2010-sept-xeneca presentation to city council
DESCRIPTION
This file is not complete or final!TRANSCRIPT
Waterpower Development on the Vermilion River A Presentation to the City of Greater Sudbury
September 23, 2010
By Mark Holmes, President Marlyn Consulting, in Association with
Ontario 1713399 and 1713400 and in partnership with Xeneca Power
Development Inc.
Building a greener Ontario through clean, renewable energy
Reason for Meeting
• To provide to City of Sudbury an overview of Vermilion River green
energy projects and project proponents.
• To provide the City with an overview of Ontario’s green electricity
development policies and objectives.
• To provide Project history and status updates.
• Outline next steps and timelines in Project development.
Patrick Gillette, BA, MES, MPA, President/COO
President & Owner - Xeneca Power Development Inc.
$400 million Energy Project Financing
1000 MW of Project Development experience
Co-founder Canadian Renewable Energy Corp. (CREC)
Uwe Roeper, M.Sc., P.Eng, CEO
President - Ortech Energy, Ortech Environmental
Co-founder of CREC
Xeneca Power Development
Mark Holmes, VP Corporate Affairs
Over 15 years resource use and management experience
Six years energy sector consulting
Extensive resource use experience in forestry, mining and wildlife conservation
25 years Regulatory, Government Relations, Communications background
Edmond Laratta, M.Eng., P.Eng., Manager , Environmental Affairs
Over 35 years of diverse environmental assessment, regulation compliance and
program implementation practice
Extensive background of training including: risk management, waterpower geology,
groundwater contamination transport and hazardous waste management
Xeneca Power Development
Xeneca Power Development Well capitalized and experienced partners and investors in the
renewable energy field. Business run by an experienced
management team with a proven record of success.
Xeneca Structure
Firelight Infrastructure
Partners
OP Trust
Dundee Realty
Corporation
Directors / Executive Team
Jason Lester, COO Dundee Realty Corporation / Director Xeneca
Gavin Ingram, OPTrust / Director Xeneca
Uwe Roeper, CEO / Director Xeneca
Patrick Gillette, President / COO / Director Xeneca
Xeneca’s Senior
Management Uwe Roeper Patrick Gillette
Mark Holmes Arnold Chan
Xeneca LP
XENECA
Provincial Profile
• 130 MW of Ontario projects submitted to
the Ontario Power Authority’s Feed-In
Tariff (FIT) program.
• 72 MW representing 19 projects,
including four projects on the Vermilion
and one of the Wahnapitae near
Kilarney, have been approved for FIT
contracts. Another 14 projects are
awaiting assessment for connection to
the electricity grid.
• With FIT Contract there is a five year
window for development. Projects need
to move quickly and concurrently
through several approval processes.
Why waterpower?
Currently, Ontario has a
surplus of base load power,
but lacks peaking power
production, and, as such,
efforts are being made to
increase availability of “stored
power.” Waterpower is an
excellent means to balance the
supply mix. Water can be
stored behind dams in
reservoirs, or simply
redirected when needed to
generate power, and, unlike
fossil fuels and biomass, there
are no emissions.
Current Public Policy
• Government and Power
Authorities recognize need for
local generation which is strongly
encouraged via public policy.
• Green Energy Act (GEA) dovetails
with Ontario Power Authority
power purchase agreements and
MOE’s Environmental Approval
process.
• MNR revamping its site release
policy to merge with GEA.
Current Public Policy – cont.
• Federal policy also strongly
encourages the development
of green, renewable energy.
• Helps achieve goal of
reducing atmospheric
emissions.
• Several Federal programs
including Green Energy Fund
in place to facilitate green
energy development.
Why the Vermilion River?
Long distance transmission,
and infrastructure is costly to
build and maintain. Power
produced and used locally is
more economical and
environmentally sound.
Vermilion River has good flow
regimes and adequate head…
the two main factors in making
waterpower development
practical and economical.
Impacts on Sudbury
and area?
• Hydrology and topography show the
Vermilion sites have good
generation potential with a total
installed capacity of about 11.8 MW.
• Sites known as Wabageshik, At Soo
Crossing, Cascade Falls and
McPherson Falls and are upstream
from existing Vale Inco
developments at Wabageshik Lake.
• Supports development of renewable
energy.
Vermilion River upstream projects
Economic Impacts
Approximate economic
activity (direct) to build in
Ontario is $5 million per MW.
Direct job creation
(construction only) 10,000
person hours per MW. Indirect
jobs multiply by 1.5.
Local/Regional economic
boost of $2.5 million per MW.
Economic Impacts – cont.
Broad based economic stimulus (engineering, consulting, legal,
goods & services).
First Nations participation incentives.
Revenue to Ontario (GRC) downloads to municipalities. City of
Greater Sudbury may want to open discussion with Ministry of
Municipal Affairs and Housing.
Provincial and Federal Income taxes.
May assist mining companies by providing more reliable power
with some potential cost savings.
The Vermilion River Projects
• Work progressing since 2008.
• Potential for about just over
11 MW.
• Transmission lines
connecting at Larchwood
and/or Espanola TS .
• More economic opportunity
associated with construction
of transmission.
Project Status
• Land ownership determined
and agreements with mining
companies, City of Greater
Sudbury are being sought.
• Engineering review of
hydrology.
• Environmental field studies
have begun.
• LiDAR digital aerial survey
completed and accurate
within 2-4 cm.
• FIT Contract Awarded
April 8, 2010.
Outlet Kap Lake
• First Nations discussions
initiated with some Communities.
MNR identifies and provides
notification, proponent duty to
consult and work toward B 2 B
arrangements.
• Stakeholder consultation under
way with newspaper
advertisements of Notice of
Commencement.
• Public Information sessions
being organized.
Project Status - cont.
At Soo Crossing Project
• Existing rapids/falls on
Vermilion River ±70 m
upstream of existing
railway bridge, ±2.6 km
downstream of Highway
17.
• Concrete spillway dam
and fill embankments
Penstock and
powerhouse.
• ±1.5 km new access road
to existing Hwy 55.
• Xeneca requests City
input and support.
Cascade Falls Project
• Existing rapids/falls on
Vermilion River ±400 m
downstream of hydro
corridor, ±4.4 km
upstream of Highway 17.
• Concrete spillway dam,
intake channel and
Powerhouse,
transformer station.
• ±1.5 km new access road
to existing Hwy 55.
• Xeneca requests City
input and support.
McPherson Falls Project
• Existing rapids/falls on
Vermilion River ±8 km
upstream of Highway 17.
• Concrete spillway dam
Intake channel and
Powerhouse,
transformer station.
• ±3.5 km new access road
to existing local road.
• Xeneca requests City
input and support.
Wabageshik Project
• Existing rapids/falls on
Vermilion River
approximately ±400 m
downstream of existing
road, approximately
±600 m downstream of
Wabageshik Lake.
• Concrete spillway dam,
Powerhouse,
transformer station, ±500
m new access road to
existing local road.
• Xeneca requests City
input and support.
Next Steps
• Agency coordination meetings,Q4, 2010
• Data collection Q2-Q4, 2010 and possible Q1 and Q2, 2011
• Public information centres Q4, 2010
• Addressing agency input Q1-Q2, 2011
• EA completion Q2-Q3, 2011
• Equipment order Q4, 2011
• Approvals and permitting Q3, 2011-Q3, 2012
• Detail design Q1–Q4, 2012
• Construction Q1, 2013–Q4, 2014
• Testing and commissioning 2015
Thank You
Questions….. Discussion