3. creativity phase
TRANSCRIPT
1/29/2015
1
TASK FORCE – VALUE ENGINEERING22ND ICID CONGRESS AND 65TH IEC MEETING, GWANGJU SEPTEMBER
14-20 2014
NOR HISHAM BIN MOHD GHAZALI MALAYSIAN NATIONAL COMMITTEE ON IRRIGATION & DRAINAGE
SECTION 1
VALUE MANAGEMENT – MALAYSIAN PRACTISE
2
1/29/2015
2
INTRODUCTION
Value Management introduced into the Malaysian Government project implementation framework through Economic Planning Unit, Prime Minister’s
Department Circular No. 3-2009. Designed as a key management tool in the
execution of the 10th Malaysia Plan . Reasons for implementation: to enhance project
optimisation and maximise value This presentation demonstrates the value
management process as practised by the Malaysian Government for flood mitigation projects.
3
PURPOSE AND OBJECTIVE OF VM
To identify and analyse options, to remove components and costs not contributing value to the proposed service, system or project objectives without adversely affecting its objectives and functions.
A multi-disciplinary engagement that analyses the functions of designs, projects, services, products, facilities or systems
To maximise benefits and achieve optimal costs. To overcome planning flaws which have resulted in
output or facilities whose performance were not optimal or below their true value potential.
4
1/29/2015
3
RATIONALE
TO OVERCOME PLANNING WEAKNESSES SUCH AS: Poor scoping exercise that failed to accommodate or
consider key options or functions that, with wider consultation, could have been exploited;
Design inadequacies which produced facilities that were limited in its ability to serve a wider clientele;
Poor financial planning and budget preparation to support project requirements;
Poor resource sharing and integration between the government agencies involved (working in silos).
5
6
• Ensure value transition• Ensure value continuity • Ensure value consistency• Manage project risks
maximizing value delivery
• Clear value objectives• Ensure value transition• Ensure value continuity • Ensure value consistency• Manage strategic risks
• Ensure value transition• Ensure value continuity • Ensure value consistency • Review value realization• Learn the lessons & improve
value
criteria
Lessons learned &
Improvement
value
criteria
VA VE VR
1/29/2015
4
1. Information Phase
2. Function Analysis Phase 3.Creativity Phase
VE LAB STAGE
6. Presentation Phase
5. Development Phase 4.Evaluation Phase
PRE LAB STAGE
LAB STAGE
POST LAB STAGE
1. INFORMATION PHASE
2. FUNCTION ANALYSIS PHASE
3. CREATIVITY PHASE
4. EVALUATION PHASE
5. DEVELOPMENT PHASE
6. PRESENTATION PHASE
1 - 2 WEEKS PRIOR TO LAB
3 - 4 DAYS LAB (WORKSHOP)
1 – 2 WEEKS POST LAB FOR PRODUCING VE LAB REPORT;
IMPLEMENTATION - AS SCHEDULED IN THE LAB ACTION PLAN
VE study durationvalue engineering value engineering
The more time that is spent on pre study information gathering &
preparing, the better the study will be”- Steven male et al, 1998 -
©2013JKRMALAYSIA
1/29/2015
5
AuthorizeEntities with executive
authority to take decisions or resolve issues in lab
ConsultExperts who have to be consulted on particular
aspects during lab
InformEntities who have to be
informed on lab decisions ( not to participate)
DoEntities who have to carry
out major tasks of lab recommendations
value engineering
VE study composition
©2013JKRMALAYSIA
FRAMEWORK AND FORMAT
VM is imposed on projects valued at RM50 million above
Can be imposed if deemed necessary by Economic Planning Unit based on project complexity or importance
Consultative and inclusive approach involving all subject matter experts and stakeholders
Lab/workshop environment Every stage guided by forms/templates leading to
final report Endorsed by implementation agency and budget
controllers10
1/29/2015
6
1. INFORMATION PHASE
INTRODUCTION & TEAM BUILDING• Participants’ introduction,
• Ice breaking • briefing on agenda & lab objectives
SHARING OF PROJECT & DESIGN INFORMATION• Review VALUE ASSESSMENT (VA) Report , • Project Brief, • SOA, data, drawing, document, authorities requirement etc
ESTABLISH COST MODEL & CLIENT VALUE SYSTEMS• Validate initial study on Client Value System, • Cost Model
ESTABLISH & PRESENT PARAMETERS• Brainstorm, record and present requirements/ parameters / limitations of VE lab study scope• Agreed parameters (must have) of VE lab study scope [INFORMATION PHASE TEMPLATE]
SECRETARIAT/GROUP LEADER
GROUP LEADER/CONSULTANT
LAB
LAB
VALUE MANAGEMENT Reference : JKR.VE.Lab.06Page No : 1Issue No : 1
List Of ParticipantsRevision No : 00Date
PROJECT : Rancangan Tebatan Banjir Sg Kedah/Anak Bukit, Kedah Darul Aman.
Group : A Date : 10/11/2013 Page : 1/1
NAME POSITION COMPANY TELEPHONE / EMAILTeam Leader :
Team Member 123456789
10
Facilitator
1 Idrus Ahmad TP BBI2 Hassan KPP BPMI3 Rosazlan KPPK BPME
LAB PARTICIPANTS
1/29/2015
7
INFORMATION PHASE TEMPLATE
VALUE MANAGEMENT Reference
: JKR.VE.Lab.01
Page No : 1Issue No : 1
Information Phase Revision No : 00Date : MAC 2012
PROJECT : Rancangan Tebatan Banjir Sg Kedah/Anak Bukit, Kedah Darul Aman. GROUP : A
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 8/10
SCOPE : DATE : 10/11/2013
REF. ISSUES ADDRESSED REMARKS
VALUE MANAGEMENT Reference
: JKR.VE.Lab.01
Page No : 1Issue No : 1
Information Phase Revision No : 00Date : MAC 2012
PROJECT
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4 (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
GROUP : A
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 1/10
SCOPE : GENERAL & PRELIMINARIES ITEMS DATE : 24/06/2013
REF. ISSUES ADDRESSED REMARKS
GENERAL & PRELIMINARIES ITEMS
1 To include all Contractual Requirements
2 To include all S.O.'s Requirements
3 To include all Project Requirements
4 To include all Authorities Requirements
5 To include all Contractor Requirements
INFORMATION PHASE TEMPLATE
1/29/2015
8
VALUE MANAGEMENT Reference
: JKR.VE.Lab.01
Page No : 1Issue No : 1
Information Phase Revision No : 00Date : MAC 2012
PROJECT
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4 (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
GROUP : A
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 1/10
SCOPE : EARTHWORK / DRAINAGE / PAVEMENT / GEOTECHNICAL / PROVISIONAL SUM DATE : 24/06/2013
REF. ISSUES ADDRESSED REMARKS
Drainage Works
1 Must refer to JKR Standard specification and method of measurement (MOM)
2 Refer to JPS guidelines and requirements (where applicable)
3 Proper drainage structures to be provided to cater for actual need
4 To comply Arahan Teknik (Jalan) guidelines, REAM and MASMA guidelines
5 Reevaluate existing drain/culvert and to upgrade as necessary
INFORMATION PHASE TEMPLATE
INFORMATION PHASE TEMPLATE
VALUE MANAGEMENTReference
: JKR.VE.Lab.01
Page No : 1Issue No : 1
Information PhaseRevision No : 00Date : MAC 2012
PROJECT
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4 (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
GROUP : A
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 3/10
SCOPE : EARTHWORK / DRAINAGE / PAVEMENT / GEOTECHNICAL / PROVISIONAL SUM DATE : 24/06/2013
REF. ISSUES ADDRESSED REMARKS
Road Pavement1 Must follow R4 standard2 Must follow ATJ 5/853 Lane width 3.25m4 Climbing lane width 3.25m5 Road shoulder 2.5m width - paved 1.5m, unpaved 1m6 Design speed 60km/h
7Pavement thickness, Wearing Course = 50mm, Binder Course = 60mm, Road Base = 300mm, Sub-Base = 150mm
8 Marginal strip 0.5m
9 Pavement design should consider high volume of heavy vehicle.
10 To include treatment to existing pavement. Eg: resurface and tapping
11 To provide layby for enforcement vehicle parking
1/29/2015
9
2. FUNCTION ANALYSIS PHASE
ACTIVITIES TECHNIQUES OUTPUTSESTABLISH OR
VERIFY PROJECT FUNCTIONS & ALIGN
DELIVERABLES
Brainstorm functions, establish FAST Diagram & align with deliverables
Verified Project Functions & deliverables
[FAST DIGRAM]
ANALYSE FUNCTIONS AT
SPACE / ELEMENT / COMPONENT
LEVELS
Brainstorm functions for selected spaces, elements & components; analyze spaces adjacency & flows
Identified functions of spaces, elements & components understudy [FUNCTION ANALYSIS TEMPLATE]
IDENTIFY MISMATCHES
Discuss and record possible and identified value mismatches
Identified mismatches for value improvement [FUNCTION ANALYSIS TEMPLATE]
PRESENT ANALYSIS Present function analysis & finalize scope of VE lab study (potential for value improvement)
Verified function analysis and agreed scope of VE lab study [FUNCTION ANALYSIS TEMPLATE]
VALUE MANAGEMENT Reference : JKR.VE.Lab.02a
Page No : 1Issue No : 1
Function Analysis Phase (Sheet 1) Revision No : 00Date : MAC 2012
PROJECT GROUP :
LEVEL PAGE :
SCOPE DATE :
REF. SCOPE DESCRIPTIONFUNCTION AREA (m²) USER CAPACITY
REMARKS VERB NOUN TYPE COST (RM) SPECIFICATION
Notes:FUNCTION -
TYPE:B - BASIC FUNCTION
S - SECONDARY FUNCTIONRS - REQUIRED SECONDARY FUNCTION
FUNCTION ANALYSIS PHASE TEMPLATE
1/29/2015
10
VALUE MANAGEMENT Reference : JKR.VE.Lab.02a
Page No : 1Issue No : 1
Function Analysis Phase (Sheet 1)Revision No : 00Date : MAC 2012
PROJECT: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4 (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan GROUP : A
LEVEL : PROJECT/ SPACE/ELEMENT/ COMPONENT PAGE : 1/5
SCOPE: General & Preliminaries Item, Drainage Work, Pavement Works, Road Furniture, Traffic Management & Temporary Road Diversion DATE
: 24/06/2013
REF. SCOPE DESCRIPTIONFUNCTION AREA (m²) USER CAPACITY
REMARKS VERB NOUN TYPE COST (RM) SPECIFICATION
1 GENERAL & PRELIMINARIES ITEMS 1,967,800.00 include CIDB Levy
To include all Contractual Requirements Comply JPS req. B
To include all S.O. Requirements Comply JPS req. B
To include all Project Requirements Comply JPS req. B
To include all Authorities Requirements Comply DOSH req. B OSHA
To include all Contractor Requirements Comply Contr. req. B
2 Drainage Works 568,000.00
Drainage Discharge Water B JKR Spec/MSMA (JPS)
Culvert Discharge Water B REAM
Inlet/Outlet Protection Protect In/outlets B
Sump Collect Water B
Notes:FUNCTION -
TYPE:B - BASIC FUNCTION
S - SECONDARY FUNCTIONRS - REQUIRED SECONDARY FUNCTION
FUNCTION ANALYSIS PHASE TEMPLATE
3. CREATIVITY PHASE
ACTIVITIES TECHNIQUES OUTPUTS
BRAINSTORMING IDEAS
• Apply “Creative & Innovative Thinking” techniques
A broad list of generated ideas [CREATIVITY PHASE TEMPLATE]
RECORD IDEAS
• Record all ideas in templates
• Do not judge yet!
PRESENT IDEAS
• Present to exhaust ideas (go for quantity)
1/29/2015
11
SincereBe open mindRespect othersCreate permissive environmentGood human relationsParticipateRespondAppreciateDo not pre-judgeQuantity first, quality later
RULES OF BRAINSTORMING
…3. CREATIVITY PHASE
Simplify anything?Eliminate anything?
Add anything?Relocate anything?Change anything?Improve anything?
Combine anything?
How else may the function be performed?
“Can
We”…?
What else can perform the
required function?
BRAINSTORMING QUESTIONS..........
…3. CREATIVITY PHASE
1/29/2015
12
VALUE MANAGEMENT Reference : JKR.VE.Lab.03Page No : 1Issue No : 1
Creativity Phase & Evaluation Phase Revision No : 00Date : MAC 2012
PROJECT
LEVEL PAGE
SCOPE DATE
REF.
CREATIVITY PHASE EVALUATION PHASE
GENERATED IDEASClient
acceptability
Functional
suitability
Technical
feasibility
Economical
feasibility
JUDGEMENT(E) - EVALUATE
(I) - INFORMATION
(D) - DISCARD
CREATIVITY & EVALUATION PHASE TEMPLATE
4. EVALUATION PHASE
ACTIVITIES TECHNIQUES OUTPUTS
JUDGE IDEAS
• Judge each generated idea in terms of:
* Client Acceptable
* Functionally Suitable
* Technically Feasible
* Economically Feasible•Judgement on ideas•Ranked ideas (E/I/D)•Shortlisted of “EVALUATE” ideas
[EVALUATION PHASE TEMPLATE]
RANK IDEAS
• Rank each generated idea whether (with consensus):* Evaluate – Potential solution* Information – Potential for
future* Discard – Non potential
PRESENT• Present to shortlist ideas
(judged & ranked as “Evaluate”) as consensus
1/29/2015
13
VALUE MANAGEMENT Reference : JKR.VE.Lab.03Page No : 1Issue No : 1
Creativity Phase & Evaluation Phase Revision No : 00Date : MAC 2012
PROJECT: Membina Dan Menyiapkan 'Viaduct' Dan Lain-lain Kerja Yang Berkaitan Di Seksyen 49, Laluan 4 (KM 157 Gerik - Kota Bharu), Koridor Ekologi Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan : A
LEVEL : PROJECT / SPACE / ELEMENT / COMPONENT PAGE : 1/8
SCOPE : EARTHWORK / DRAINAGE / PAVEMENT / GEOTECHNICAL / PROVISIONAL SUM DATE : 25/06/2013
REF.
CREATIVITY PHASE EVALUATION PHASE
GENERATED IDEASClient
acceptability
Functional
suitability
Technical
feasibility
Economical
feasibility
JUDGEMENT(E) - EVALUATE
(I) - INFORMATION
(D) - DISCARD
GENERAL AND PRELIMINARIES ITEM
A1Can we increase percentage of preliminaries value (from 6.7% to 7.0% or higher)?
/ / / x E
Contractual Requirements
A2Can we include Performance Guarantee Sum in the BQ?
/ / / / E
A3 Can we include Advance Payment in the BQ? / x x / D
S.O. Requirements
A4 Can we reduce the number of vehicles required? X / / / D
A5Can we include motorcycle as vehicle required in the BQ?
X / / X D
Project Requirements
A6 Can we relocate S.O.'s site office nearly to site area? / / / / E
CREATIVITY & EVALUATION PHASE TEMPLATE
4.Evaluation Phase
5.Development Phase
6.Presentation Phase
3.Creativity Phase
4. EVALUATION PHASE
DECISION
AGREE
NOT AGREE
1/29/2015
14
WHETHER:
“EVALUATE” – Potential solution
“INFORMATION” – Potential idea for future
“DISCARD” – Non potential ideas
RANK EACH IDEA (WITH CONSENSUS) TO
SHORTLIST IDEAS FOR FURTHER EVALUATION:
…4. EVALUATION PHASE
VALUE MANAGEMENT Reference : JKR.VE.Lab.03Page No : 1Issue No : 1
Creativity Phase & Evaluation Phase Revision No : 00Date : MAC 2012
PROJECT
LEVEL PAGE
SCOPE DATE
REF.
CREATIVITY PHASE EVALUATION PHASE
GENERATED IDEASClient
acceptability
Functional
suitability
Technical
feasibility
Economical
feasibility
JUDGEMENT(E) - EVALUATE
(I) - INFORMATION
(D) - DISCARD
GENERAL AND PRELIMINARIES ITEM
A1Can we increase percentage of preliminaries value (from 6.7% to 7.0% or higher)?
/ / / x E
Contractual Requirements
A2Can we include Performance Guarantee Sum in the BQ?
/ / / / E
A3 Can we include Advance Payment in the BQ? / x x / D
S.O. Requirements
A4 Can we reduce the number of vehicles required? X / / / D
A5Can we include motorcycle as vehicle required in the BQ?
X / / X D
Project Requirements
A6 Can we relocate S.O.'s site office nearly to site area? / / / / E
CREATIVITY & EVALUATION PHASE TEMPLATE
1/29/2015
15
5. DEVELOPMENT PHASE
ACTIVITIES TECHNIQUES OUTPUTS
DEVELOP IDEAS
• Expand “Evaluate” ideas into workable solutions by evaluating:
* Advantages & disadvantages
* Innovation created
* Risks or constraints
* Cost implication
• Support idea with illustrations, sketches etc
• Detail evaluation of ideas • Recommended ideas [DEVELOPMENT
PHASE TEMPLATE]
FINALIZE IDEAS • Discuss and gain consensus on best ideas for recommendation (if two or more potential ideas)
SUMMARIZE COST
• Summarize costs optimization of all recommended ideas
• Review Cost Model
• Reviewed Cost Model
PROJECT WORK PROGRAMMING
& ACTION PLANNING
• Establish or review project work programme (CPM)
• Develop and agree Action Plan for post lab implementation
• Project Work Programme• Agreed Action Plan
INITIATEPROJECT RISK MANAGEMENT
• Identify and register project risks
• Discuss mitigation measures & responsible party (if possible)
• Identified project risks[RISK REGISTER TEMPLATE
ASSESS VE STUDY
OBJECTIVES
• Assess achievement of each VE Study Objective
• Identify lessons learned • VE Study assessment• Identified lessons learned
DEVELOPMENT PHASE TEMPLATE
VALUE MANAGEMENT Reference : JKR.VE.Lab.04Page No : 1Issue No : 1
Development Phase Revision No : 00Date : MAC 2012
PROJECTGROUP :
RECOMMENDATION BOX:
YES/ NO
EVALUATED IDEA
(From Can We…)PAGE :
DATE : 25/06/2013REGISTRATION NO:1
EXISTING DESIGN / SKETCH COST BREAKDOWN
COST BREAKDOWN
ADVANTAGES / INNOVATION DISADVANTAGES / RISK COST IMPLICATION
realistic estimation increase costORIGINAL DESIGN COST
(RM)
EVALUATED IDEA COST
(RM)
NETT SAVING OR
EXTRA COST
(RM)
1/29/2015
16
DEVELOPMENT PHASE TEMPLATE
VALUE MANAGEMENT Reference : JKR.VE.Lab.04Page No : 1Issue No : 1
Development Phase Revision No : 00Date : MAC 2012
PROJECT
: Membina Dan Menyiapkan 'Viaduct' Dan Lain-lain Kerja Yang Berkaitan Di Seksyen 49, Laluan 4 (KM 157 Gerik - Kota Bharu), Koridor Ekologi Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
GROUP
: ARECOMMENDATIO
N BOX:
YES/ NO
EVALUATED IDEA
: A1: Can we increase percentage of preliminaries value (from 6.7% to 7.0% or higher)? PAGE : 1/26
DATE : 25/06/2013REGISTRATION NO:1
EXISTING DESIGN / SKETCH COST BREAKDOWN
EXISTING preliminaries is 6.7%
EVALUATED IDEA / SKETCH COST BREAKDOWN
Increase preliminaries to 7%
ADVANTAGES / INNOVATION DISADVANTAGES / RISK COST IMPLICATION
realistic estimation increase costORIGINAL DESIGN COST
(RM)
EVALUATED IDEA COST
(RM)
NETT SAVING OR
EXTRA COST
(RM)
SUMMARY OF RECOMMENDATION IDEAS (GROUP A)No Ref Description
Amount (RM) NETT VALUE
(RM)Saving Extra
GENERAL AND PRELIMINARIES ITEM
1 A1 Can we increase the % of preliminaries value from 6.7% to 7% or higher?
2 A2 Can we include Performance Guarantee Sum in the BQ?
3A6 Can we fixed the S.O.'s site office at the open area closed to the site?
A8 Can we allow extra cost and resource for generator set for electrical supply?
4 A10 Can we include any cost for DOSH requirement?
DRAINAGE WORKS
5 A11 Can we include outfall drain for this project?
PAVEMENT WORKS
6 A18 Can we utilize existing road diversion area as replacement of layby?
ROAD FURNITURE
7 A20 Can we include a solar flashing light before approaching this area?
8 A21 Can we install a TL4 safety barrier at the high possibility accident area?
9 A22Can we add a warning signboard 500m and 100m on both side before and after the area to alert all vehicle
driver?
10 A24 Can we change the transverse bar to rumble strip?
11 A25 Can we add 'cat eye' embedded to the parapet wall ?
ENVIRONMENTAL
12 A37 Can we review the overall cost price for EPW?
TRAFIC MANAGEMENT AND CONTROL
13 A27 Can we reduce the used of sheet pile?
14 A29 Can we relocate any of all the services utilities on the existing road?
PROVISIONAL SUM
15 A31 Can we inlude RSA Stage 5 in after CPC?
16 A41 Can we omit Billboard?
MAINTENANCE
17 A38 Can we itemized road and temporary road diversion maintenance?
VARIATION OF PRICE (VOP)
18 A39 Can we review VOP?
PROFESSIONAL FEES
19 A40 Can we review Professional Fees?
SUBTOTAL (SAVING/EXTRA)
NETT EXTRA TO PROJECT COST(EXTRA COST)
DEVELOPMENT PHASE TEMPLATE
1/29/2015
17
4.Evaluation Phase
5.Development Phase
6.Presentation Phase
6. PRESENTATION PHASE
3.Creativity Phase
DECISION?NOT AGREE
AGREE
NOT AGREE
DECISION?
IMPLEMENTATION
AGREE
6. PRESENTATION PHASE
ACTIVITIES TECHNIQUES OUTPUTS
REPORTING • Prepare initial VE report and presentation slides
• Initial VE Report• Presentation Slides• Finalized VE ReportPRESENT &
REVIEW
• Present initial VE Report and obtain stakeholders’ feedback
• Review and finalize VE Report (if necessary)
SIGNING OFF* Not necessarily during lab stage
• Secure stakeholders’ approval (signing-off)
• Approved VE Report* Can be during Post Lab Stage
1/29/2015
18
PART 2
VM for PEKAN FLOOD MITIGATION PROJECT PHASE II
35
Project Background Information
Item
Topic Page
1 PROJECT INFORMATION
1.1 PROJECT BACKGROUND 3-5
1.2 PROJECT INTRODUCTION 6-7
1.3 OBJECTIVE 8
1.4 SCOPE 9
1.5 OUTCOME 10
1.6 PROJECT GIVENS / CONSTRAINTS 11
1.7 PROJECT MUST 12
1.8 FAST DIAGRAM 13
1.9 PRE-LAB PROJECT COSTS 14
2 LAB ANALYSIS 15-16
3 POST-LAB PROJCET COSTS 17
4 LAB SUMMARY AND CONCLUSION 18
5 ACTION PLAN 19-24
7 ENDORESMENT OF LAB DECISIONS 25
8 CASH FLOW PROJECTIONS 26
8 ATTACHMENTS36
CONTENTS
1/29/2015
19
PROJECT BACKGROUND INFORMATION PHASE
37
• Pekan town lies at near the mouth of the Pahang River where
monsoonal floods are common during the months of November till
March
• Flood impact is heightened when heavy rainfall in the town and
surroundings as well as in the upper catchment coincides with high
tide in the South China Sea.
• The worst recorded flooding occurred in 1926 dan 1971.
• Flood of 2007/2008 was the worst in three decades causing much
property loss and disruption of economic activities, power and road
links.
PEKAN
To Kuantan
To Rompin
SOUTHCHINA
SEA
SOUTHCHINA
SEA
LOCATION PLAN
PEKAN
KUANTAN
ROMPIN
BERA
BENTONG
MARAN
TEMERLOH
JERANTUT
LIPIS
RAUB
PROJECT SITE
PROJECT BACKGROUND INFORMATION PHASE
1/29/2015
20
Month, Year Flood Levels (m RL)1926 5.79
Jan,1971 4.85Jan, 2000 3.03Jan, 2001 2.93Dec, 2001 3.91Jan, 2002 3.77Dec, 2003 3.4Dec, 2004 2.99Feb, 2006 2.91Dec, 2006 3.02Dec, 2007 4.01Jan, 2008 2.6Feb, 2008 2.56Jan, 2009 2.89
ARI or Return Period
Event (Year)AUSTEC Report
(Flood Level, m RL)Current Analysis
(Flood Level, m RL)2 - - 3.095 - 3.96 3.6910 - 4.42 4.1525 - 4.88 4.76
(30) Jan 1971 - 4.8850 - 5.49 5.22100 - - 5.69
1926 6.20 5.79
Based on january 1971
event, it was agreed that the
flodd mitigation for Pekan
would target a 30-year ARI
In December 2007, the flood
level was an 8.5 year ARI
event
PROJECT BACKGROUND INFORMATION PHASE
• Pekan Flood Mitigation Project started since the 3rd
Malaysia Planin 1978 and until the 9th Plan in 2010, a total
of RM 22,094,914 had been spent to control the flood.
• Flood areas have increased from 1830 ha. to 2,600 ha.
• Studies have reassessed the flood risk areas and revised
them to 6,200 ha.
• In the 10th Malaysia Plan, MYR XXXX has been allocated
for protection of 6,200 ha.
INTRODUCTION INFORMATION PHASE
1/29/2015
21
U
Poldering Parcel 1
Poldering Parcel 3
Possible Future“Poldering Parcel”
Poldering Parcel 2
PEKAN FLOOD MITIGATION MASTER PLAN
Flood Mitigation for Pekan to be divided into 3 parcels as follows;
Parcel 1 :Royal town of Pekan (2,600 ha)Parcel 2 :Mosque, hospital and Pelangkah Residential Area (1500 ha)Parcel 3. Miang & Durian Sebatang Rivers Agricultural Area (2100 ha)
PROJECT INTRODUCTION INFORMATION PHASE
OBJECTIVE INFORMATION PHASE
42
• To protect Pekan town and its surrounding, Miang
River village to the south, Pulau Keladi to the
west, Pasir Panjang to the east from bank
overflow of Pahang River with a protection level of
30 years ARI.
• To minimise destruction of property, loss of lives
and road connections due to floods in order to
sustain economic activities
1/29/2015
22
ORIGINAL SCOPE INFORMATION PHASE
43
Under the 10th Malaysia Plan, the original scope of works for Pekan
Flood Mitigation was as follows:-
Project area: Pekan Town and surroundings (2600 ha.)
1. Land acquisition from local government Pahang River (102.5
acres)
2. Consultant and survey fees
3. Upgrade and construction of pump houses at Belibis River
4. Construction of flood control bund/levee along Pahang River
(2.7km)
5. Construction of control structures
6. Construction of internal drainage
NO. DESCRIOPTIONAMOUNT
(RM)
1. Preliminary works
2.Upgrading and Construction of Pump houses at Sungai Belibis (Parcel 1)
3. Construction of Flood Protection Bund/levees (Parcel 1)
4.Construction of Flow Control Structures (hydraulic structures) (Parcel 1)
5. Construction of internal drainage system (Parcel 1)
6. Land acquisition (Parcel 1)
7. Consultancy fees (Parcel 1)
8. Provisional Sum, Variation of Price, Supervision (Parcel 1)
9. Parcel 2 (inclusive of Land acquisition, VoP, Preliminaries, Perunding, Supervision, and Prov. Sum)
10. Parcel 3 (inclusive of Land acquisition, VoP, Preliminaries, Perunding, Supervision, and Prov. Sum)
11 Earlier works for Pekan Phase I (completed 2012)
Jumlah :
PRE LAB PROJECT COSTS INFORMATION PHASE
44
1/29/2015
23
OUTCOME INFORMATION PHASE
45
1. Bund and associated flood control structures areable to protect Pekan and its surroundings from twoflood hazards, Pahang River overflow and swampoverflow from the west and south (total area 6,200ha) to a protection level of 30-year ARI.
2. Improvement to internal drainage are able toovercome flash flood occurrences in Pekan towncenter up to protection level of 10-year ARI.
PROJECT GIVENS / CONSTRAINTS INFORMATION PHASE
46
No. ITEM
PROJECT GIVEN
1. Approved total project cost RM 600 million and implemented in phases
PROJECT CONSTRAINTS
1. 10th Plan (RP3-RP4) allocation of RM140 million to be completed by 2015.
2. Phase implementation causes cost increase and delayed achievement of full project benefits
3. Ketapang link – a proposed crossing over a key watercourse separating a residential area in the flood zone - has been approved by the local planners
4. Pekan to Rompin main road upgrading works have been scheduled for completion by Public Works Dept. (JKR) latest by 2017
1/29/2015
24
47
COMMENT = (A = AGREE, D = DISCARD, I = INFORMATION ONLY)
PROJECT MUSTFUNCTION ANALYSIS TEMPLATE
No. ITEM Comment
Project must …
1. Achieve its objective A
2. Be carried in phases and completedlatest by 2019 A
3. Utilities must be relocated before project physical works commence A
4. Land acquisition to be completed before project commences A
5. All relevant agencies / stakeholders affected by the project must engaged/consulted
A
6. If bridges are affected and if alternative routes are 1 km or more away, temp bridges/crossings must be constructed before existing bridges are demolished
A
7. Keep within project allocation ceiling A
8. Erosion & sediment control best practises to be incorporated to the maximum A
9. Improve flow efficiency in existing drainage system A
10. Employ poldering concept A
48
FAST DIAGRAM FUNCTION ANALYSIS
PHASE
Improve river conveyance
Geotechnical works
HOW
Detail Design
WHY
Structures
Earthworks
Divert flow
Flood forecasting
Flood warnings
Flood maps
Non-Structures
Drainage works
Landscape works
Study
Survey / SI
M & E works
Instrument
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences Improve river
conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences Improve river
conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences Improve river
conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences Improve river
conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences Improve river
conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Instrument
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Instrument
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Instrument
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Instrument
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Landscape works
Instrument
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
M & E works
Landscape works
Instrument
Flood maps
Flood warnings
Flood forecasting
Improve river conveyance
Divert flow
Survey / SI
Study
Detail Design
Structures
Non-Structures
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Geotechnical works
Earthworks
Drainage works
M & E works
Landscape worksReplace bridges
Relocate utilities
Produce flood hazard map
Alert community
Forecast flood
Widen / deepen rivers
Improve river conveyance
Build flood bund / wall
Build channel / tunnel
Divert flow
Survey / SI
Study
Detail Design
Implement structural measures
Implement non
structural measures
Acquire land
Flood damages
Flood losses
Flood victims
Reduce flood risk
Flood depth
Flood area
Flood occurrences
Remove constriction
Construction
Install siren
Install system and
instrument
Flood Mitigation
1/29/2015
25
Bil. Question Comment
Can we….?i) Simplify/eliminate/add/combine/transfer or
move/change/modify/exchange
1. Reduce cost of land acquisitioni. Pahang River type 1 bund from RM250,000/acre to RM
200,000/acreii. Pahang River type 2 bund from RM250,000/acre to RM
200,000/acreiii. Ketapang Link from RM250,000/acre ke RM 200,000/acreiv. Collector drain from RM 250,000/acre ke RM200,000/acre
E
2. Change Ketapang Link alignment by considering development proposal to include ‘single carriage way type R2 without shoulder
D
3. Reduce cost of utilities relocation to RM1,000,000.00 E
4. Need for TNB (power) sub station for Belibis Pump Station D
5. Extend type 3 bund to the road junction leading to Pasir Panjang E
6. Remove the proposed TNB sub station at Sungai Mat Dulang Control Structure
E
7. Add TNB sub station for Control structures along Pahang River bund E
8. Examine size of Ketapang Link and replace with bridge with roadculvert
E
9. Re-examine size of control room at Sungai Belibis pump station E
49
“CAN WE…” PARCEL 1 - PHASE II CREATIVITY PHASE
Lampiran 4a
Nos. Question Comment
Can we….?i) Simplify/eliminate/add/combine/transfer or
move/change/modify/exchange
10. Remove the item of protection of existing structures from the PDA E
11. Remove the need of Quality Assurance from the PDA E
12. Deepen Pahang River D
13. Remove the landscape component E
14. Replace borepiles in bund type 2 design with spun piles E
15. Change Type 1design from vertical flood wall to earth bund E
16. Review land area to acquire for bund type 1 design
17. Add land acquisition area for type 1 flood protection bund E
18. Review need of pump of 2500 l/s capacity for Sungai Belibis pump house
D
19. Provide mobile gen-set to replace standby gen-set E
50
“CAN WE…” – PARCEL I, PHASE II CREATIVITY PHASE
Lampiran 4…
(E = Evaluated, D = DISCARD, I = Information Only)
1/29/2015
26
Bil. Question Comment
Can we….?i) Simplify/eliminate/add/combine/transfer or
move/change/modify/exchange
20. Reduce cost of land acquisition
i. Bunds for Parcel 2 from RM110,000/acre to RM 100,000/acreii. Sungai Genuk from RM110,000/acre to RM 100,000/acre
51
“CAN WE…” PARCEL 2CREATIVITY PHASE
Lampiran 4a
(E = Evaluate, D = Discard , I = Information Only)
Nos. Question Review
Can we….?i) Simplify/eliminate/add/combine/transfer or
move/change/modify/exchange
21. Reduce cost of land acquisition
i. Bunds for Parcel 3 from RM110,000/acre to RM 100,000/acreii. Sungai Air Tawar from RM110,000/acre to RM 100,000/acre
E
22. Reduce coverage area for Parcel 3 E
23. Review size of bridge crossing Air Hitam River E
52
“CAN WE…” PARCEL 3CREATIVITY PHASE
Lampiran 4a
Total Ideas = 23Total Ideas Evaluated = 20Total Ideas Discarded = 3
(E = Evaluate, D = Discard , I = Information Only)
1/29/2015
27
1) “CAN WE” Reduce cost of land acquisition
i. Bunds for Parcel 2 from RM110,000/acre to RM 100,000/acre
ii. Sungai Genuk from RM110,000/acre to RM 100,000/acreiii. Bunds for Parcel 3 from RM110,000/acre to RM
100,000/acreiv. Sungai Air Tawar from RM110,000/acre to RM 100,000/acre
REFERENCE: “Can We”for Parcel 1 Phase II no. 1/22 sahaja
Strength: Weakness: Savings : RM5,225,000
Reasonable costs of land acquisition
NIL Addition : RM 0
Lain-lain :
Discussion with Land Office and Evaluation Dept. on 4 & 5 December 2012
53
Skop / Spesifikasi Asal Skop / Spesifikasi Cadangan
RM250,000/ acre RM200,000/ acre
VALUE IMPLICATIONS / RECOMMENDATIONS OF “CAN WE”EVALUATION/DEVELOPME
NT PHASE
Lampiran 5a
54
ii) DETAILED COST PROPOSALS
NOS. ITEM / WORKQUANTIT
YRATE (RM)
AMOUNT(RM)
1 Bund type 1 Pahang River 21
2 Ketapang Link 4.5
3 Air Hitam River 21
4 Collector Drain 56
JUMLAH (RM)
VALUE IMPLICATIONS / RECOMMENDATIONS OF “CAN WE” – samb’
Lampiran5a
iii) COST SUMMARY
Original cost RM
Proposed cost RM
Savings (-) (-)RM
EVALUATION/DEVELOPME
NT PHASE
1/29/2015
28
2) “CAN WE” Add power sub station at Belibis Pump Station if we use existing pump
Rujukan: *refer slide “Can
We” for item Parcel 1 Phase II no. 4/22 sahaja
Strength: Weakness: Savings : RM 220,000
Cost savings Cost will increase if current situations demand an additionasl sub-station.
Add : RM
Not top be included in SCOPE if 2500l/s or more capacity pumps needed
Power interruptions will occur Others :
55
Skop / Spesifikasi Asal Skop / Spesifikasi Cadangan
TNB Sub Station Not in original scope
VALUE IMPLICATIONS / RECOMMENDATIONS OF “CAN WE”
Lampiran 5a
EVALUATION/DEVELOPME
NT PHASE
56
ii) Cadangan Kos Teperinci
Bil. ITEM / Perihal Kerja KuantitiKadar
Harga (RM)Amaun (RM)
1 TNB Sub Station 1
2
3
JUMLAH (RM)
VALUE IMPLICATIONS / RECOMMENDATIONS OF “CAN WE” – samb’
Lampiran5a
iii) Ringkasan Kos
Kos Asal RM 000
Kos Cadangan RM 0
Penjimatan (-) (-)RM ,000
EVALUATION/DEVELOPME
NT PHASE
1/29/2015
29
IDEA
TOTAL SUBMITTEDTOTAL
EVALUATEDTOTAL ACCEPTED
22 19 17
COST REDUCTIONS RM 0
COST ADDITIONS RM 0
FINAL TOTAL (reduction/addition)
RM 0
57
REPORT SUMMARYPRESENTATIO
N PHASE
Lampiran 6
Original Project Scope Lab Analysis Post-lab Project Scope
Land acquisition1.1) RM250,000/ acre1.2) RM110,000/ acre
Members from Evaluation Dept., Pekan Land and DistrictOffice and Office of Land and Mines concur that landacquisition cost can be reduced by RM 50,000/acre andRM10,000/acre respectively
Land acquisition1.1) RM200,000/ acre1.2) RM100,000/ acre
2) River Bund Type 2 –Borepile
Piling system can be switched to spun piles at lower cost 2.1) River Bund Type 2 – Spun pile
3) Land acquisition 15 km Parcel 3 bund/leveee can be targeted at residential andmarked-for-development areas only
3.1) Land acquisition 9.5km
4) Not in scope Necessary to extend bunding to Junection at Pasir Panjangvillage to increase protection of lands marked placed underEast Coast Economic Region (special areas of economicdevelopment)
4) Flood control levee 1.6km long
5) Protection of Existing Structures
Not necessary. 5) Removed from scope
6) Landscaping along Pahang River levee (RM4.8 million)
Landscape necessary for strategic areas 6) Landscaping for strategic areas only (RM2.0 million)
7)Ketapang Link: 10 m channel, bridge 1 unit
Size of Ketapang link can be reduced based on currentneeds. A bridge is unnecessary and can be replaced with aculvert
7) Ketapang Link channel size 5m, twin box
culvert 1 unit
58
LAB ANALYSIS PRESENTATION PHASE
1/29/2015
30
Original Project Scope Lab Analysis Post-lab Project Scope
8) Utilities relocation cost RM1.5 million
Utility companies agree that cost can be reduced by RM500,000.
8) Utilities relocation cost RM1.0 million
9) TNB sub station at SungaiMat Dulang
TNB (power company) assures that existing sub-stations cansupport additional load requirements
9) Removed from scope
10) Not in scope Lab agrees the need for additional power sub-station tosupport control structures along Pahang river bunds due tolong distance to existing sub-stations
10) TNB sub station for control structures along Pahang River bund
11) Control house - area240 m2
Lab agrees that size of control house can be reduced ifstandby gensets are replaced by portable genset
11) Control house – area reduced to 180m2
12) Quality Assurance elements
Quality Assurance elements have already been includedunder preliminary costs
12) Removed from project scope
13) 3 nos. standby Gen-setsat the control house
Lab agrees that mobile Gen-sets are more suitable as usageis not frequent
13) 1 nos. mobile genset
59
LAB ANALYSIS PRESENTATION PHASE
Preliminary Detailed Abstract
BIL. DESCRIPTIONAMOUNT
(RM)
1. Preliminary works
2.Upgrading and Construction of Pump houses at Sungai Belibis(Parcel 1)
3. Construction of Flood Protection Bund/levees (Parcel 1)
4.Construction of Flow Control Structures (hydraulic structures) (Parcel 1)
5. Construction of internal drainage system (Parcel 1)
6. Land acquisition (Parcel 1)
7. Consultancy fees (Parcel 1)
8. Provisional Sum, Variation of Price, Supervision (Parcel 1)
9. Parcel 2 (inclusive of Land acquisition, VoP, Preliminaries, Perunding, Supervision, and Prov. Sum)
10. Parcel 3 (inclusive of Land acquisition, VoP, Preliminaries, Perunding, Supervision, and Prov. Sum)
11 Completed works under Phase I (actual costs)
Total :
POST-LAB PROJECT COSTSPRESENTATIO
N PHASE
60
1/29/2015
31
61
LAB SUMMARY PRESENTATION PHASE
Ob
jeck
tif
• To protect Pekan town and its surrounding, Miang River village to the south, Pulau Keladi to the west, PasirPanjang to the east from bank overflow of Pahang River with a protection level of 30 years ARI.
• To minimise destruction of property, loss of lives and road connections due to floods in order to sustain economicactivities
Pro
ject
sco
pe
Project Area: Pekan and surroundings (2600 ha.)
1. Land acquisition from local government PahangRiver (102.5 acres)
2. Consultant and survey fees3. Upgrade and construction of pump houses at
Belibis River4. Construction of flood control bund/levee along
Pahang River (2.7km)5. Construction of control structures6. Construction of internal drainage
Project Area: Pekan and surroundings (6,200 ha.)
1. Land acquisition from local government PahangRiver (756 acres)
2. Consultant and survey fees3. Upgrade and construction of pump houses at
Belibis River4. Construction of flood control bund/levee along
Pahang River (4.25km)5. Construction of control structures6. Construction of internal drainage7. Construction of bund/levee Parcel 2 (15km)8. Construction of bund/levee parcel 3 (9.5km)
Pro
ject
C
ost s DE
Original Now Difference
XXX XXX MYR 35.14 MILLION
19.5
Original Now
PEKAN FLOOD MITIGATION PLAN PHASE II
5.86 %
50.0
Cei
lin g
2013 2014 2015 70.5
XXX XXX2017 2018 2019 XXX
2016 XXX
2020 XXX
62
ACTION PLAN PRESENTATION PHASE
ACTION BY COMPLETION DATE OUTPUT
1VA report (draft) to VM Section, EPU
JPSM 14 December 2012 Finalise report
2VA report approved and returned to JPS
EPU 21 December 2012Draft VA report approved
3 Report signing ceremony EPU/NRE/JPS 4 January 2013 VA report signed
4
Report circulated :-a. EPU (2 set)b. NRE (1 set)c. JPS Pahang State (1 set)d. JPS Malaysia HQ (1 set)e. National Audit Dept. ( 1
set)
JPSM 11 January 2013Records and reference/action
1/29/2015
32
63
ACTION PLAN – PARCEL 1 PRESENTATION PHASE
BIL ACTION BY COMPLETION DATE OUTPUT
5 Appointment of consultant JPSM 25 February 2013Letter of Appointment
6Prepare design and Biils of Quantities
JPS / Consultants 15 August 2013Design plans and Bills of Quantities ready
7Conduct Value Engineering (VE)
JPS / Consultants 30 August 2013 Design plans and Bills of Quantities finalised
8 Land acquisition JPS / Consultants 30 September 2013Complete land acquisition
9 Prepare Tender Documents JPS / Consultants 30 October 2013Tender Documents
ready
64
ACTION PLAN – PARCEL 1 (continued) PRESENTATION PHASE
BIL ACTION BY COMPLETION DATE OUTPUT
10 Issue Letter of Acceptance JPS / Consultants 25 March 2014 Tarikh milik tapak
11. Construction completed JPS / Contractor 30 October 2017Certificate of Completion
1/29/2015
33
65
ACTION PLAN – PARCEL 2 PRESENTATION PHASE
BIL ACTION BY COMPLETION DATE OUTPUT
12. Appoint study consultant JPSM 01 February 2016Issue appointment letter
13.Conduct Value Engineering (VE)
JPS / Consultants 15 February 2017Design plans and Bills of Quantities ready
14. Land acquisition JPS / Consultants 03 March 2017 Design plans and Bills of Quantities finalised
15. Prepare Tender Documents JPS / Consultants 15 February 2017Land acquisition completed
16. Prepare Tender Documents JPS / Consultants 15 July 2017 Tender Documents
66
ACTION PLAN – PARCEL 2 CONTINUED PRESENTATION PHASE
BIL ACTION BY COMPLETION DATE OUTPUT
17. Letter of acceptance JPS / Consultants 25 September 2017 Site possession
18. COMPLETION of works JPS/Contractor 30 October 2019Certificate of completion
1/29/2015
34
67
ACTION PLAN – PARCEL 3 PRESENTATION PHASE
BIL ACTION BY COMPLETION DATE OUTPUT
19. PREPARE Tender Documents JPS / Consultants 15 July 2017 Tender Dokumen
20. Issue Letter of Acceptance JPS / Consultants 25 March 2018Date of Site Possession
21. Completion of works JPS/Contractor 30 October 2019Certificate of Completion
NO. ORIGINAL PROPOSEDValueAdded
Addition(RM)
Reduction
(RM)
1/22Harga tanah parcel 1 RM250,000/ ekar
Harga tanah parcel 1 RM200,000/ ekar
-
3/22Kos Pengalihan UtilitiRM1.5Juta
Kos Pengalihan UtilitiRM1.0Juta
5/22Tiada dalam skop asal Bund Type 3 ext – 500m
Bund Type 4 – 800mBund Type 5 – 250m
√
6/221 no TNB sub station diStruktur Kawalan Mat Dulang
Tiada
7/22Tiada dalam skop asal TNB sub station di Ban Sg
Pahang Control Structure√
8/22
Skop Ketapang Link -channel 10m, jambatan 1 unit
channel 5 m, twin box culvert
9/22Control house with meeting room
Control house without meeting room
10/22Keperluan Protection Existing Structures
Tiada keperluan Protection Existing Structures
68
SUMMARY OF OVERALL PROPOSAL - VMPRESENTATION
PHASE
Lampiran 7
1/29/2015
35
ENDORSEMENT OF VALUE MANAGEMENT LAB CONCLUSIONS
Project Cost : RM XXX,XXX,XXX.00
Finalised Project Scope
Project Area: Pekan town andsurroundings (6,200 ha.)
1. Land acquisition from lcoalgovernment along Pahang River(756 acres)
2. Consultancy and Survey Costs3. Upgrading and construction of
pump houses at Sungai Belibis4. Construction of flood protection
bund along Pahang River (4.25km)
5. Construction of controlstructures
6. Construction of internaldrainage system
7. Bund construction - Parcel 2 (15km)
8. Bund construction - Parcel 3(9.5 km)
The Ministry of Natural Resources and Environemnt and the Economic PlanningUnit, Prime Minister’s Dept. agree with the scope and costs as decided/agreed inthe Value Management Lab of 03-07 December 2012 for the Proposed PekanFlood Mitigation Project Phase II
Name : XXXXXXXXXXPosition : Undersecretary
Development DivisionMinistry of Natural Resources and Environemnt
Date : ………………………….
Signature
Name : XXXXXXXXXPosition : Director Economic Section-Environment and Natural Resources,
Economic Planning Unit, Prime Minister’s Dept.
Date : ………………………….
SignatureName : XXXXXXXXXXXXXPosition : Director General
Department of Irrigation and Drainage
Date : ………………………….
Tandatangan
69
PRESENTATION PHASE
Nota : VE must be conducted before tendering
Closing Remarks
• VM relatively new but gaining strong momentum
• To adopt VM into various types of development projects and fine tuning intervention criteria
• Establishing pool of experienced facilitators and subject matter specialists
• Improving lab process
70
1/29/2015
36
Thank you
A Contribution by the Malaysian National Committee of Irrigation and Drainage
September 2014
Acknowledgment: Idrus Ahmad & Rohani Ahmad, Dept. of Irrigation & Drainage ; Zawidatul Asma Ghazali (Dept. Of Public Works), Malaysia