volumn cut fill.

Firm up the quantity of Earth works cut fill for whole sections 27.6km. (earth volumn about Cut=209082 m3 and fill=347545 m3)

Firm up the quantity of Earth works cut fill for by sections: earth volumn from PK 0+000 to 3+800, 7+200 to 8+300, 12+550 to 15+100, 19+100 to 21+500 and 24+650 to 27+600 Cut=154527 m3 and 15+900 to 27+600 for fill=226628 m3). Just leveling, scarifying and clearance on the existing embankment from 0+000 to 15+900.

5.1.2 Earth Work

Site Clearance Remove the some tree and strip rub, rubbish along the main canal from PK 2+000 to 10+000

5.2  Improvement of Existing Structure 

5.3 New Construction Work 

type of Structures Description Location

Head Regulator Not start

Duck weir a) Redesign the new crest level by reduce EL from 22.30 to 21.50 b) Excavation work surrounding structure and compaction and leveling of footing and its structure

Auto flappy gate Redesign the water gate height by raise from level EL 21.08 to 21.5 extrudes about 0.5m.

Cross regulator a) Remove of Existing Cabion matress and geotextiles

b) Soil Excavation and back fill for reforming of canal

PK 21+425

Off take Not start

Type of Structures Description Location

Gross Regulator Structure excavation with leveling and compaction for foundation and structures

PK 1+400

Foot bridge Soil Excavation for bridge footing PK 2+000

Off take-LEFT Not start

Off take-RIGHT Not start

Page 36: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

5

6. Detail Design of Secondary and Tertiary Canal 

a) Locations and Alignment of Secondary canal

6 Secondary canal (SC) No Update

b) Locations and Alignment of Tertiary canal

Not yet done -

7. The Issue In term waiting for Firm up the quantity result of PMIC by joint resurvey with contractor in such missing some items showing in drawings but not including in Bill of contract and the initial estimate was showing big variation works. With this concern the contract has been started with some sections only until the final quantity and new agreement on this update has been approved. The contractor has mobilized only view new constructions and improve on existing structure only. For earth work just start with cutting tree and clearance along the main canal slope both side.

8. Solutions For Improvement of Main Canal can be start only sections was not much difference from Contractor. And Construction and Improvement works encouraged the contractor to mobilize more workers and equipment to the site to be according with the construction schedule and method.

9. Next plan a) Main Canal Clearance along the slope only b) Improvement of Head Work (Duckbill Weir and Autoflappy gate) c) Improvement of Cross Regulator at PK 3+125 d) Improvement of Off take at PK 3+095 (1gate, 1 cell box) e) Construction of New Bridge at PK 1+400 f) Construction of New Cross Regulator at PK 2+000 and 4+700

10. List of correspondences 

11.   Appendixes 

Appendix 1- Contractors’ personnel

Cross Drain Siphon Soil Excavation for Structure foundation PK 23+900

Sampling and Soil testing by

Laboratory Activity Report April 2016

Page 37: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

6

No. Position Name

1 Director Mr. Kong Bunhav

2 Project Manager Mr. Ung Kotaro

3 Site Manager Mr.Nara

4 Surveyor Mr.Pheara

Appendix 2- Contractor’ equipment

No. Equipment Type and Characteristics Equipment On site

1 Excavator (0.8-0.9) m3 6

2 Bulldozer 2

3 Roller (1ton) 1

4 Vibrating Roller (25ton) 4

5 Dump Truck 25m3 3

6 Water Truck 2

7 Manual Concrete Mixer 6

8 Trailer 1

Page 38: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

7

Appendix 3- Contractor’ Work Program for 1st Tree Month

Page 39: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

8

Appendix 4- Work Progresses

(Please find in the PC Contractor Minitoring Report)

Appendix 5- Photographs

New Code level design of New structures

Page 40: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

9

Field visit of MPU, PMIC, Contractor and Construction Management Team

Soil Excavation for New Cross Regulator PK 1+400

Page 41: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016

10

Excavation and removing the existing cabion matress and stone of Existing cross regulator PK 21+425

New site camp and stock pill location at PK 10+545

Page 42: 3. Monthly report for April 2016uplands-irrigation-mowram.gov.kh/giant_uploads/2018/03/3.-Monthly... · The bill of quantities (BOQ) for the main canal rehabilitation as estimated

| P a g e Monthly Progress Report –April-2016