February 17, 2011 Mr. Kyle Khone Mr. Kent Bolton Chair, Technical Studies Subcommittee WECC Technical Staff Boneville Power Administration Transmission University of Utah Research Park 905 NE 11th Ave. 615 Arapeen Utah, Suite 210 Portland, OR 97232 Salt Lake City, UT 84108- 1288 A new SVC (-75 / 200 MVAr) will connected at Tecnologico (20111 “TEK-230 “) substation for local voltage support and to increase reactive margin in the Valley Area of the CFE Baja California system. Dynamic model will be provided by the vendor shortly, commercial operation is scheduled for late March, 2011. New substation “El Centinela” (20453 “CNT-230 “) between TL 20111 “TEK-230 “ – 20112 “STB-230 “ 230 kV. Commercial date, November 2011. New substation “Carranza” (204161 CZA-161 ”) between TL 20153 “GOR-16 “ – 20147 “CTY-161 “ 161 kV. Commercial date, November 2011. Comisión Federal de Electricidad

Upload: others

Post on 02-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

2011 CFE Annual Progress Report

(Comisión Federal de Electricidad)

February 17, 2011

Mr. Kyle KhoneMr. Kent Bolton

Chair, Technical Studies SubcommitteeWECC Technical Staff

Boneville Power Administration TransmissionUniversity of Utah Research Park

905 NE 11th Ave.615 Arapeen Utah, Suite 210

Portland, OR 97232Salt Lake City, UT 84108-1288

A new SVC (-75 / 200 MVAr) will connected at Tecnologico (20111 “TEK-230 “) substation for local voltage support and to increase reactive margin in the Valley Area of the CFE Baja California system.

Dynamic model will be provided by the vendor shortly, commercial operation is scheduled for late March, 2011.

New substation “El Centinela” (20453 “CNT-230 “) between TL 20111 “TEK-230 “ – 20112 “STB-230 “ 230 kV. Commercial date, November 2011.

New substation “Carranza” (204161 CZA-161 ”) between TL 20153 “GOR-16 “ – 20147 “CTY-161 “ 161 kV. Commercial date, November 2011.

No one of the above new transmission facilities affect to neighbor systems.

Last Annual Progress Report was sent on February 19, 2010.

If you have any questions regarding the Annual Progress Report, please contact Jose Santamaria at 011 52 (686) 558-1541 or via e-mail at [email protected] or Alberto Gonzalez at 011 52 (686) 558-1517 or via e-mail at [email protected].

Sincerely,

Jose SantamariaAlberto Gonzalez

CFE´s Planning OperationAnalysis Department Chief

SRWG memberPCC member