2017 – 2021 strategic plan - ago.gov.zm · 2017 – 2021 strategic plan ... 17 2.4 stakeholders...
TRANSCRIPT
Prepared by:
The Office of the Auditor GeneralIn collaboration with
Management Development DivisionCabinet Office
June, 2017
2017 – 2021 Strategic Plan
OFFICE OF THE AUDITOR GENERAL
TABLE OF CONTENTS
ACRONYMS ................................................................................................................................................................................ ii
FOREWORD ............................................................................................................................................................................... iii
ACKNOWLEDGEMENTS ............................................................................................................................................................ iv
EXECUTIVE SUMMARY............................................................................................................................................................... v
1.0 INTRODUCTION ............................................................................................................................................................1
1.1 Background .................................................................................................................................................................................1
1.2 Functions .....................................................................................................................................................................................1
1.3 Organizational Structure ..........................................................................................................................................................2
1.4 Strategic Operational Linkages ...............................................................................................................................................2
1.5 Rationale for Developing the 2017-2021 Strategic Plan ....................................................................................................3
1.6 Methodology ..............................................................................................................................................................................3
1.7 Plan Coverage .............................................................................................................................................................................4
2.0 ENVIRONMENTAL ANALYSIS ........................................................................................................................................6
2.1 External Environmental Analysis .............................................................................................................................................6
2.2 Internal Environmental Analysis ...........................................................................................................................................14
2.3 Clients Analysis .........................................................................................................................................................................17
2.4 Stakeholders Analysis ..............................................................................................................................................................17
2.5 Strategic/ Core Issues ..............................................................................................................................................................20
3.1 Vision ..........................................................................................................................................................................................20
3.2 Mission .......................................................................................................................................................................................20
3.3 Goal .............................................................................................................................................................................................21
3.4 Values .........................................................................................................................................................................................21
4.0 OBJECTIVES, STRATEGIES AND PERFORMANCE INDICATORS ................................................................................. 22
5.0 PRE- CONDITIONS ..................................................................................................................................................... 34
6.0 GENERAL ASSUMPTIONS .......................................................................................................................................... 35
7.0 LINKING THE STRATEGIC PLAN TO THE BUDGETING PROCESS ............................................................................... 35
8.0 MONITORING AND EVALUATION OF THE STRATEGIC PLAN .................................................................................... 35
9.0 STRUCTURAL IMPLICATIONS .................................................................................................................................... 36
Appendix I - Indicative Core Functional Structure for OAG ................................................................................................. 37
Appendix ii - Summary of the SWOT Analysis ...................................................................................................................... 38
ACRONYMS
AFROSAI African Organisation of Supreme Audit Institutions
AFROSAI-E African Organisation of Supreme Audit Institutions – English Speaking
CAATs Computer Aided Audit Techniques
CPs Cooperating Partners
HRA Human Resource and Administration
IA Institutional Assessment
ICBF Institutional Capacity Building Framework
ICT Information Communication Technology
IFMIS Integrated Financial Management Information System
INCOSAI International Congress of Supreme Audit Institutions
ISSAIs International Standards of Supreme Audit Institutions
M&E Monitoring and Evaluation
MDD Management Development Division
MPSAs Ministries, Provinces and other Spending Agencies
NAO National Audit Office
OAG Office of the Auditor General
PESTEL Political Economic Social and Technological
PF Patriotic Front
PMS Performance Management System
SAIs Supreme Audit Institutions
SAI PMF Supreme Audit Institution Performance Measurement Framework
7NDP Seventh National Development Plan
SAC State Audit Commission
SWOT Strengths Weaknesses Opportunities Threats
FOREWORD
I am pleased to present the 2017 to 2021 Strategic Plan for the Office of the Auditor General (OAG). This Plan provides a strategic framework for improved audit service delivery.
With the expansion of the mandate of OAG in accordance with the Constitution (Amendment) Act No. 2 of 2016, the Office through this Plan will ensure that public resources are used for national development and wellbeing of citizens. The Office will remain committed to promoting accountability and prudent management of public resources.
The Strategic Plan outlines the priorities of the Office for the period 2017 to 2021. It is my sincere hope and trust that my Office will continue receiving the much needed support from all our esteemed stakeholders for its effective and efficient implementation.
I, therefore, implore my staff to remain committed to ensure successful implementation of the 2017 to 2021 Strategic Plan.
Ron M. Mwambwa Acting Auditor General
ACKNOWLEDGEMENTS
The development of this Strategic Plan would not have been possible without technical support from Management Development Division-Cabinet Office, the Cooperating Partners and other stakeholders. I am grateful for their support. I would also like to thank all members of staff for their commitment and valuable contributions during the consultative process.
Finally, I am grateful to the energetic Core Team that spearheaded the whole strategic planning process from the review of the performance of the Office during the 2014 to 2016 Strategic Plan period to the formulation of this new Plan covering 2017 to 2021.
Davison K. MendamendaDeputy Auditor General – Corporate Services
EXECUTIVE SUMMARY
The Office of the Auditor General (OAG) is the Supreme Audit Institution (SAI) of Zambia and draws its mandate from the Constitution (Amendment) Act No. 2 of 2016 under Article 250 and the Public Audit Act No. 29 of 2016. The Office engaged Management Development Division (MDD) - Cabinet Office to provide technical support to review the performance of the Office during the period 2014 to 2016 and to develop the 2017 to 2021 Strategic Plan due to the following reasons:
• Expiry of the Office of the Auditor General 2014 to 2016 Strategic plan;• Need to take on board national priorities outlined in the Seventh National Development Plan and
the aspirations of the current administration in the revised 2017 to 2021 Patriotic Front Manifesto;• Need to align all national programmes and activities to the electoral cycle; and• Non-attainment of the targets to reduce irregular payments, which instead increased from K26
million in 2014 to K115 million in 2015.
According to the Public Audit Act No. 29 of 2016, the Office of the Auditor-General (OAG) is to be established as the National Audit Office (NAO). The transformation is aimed at enhancing the financial and administrative autonomy of the Office, and strengthening its functions by expanding the mandate to include the auditing of Local Authorities as provided for under the Constitution (Amendment) Act No. 2 of 2016, Article 250 among others. However, the change of the name from OAG to NAO, the operationalisation of the State Audit Commission Act and the Public Audit Act, which are key for the Office to attain administrative and financial autonomy, await the issuing of the Statutory Instruments.
The main function of the OAG is to audit the accounts of State organs, State institutions, provincial administration and local authorities; and other institutions financed from public funds. In this respect, the OAG conducts external audit on these institutions to examine whether the funds appropriated by Parliament or raised by the Government and disbursed have been applied for the purposes for which they were appropriated or raised.
The assessment of the Office‘s performance during 2014 to 2016 and development of the 2017 to 2021 Strategic Plan took a consultative process involving stakeholders namely: staff, management, clients and other stakeholders. The stakeholders were consulted to provide feedback on the performance of the Office and to suggest areas for improvement. The assessment showed an average overall performance of 50% during the period under review although there was exceptional performance in other areas of auditing. The average overall performance was largely attributed to support from Government and Cooperating partners; technical support from regional audit bodies such as AFROSAI-E and the INTOSAI and staff commitment towards work.
This Strategic Plan was developed with a focus on addressing the main challenges faced by the Office and consolidating some of the gains recorded. Against this background, OAG’s strategic direction for the period 2017 to 2021 is illustrated in the following statements:
Vision: “A dynamic audit institution that promotes transparency, accountability and prudent management of public resources.”
Mission:“To independently and objectively provide quality auditing services in order to assure our stakeholders that public resources are being used for national development and wellbeing of citizens.”
Goal: To give assurance that at least 80% of public resources are applied towards development outcomes.
Values:To independently and objectively provide quality auditing services, OAG shall uphold the values of Integrity, Professionalism, Objectivity, Team-work, Confidentiality, Excellence, Innovation and Respect.
Objectives:
In the next five years, OAG will pursue the following objectives:
i. To provide timely and value adding auditing services for enhanced accountability, transparency and integrity of government and the public sector for the benefit of society.
ii. To effectively plan, execute, monitor and evaluate programmes and provide management information for timely decision making and attainment of set objectives.
iii. To efficiently and effectively manage the human resources in order to achieve exceptional individual and organisational performance.
iv. To efficiently and effectively provide financial and administrative services for organisational efficiency and attainment of set objectives.
Key Strategies:
Among the key strategies to realise the objectives are:i. Strengthen the mechanism for follow up on audit recommendations of Parliament;ii. Strengthen the sensitization programme to reduce the number of recurring audit queries; iii. Enforce adherence to auditing standards; iv. Develop and implement a communication strategy;v. Develop and implement a mechanism for follow up on developmental programmes; vi. Develop and implement a Human Resource Strategy;vii. Develop and implement a Performance Management System;viii. Review and operationalise the organisation structure and job Descriptions; ix. Develop and implement a resource mobilization strategy; andx. Develop and implement a monitoring and evaluation mechanism for procurement.
These strategies will result in the following among others:
i. Reduction in the number of qualified opinions and recurring audit queries, demonstrating improvements in the management of public resources;
ii. Improved information management and organizational efficiency, demonstrating enhanced internal processes and organisational capacity;
iii. Positive response from clients and stakeholders, demonstrating a high level of satisfaction; and
iv. Improved positive image of the Office.
1.0 INTRODUCTION
1.1 Background
The Office of the Auditor General (OAG) is a government institution charged with the responsibility of providing audit services to Ministries, Provinces and other Spending Agencies (MPSAs) as well as private institutions which receive government subvention in any financial year. The Office plays an oversight role in the use of public resources appropriated by Parliament or raised by Government.
According to the Public Audit Act No. 29 of 2016, the Office of the Auditor-General (OAG) is to be established as the National Audit Office (NAO). The Auditor-General is the Chief Executive Officer of NAO appointed under Article 249 (1) of the Constitution. The transformation is aimed at enhancing the financial and administrative autonomy of the Office, and strengthening its functions by expanding the mandate to include the auditing of Local Authorities as provided for under the Constitution (Amendment) Act No. 2 of 2016, Article 250 among others. However, the change of the name from OAG to NAO, the operationalisation of the State Audit Commission Act and the Public Audit Act, which are key for the Office to attain administrative and financial autonomy, await the issuing of the Statutory Instruments.
The timelines for submitting audit reports at the end of each financial year have been reduced from twelve months to not later than nine (9) months after the end of each financial year.
The role of OAG in ensuring prudent management and utilisation of public resources is well underscored in the Seventh National Development Plan, which has prioritized enhancing domestic resource mobilisation, reforecasting of public spending and restoring budget credibility to contribute to the well-being of the Nation and achievement of the Vision 2030.
1.2 Functions
The functions of OAG as provided for under the Constitution (Amendment) Act No. 2 of 2016 Article 250 and the Public Audit Act No. 29 of 2016 are as follows:
a) audit the accounts of State organs, State institutions, Provincial Administration and Local Authorities as well as institutions financed from public funds;
b) audit the accounts that relate to the stocks, shares and stores of the Government;
c) conduct financial and value for money audits, including forensic audits and any other type of audit, in respect of any project that involves the use of public funds;
d) Carry out special, environmental, procurement and contract audits or reviews of the state organs, state institutions and private institutions;
e) Ascertain that money appropriated by Parliament or raised by the Government and disbursed has been applied for the purpose for which it was appropriated or raised; was expended in conformity with the authority that governs it; and was expended economically, efficiently and effectively; and
f) Recommend to the Director of Public Prosecutions or a law enforcement agency any matter within the competence of the Auditor-General that may require to be prosecuted.
1.3 Organizational Structure
The OAG is headed by the Auditor General who is assisted by two Deputy Auditors General in charge of the Audit Division and Corporate Services Division. There are seven directorates, of which five (5) are under the Audit Division and two (2) under the Corporate Services Division. The operations are required to be decentralized to all the provinces and progressively to the districts as provided for under the Constitution (Amendment) Act No. 2 of 2016 Article 249 (2).
1.4 Strategic Operational Linkages
In executing its functions, OAG closely collaborates with institutions, such as, the National Assembly, National Prosecution Authority, Drug Enforcement Commission (DEC), Anti-Corruption Commission (ACC), Ministries, Provinces and other Spending Agencies (MPSAs). The NAO also values strategic alliances with stakeholders including, the Cooperating Partners (CPs), Civil Society Organisations (CSOs) and Supreme Audit Institutions, such as, International Organisation of Supreme Audit Institutions (INTOSAI), African Organisation of Supreme Audit Institutions (AFROSAI), African Organisation of Supreme Audit Institutions- English Speaking Countries ( AFROSAI-E) and INTOSAI Development Initiative (IDI).
1.5 Rationale for Developing the 2017-2021 Strategic Plan
The development of the 2017 to 2021 Strategic Plan was necessitated by the national priorities including improving transparency and accountability for enhanced public service delivery and growth in the economy as outlined in the Seventh National Development Plan, and recognition of the role of the Office in ensuring accountability and transparency in the use of public funds from taxes and donors in the revised Patriotic Front Manifesto, the expiry of the 2013 to 2016 Strategic Plan, and challenges faced by the Office during the implementation of the 2013 to 2016 Strategic Plan. The challenges included non-attainment of set targets such as reducing irregularities in the use of public funds. The 2015 Auditor General’s Report for instance, indicated an increase in irregular payments from K26 million in 2014 to K115 million in 2015. Further, the development of the Plan was necessitated by the need to align all national programmes and activities to the electoral cycle.
1.6 Methodology
The OAG engaged Management Development Division (MDD) - Cabinet Office to provide technical support to review the 2014 to 2016 Strategic Plan and develop the 2017 to 2021 Strategic Plan. A Core Team was constituted to spearhead the process, which involved a two pronged approach, that is, Institutional Assessment (IA) and Organisational Development (OD).
The IA involved determination of the performance of the Office during the period 2014 to 2016 and its internal capabilities. Various stakeholders were engaged to solicit for information on the performance and suggest areas for improvement. The views of stakeholders were obtained through a self-completion questionnaire and one-day engagement sessions to allow for free expression of views and building consensus on key issues respectively. The internal capabilities were determined using a number of tools including, the McKinsey 7s Model, Lewin’s Simple Change Management Model, Objective and Problem Trees, SWOT and PESTEL Analyses.
The information gathered informed the determination of the strategic direction for OAG for the next five years in terms of the Vision, Mission, and Goal, Objectives and their related strategies and Performance Indicators. The Plan was validated by various stakeholders.
1.7 Plan Coverage
The rest of the Plan is laid out as follows:
(i) Environmental Analysis
This Section analyses the internal and external environments within which OAG has been operating during the period 2014 to 2016 and provides an outlook for the next five (5) years. Specifically, the Section highlights some key developments that have taken place in the recent past, which have had or might have an impact on OAG’s operations and, therefore, may be of significance in future. These developments relate to political/policy, economic, social,, technological, legal and environmental (PESTEL). In addition, the Section gives some highlights on the performance of the Office during the period 2014 to 2016.
In the process, the Office’s Strengths, Weaknesses, Opportunities and Threats (SWOT) are highlighted. Further, the Section identifies OAG’s clients and stakeholders and their needs and concerns/interests respectively. The Section concludes with the identification of the policy and/or legal challenges (core issues) that need to be addressed for the Office to effectively and efficiently execute its mandate.
(ii) Vision, Mission, Goal and Value Statements
The Vision, Mission, Value and Goal Statements of the Office are articulated under this Section. The Vision statement illustrates the Office’s desired future successful state of being, while the Mission statement defines the Office’s fundamental purpose for its continued existence in the next five (5) years. The Goal statement projects strategically OAG’s broad but realistic targets to be achieved within the Plan period.
Finally, the Section outlines the Values that the Office shall uphold in the execution of its mandate in order to live up to the expectations of its clients, stakeholders and the Nation as a whole.
(iii) Objectives and Performance Indicators
The objectives of OAG to be pursued in the next five (5) years are outlined under this section. The objectives have been developed in line with the Vision, Mission and Goal Statements of the Office and taking into account the outcome of the SWOT, PESTLE, Clients and Stakeholders analyses. The objectives are accompanied by Performance indicators which are variables by which the achievement of the set objectives will be measured.
(iv) Strategies
Strategies, which are the most feasible courses of action to be taken by OAG to achieve the set objectives, and ultimately, the Goal, Mission and Vision, are outlined under this Section.
(v) Pre-Conditions
The critical success factors within the control of OAG that need to be in place for successful implementation of the Strategic Plan are presented under this Section.
(vi) Assumptions
The critical success factors outside the control of the Office that need to be in place for successful implementation of the Strategic Plan are presented under this Section.
(vii) Strategic Plan – Budget Linkage
The success of the Strategic Plan depends on how resources are planned, mobilised and allocated for the implementation of all the activities associated with the identified strategies to contribute to the achievement of the set objectives. Such activities and associated costs will be outlined in OAG’s Annual Operational Plans.
Accordingly, this Section provides general guidelines and underscores the importance of linking the Strategic Plan to the annual budgeting process to ensure that adequate resources are mobilised timely and made available for implementation of the Strategic Plan.
(viii) Monitoring and Evaluation
Monitoring and Evaluation (M&E) is crucial to ensuring successful implementation of the Plan and achievement of the desired impact. This Section, therefore, provides general guidelines and underscores the importance of an M&E Mechanism/Framework to the successful implementation of the Strategic Plan and the realization of the desired impact.
(ix) Structural Implications of the Strategic Plan
This section highlights what the structural implications are in terms of core functions or core business of OAG arising from the Strategic Plan developed. There may be inevitable structural changes that might come about as a result of the desire to address the challenges affecting the Office and achieve the objectives that have been set by the time the Plan expires.
2.0 ENVIRONMENTAL ANALYSIS
The performance of OAG during the period under review was impacted by both internal and external factors as follows:
2.1 External Environmental Analysis
The external environment was analysed using the PESTEL tool and the findings were as follows:
a) Political/ Policy developments
(i) Continuity of the Patriotic Front (PF) in Government
Following the 2016 general elections in which the PF retained the trust of the people of Zambia, there has been continued support to enhance the operations of OAG by the PF Government. During the period 2014 to 2016, the PF Government pledged to and adequately funded the Office to enable it effectively execute its mandate. Government support is further evidenced by granting the Office Autonomy as provided for in the Constitution (Amendment) Act No.2 of 2016.
OAG’s administrative and financial independence will, therefore, be strengthened in line with International Standards for Supreme Audit Institutions (ISSAI 1 and 10). OAG will continue to engage Government to fulfil its commitment to adequately fund the Office. The Office will also put measures in place to ensure prudent utilisation of the resources. In addition, the Office will operationalise the State Audit Commission Act No. 27 of 2016 and the Public Audit Act No. 29 of 2016.
(ii) Creation of New Ministries and Districts
The creation of new ministries and districts has increased the scope and coverage for OAG. The Office will engage Government for increased funding and staffing to enable it carry out its mandate. A resource mobilisation strategy will also be developed for alternative support and the structure of OAG will be reviewed to cater for the new districts.
(iii) Approval of the National Climate Change policy
The approval of the National Climate Change Policy in April 2016 requires commitment from all the institutions to mainstream climate change issues. In this regard, OAG will engage Cooperating Partners for financial and technical support, engage the SAI community to develop an Environmental Audit Manual and increased audit coverage to include issues related to Climate Change.
(iv) Developments in the INTOSAI Community
The OAG is a member of INTOSAI as well as its regional bodies AFROSAI and AFROSAI-E. Over the years, these bodies have adopted various standards and guidelines providing guidance on operations of SAIs. The adoption of ISSAI 12 on the value and benefits of SAIs provides a new framework to understand the uniqueness of the role of SAIs in their respective environments. In addition, the professionalization agenda adopted during the 2016 International Congress of Supreme Audit Institutions (INCOSAI) suggests a path Supreme Audit Institutions should follow to improve Public Financial Management in their country context. At the same meeting, the adoption of the SAI PMF and ICBF also provide useful analytical tools to assist SAIs evaluate their performance.
b) Economic Developments
(i) Increase in Exchange and Inflation Rates
During the period under review, Zambia experienced volatility in the exchange rate which saw the exchange rates increase from $1 = K6.2 in August 2015 to $1 = K15 by January 2016, before averaging to between K9 and K10 at close of 2016. The inflation rate also increased from 7.9% in January 2015 to 21.1% in December 2015 before declining to single digit of 7.2% at end of December 2016. This negatively affected OAG as evidenced by the funding of 64% of the 2016 budget.
To mitigate the above challenges, Office will develop a resource mobilisation plan and prioritise implementation of programmes.
c) Technological Developments
(i) E-Government Initiative and Social Media
The advancements in technology have resulted in the introduction of the E-Government Initiative, which includes Integrated Financial Management Information System (IFMIS), Treasury Single Account (TSA), Smart Zambia Institute, Big Data and Mobile computing. The advancements have also resulted in increased use of the social media, such as, Facebook, Twitter, WhatsApp, Instagram, LinkedIn and Imo. These developments have positively impacted and likely to continue impacting on the operations of OAG. The following have been the major benefits:
• Improved efficiency in the accounting and auditing processes;
• Increase in Audit coverage;
• Savings on hardware and software costs;
• Easy access to information; and
• Increased productivity arising from virtual work environment.
To optimise the developments, the Office will take the following measures:
• Build adequate capacity of staff to make use of the technology;
• Continuously collaborate with Smart Zambia Institute for technical support;
• Maintain the systems and put in place security measures to safe guard the information;
• Strengthen the performance management system to ensure maximum staff commitment to duty; and
• Develop and implement the ICT policy and Plan to guide ICT operations and use in the Office.
d) Ecological/ Environmental Developments
(i) Effects of global warming/industrial pollution
With the effects of global warming/ industrial pollution, the OAG will promote environmental audits which are not currently pronounced. This is in line with the adoption of the United Nations 2030 Agenda for sustainable development which is currently the benchmark against which progress in the area of sustainable development will be measured. This will result in increased audit coverage and
generation of revenue through the SI. The Office will develop and implement a resource mobilisation Plan for funds to increase awareness and recruitment of specialized staff. The Office will also regularly produce up to date reports to gain stakeholder confidence.
e) Legal Developments
(i) Enactment of the State Audit Commission Act No 27 of 2016
The enactment of the State Audit Commission Act No 27 of 2016 established the State Audit Commission and provided for the administrative and financial autonomy of OAG. The Office will develop and implement systems and procedures that will ensure efficient and effective service delivery. The wrong referencing of Article 234(2) (a) to Article 249(2)m, however, has a potential to conflict with the provisions of Article 250 (2) with regard to the independence of the OAG. The Office will, therefore, engage the Ministry of Justice to correct the referencing.
(ii) Amendment of the Constitution of Zambia
The Constitution (Amendment) Act No. 2 of 2016, has provided OAG with the following, among others:
• Reduced timelines for submitting audit reports at the end of each financial year from twelve months to not later than nine (9) months after the end of each financial year - Article 211 & 212;
• Expansion of the mandate to Audit Local Authorities - Article 250;
• Introduction of New Commissions - Part XVIII;
• Decentralization to Provinces & Districts - Article 249(2).
• Powers to recommend prosecution to the DPP or any other law enforcement agency - Article 250(e).
• Appointment of the Auditor General (AG) by SAC; and
• Expansion of types of Audits (procurement audit) - clause 14.
To optimize the developments, OAG will take the following measures:
• Enhance the auditing systems and procedures;
• Sensitize clients on the new audit period;
• Promote transparency in the appointment of the AG;
• Develop and implement a succession plan;
• Recognise deserving staff;
• Enrich jobs to motivate staff; and
• Strictly enforce accounting and audit standards.
(iii) Enactment of the Public Audit Act No. 29 of 2016
The Public Audit Act No. 29 of 2016 provides for the establishment of the Office of the Auditor General under Article 4(1) and for the following:
• Mandate to Charge and Collect audit fees - Clause 32(b);
• Surcharging and Disallowance of expenditure - Clause 26;
• Stipulation of Auditing Standards to follow - Clause 28;
• Appointment of External Auditors by State Audit Commission to audit OAG - Clause 34(2);
• Mandate to make regulation using Statutory Instruments (Sis) - Clause 39;
• Power to examine bank accounts for suspicious transactions - (Part 5-General provisions Clause 36(1);
• Expansion of types of Audits (procurement audit) - Clause 14; and
• Revenue generation
These will result in saving of public resources and reduced misappropriation, production of quality audits, enhanced Transparency and Accountability and positive image of the Office.
OAG will take advantage of the developments by developing regulations on charging of audit fees and modalities to surcharge and disallow expenditure. The Office will also enhance audit procedures and standards and develop and implement capacity building programmes in auditing standards for audit staff
2.1.1 Opportunities
Arising from the external environmental analysis, the following are some of the opportunities that OAG should take advantage of in executing its mandate in the five years:
a) Government support
The Government recognises the important role the Office plays in promoting transparency and accountability (prudent management) in the use of public resources. The Government has, therefore, continued to strengthen governance institutions such as OAG through provision of enabling legislation and funding as well as creating platforms for constructive engagements. OAG will continue engaging government for support.
b) Good Working Relationship with Strategic Institutions
The Office has a good working relationship with Cabinet Office. In this regard, there is efficient provision of administrative services such as facilitating the reorganisation of OAG and management of staff matters. The Ministry of Justice has also been supportive in providing technical support on legal matters. Further, the good working relationship with Ministry of Finance and Ministry of Justice ensures that the Public Accounts Committee (PAC) recommendations made on audits are resolved. In addition, the Ministry of Finance has continued to allow dialogue on issues of funding to OAG whenever need arises. The Office will strengthen collaboration with these stakeholders.
c) Support from Cooperating Partners
Cooperating Partners (CPs) have continued to provide both technical and financial support to the Office in carrying out its mandate. OAG will continue to leverage on this support to mitigate some of its challenges and ensure that all the support provided is put to good use or intended purpose.
d) Availability of SMART Zambia Institute
The SMART Zambia Institute is available to provide technical support in the implementation of ICT strategies in OAG in line with the E-Government initiative which is aimed at enhancing ICT utilisation in the provision of services in the Public Sector. The Office will engage the Institute to improve its ICT infrastructure and skills.
2.1.2 Threats
The opportunities above notwithstanding, there are also a number of threats that have had a negative impact on the operations of the Office and are likely to be of concern during the period 2017 to 2021 unless measures are taken to mitigate the effects. The threats include the following:
a) Delayed Feedback or Approval from External Stakeholders
The timeframe in which feedback or approval from external stakeholders is expected to be received is not within the control of the OAG. This can result in delays in implementation of vital work processes and subsequently fail to deliver the expectations of the citizenry. For example, the operationalisation of the State Audit Commission Act and the Public Audit Act, which are key for the Office to attain administrative and financial autonomy, await the issuing of the Statutory Instruments. The Office will continue engaging institutions and authorities to facilitate successful implementation of this Strategic Plan.
b) Unavailability of Support from Cooperating Partners
Cooperating Partners play a key role in execution of OAG mandate through technical and financial support. In the event that CPs are not available to support the Office, given adverse global economic development, the operations of the Office may be affected. The Office will develop and implement a stakeholder engagement plan.
c) Inadequate and Untimely Funding
Ministry of Finance sets the budget ceiling for the Office according to the national resource envelope and disburses the resources according to the revenue collections. The extent to which the annual work plan of the Office is executed is, therefore, largely dependent on the Treasury. The Office will timely engage the Ministry for timely and adequate funds.
2.2 Internal Environmental Analysis
2.2.1 Performance Against the 2014 to 2016 Strategic Plan
The overall performance of OAG during the period under review was rated as average, at 50%. However, the audit coverage in terms of institutions audited was exceptional at 95%, while expenditure was at 87% with revenue audit coverage being the lowest at 80%. The average overall performance was largely attributed to support from Government and Cooperating Partners, technical support from regional audit bodies, such as, AFROSAI-E and the INTOSAI; and staff commitment towards work among others.
The implementation of the Strategic Plan resulted in improved capacity to carry out more audits in line with ISSAIs, leading to improved quality of audit reports; effectiveness in conducting audits, leading to improved audit scope and coverage and increased number of reports being
published; and enhanced contribution to public awareness in particular, on matters relating to accountability and transparency in the management of public resources.
The major challenges, however were delays in the operationalisation of the SAC and inadequate and intermittent funding. The Office also saw an increase in irregular payments from K26 million in 2014 to K115 million in 2015.
2.2.2 Institutional Assessment
The assessment also revealed a number of strengths and weaknesses that the Office should optimise and mitigate respectively. The following are the strengths, and weaknesses identified:
a) Strengths
(i) Support from Management and Leadership
The management and Leadership of OAG is visionary and committed to ensuring that Office operations are effectively and efficiently carried out. The continuation of this support will enable the office to improve its operations in tandem with the evolving external environment, the national development priorities and to meet the expectations of stakeholders. The Staff will continue engaging management and the leadership for their support and guidance in implementing programmes of the Office.
(ii) Availability of Qualified and Competent Staff
The Office has qualified and competent staff in various disciplines of auditing. As of December 2016, the Office had fully qualified accountants which included ACCA-99, CIMA-8, ZICA-24, Bachelor in Accountancy-35 and other Degrees-25. This has enabled the Office to execute its mandate in a professional manner. OAG will continue building the capacity of staff and set specific individual targets to ensure timely implementation of programmes.
(iii) Availability of the Learning and Innovation Centre
The Office has a Learning and Innovation Centre used for conducting in-house training programmes. This has enabled the Office to save training costs. The Office will build the capacity of the Center and develop tailor made programmes for OAG staff.
(iv) Legal Provisions to Mobilise Resources
The Constitution (Amendment) Act No. 2 of 2016 and the Public Audit Act No. 29 of 2016 have provided the Office with opportunities of raising revenue through charging of audit fees in addition to the funding from the Treasury. Currently, funding to the Office has been erratic and not adequate. Consequently, the audit coverage has been negatively affected. Therefore, the opportunity to generate own revenue will enable the Office to increase its audit scope. The Office will, therefore, develop relevant regulations to facilitate revenue generation.
(v) Availability of the Integrity Committee
The Office has in place an Integrity Committee (IC) whose role is to deter corrupt activities and maladministration in the institution. The availability of the Committee promotes ethical values in the Institution. In this regard, the Office will actively engage the Committee to ensure adherence to the ethical values.
a) Weaknesses
(i) Resistance to change
The Office has in the recent past been undergoing change in all its work processes. However, instances of resistance to change have been observed during the transition period. As a result, this has negatively affected the pace of implementation of certain activities in the Office.
The Office will develop and implement a change management programme to enable staff understand and appreciate the importance of the changes taking place in the institution.
(ii) Lack of Understanding of the Role of the Integrity Committee
Despite the availability of the Integrity Committee in the Office, there is little understanding of the role of the Committee. As a result, the Office is not benefiting fully from the work of the Committee which promotes ethical behaviour among staff. There is need, therefore, for the Committee to actively engage the staff by sensitising them on the role of the Committee.
(iii) Ineffective Communication
There are instances of ineffective communication among the staff and this has led to misinterpretation of information. A communication strategy will be developed and implemented to promote effective communication and team building among the staff.
(iv) Inadequate ICT infrastructure and equipment
The Office lacks adequate Information Communication Technology (ICT) infrastructure and equipment to sustain the ICT needs, such as, the automation of audit processes and the integration of operational systems. This has contributed to the delayed completion of audit assignments and challenges to access information within the Office and outside. The OAG will develop and implement an institutional ICT policy to enable the Office to automate and integrate the systems.
(v) Inadequate capabilities to develop and manage ICT systems
There are inadequate skills amongst the staff to develop ICT systems. This has made it difficult for the Office to implement some of its ICT strategies and the e-Government initiatives that are aimed at enhancing the efficiency and effectiveness in the operations of the Office. OAG will develop and implement a skills capacity building programme for staff. A summary of the SWOT Analysis is at Appendix ii.
2.3 Clients Analysis
Ministries Provinces and other Spending Agencies that receive or manage public funds were identified as OAG clients. The client survey undertaken identified the following as their needs:
a) Quality Audit Services
The clients expect to receive quality audit services by:
• Actively interacting with clients during the audit process;
• Timely completion of audits;
• Widening the audit scope;
• Rotating staff on audit assignments;
• Exhibiting ethical behaviour; and
• Carrying out value for money audits.
b) Provision of Advisory
The clients indicated that the Office should be able to offer advisory services in addition to the audit services they are currently receiving. This will assist in resolving a number of audit queries.
2.4 Stakeholders Analysis
The Office identified sixteen (16) stakeholders whose interests/concerns are presented in the table below.
S/N Stakeholder Inter est/ Concerns
Parliament • Timely production of quality and value adding Audit reports
• Timely production of PAC status reports
Cabinet Office Timely production of the OAG administrative report.
Ministry of Finance • Timely certification of accounts and production of PAC status reports
• Timely production of performance audit reports• Prudent utilisation of funds
Media Institute of Southern Africa – Zambia Timely production of quality Audit Reports and the impact
Drug Enforcement Commission • Timely production of Financial and Forensic Reports• Effective collaboration • Provision of expert witnesses
Zambia Information Communication Authority • Adherence to ICT regulations and Standards • Adherence to professional ethics
Transparency International Zambia Timely production of quality Audit Reports and the impact
Jesuit Centre for Theological Reflection Timely production of quality Audit Reports and the impact
Anti-Corruption Commission • Timely production of Financial and Forensic Reports• Effective collaboration • Provision of expert witnesses
S/N Stakeholder Inter est/ Concerns
Zambia Public Procurement Authority • Enhanced quality of procurement audits• Effective collaboration
Cooperating Partners • Enhanced provision of audit services to Government and donor funded projects
• Prudent utilisation of funds and the impact
Policy Monitoring and Research Centre • Timely production of quality Audit Reports and the impact
• Effective collaboration
Professional Bodies (ACCA, ZIHRM, ZICA, CIMA, ZIPS, ICTSZ e.t.c)
Adherence to professional ethics and standards
Financial Intelligence Centre • Timely production of Financial and Forensic Reports• Effective collaboration
Civil Society for Poverty Reduction Timely production of quality Audit Reports and the impact
Supreme Audit Institutions Community (INTOSAI, AFROSAI, AFROSAI-E, IDI)
• Timely production of quality Audit Reports and the impact
• Adherence to professional ethics and standards• Effective collaboration and active participation in various
programmes.• SAI Zambia has contributed significantly in various
forums e.g the INTOSAI Working Group on Public Debt, and the OAG has been the External Auditor of AFROSAI for the last three years.
General Public • Timely production of quality and value adding Audit reports and the impact.
• An accountable Office of the Auditor General• Prosecution of offenders
2.5 Strategic/ Core Issues
The analysis identified two challenges that require legal intervention. These are, non-operationalization of the SAC because the Office cannot appoint Commissioners, Auditor General & Deputy Auditor Generals and non-operationalization of the Public Audit Act due to the absence of Commencement Orders. The effects have been perceived lack of commitment of the Office to enhance good governance. In addition, the Office has not been able to mobilize resources and surcharge and disallow expenditure by the OAG resulting in the loss of public funds.
The Office will engage relevant authorities on the issuance of Statutory Instrument (SI).
3.0 STRATEGIC DIRECTION
In the next five years, OAG will pursue the following strategic direction:
3.1 Vision
The Office shall, in the next five years, strive to be:
“A dynamic audit institution that promotes transparency, accountability and prudent management of public resources”.
Through this vision statement, OAG has committed itself to overcoming its limitations and accordingly, strategically reposition itself to respond to the concerns of its stakeholders, the needs of its clients and the economy in general. In this regard, the vision will serve as a standard guide in the Office’s promotion of transparency and accountability in the use of public resources appropriated by Parliament or raised by Government.
3.2 Mission
For the next five (5) years the Office has committed itself:
“To independently and objectively provide quality auditing services in order to assure our stakeholders that public resources are being used for national development and wellbeing of citizens”.
Through this Mission Statement, OAG commits enhancing the image of the Office by professionally providing audit services to its clients.
3.3 Goal
In line with the Vision and Mission statements, coupled with the need to further refocus the operations and provide overarching performance benchmarks, OAG has set for itself the goal below to be pursued in the next five (5) years as follows:
“To give assurance that at least 80% of public resources are applied towards development outcomes.”
3.4 Values
To independently and objectively provide quality auditing services, and ensuring attainment of the vision, mission and goals, the Office shall uphold the following core values:
(a) Integrity: Putting the obligations of OAG above one’s personal interests, and conducting oneself in a manner that is beyond reproach;
(b) Professionalism: Exhibiting competence, skills, good judgement, conduct and behaviour.
(c) Confidentiality: Being trustworthy by not revealing or disclosing privileged information to unauthorised persons;
(d) Team Work: Willing to cooperate and effectively contribute and participate as part of the team;
(e) Excellence: Commitment to being the best and/or delivering the best service;
(f) Innovation: Introducing new ideas and methods of delivering our services; and
(g) Respect: Considerate to one another, recognising each other’s differences and understanding the stakeholder’s needs and expectations.
4.0
OBJ
ECTI
VES
, STR
ATEG
IES
AN
D P
ERFO
RMA
NCE
IND
ICAT
ORS
In th
e ne
xt fi
ve (5
) yea
rs, O
AG w
ill p
ursu
e th
e fo
llow
ing
four
(4) o
bjec
tives
and
thei
r ass
ocia
ted
stra
tegi
es in
its q
uest
to a
chie
ve th
e se
t vis
ion,
mis
sion
and
go
al.
4.1
Obj
ecti
ve 1
: To
pro
vide
tim
ely
and
valu
e ad
ding
aud
itin
g se
rvic
es fo
r enh
ance
d ac
coun
tabi
lity,
tran
spar
ency
and
inte
grit
y of
gov
ernm
ent
and
the
publ
ic s
ecto
r for
the
bene
fit o
f soc
iety
4.1.
1 St
rate
gies
, Per
form
ance
Indi
cato
rs a
nd T
arge
ts
Stra
tegy
Indi
cato
rBa
selin
e 20
16Ta
rget
2017
2018
2019
2020
2021
1.St
reng
then
the
mec
hani
sm fo
r fol
low
up
on a
udit
reco
mm
enda
tions
of P
arlia
men
ti.
25%
redu
ctio
n in
the
num
ber o
f qu
alifi
ed o
pini
ons
by D
ecem
ber 2
021
30%
of t
he a
udite
d fin
anci
al s
tate
men
ts
wer
e qu
alifi
ed.
5%5%
5%5%
5%
ii. 9
5% o
f the
inst
itutio
ns a
udite
d an
nual
ly88
% o
f the
inst
itutio
ns w
ere
audi
ted
for
the
2015
acc
ount
s.91
%92
%93
%94
%95
%
iii. 9
0% o
f the
tota
l rev
enue
and
ex
pend
iture
aud
ited
annu
ally
74%
of t
otal
reve
nue
and
expe
nditu
re o
f th
e 20
15 a
ccou
nts
was
aud
ited.
78%
82%
86%
90%
90%
2.St
reng
then
the
sens
itiza
tion
prog
ram
me
to re
duce
the
num
ber o
f rec
urrin
g au
dit
quer
ies
8% re
duct
ion
in re
curr
ing
audi
t que
ries
by D
ecem
ber 2
021
Que
ries
in th
e 20
15 m
ain
audi
t rep
ort
1.6%
1.6%
1.6%
1.6%
1.6%
3.En
forc
e ad
here
nce
to a
uditi
ng s
tand
ards
90%
pos
itive
resp
onse
from
ann
ual
serv
ice
deliv
ery
surv
eys
on s
take
hold
er
satis
fact
ion
by D
ecem
ber 2
018
and
sust
aine
d th
erea
fter
83%
86%
90%
90%
90%
90%
4.
Dev
elop
and
impl
emen
t a m
echa
nism
for
follo
w u
p on
dev
elop
men
tal p
rogr
amm
es80
% p
ositi
ve fe
edba
ck fr
om b
enefi
ciar
ies
of d
evel
opm
enta
l pro
gram
mes
by
2019
an
d su
stai
ned
ther
eaft
er
72%
74%
76%
80%
80%
80%
5.D
evel
op a
nd im
plem
ent a
com
mun
icat
ion
stra
tegy
.90
% p
ositi
ve re
spon
se fr
om a
nnua
l in
form
atio
n di
ssem
inat
ion
surv
eys
real
ised
by
Dec
embe
r 201
7 an
d su
stai
ned
ther
eaft
er
83%
90%
90%
90%
90%
90%
4.2
Obj
ecti
ve 2
: To
effec
tive
ly p
lan,
exe
cute
, mon
itor
and
eva
luat
e pr
ogra
mm
es a
nd p
rovi
de m
anag
emen
t in
form
atio
n fo
r ti
mel
y de
cisi
on
mak
ing
and
atta
inm
ent o
f set
obj
ecti
ves
4.2.
1 St
rate
gies
, Per
form
ance
Indi
cato
rs a
nd T
arge
ts
Stra
tegy
Indi
cato
rBa
selin
e 20
16
Targ
et
2017
2018
2019
2020
2021
1.D
evel
op a
nd im
plem
ent
an a
utom
ated
and
in
tegr
ated
Man
agem
ent
Info
rmat
ion
Syst
em.
Aver
age
stan
dard
aud
it du
ratio
n re
duce
d fr
om
55 to
45
days
by
202
55 d
ays
53 d
ays
51 d
ays
49 d
ays
47 d
ays
45 d
ays
2.St
reng
then
the
M&
E Fu
nctio
n an
d th
e Fr
amew
ork
for m
onito
ring
all
prog
ram
mes
.
100%
of p
lann
ed
activ
ities
att
aine
d w
ithin
the
set t
imel
ines
an
d bu
dget
;
85%
90%
95%
100%
100%
100%
3.D
evel
op a
nd im
plem
ent
an in
stitu
tiona
l IC
T po
licy
and
Stra
tegy
to g
uide
th
e im
plem
enta
tion
and
use
of a
utom
ated
In
form
atio
n Sy
stem
s.
Inst
itutio
nal I
CT
Polic
y an
d St
rate
gy d
evel
oped
an
d im
plem
ente
d by
Ju
ne, 2
018
No
Inst
itutio
nal
ICT
Polic
y or
St
rate
gy
•In
stitu
tiona
l IC
T Po
licy
and
Stra
tegy
•
Impl
emen
tatio
n co
mm
ence
d
Man
agem
ent
Info
rmat
ion
Syst
em
inte
grat
ed a
nd
oper
atio
nalis
ed b
y D
ecem
ber,
2018
•IF
MIS
•PM
EC•
Hum
an R
esou
rce
Man
agem
ent
Syst
em
•Au
dit M
anag
emen
t Sy
stem
(AM
S)
•Li
brar
y
•H
elp
Des
k In
form
atio
n Sy
stem
•Fl
eet M
anag
emen
t•
Ass
et M
anag
emen
t In
form
atio
n
Inte
rnet
con
nect
ivity
at
all t
imes
N/A
Inte
rnet
con
nect
ivity
re
stor
ed w
ithin
1 h
our.
Inte
rnet
con
nect
ivity
re
stor
ed w
ithin
1 h
our.
Inte
rnet
co
nnec
tivity
re
stor
ed w
ithin
1
hour
.
Inte
rnet
co
nnec
tivity
re
stor
ed
with
in 1
hou
r.
Inte
rnet
co
nnec
tivity
re
stor
ed w
ithin
1
hour
.
4.D
evel
op a
nd
oper
atio
nalis
e an
ICT
disa
ster
reco
very
pla
n.
Lost
info
rmat
ion
reco
vere
d w
ithin
24
hour
s
N/A
Dat
a re
cove
red
with
in 2
4 ho
urs
Dat
a re
cove
red
with
in 2
4 D
ata
reco
vere
d w
ithin
24
Dat
a re
cove
red
with
in 2
4
Dat
a re
cove
red
with
in 2
4
5.D
evel
op a
nd im
plem
ent
a ris
k m
anag
emen
t st
rate
gy.
Risk
man
agem
ent
stra
tegy
dev
elop
ed a
nd
impl
emen
ted
by Ju
ne
2018
.
No
Risk
m
anag
emen
t st
rate
gy in
pl
ace.
Risk
man
agem
ent
stra
tegy
dev
elop
ed a
nd
impl
emen
ted
4.3
Obj
ecti
ve 3
: To
effici
entl
y an
d eff
ecti
vely
man
age
the
hum
an r
esou
rces
in o
rder
to
achi
eve
exce
ptio
nal i
ndiv
idua
l and
org
anis
atio
nal
perf
orm
ance
.
4.3.
1 St
rate
gies
, Per
form
ance
Indi
cato
rs a
nd T
arge
ts
Stra
tegy
Indi
cato
rBa
selin
e 20
16Ta
rget
2017
2018
2019
2020
2021
1.D
evel
op a
nd im
plem
ent
a H
uman
Res
ourc
e St
rate
gy
Hum
an R
esou
rce
Stra
tegy
dev
elop
ed
by D
ecem
ber 2
017
and
impl
emen
tatio
n co
mm
ence
d by
Ja
nuar
y 20
18
No
Hum
an R
esou
rce
Stra
tegy
in p
lace
.H
uman
Res
ourc
e St
rate
gy
deve
lope
d.
Hum
an R
esou
rce
Stra
tegy
impl
emen
tatio
n co
mm
ence
d.
2.D
evel
op a
nd im
plem
ent
a Pe
rfor
man
ce
Man
agem
ent S
yste
m
i. Pe
rfor
man
ce
Man
agem
ent
Syst
em d
evel
oped
by
June
20
18, a
nd
impl
emen
ted
by
Dec
embe
r 201
8
GRZ
Ann
ual P
erfo
rman
ce
App
rais
al S
yste
m
•Pe
rfor
man
ce
Man
agem
ent
Syst
em d
evel
oped
fo
r OAG
•Pe
rfor
man
ce
Man
agem
ent
Syst
em
Impl
emen
ted
ii. T
rain
ing
Nee
ds
Ana
lysi
s (T
NA
) un
dert
aken
by
30th
Sep
tem
ber o
f ea
ch y
ear
TNA
und
erta
ken
by 3
0th
Sept
embe
r
TNA
und
erta
ken
by 3
0th
Sept
embe
rTN
A
unde
rtak
en
by 3
0th
Sept
embe
r
TNA
un
dert
aken
by
30t
h Se
ptem
ber
TNA
un
dert
aken
by
30t
h Se
ptem
ber
iii. 1
00%
of i
ndiv
idua
l ta
rget
s at
tain
ed
annu
ally
N/A
100%
of
indi
vidu
al
targ
ets
atta
ined
100%
of i
ndiv
idua
l ta
rget
s at
tain
ed
100%
of
indi
vidu
al
targ
ets
atta
ined
100%
of
indi
vidu
al
targ
ets
atta
ined
100%
of
indi
vidu
al
targ
ets
atta
ined
3.En
hanc
e th
e im
plem
enta
tion
of th
e St
aff W
elln
ess
Polic
y
90 %
sat
isfa
ctio
n le
vels
fr
om a
nnua
l sta
ff su
rvey
s at
tain
ed b
y D
ecem
ber,
2021
and
m
aint
aine
d an
nual
ly
ther
eaft
er
80%
82%
84%
86%
88%
90%
Stra
tegy
Indi
cato
rBa
selin
e 20
16Ta
rget
2017
2018
2019
2020
2021
4.Re
view
and
op
erat
iona
lise
the
orga
nisa
tion
stru
ctur
e an
d jo
b D
escr
iptio
ns
i. O
rgan
isat
ion
stru
ctur
e re
view
ed
by D
ecem
ber 2
017
2010
Res
truc
turin
g re
port
Org
anis
atio
n st
ruct
ure
revi
ewed
ii. J
ob D
escr
iptio
ns
revi
ewed
by
Dec
embe
r 201
7
2004
job
desc
riptio
ns
curr
ently
in u
seA
ll jo
b de
scrip
tions
re
view
ed
iii. 1
00%
of t
he s
taff
esta
blis
hmen
t fille
d at
all
times
84%
90%
95%
100%
100%
100%
5.En
hanc
e th
e op
erat
ions
of
the
Lear
ning
and
in
nova
tion
Cent
re
Lear
ning
and
in
nova
tion
Cent
re
(LIC
) enh
ance
d an
d op
erat
iona
lised
by
Dec
embe
r 201
8
•Th
e LI
C ha
s no
eq
uipm
ent s
uch
as c
ompu
ters
, pr
ojec
tors
and
oth
er
pres
enta
tion
faci
litie
s.
•N
o sp
ecifi
c tr
aini
ng
cale
ndar
in p
lace
.
•Tr
aini
ng
cale
ndar
in
plac
e
•Co
mpu
ters
, pr
ojec
tors
and
oth
er
pres
enta
tion
faci
litie
s pr
ocur
ed a
nd
inst
alle
d
4.4
Obj
ecti
ve 4
: To
effici
entl
y an
d eff
ecti
vely
pro
vide
fina
ncia
l and
adm
inis
trat
ive
serv
ices
for o
rgan
isat
iona
l effi
cien
cy a
nd a
ttai
nmen
t of s
et
obje
ctiv
es.
4.4.
1 St
rate
gies
, Per
form
ance
Indi
cato
rs a
nd T
arge
ts
Stra
tegy
Indi
cato
rBa
selin
e 20
16
Targ
et
2017
2018
2019
2020
2021
1.D
evel
op a
nd
impl
emen
t a
finan
cial
man
ual
i. Fin
anci
al m
anua
l de
velo
ped
by 3
1st
Dec
embe
r 201
8
OAG
doe
s no
t ha
ve it
s ow
n fin
anci
al m
anua
l bu
t use
s th
e m
anua
l fro
m
Min
istr
y of
Fi
nanc
e.
Fina
ncia
l man
ual
deve
lope
d
ii. Fi
nanc
ial r
eque
sts
proc
esse
d w
ithin
24
Hou
rs
Fina
ncia
l re
ques
ts
proc
esse
d w
ithin
48
Hou
rs
Fina
ncia
l re
ques
ts
proc
esse
d w
ithin
24
Hou
rs
Fina
ncia
l req
uest
s pr
oces
sed
with
in 2
4 H
ours
Fina
ncia
l req
uest
s pr
oces
sed
with
in 2
4 H
ours
Fina
ncia
l req
uest
s pr
oces
sed
with
in 2
4 H
ours
Fina
ncia
l req
uest
s pr
oces
sed
with
in 2
4 H
ours
2.D
evel
op a
nd
impl
emen
t a
reso
urce
m
obili
zatio
n st
rate
gy
20%
of t
he to
tal b
udge
t m
obili
sed
from
oth
er
sour
ces
annu
ally
14%
rais
ed fr
om
othe
r sou
rces
ot
her t
han
the
Min
istr
y of
Fi
nanc
e.
16%
18%
20%
20%
20%
Dra
ft S
tatu
tory
In
stru
men
t for
cha
rgin
g au
dit f
ees
prep
ared
and
su
bmitt
ed to
rele
vant
au
thor
ities
by
30th
June
20
18
•Pu
blic
Aud
it Ac
t ena
cted
•
No
regu
latio
ns
in p
lace
for
char
ging
aud
it fe
es
Dra
ft S
tatu
tory
In
stru
men
t for
ch
argi
ng a
udit
fees
pre
pare
d an
d su
bmitt
ed to
rele
vant
au
thor
ities
3.D
evel
op a
nd
impl
emen
t a
mon
itorin
g an
d ev
alua
tion
mec
hani
sm fo
r pr
ocur
emen
t
90%
of a
ll pl
anne
d ac
tiviti
es in
the
proc
urem
ent p
lan
atta
ined
with
in th
e se
t tim
elin
es a
nd b
udge
t
N/A
90%
90%
90%
90%
90%
Stra
tegy
Indi
cato
rBa
selin
e 20
16
Targ
et
2017
2018
2019
2020
2021
4.Co
nstit
ute
and
oper
atio
nalis
e an
Au
dit C
omm
ittee
90%
of r
ecom
men
datio
ns
from
the
Inte
rnal
Aud
it Re
port
impl
emen
ted
No
Audi
t Co
mm
ittee
in
plac
e
Audi
t Co
mm
ittee
Co
nstit
uted
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al A
udit
Repo
rt im
plem
ente
d
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al
Audi
t Rep
ort
impl
emen
ted
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al
Audi
t Rep
ort
impl
emen
ted
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al
Audi
t Rep
ort
impl
emen
ted
5.St
reng
then
ad
min
istr
ativ
e su
ppor
t sys
tem
s
90%
sta
ff sa
tisfa
ctio
n le
vel i
n pr
ovis
ion
of
adm
inis
trat
ive
serv
ices
at
tain
ed b
y 20
19 a
nd
sust
aine
d th
erea
fter
N/A
80%
85%
90%
sta
ff sa
tisfa
ctio
n le
vel i
n pr
ovis
ion
of a
dmin
istr
ativ
e se
rvic
es
90%
sta
ff sa
tisfa
ctio
n le
vel
in p
rovi
sion
of
adm
inis
trat
ive
serv
ices
90%
sta
ff sa
tisfa
ctio
n le
vel i
n pr
ovis
ion
of a
dmin
istr
ativ
e se
rvic
es
Stra
tegy
Indi
cato
rBa
selin
e 20
16
Targ
et
2017
2018
2019
2020
2021
4.Co
nstit
ute
and
oper
atio
nalis
e an
Au
dit C
omm
ittee
90%
of r
ecom
men
datio
ns
from
the
Inte
rnal
Aud
it Re
port
impl
emen
ted
No
Audi
t Co
mm
ittee
in
plac
e
Audi
t Co
mm
ittee
Co
nstit
uted
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al A
udit
Repo
rt im
plem
ente
d
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al
Audi
t Rep
ort
impl
emen
ted
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al
Audi
t Rep
ort
impl
emen
ted
90%
of
reco
mm
enda
tions
fr
om th
e In
tern
al
Audi
t Rep
ort
impl
emen
ted
5.St
reng
then
ad
min
istr
ativ
e su
ppor
t sys
tem
s
90%
sta
ff sa
tisfa
ctio
n le
vel i
n pr
ovis
ion
of
adm
inis
trat
ive
serv
ices
at
tain
ed b
y 20
19 a
nd
sust
aine
d th
erea
fter
N/A
80%
85%
90%
sta
ff sa
tisfa
ctio
n le
vel i
n pr
ovis
ion
of a
dmin
istr
ativ
e se
rvic
es
90%
sta
ff sa
tisfa
ctio
n le
vel
in p
rovi
sion
of
adm
inis
trat
ive
serv
ices
90%
sta
ff sa
tisfa
ctio
n le
vel i
n pr
ovis
ion
of a
dmin
istr
ativ
e se
rvic
es
5.0 PRE- CONDITIONS
The following factors which are within the control of OAG will be critical for the successful implementation of the Strategic Plan.
i. Adequate, skilled and committed staff
The effective implementation of the Strategic Plan will depend largely on recruiting the right people, placing them in the right positions and retaining them over a long period of time. The staff should possess the right skills, knowledge and experience. Commitment from employees will also be important to achieve the strategic goals.
ii. Availability of operational tools and information
Effective implementation of the plan requires availability of essential operational tools and equipment for the staff.
iii. Support from leadership and management
Senior management sets the direction for the organisation, energises creativity and innovation and drives the effective implementation of the strategies. The support of leadership and management will be key to the successful implementation of the Strategic Plan.
iv. Operationalization of the Learning and Innovation Centre
The Learning and Innovation Centre is intended to provide in-house training for the staff to enable them expand their knowledge and skill base. For successful implementation of the plan, a fully operational Learning and innovation Centre should be in place.
v. Adequate Office Accommodation
The decentralisation of the operations of OAG will require that the securing of adequate and conducive office accommodation for the officers who will be deployed to the district offices for operations.
6.0 GENERAL ASSUMPTIONS
The following factors though outside the control of OAG will be critical for successful implementation of the Strategic Plan.
i. Timely issuance of Statutory Instrument to operationalise some provisions of the Public Audit Act No.29 of 2016;
ii. Timely issuance of the Commencement Order for the State Audit Commission Act No. 27 of 2016 ;
iii. Timely issuance of the Commencement Order for the Public Audit Act No.29 of 2016;
iv. Fully funded budget;
v. Continued political goodwill and support;
vi. Continued support from Cooperating Partners; and
vii. Continued support from the SAI Community.
7.0 LINKING THE STRATEGIC PLAN TO THE BUDGETING PROCESSTo operationalise the Strategic Plan, it is imperative that it is translated into an Implementation (operational) Plan, broken down into annual institutional, departmental and individual work plans and costed. Accordingly, OAG will develop a five-year implementation plan as well as annual institutional, departmental and individual work plans linked to the Strategic Plan and the resource envelope. Both the five-year implementation plan and annual plans should have realistic targets and schedules of activities with costings arrived at by taking into account the nature, type and quantities of inputs as well as their pricing.
8.0 MONITORING AND EVALUATION OF THE STRATEGIC PLANMonitoring and Evaluation (M&E) will be vital for effective implementation of the Plan and ascertaining its impact. The M&E mechanism once strengthened with component of Quality Control and Assurance systems embedded will enable OAG track progress and evaluate its performance against set objectives and targets as well as institute corrective measures timely. The monitoring and evaluation will be done at individual, departmental and institutional levels.
Accordingly, annual progress reports on the implementation of the Plan will be prepared. A mid-term evaluation will also be undertaken in June 2019 to assess the progress being made towards achieving set objectives. A terminal evaluation will be conducted in December 2021 to determine the overall impact of the Plan and inform the preparation of the next Plan for the period 2022-2026. The key stakeholders will be engaged to provide feedback on the performance of OAG and recommend areas for improvement.
9.0 STRUCTURAL IMPLICATIONS
The Strategic planning process culminated into the development of an indicative core functional structure for OAG, underscoring the key areas where results will be expected for the Office to succeed in its auditing endeavours. The indicative core functional structure was arrived at by grouping various objectives into specialized functional areas using the following criteria: -
(i) Similarity of objectives;
(ii) Uniqueness of the objectives;
(iii) Accountability for the objectives; and
(iv) Coordination of the objectives.
Through the clustering of the objectives, the following core functions were identified and agreed to:
(i) Audit Services (Objectives 1);
(ii) Planning and Information (Objective 2);
(iii) Human Resource Management (Objectives 3); and
(iv) Finance and Logistics (Objectives 4).
For a pictorial presentation of the indicative Core Functional Structure, refer to Appendix 1. Appendix ii - Summary of the SWOT Analysis
Positive Factors
Strengths Optimisation measures
Support from Management and Leadership
Staff will continue engaging management and leadership for their support in implementing programmes of the Office.
Availability of qualified and competent staff
OAG will continue building the capacity of staff and set specific individual targets to ensure timely implementation of programmes.
Availability of the Learning and Innovation Centre
The Office will build the capacity of the Center and develop tailor made programmes for OAG.
Legal Provisions to Mobilise Resources
The Office will develop relevant regulations to facilitate revenue generation.
Availability of the Integrity Committee
The Office will actively engage the Committee ensure adherence to the ethical values.
Opportunities Optimisation measures
Government Support OAG will continue engaging government for support.
Good working relationship with strategic institutions
The Office will strengthen collaboration with stakeholders.
Support from Cooperating Partners
The OAG will continue to leverage on this support to mitigate some of its challenges.
Availability of SMART Zambia Institute
The Office will engage the Institute to improve its ICT infrastructure.
Negative Factors Mitigation Measures
Weaknesses
Resistance to change The Office will develop and implement a change management programme to enable staff understand and appreciate the importance of changes in the institution.
Lack of Understanding of the Role of the Integrity Committee
The Integrity Committee will engage staff by sensitising them on the role of the Committee.
Positive Factors
Ineffective Communication
A communication strategy will be developed and implemented to promote effective communication and team building among the staff
Inadequate ICT infrastructure and equipment
The OAG will develop and implement an institutional ICT policy to enable the Office to automate and integrate the systems.
Inadequate capabilities to develop and manage ICT systems
OAG develop and implement a skills capacity building programme for staff
Threats Mitigation Measures
Delayed Feedback or Approval from External Stakeholders
The Office will continue engaging institutions and authorities to facilitate successful implementation of this Strategic Plan.
Unavailability of Support from Cooperating Partners
OAG will develop and implement a stakeholder engagement plan.
Inadequate Financial Resources
The Office will timely engage the Ministry for timely and adequate funds.