Assembly of a Wall with cost and micro production time simulation.
Individual part by Emanuele Bianco 3J group 2
![Page 2: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/2.jpg)
Assembly of a wall- table of contents
1. Documents 2. Wall chosen 3. Wall assembly-timber frame 4. Wall assembly-plywood 5. Wall assembly-insulation 6. Wall assembly-lathes 7. Wall assembly-cladding in walls workshop 8. Wall assembly-assembly wall with gr.floor 9. Wall assembly-cladding at gr.floor workshop 10. Wall assembly-assembly with ceiling 11. Wall assembly-plasterboards 12. Wall assembly-connection with foundation wall n 1 13. Wall assembly-window profile 14. Wall assembly-connection between two units top view 15. Wall assembly-connection between two units section 16. Production flow chart walls 17. Time estimation 18. Manufacturing cost 19. Cost comparison
![Page 3: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/3.jpg)
Assembly of a wall- documents
Property
Analysis
Property
analysis of
timber
![Page 5: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/5.jpg)
Overview of the production flow of wall n. 1 between the workshops
![Page 6: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/6.jpg)
Standard wall construction
![Page 20: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/20.jpg)
Timber frame construction of all units
details
Unit 1 Unit 2
Unit 3
![Page 22: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/22.jpg)
120.30 H for manufacturing of Wall n 1 in fabric
Micro production time simulation details
![Page 23: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/23.jpg)
Manufacturing cost/ elemental cost sigma ( blu book netto uden salær)
details
Manufacturing cost wall n 1: 14270,285DKK
Database Sigma cost wall n 1* 20078,00 DKK
*Prisdatabasen2012/netto/nybyggeri
![Page 24: 3. Assembly of a Wall- 3rd semester individual work Emanuele Bianco](https://reader031.vdocuments.site/reader031/viewer/2022020502/568c48931a28ab491690b725/html5/thumbnails/24.jpg)
Cost comparison details
1: Manufacturing cost wall n 1: 14270,285DKK 2:Database Sigma cost wall n 1* 20078,00 DKK