2015/2016 adopted capital improvement programs

134
Lathrop Community ComplexGeneration Center Building City of Lathrop California Capital Improvement Programs Fiscal Year 2015-2016

Upload: city-of-lathrop

Post on 24-Jul-2016

221 views

Category:

Documents


0 download

DESCRIPTION

City of Lathrop 2015/2016 Fiscal Year Adopted Capital Improvement Program

TRANSCRIPT

  • LathropCommunityComplexGenerationCenterBuilding

    City of Lathrop California

    Capital Improvement Programs

    Fiscal Year 2015-2016

  • CAPITALIMPROVEMENTPROGRAM

  • Capital Improvement Program

    Fiscal Year 2015-16 through 2019-20

    Prior &

    Current Year

    Actuals

    Carry Forward

    FY 15-16

    New Funding

    Request

    FY 15-16

    Planned

    FY 2016-17

    Planned

    FY 2017-18

    Planned

    FY 2018-19

    Planned

    FY 2019-20

    Total Project

    Needs

    GG 10-17

    Retaining Wall and Landscaping

    at Towne Centre Dr & Village Ave (Tract 3410) 9,618$ 290,382$ -$ -$ -$ -$ -$ 300,000$

    GG 11-09 Financial Management System 538,400$ 62,525$ -$ -$ -$ -$ -$ 600,925$

    GG 12-14 Solar Energy Project 18,734$ 35,766$ -$ -$ -$ -$ -$ 54,500$

    GG 13-06 Capital Facility Fee Study Update 29,437$ 140,563$ -$ -$ -$ -$ -$ 170,000$

    GG 15-18 City Hall Reorganization -$ 265,000$ -$ -$ -$ -$ -$ 265,000$

    596,189$ 794,236$ -$ -$ -$ -$ -$ 1,390,425$

    PK 15-11 River Park South Restroom Installation -$ 60,500$ -$ -$ -$ -$ -$ 60,500$

    PK 15-14 7th Street Skate Park Renovation and Site Cleanup -$ 95,000$ -$ -$ -$ -$ -$ 95,000$

    PK 16-07 City Park Equipment and Rubberized Surface Improvements -$ -$ 369,635$ -$ -$ -$ -$ 369,635$

    -$ 155,500$ 369,635$ -$ -$ -$ -$ 525,135$

    PS 97-02 Lathrop Road Westerly Grade Separation 15,927,677$ 3,727,501$ 975,121$ -$ -$ -$ -$ 20,630,299$

    PS 02-04 Regional Pedestrian Bikeway 17,980$ 61,035$ -$ 100,000$ -$ -$ -$ 179,015$

    PS 02-24 Lathrop Road Widening Rehabilitation 57,144$ 2,138,813$ 193,731$ -$ -$ -$ -$ 2,389,688$

    PS 09-04 River Island Pkwy/Bradshaw Crossing Bridge 1,424,426$ 141,920$ -$ -$ -$ -$ -$ 1,566,346$

    PS 12-04 Manthey Road Bridge Replacement 677,991$ 3,485,909$ 688,200$ 172,050$ 2,265,324$ 37,234,674$ -$ 44,524,148$

    PS 12-15 Harlan Road Improvements 135,838$ 197,623$ -$ 3,400,000$ -$ -$ -$ 3,733,461$

    Street Improvements

    Project Description

    General Government and Public Safety

    General Government and Public Safety Subtotal:

    Parks & Recreation Improvements

    Parks & Recreation Subtotal:

    PS 14-04 Harlan Road Precise Plan Line -$ 802,229$ -$ 500,000$ 2,100,000$ -$ -$ 3,402,229$

    PS 15-04 Sidewalk Repair Program 1,080$ 172,982$ -$ 80,000$ 80,000$ 80,000$ 80,000$ 494,062$

    PS 15-15 Thomsen Road Sidewalk Improvements -$ 43,270$ -$ -$ -$ -$ -$ 43,270$

    PS 15-19 5th Street Sidewalk Improvement -$ 75,000$ 300,000$ 340,000$ -$ -$ -$ 715,000$

    PS 16-01 City-wide Road Maintenance & Repair Program -$ 493,522$ 811,531$ 975,000$ 500,000$ 500,000$ 500,000$ 3,780,053$

    PS 16-02 Traffic Calming Measures -$ 22,154$ 25,000$ -$ -$ -$ -$ 47,154$

    18,242,136$ 11,361,958$ 2,993,583$ 5,567,050$ 4,945,324$ 37,814,674$ 580,000$ 81,504,725$ Street Subtotal:

  • Capital Improvement Program

    Fiscal Year 2015-16 through 2019-20

    Prior &

    Current Year

    Actuals

    Carry Forward

    FY 15-16

    New Funding

    Request

    FY 15-16

    Planned

    FY 2016-17

    Planned

    FY 2017-18

    Planned

    FY 2018-19

    Planned

    FY 2019-20

    Total Project

    NeedsProject Description

    PW 08-09 Well 21 Improvements 331,246$ 1,966,823$ -$ -$ -$ -$ -$ 2,298,069$

    PW 10-10 UWMP and Water Master Plan Updates 149,157$ 48,098$ 225,000$ -$ -$ -$ 150,000$ 572,255$

    PW 12-08 Citywide Water System Repairs 1,440$ 133,560$ -$ -$ -$ -$ -$ 135,000$

    PW 13-08 Water Meter Improvements 396,718$ 100,449$ 245,000$ 270,000$ 270,000$ -$ -$ 1,282,167$

    PW 14-08 Modifications for Wells 7, 8 and 9 343,388$ 96,612$ -$ -$ -$ -$ -$ 440,000$

    PW 15-05 Well 10 Emergency Power 214$ 339,786$ -$ -$ -$ -$ -$ 340,000$

    PW 16-04 Sustainable Groundwater Management Act Compliance -$ -$ 100,000$ -$ -$ -$ -$ 100,000$

    1,222,163$ 2,685,328$ 570,000$ 270,000$ 270,000$ -$ 150,000$ 5,167,491$

    SD 14-13 Urban Level Flood Protection 200-Year Floodplains 949,590$ 1,047,092$ 1,500,000$ -$ -$ -$ -$ 3,496,682$

    949,590$ 1,047,092$ 1,500,000$ -$ -$ -$ -$ 3,496,682$

    WW 10-15 Lathrop Consolidated Treatment Facility Expansion 7,041,507$ 1,154,172$ 250,000$ -$ -$ -$ -$ 8,445,679$

    WW 11-06 Crossroads Wastewater Treatment Plant Improvements 515,085$ 39,913$ -$ 1,050,000$ -$ -$ -$ 1,604,998$

    WW 12-07 Sewer Plant Upgrades and Maintenance 134,449$ 397,251$ -$ 160,000$ 32,000$ 80,000$ 65,000$ 868,700$

    WW 13-02 East Side Wastewater Collection System 8,390$ 91,610$ -$ -$ -$ 235,000$ 1,200,000$ 1,535,000$

    WW 13-09 Wastewater Pump Station Improvements 29,459$ 245,541$ -$ -$ -$ -$ -$ 275,000$

    Wastewater Improvements

    Water Improvements

    Water Subtotal:

    Drainage Improvements

    Drainage Subtotal:

    Wastewater Pump Station Improvements 29,459$ 245,541$ -$ -$ -$ -$ -$ 275,000$

    WW 14-14 LCTF Expansion fr 1.0 mgd to 2.0 mgd 276,746$ 4,194,360$ 18,162,792$ 18,675,000$ 14,600,000$ -$ -$ 55,908,898$

    WW 15-08 Wastewater Master Plan Update -$ 500,000$ -$ -$ -$ -$ -$ 500,000$

    WW 15-20 Crossroads Wastewater Treatment Plant Decommissioning -$ -$ 300,000$ -$ -$ -$ -$ 300,000$

    8,005,636$ 6,622,847$ 18,712,792$ 19,885,000$ 14,632,000$ 315,000$ 1,265,000$ 69,438,275$

    29,015,714$ 22,666,961$ 24,146,010$ 25,722,050$ 19,847,324$ 38,129,674$ 1,995,000$ 161,522,733$

    Wastewater Subtotal:

    Grand Total CIP:

  • Capital Improvement Program

    Fiscal Year 2015-16 through 2019-20

    Prior &

    Current Year

    Actuals

    Carry Forward

    FY 15-16

    New Funding

    Request

    FY 15-16

    Planned

    FY 2016-17

    Planned

    FY 2017-18

    Planned

    FY 2018-19

    Planned

    FY 2019-20

    Total Project

    NeedsProject Description

    GG 08-05 Animal Shelter -$ -$ -$ -$ -$ -$ 5,055,000$ 5,055,000$

    GG 15-10 Historic Center Feasability Study -$ -$ -$ 20,000$ -$ -$ -$ 20,000$

    PK 14-01 City Wide Park Master Plan -$ -$ -$ 175,000$ 50,000$ -$ -$ 225,000$

    PK 14-03 Soccer Complex -$ 50,000$ -$ 100,000$ -$ -$ -$ 150,000$

    PS 06-06 Louise Avenue and I-5 Improvements 1,854,755$ 272,442$ -$ -$ -$ -$ -$ 2,127,197$

    PS 06-16 Lathrop Road and I-5 Improvements 143,975$ -$ -$ 150,000$ -$ -$ -$ 293,975$

    PS 15-02 Louise Avenue & Mckinley Avenue Signal Improvements -$ -$ -$ -$ 450,000$ -$ -$ 450,000$

    PS 16-03 Louise Avenue Pavement Rehabilitation -$ -$ -$ 1,000,000$ -$ -$ -$ 1,000,000$

    SD 08-07 Shilling Storm Water Pump Station & Force Main -$ 282,000$ -$ -$ -$ -$ 1,350,000$ 1,632,000$

    RW 16-06 Recycled Water Program Implementation -$ -$ -$ 100,000$ -$ -$ -$ 100,000$

    1,998,730$ 604,442$ -$ 1,545,000$ 500,000$ -$ 6,405,000$ 11,053,172$

    GG 15-07 ADA Transition Plan Implementation -$ 104,000$ 7,500$ 45,000$ 45,000$ 45,000$ 479,200$ 725,700$

    PW 10-09 Urban Water Management Plan Implementation 76,463$ 169,285$ 86,000$ 53,799$ 56,500$ 59,325$ 62,325$ 563,697$

    SD 14-10 Storm Water Management Plan -$ -$ 40,000$ 50,000$ 50,000$ -$ -$ 140,000$

    WW 11-08 Sewer System Management Plan -$ -$ 56,666$ 56,666$ 56,666$ 56,666$ 56,666$ 283,330$

    76,463$ 273,285$ 190,166$ 205,465$ 208,166$ 160,991$ 598,191$ 1,712,727$

    Regulatory Compliance Programs

    Regulatory Permitting Requirements Total:

    Future Capital Improvement Projects

    Future Capital Improvement Projects Subtotal:

    76,463$ 273,285$ 190,166$ 205,465$ 208,166$ 160,991$ 598,191$ 1,712,727$ Regulatory Permitting Requirements Total:

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - General GovernmentPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    5 Current Projects 1,390,425 596,189 794,236

    2 Future Projects 5,075,000 20,000 5,055,000

    0 New Projects -

    7 Totals 6,465,425 596,189 794,236 - 20,000 - - 5,055,000

    by Funding Sources

    General Fund

    GG11-09 487,598 425,073 62,525

    GG12-14 42,000 18,660 23,340

    GG15-10 20,000 20,000

    GG15-18 265,000 265,000

    814,598 443,733 350,865 - 20,000 - - -

    Enterprise Funds

    GG12-14 12,500 73 12,427

    12,500 73 12,427 - - - - -

    GG11-09 56,663 56,663

    56,663 56,663 - - - - - -

    GG11-09 56,664 56,664

    56,664 56,664 - - - - - -

    Subtotal:

    Historic Center

    F1010-General

    F5600-Water Cap Repl

    F5620-Water

    F6010-Sewer

    Subtotal:

    Financial Mgmt Sys

    Financial Mgmt Sys

    Solar Energy Project

    Subtotal:

    Financial Mgmt Sys

    Subtotal:

    Solar Energy Project

    City Hall

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - General GovernmentPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    by Funding Sources Continued

    GG08-05 5,055,000 5,055,000

    5,055,000 - - - - - - 5,055,000

    GG13-06 70,000 12,069 57,931

    70,000 12,069 57,931 - - - - -

    GG10-17 300,000 9,618 290,382

    GG13-06 100,000 17,369 82,631

    400,000 26,987 373,013 - - - - -

    6,465,425 596,189 794,236 - 20,000 - - 5,055,000

    CFF Study Update

    Animal Shelter

    Total:

    Subtotal:

    Subtotal:

    F2710-Developer Contribution

    Subtotal:

    Retaining Wall &

    CFF Study Update

    F2290-Administration

    F2270-City Services

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Parks and RecreationPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    2 Current Projects 155,500 155,500

    2 Future Projects 375,000 50,000 275,000 50,000

    1 New Projects 369,635 369,635

    5 Totals 900,135 - 205,500 369,635 275,000 50,000 - -

    by Funding Sources

    General Fund

    PK14-01 225,000 175,000 50,000

    225,000 - - - 175,000 50,000 - -

    Special Revenue Funds

    PK15-11 60,500 60,500

    PK15-14 95,000 95,000

    PK16-07 308,635 308,635

    464,135 - 155,500 308,635 - - - -

    PK14-03 150,000 50,000 100,000

    150,000 - 50,000 - 100,000 - - -

    PK16-07 61,000 - 61,000

    61,000 - - 61,000 - - - -

    900,135 - 205,500 369,635 275,000 50,000 - - Total:

    Subtotal:

    Subtotal:

    Subtotal:

    F1010-General Fund

    F2260-CFF Culture & Leisure

    F2650-CDBG Fund

    Soccer Complex

    City Wide Master

    F1060-Measure C

    City Park Equip &

    Subtotal:

    Linear Park

    7th St Skate Park

    City Park Equip &

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Street ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    10 Current Projects 77,677,519 18,242,136 10,846,282 2,157,052 4,592,050 4,445,324 37,314,674 80,000

    4 Future Projects 3,871,172 1,998,730 272,442 1,150,000 450,000

    2 New Projects 3,827,207 515,676 836,531 975,000 500,000 500,000 500,000

    16 Totals 85,375,897 20,240,866 11,634,400 2,993,583 6,717,050 5,395,324 37,814,674 580,000

    by Funding Sources

    Special Revenue Funds

    PS97-02 5,401,000 4,292,401 1,108,599

    PS02-24 601,342 601,342

    PS12-04 8,000 4,173 3,827

    PS15-02 50,000 50,000

    PS15-04 320,516 50,000 67,629 67,629 67,629 67,629

    PS15-15 43,270 43,270

    PS15-19 75,000 75,000

    PS16-01 22,907 22,907

    PS16-02 22,154 22,154

    6,544,189 4,296,574 1,927,099 - 67,629 117,629 67,629 67,629

    PS97-02 10,855,000 8,236,098 2,618,902 -

    PS02-04 64,217 15,615 48,602

    10,919,217 8,251,713 2,667,504 - - - - -

    CityWide Rd Maint

    Traffic Calming Meas

    Louise/Mckinley Signl

    Sidewalk Repair

    Thomsen Rd Sidewalk

    Subtotal:

    Subtotal:

    F2030-Gas Tax

    F2110-Measure K

    5th St Sidewalk

    Manthey Bridge Repl

    Lathrop West Grade

    Lathrop West Grade

    Lathrop Widening Reh

    Pedestrian Bikeway

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Street ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    by Funding Sources Continued

    PS97-02 200,000 200,000

    PS02-04 114,798 2,365 12,433 100,000

    PS02-24 13,731 13,731

    PS15-04 173,546 1,080 122,982 12,371 12,371 12,371 12,371

    PS16-01 3,216,590 405,059 811,531 500,000 500,000 500,000 500,000

    PS16-02 25,000 25,000

    3,743,665 203,445 540,474 850,262 612,371 512,371 512,371 512,371

    PS12-04 39,469,350 673,818 3,310,032 516,150 34,969,350

    PS15-19 640,000 300,000 340,000

    40,109,350 673,818 3,310,032 816,150 340,000 - 34,969,350 -

    PS97-02 2,700,042 2,700,042

    2,700,042 2,700,042 - - - - - -

    PS16-01 65,556 65,556

    65,556 - 65,556 - - - - -

    PS97-02 136 136

    PS02-24 483,645 483,645

    483,781 136 483,645 - - - - -

    PS97-02 499,000 499,000

    PS02-24 1,110,970 57,144 1,053,826

    PS12-15 126,195 51,240 74,955

    1,736,165 607,384 1,128,781 - - - - -

    PS02-24 180,000 180,000

    PS12-15 174,266 51,598 122,668

    354,266 51,598 122,668 180,000 - - - -

    Lathrop Widening Reh

    CityWide Rd Maint

    Traffic Calming Meas

    Lathrop Widening Reh

    F2250-CFF Local Transportation

    CityWide Rd Maint

    Lathrop West Grade

    Lathrop Widening Reh

    Subtotal:

    Subtotal:

    Subtotal:

    Lathrop West Grade

    F2280-CFF Storm Drain

    Subtotal:

    F2140-TDA Funds

    F2150-Federal

    Lathrop West Grade

    Harlan Rd Imprvmnts

    Pedestrian Bikeway

    Sidewalk Repair

    Manthey Bridge Repl

    Lathrop West Grade

    F2180-Xroads Street Improvements

    F2230-CFF-Regional Transportation

    Lathrop Widening Reh

    Subtotal:

    Subtotal:

    Subtotal:

    F2160-STIP

    5th St Sidewalk

    Harlan Rd Imprvmnts

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Street ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    by Funding Sources Continued

    PS06-06 1,904,489 1,632,047 272,442

    PS12-04 1,682,266 57,350 57,350 57,350 755,108 755,108

    PS14-04 2,229 2,229

    3,588,984 1,632,047 332,021 57,350 57,350 755,108 755,108 -

    PS06-16 29,396 29,396

    PS12-04 1,682,266 57,350 57,350 57,350 755,108 755,108

    1,711,662 29,396 57,350 57,350 57,350 755,108 755,108 -

    PS14-04 283,000 283,000

    283,000 - 283,000 - - - - -

    PS12-04 1,682,266 57,350 57,350 57,350 755,108 755,108

    PS14-04 517,000 517,000

    2,199,266 - 574,350 57,350 57,350 755,108 755,108 -

    PS14-04 500,000 500,000

    500,000 - - - 500,000 - - -

    PS12-15 33,000 33,000

    33,000 33,000 - - - - - -

    Subtotal:

    Subtotal:

    Subtotal:

    F2360- RTIF Lathrop Local West Transportation

    F6030- Sewer CFF

    Manthey Bridge Repl

    F2330- WLSP Regional Transportation

    Lathrop/I-5 Imprvmnts

    Subtotal:

    Roth Rd/I-5 Imprvmnts

    F2320- CFF W/C Lathrop Transportation

    Manthey Bridge Repl

    Manthey Bridge Repl

    Harlan Rd Imprvmnts

    Roth Rd/I-5 Imprvmnts

    Subtotal:

    F2420- North Lathrop Impact Fee

    Roth Rd/I-5 Imprvmnts

    Roth Rd/I-5 Imprvmnts

    Subtotal:

    F2340- RTIF Lathrop Local East Transportation

    Louise/I-5 Imprvmnts

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Street ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    by Funding Sources Continued

    Other Sources

    PS06-06 222,708 222,708

    PS06-16 264,579 114,579 150,000

    PS09-04 1,566,346 1,424,426 141,920

    PS12-15 3,400,000 3,400,000

    5,453,633 1,761,713 141,920 - 3,550,000 - - -

    PS97-02 975,121 975,121

    975,121 - - 975,121 - - - -

    PS15-02 400,000 400,000

    400,000 - - - - 400,000 - -

    PS14-04 2,100,000 2,100,000

    2,100,000 - - - - 2,100,000 - -

    PS16-03 1,000,000 1,000,000

    1,000,000 - - - 1,000,000 - - -

    PS16-01 475,000 475,000

    475,000 - - - 475,000 - - -

    85,375,897 20,240,866 11,634,400 2,993,583 6,717,050 5,395,324 37,814,674 580,000

    Subtotal:

    F2710-Developer Contribution

    Louise/I-5 Imprvmnts

    Harlan Rd Imprvmnts

    Subtotal:

    Subtotal:

    Total:

    RSTP

    Louise Ave Pavement

    CityWide Rd Maint

    Lathrop/I-5 Imprvmnts

    RI Pkwy Bradshaw Xing

    Lathrop West Grade

    Subtotal:

    Railroad

    Congestion Mitigation and Air Quality (CMAQ)

    Louise/Mckinley Signl

    Subtotal:

    Roth Rd/I-5 Imprvmnts

    Subtotal:

    To be determined

    City of Manteca - Center Point (RTIP)

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group PW - Water ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    5 Current Projects 5,631,188 1,298,626 2,854,613 556,000 323,799 326,500 59,325 212,325

    - Future Projects

    1 New Projects 100,000 100,000

    6 Totals 5,731,188 1,298,626 2,854,613 656,000 323,799 326,500 59,325 212,325

    by Funding Sources

    Enterprise Funds

    PW10-10 572,255 149,157 48,098 225,000 150,000

    PW12-08 135,000 1,440 133,560

    PW13-08 1,184,667 299,218 100,449 245,000 270,000 270,000

    PW14-08 440,000 343,388 96,612PW15-05 340,000 214 339,786

    PW16-04 100,000 100,000

    2,771,922 793,417 718,505 570,000 270,000 270,000 - 150,000

    PW08-09 171,041 171,041

    171,041 171,041 - - - - - -

    PW10-09 563,697 76,463 169,285 86,000 53,799 56,500 59,325 62,325

    PW13-08 97,500 97,500

    661,197 173,963 169,285 86,000 53,799 56,500 59,325 62,325

    Water Meter Rep

    Subtotal:

    Subtotal:

    UWMP - Reg Com

    Subtotal:

    Water Sys Repair

    Water Meter Rep

    Well 7 8 & 9 Mod

    Well 21 Post Con

    WMP Update

    Well 10 Power

    Sustainable GW

    F560-Water Cap Repl

    F561-Water Expansion

    F562-Water

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group PW - Water ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    PW08-09 1,531,471 145,867 1,385,604

    1,531,471 145,867 1,385,604 - - - - -

    Other Sources

    PW08-09 14,338 14,338

    14,338 14,338 - - - - - -

    PW08-09 581,219 581,219

    581,219 - 581,219 - - - - -

    5,731,188 1,298,626 2,854,613 656,000 323,799 326,500 59,325 212,325

    Project Buy In Fund 562 & 541

    Well 21 Post Con

    Total:

    Subtotal:

    Subtotal:

    F541 - CFD 2003-01

    F271-Developer Contribution

    Well 21 Post Con

    Subtotal:

    Well 21 Post Con

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Drainage ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    1 Current Projects 3,496,682 949,590 1,047,092 1,500,000

    1 Future Projects 1,632,000 282,000 1,350,000

    0 New Projects

    2 Totals 5,128,682 949,590 1,329,092 1,500,000 - - - 1,350,000

    by Funding Sources

    Special Revenue Funds

    SD14-13 45,000 29,633 15,367

    45,000 29,633 15,367 - - - - -

    SD14-13 801,141 459,742 341,399

    801,141 459,742 341,399 - - - - -

    SD08-07 1,500,000 150,000 1,350,000

    1,500,000 - 150,000 - - - - 1,350,000

    SD08-07 132,000 132,000

    SD14-13 2,650,541 460,215 690,326 1,500,000

    2,782,541 460,215 822,326 1,500,000 - - - -

    5,128,682 949,590 1,329,092 1,500,000 - - - 1,350,000

    F101-General Fund

    ULFP Protection

    Subtotal:

    Subtotal:

    Total:

    Subtotal:

    F271-Developer Contribution

    Shilling SWPS

    ULFP Protection

    F105-Economic Development

    ULFP Protection

    Subtotal:

    F234-CFF Regional Trans

    Shilling SWPS

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Wastewater ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    7 Current Projects 69,138,275 8,005,636 6,622,847 18,412,792 19,885,000 14,632,000 315,000 1,265,000

    - Future Projects

    1 New Projects 300,000 300,000

    8 Totals 69,438,275 8,005,636 6,622,847 18,712,792 19,885,000 14,632,000 315,000 1,265,000

    by Funding Sources

    WW11-06 9,192 9,192

    9,192 9,192 - - - - - -

    WW13-02 1,535,000 8,390 91,610 235,000 1,200,000

    WW13-09 150,000 16,029 133,971

    WW15-08 187,500 187,500

    1,872,500 24,419 413,081 - - - 235,000 1,200,000

    WW11-06 22,116 22,116

    WW12-07 211,000 43,728 167,272

    WW14-14 33,898 32,300 1,598

    WW15-08 44,500 44,500

    WW15-20 300,000 300,000

    611,514 98,144 213,370 300,000 - - - -

    WW10-15 83,991 69,089 14,902

    WW12-07 657,700 90,721 229,979 160,000 32,000 80,000 65,000

    WW13-09 125,000 13,430 111,570

    WW15-08 268,000 268,000

    1,134,691 173,240 624,451 - 160,000 32,000 80,000 65,000

    WWMP Update

    WWMP Update

    Sewer Plant Upgd

    WWPS Imprvmnts

    LCTF Expansion

    F605-Crossroads

    F606-Capital Replacement

    Xrds WWTP Expan

    Subtotal:

    WWMP Update

    Xrds WWTP Expan

    Sewer Plant Upgd

    LCTF Phase 2

    Subtotal:

    Subtotal:

    F611-WW Capital Replacement

    F607-Crossroads Capital Replacement

    Subtotal:

    East Side WW Col

    WWPS Imprvmnts

    Xrds WWTP

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Wastewater ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    by Funding Sources Continued

    WW10-15 8,244,618 6,855,348 1,139,270 250,000

    WW11-06 1,573,690 483,777 39,913 1,050,000

    WW14-14 55,875,000 244,446 4,192,762 18,162,792 18,675,000 14,600,000

    65,693,308 7,583,571 5,371,945 18,412,792 19,725,000 14,600,000 - -

    WW10-15 117,070 117,070

    117,070 117,070 - - - - - -

    69,438,275 8,005,636 6,622,847 18,712,792 19,885,000 14,632,000 315,000 1,265,000

    Subtotal:

    Total:

    Subtotal:

    F105-Economic Development

    F271-Developer Contribution

    Xrds WWTP Expan

    LCTF Expansion

    LCTF Expansion

    LCTF Phase 2

  • CITY OF LATHROP

    CAPITAL IMPROVEMENT PROGRAM

    FIVE YEAR PLAN FY 15-16 THROUGH FY 19-20

    CIP SUMMARY

    Group - Recycled Water ImprovementsPrior & Carry New Funding

    Total Est. Current Year Forward Request Planned Planned Planned Planned

    by Project Type Cost Actuals FY 15-16 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20

    - Current Projects

    - Future Projects

    1 New Projects 100,000 100,000

    1 Totals 100,000 - - - 100,000 - - -

    by Funding Sources

    RW16-06 100,000 100,000

    100,000 - - - 100,000 - - -

    100,000 - - - 100,000 - - -

    F608-WW Recycling Plant -#1 MBR

    RW Program

    Subtotal:

    Total:

  • Street Improvements,

    $2,993,583 , 12%

    Water Improvements,

    $656,000 , 3%

    Recycled Water Improvements,

    $- , 0%

    Parks & Recreation

    Improvements, $369,635 , 2%

    General Government & Public

    Safety, $7,500 , 0%

    Drainage Improvements,

    $1,500,000 , 6%

    CIP by Project Category FY 2015-2016 New Funding Request

    Wastewater Improvements,

    $18,712,792 , 77%

  • Street Improvements,

    $85,375,897 , 49%

    Recycled Water Improvements,

    $100,000 , 0%

    Parks & Recreation

    Improvements, $900,135 , 1%

    General Government & Public

    Safety, $6,465,425 , 4%Drainage Improvements,

    $5,128,682 , 3%

    CIP by Project Category 5-Year Funding Program FYs 2016-2020

    Water Improvements,

    $5,731,188 , 3%

    Wastewater Improvements,

    $69,438,275 , 40%

  • GG 10-17

    Contact Number:209-941-7363

    Project Description:

    Justification:

    Capital Improvement Project Plan

    Department Responsible:Parks & Recreation/ Ken Reed

    Project Number:

    GG 10-17

    Project Number:Retaining Wall and Landscaping at Towne Centre Drive and Village Avenue Tract 3410

    The project consists of constructing a retaining wall to provide for a pedestrian pathway and storm drain corridor from Johnson Ferry Road to Village Avenue. The project includes minor landscaping of the entry median to Tract 3410. The City has designed the improvements and filed for the permits and Woodside Homes will pull the permits and construct the retaining wall and the landscaping along Towne Centre. The reimbursement agreement is currently approved and woodside plans on starting construction spring of 2015

    These improvements were part of the subdivision improvement agreement with Lafferty Homes for Tract 3410. Lafferty Homes experienced financial difficulties and were unable to perform. The City placed a claim on the $300,000 performance bond for these improvements. The bonding company elected to pay the City the $300,000 rather than construct these improvements. The City is responsible for installing these improvements with the bond proceeds.

  • GG 10-17

    Contact Number:209-941-7363

    Capital Improvement Project Plan

    Department Responsible:Parks & Recreation/ Ken Reed

    Project Number:

    GG 10-17

    Project Number:Retaining Wall and Landscaping at Towne Centre Drive and Village Avenue Tract 3410

    Critical DateN/A

    Fall 2013Summer 2014Summer 2015

    Fall/winter 2015

    Prior & Current Year Actual

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    9,618 290,382 - - - - - 300,000 9,618$ 290,382$ -$ -$ -$ -$ -$ 300,000$

    Prior & Current Year Actual

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    DescriptionsAppraisal, negotiations & grading of sitePrepare Plans and SpecificationsCouncil approves plans and authorizes bidding the projectWoodside Homes works on the installation of te retaining wallImprovements complete and accepted by City Council

    Developer bond proceeds Fund (2710)Total Revenues:

    Project Components & Estimated Timeline

    Source of Funds

    ComponentsAcquisition & PreparationDesign PhaseBid ProcessConstruction PhaseCompletion

    Use of Funds Year Actual FY 2015/16 Recommended Planned Planned Planned Planned Allocations

    - - - - - - - -

    9,618 1,663 - - - - 11,281 - - - - - - - -

    - 288,719 - - - - 288,719 - - - - - - - -

    9,618$ 290,382$ -$ -$ -$ -$ -$ 300,000$ 9,618$ 290,382$ -$ -$ -$ -$ -$ 300,000$ Total Expenditures:

    Developer Bond proceeds Fund (2710)

    Developer Bond proceeds Fund (2710)Project ManagementDesign and Engineering Land AcquisitionConstructionMiscellaneous

  • GG 11-09

    Contact Number:209-941-7349

    Project Description:

    Justification:

    Replace City's Financial Management System with an Enterprise Resource Planning System (ERP)This project consists of five modules and is 95% complete. The Finance module was configured and went live July 1st 2013. On September 1st, 2013 the following three modules went live: 1. Community Development 2. Utilities 3. Human ResourcesThe only module left to be implemented is the IVR (Interactive Voice Response) integration.

    City currently has and supports three different computer software systems with very limited integration between them, which generates a significant amount of manual labor. Several benefits could be achieved with an Enterprise Resource Planning system. For instance, eliminating the manual labor for integration. Additionally, Citizens and Businesses would have the capability to review and/or make payments to accounts via the internet for business license and vendor purchase orders and invoicing. The proposal is to bring all three systems together with this new technology and in the process save the City approximately $1.2 Million in 10 years just in annual maintenance costs, not including the efficiencies and stream line of the current manual processes.

    Capital Improvement Project Plan

    Department Responsible:Information Technology

    Project Number:GG 11-09

    Project Name:Financial Management System

  • GG 11-09

    Contact Number:209-941-7349

    Capital Improvement Project Plan

    Department Responsible:Information Technology

    Project Number:GG 11-09

    Project Name:Financial Management System

    Critical DateJun-2011Feb-2012Mar-2012May-2012Jun-2012Aug-2012Aug-2012Sep-2012Aug-2013Jan-2014Apr-2016

    Prior & Current Year Actuals

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    425,073 62,525 - - - - - 487,598 56,663 - - - - - - 56,663 56,664 - - - - - - 56,664

    538,400$ 62,525$ -$ -$ -$ -$ -$ 600,925$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    166,073 62,525 - - - - - 228,598 - - - - - - - -

    213,100 - - - - - - 213,100 900 - - - - - - 900

    45,000 - - - - - - 45,000 425,073$ 62,525$ -$ -$ -$ -$ -$ 487,598$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    56,663 - - - - - - 56,663 - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    56,663$ -$ -$ -$ -$ -$ -$ 56,663$

    Write RFP

    Award of Contract

    Systems parallel testing

    City Council ApprovalFinalize and sign contract

    Vendor demo's and selection

    Conversion and parallel testing of system specially Utility Billing

    Vendor Evaluation

    Take contract to City Council for Approval

    Components

    Complete Needs Analysis

    Descriptions

    Meet with all departments for requirements Release RFP to vendors

    Project Components & Estimated Timeline

    MiscellaneousTotal General Fund (1010):

    Water Equip Repl Reserves Fund (5620)

    Sewer Equip Repl Reserves Fund (6010)

    Professional ServicesProject Management

    Software

    General Fund Equip Repl Res Fund (1010)

    Implementation and "Go-live" System go-live

    Water Equip Repl Reserves Fund (5620)

    Issue RFP

    RFP Writing

    ATI/IVR

    Meet with top 3 vendors for selection

    Hardware, Software and Networking configurationSelected Vendor evaluation of City's needs

    GF Equip Repl Reserves Fund (1010)Source of Funds

    System Configuration

    Total Water Fund (5620):

    Interactive Voice Response

    Computer EquipmentSoftwareMiscellaneous

    Professional ServicesProject Management

    Total Revenues:

    Computer Equipment

  • GG 11-09

    Contact Number:209-941-7349

    Capital Improvement Project Plan

    Department Responsible:Information Technology

    Project Number:GG 11-09

    Project Name:Financial Management System

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    56,664 - - - - - - 56,664 - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    56,664$ -$ -$ -$ -$ -$ -$ 56,664$

    538,400$ 62,525$ -$ -$ -$ -$ -$ 600,925$ Total Expenditures:

    MiscellaneousTotal Sewer Fund (6010):

    Software

    Professional ServicesProject ManagementComputer Equipment

    Sewer Equip Repl Reserves Fund (6010)

  • GG 12-14

    Contact Number:209-941-7363

    Project Description:

    Justification:

    Project Name:Solar Energy Project

    Capital Improvement Project Plan

    Department Responsible:Public Works/Ken Reed

    In 2013, City Council authorized TerraVerde Renewable Partners, LLC. to conduct a competiive bid process for the installation and adopted the minimum bid criteria for the City of Lathrop's Solar Energy Project. The City has selected Barrego Solar as the qualified respondent and has executed a Solar Power Purchase Agreement with them along with the four site agreements for the following projects. This project includes the installation of Car Port solar panels at City Hall, Community Center, and Ground Mount solar panels at the Storm Drain Basin at Harlan Road, and Corporation Yard.

    Solar power will provide an opportunity for the City to reduce annual electrical operating costs by a minimum of $20,000 per year.

    Project Number:GG 12-14

  • GG 12-14

    Contact Number:209-941-7363

    Project Name:Solar Energy Project

    Capital Improvement Project Plan

    Department Responsible:Public Works/Ken Reed

    Project Number:GG 12-14

    Critical DateSpring 2015 Summer 2015 Fall 2015

    Prior & Current Year Actuals

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    18,660 23,340 - - - - - 42,000 74 12,426 - - - - - 12,500

    18,734$ 35,766$ -$ -$ -$ -$ -$ 54,500$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2014/152014/15

    Recommended2015/16 Planned

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    Total Allocations

    - - - - - - - -

    - - - - - - - -

    18,660 23,340 - - - - - 42,000 - - - - - - - -

    Descriptions

    Source of Funds

    Engineering Services

    The carport structures first and then the ground mounts next Construction of the 4 sites

    Water System Cap Repl Fund (5600)

    Construction

    Components

    Acquisition

    Project Components & Estimated Timeline Construction complete Power starts to flow

    Plan check and permits

    General Fund (1010)

    Total Revenues:

    General Fund (1010)Professional Services

    - - - - - - - -

    - - - - - - - -

    18,660$ 23,340$ -$ -$ -$ -$ -$ 42,000$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    - 12,426 - - - - - 12,426 74 - - - - - - 74 74$ 12,426$ -$ -$ -$ -$ -$ 12,500$

    18,734$ 35,766$ -$ -$ -$ -$ -$ 54,500$

    Engineering Services

    Total General Fund (1010):Miscellaneous

    ConstructionEngineering ServicesMiscellaneous

    Total Water Cap Rep Fund (5600):

    Water System Capital Repl Fund (5600)Professional ServicesAcquisition

    Total Expenditures:

  • GG 13-06

    Contact Number:209-941-7430

    Project Description:

    Justification:

    Public Works/Dameon Flores

    Capital Improvement Project Plan

    Department Responsible:

    Project Number:GG 13-06

    Project Name:Capital Facility Fee Study Update

    Capital Facility Fee review and update nexus study to ensure that the impact fees being levied are current, accurate and in compliance with the requirements of Assembly Bill AB1600 (Government Code Section 66000 et. Seq.).

    This City has entered into a contract with Goodwin Consulting Group, Inc. to update the 2005 CFF to reflect; 1) the slowdown in housing development versus the pace expected in 2005; 2) the anticipated delay in need for public infrastructure; 3) addition of specific fees for the Central Lathrop Specific Plan, the Lathrop Gateway Business Park and the South Lathrop Specific Plan. Developers for these three areas funded their share of this study. Capital facility fees are needed for these areas before permits can be issued for development.

  • GG 13-06

    Contact Number:209-941-7430Public Works/Dameon Flores

    Capital Improvement Project Plan

    Department Responsible:

    Project Number:GG 13-06

    Project Name:Capital Facility Fee Study Update

    Critical DateFall 2015

    Winter 2015

    Prior & Current Year Actuals

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    12,069 57,931 . - - - - 70,000 4,416 20,584 - 25,000 4,416 20,584 - 25,000 8,537 41,463 - 50,000

    29,437$ 140,563$ -$ -$ -$ -$ -$ 170,000$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    Project Components & Estimated Timeline

    Source of FundsAdministration Fund (2290)

    Total Revenues:Gateway Developer Fund (2710)

    CLSP Developer Fund (2710)SLSP Developer Fund (2710)

    DescriptionsComplete draft update.Council approves Capital Facility Program and fees

    ComponentsDraft ReportCompletion

    Use of Funds Year Actuals FY 2015/16 Recommended Planned Planned Planned Planned Allocations

    12,069 57,931 - - - - - 70,000 - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    12,069$ 57,931$ -$ -$ -$ -$ -$ 70,000$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    17,368 82,632 - - - - - 100,000 - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    17,368$ 82,632$ -$ -$ -$ -$ -$ 100,000$ 29,437$ 140,563$ -$ -$ -$ -$ -$ 170,000$

    Construction

    Total Expenditures:

    Total Adminsitration Fund (2290):

    Administration Fund (2290)Professional ServicesDesign and Engineering Land AcquisitionConstructionMiscellaneous

    Total Developer Fund (2710):

    Developer Fund (2710)Professional ServicesDesign and Engineering Land Acquisition

    Miscellaneous

  • GG 15-18

    Contact Number:209-941-7363

    Project Description:

    Justification:

    Project Number:GG 15-18

    Project Name:City Hall Reorganization

    Capital Improvement Project Plan

    Department Responsible:Public Works/Ken Reed

    This project will review the efficacies of City Hall and create a plan to improve traffic flow and interactions within each department. The project will also evaluate the current document storage system for each department and rearrange existing components utilized by staff to increase productivity.

    The City Hall reorganization project will increase staff productivity by creating organized spaces within assigned department areas. This project will help to decrease the amount of time spent searching for information, as well as streamline traffic flows and create efficiency within the existing space by assessing the location of existing components.

  • GG 15-18

    Contact Number:209-941-7363

    Project Number:GG 15-18

    Project Name:City Hall Reorganization

    Capital Improvement Project Plan

    Department Responsible:Public Works/Ken Reed

    Critical DateSpring 2015 Summer 2015 Winter 2015

    Prior & Current Year Actuals

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - 265,000 - - - - - 265,000 -$ 265,000$ -$ -$ -$ -$ -$ 265,000$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2014/152014/15

    Recommended2015/16 Planned

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    Total Allocations

    - 15,000 - - - - - 15,000 - - - - - - - -

    - 250,000 - - - - - 250,000 - - - - - - - -

    - - - - - - - -

    -$ 265,000$ -$ -$ -$ -$ -$ 265,000$

    Assessment & Design

    General Fund (1010)Total Revenues:

    General Fund (1010)Professional Services

    Construction

    Components

    Acquisition

    Project Components & Estimated Timeline

    Construction complete

    Source of Funds

    Engineering Services

    Assess work flow and design issues within City Hall

    Total General Fund (1010):Miscellaneous

    Implement approved changes to make the space more efficient Construction & approved changesCity Hall is made to be more efficient

    Descriptions

    -$ 265,000$ -$ -$ -$ -$ -$ 265,000$ -$ 265,000$ -$ -$ -$ -$ -$ 265,000$ Total Expenditures:

    Total General Fund (1010):

  • PK 15-11

    Contact Number:209-941-7363

    Project Description:

    Justification:

    Public Works / Ken Reed

    Council approved the purchase of the unisex restroom that staff presented (Green Flush Technologies) , The restroom has been ordered and will be delivered in June 2015. Installation will be completed by September 2015

    There were Citizen concerns that there is no location to use a restroom while using the dog parks, City Council requested Staff to create a plan to install a Unisex restroom at the South linear Park.

    Capital Improvement Project Plan

    Department Responsible:

    River Park South Restroom InstallationProject Number:PK 15-11

    Project Name:

  • PK 15-11

    Contact Number:209-941-7363Public Works / Ken Reed

    Capital Improvement Project Plan

    Department Responsible:

    River Park South Restroom InstallationProject Number:PK 15-11

    Project Name:

    Critical DateSpring 2015

    Summer of 2015Late Summer 15

    Prior & Current Year Actual

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - 60,500 - - - - - 60,500 -$ 60,500$ -$ -$ -$ -$ -$ 60,500$

    Use of Funds Prior & Current

    Year ActualCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - - - - - - - -

    - 5,000 - - - - - 5,000 - - - - - - - -

    8,500 - - - - 8,500 - 47,000 - - - - - 47,000 -$ 60,500$ -$ -$ -$ -$ -$ 60,500$ -$ 60,500$ -$ -$ -$ -$ -$ 60,500$

    Restroom

    Miscellaneous

    Construction CompleteProject Components & Estimated Timeline

    ConstructionConstruction Complete

    DescriptionsGreen Flush Technologies

    ComponentsCouncil Approved Purchase

    Total Expenditures:Total Measure C Fund (1060):

    Measure C Fund (1060)Total Revenues:

    Measure C Fund (1060)Project ManagementDesign and Engineering Land Acquisition

    Source of Funds

    Construction

  • PK 15-14

    Contact Number:209-941-7363

    Project Description:

    Justification:

    7th Street Skate Park Renovation and Site Cleanup

    This project includes removal of the Benson House, fences, all trees, and the existing components of the Skate Park. The concrete under the skate park will stay and a new skate park will be installed at the same location. There will a small amount of new fence work that needs to be completed to finish off the existing fence around the skate park. In November 2014 Council approved a budget to start the design and construction work. Construction will begin in June 2015 and will be completed by September 2015.

    This Project is needed because both the Benson House and the skate park are unsafe and we need to make sure that the site is safe and easy to maintain for the safety of our citizens. Through citizens concerns we plan on replacing the existing unsafe skate park with a new very low maintenance skate park.

    Capital Improvement Project Plan

    Department Responsible:Public Works / Ken Reed

    Project Number:PK 15-14

    Project Name:

  • PK 15-14

    Contact Number:209-941-7363

    7th Street Skate Park Renovation and Site Cleanup

    Capital Improvement Project Plan

    Department Responsible:Public Works / Ken Reed

    Project Number:PK 15-14

    Project Name:

    Critical DateSpring 2014

    Summer 2015Summer 2015

    Fall 2015

    Prior & Current Year Actuals

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - 95,000 - - - - - 95,000 -$ 95,000$ -$ -$ -$ -$ -$ 95,000$

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - - - - - - - -

    - 5,000 - - - - - 5,000 - - - - - - - -

    - 88,126 - - - - - 88,126 - 1,874 - - - - - 1,874 -$ 95,000$ -$ -$ -$ -$ -$ 95,000$ -$ 95,000$ -$ -$ -$ -$ -$ 95,000$

    Total Measure C Fund (1060):

    Measure C Fund (1060)Project ManagementDesign and Engineering Land AcquisitionConstructionMiscellaneous

    Descriptions

    Construction Completion

    Review Survey/Prepare Construction DocumentsProject bids and City Council awards contractConstruction beginsConstruction is completed/Update Database

    Total Expenditures:

    Total Revenues:

    Source of Funds

    ComponentsDesign PhaseBid/Award ProjectConstruction

    Measure C Fund (1060)

    Project Components & Estimated Timeline

  • PK 16-07

    Contact Number:209-941-7430

    Project Description:

    Justification:

    Capital Improvement Project Plan

    Department Responsible:

    City Park Equipment and Rubberized Surface ImprovementsProject Number:PK 16-07

    Project Name:

    Public Works/Milt Daley

    Replace playground, install additional playground equipment and rubberized surfacing.

    Replace outdated playground equipment at Woodfield Park and replace sand with rubberized surface. Place additional playground equipment at Mossdale Community Park and Crescent Park. Install rubberized surfacing at Mossdale Community Park and Valverde Park.

  • PK 16-07

    Contact Number:209-941-7430

    Capital Improvement Project Plan

    Department Responsible:

    City Park Equipment and Rubberized Surface ImprovementsProject Number:PK 16-07

    Project Name:

    Public Works/Milt Daley

    Critical DateSummer 2015Summer 2015

    Fall 2015Fall 2015

    Prior & Current Year Actual

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - - 308,635 - - - - 308,635 - - 61,000 - - - - 61,000 -$ -$ 369,635$ -$ -$ -$ -$ 369,635$

    Use of Funds Prior & Current

    Year ActualCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - - - - - - - -

    - - 50,000 - - - - 50,000 - - - - - - - -

    - - 258,635 - - - - 258,635 - - - - - - - -

    -$ -$ 308,635$ -$ -$ -$ -$ 308,635$

    Use of Funds Prior & Current

    Year ActualCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    - - - - - - - -

    - - - - - - - -

    - - - - - - - -

    - - 61,000 - - - - 61,000 - - - - - - - -

    -$ -$ 61,000$ -$ -$ -$ -$ 61,000$ -$ -$ 369,635$ -$ -$ -$ -$ 369,635$

    Project ManagementDesign and Engineering Land Acquisition

    Descriptions

    Total Expenditures:

    Total Measure C Fund (1060):

    Measure C Fund (1060)

    Total Revenues:

    Measure C Fund (1060)

    Components

    CDBG Fund (265)

    Miscellaneous

    Design PhaseBid Process

    Design and Engineering Land Acquisition

    CDBG Fund (265)Project Management

    Construction PhaseCompletion

    Project Components & Estimated Timeline

    Miscellaneous

    Prepare Plans and SpecificationsBidding Project

    Total CDBG Fund (265):

    Council awards the contract and construction beginsConstruction is complete

    Source of Funds

    Construction

    Construction

  • PS 97-02

    Contact Number:209-941-7430

    Project Description:

    Justification:

    Capital Improvement Project Plan

    Department Responsible:Public Works / Michael King

    Project Number:PS 97-02

    Project Name:Lathrop Road Westerly Grade Separation

    The project will construct a four-lane bridge over the Union Pacific Railroad tracks at 7th Street and includes the realignment and widening of Lathrop Road, construction of a new residential access road, relocation of the existing utilities. Construction of the project is fully funded through Measure K, Prop 1B (HRCSA) and UPRR. Currently the Contractor is in phase 3 of the construction which includes building the permanent retaining wall, the residential access road, the medians, final lift of asphalt and landscaping. Construction began in October 2013 and is expected to last until the Summer 2015.

    Lathrop Road is a regional corridor connecting I-5 to SR-99. The grade separation is needed for safety and emergency purposes and to facilitate the traffic flow along this important corridor. This crossing is ranked #26 on the statewide grade separation priority list. The project is majority funded through STIP funds, Prop 1B (HRCSA) funds, Measure K funds, as well as City CFF Program funds. The project is expected to be open for traffic by the summer of 2015.

    W

    o

    o

    d

    f

    i

    e

    l

    d

    D

    r

    i

    v

    e

    LATHROP ROAD

    U

    P

    R

    R

    U

    P

    R

    R

    5

    t

    h

    S

    t

    r

    e

    e

    t

    W

    o

    o

    d

    f

    i

    e

    l

    d

    D

    r

    i

    v

    e

    6

    t

    h

    S

    t

    r

    e

    e

    t

    7

    t

    h

    S

    t

    r

    e

    e

    t

    Sharpe Depot

    California Natural

    Products

    M

    c

    K

    i

    n

    l

    e

    y

    A

    v

    e

  • PS 97-02

    Contact Number:209-941-7430

    Capital Improvement Project Plan

    Department Responsible:Public Works / Michael King

    Project Number:PS 97-02

    Project Name:Lathrop Road Westerly Grade Separation

    Critical DateFall 2013

    Spring 2014Winter 2014

    Summer 2015

    Prior & Current Year Actuals

    Carry Forward FY 2015/16

    2015/16 Recommended

    2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    3,964,581 1,035,419 - - - - - 5,000,000 327,820 73,180 - - - - - 401,000

    8,236,098 2,618,902 - - - - - 10,855,000 200,000 - - - - - - 200,000

    2,700,042 - - - - - - 2,700,042 136 - - - - - - 136

    499,000 - - - - - - 499,000 - - 975,121 - - - - 975,121

    15,927,677$ 3,727,501$ 975,121$ -$ -$ -$ -$ 20,630,299$

    Prior & Current Carry Forward 2015/16 2016/17 2017/18 2018/19 2019/20 Total

    CFF - Regional Traffic "East" Fund (2230)

    Construction Phase 1Construction Phase 2Construction Phase 3Completion

    TDA - LTF Streets & Roads (COG) Fund (2140)

    HUTA Replacement Prop 42 Fund (2030)

    Components

    Project Components & Estimated Timeline

    Source of Funds

    Total Revenues:

    DescriptionsGroundbreaking, work on Sharpe facility and utility relocation

    Accept improvements and close out the project

    Prop 1B/HRCSA Fund (2030)

    Union Pacific Railroad CFF - Traffic Mitigation Fund (2250)

    Construct dirt embankments and concrete bridgeConstruct residential road and final improvements

    Measure K Fund (2110)

    STIP Fund (2160)

    Use of Funds Prior & Current

    Year ActualsCarry Forward

    FY 2015/162015/16

    Recommended2016/17 Planned

    2017/18 Planned

    2018/19 Planned

    2019/20 Planned

    Total Allocations

    425,665 218,316 - - - - - 643,981 - - - - - - - -

    - - - - -