2009 acec/odot conference odot’s 1r program liz hunt, p.e. odot pavement services engineer

22
2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Upload: alan-mccormick

Post on 30-Dec-2015

220 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

2009 ACEC/ODOT CONFERENCE

ODOT’S 1R PROGRAM

Liz Hunt, P.E.

ODOT Pavement Services Engineer

Page 2: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Issue With rising material and construction

costs and declining funding it is essential that ODOT’s Highway construction and maintenance programs ensure that all available dollars are directed to activities and projects which optimize the Highway System condition as a whole.

Page 3: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

1R Technical Bulletin

Page 4: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

1R Program Components

Annual bucket for preservation projects requiring only a single lift of paving.

Anticipated savings from developing projects under 1R standards (currently set at $7M/year) would be used to address substandard priority safety features.

Page 5: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

1R Projects

Address pavement feature only Adversely impacted safety features need

to be addressed like raising a guardrail to accommodate an overlay.

Safety features addressed through separate program based on priority needs.

Page 6: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

1R Standard Approval Process

Region Pavement Services Unit FHWA

Page 7: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Pavement Details

Page 8: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer
Page 9: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Eligible Projects

Single paving lift Non-structural inlay or overlay (2 to 3”) Leveling course allowed

Page 10: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer
Page 11: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer
Page 12: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer
Page 13: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer
Page 14: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Safety Feature Details

Page 15: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

1R Roadside Inventory

ROADWAY TYPICAL SECTIONS DESIGN CONSIDERATIONS (ADT – Speed) STRUCTURES SIGNS GUARDRAIL DRAINAGE FACILITIES PEDESTRIAN & BICYCLE FACILITIES SPECIAL PROBLEMS (Clear Zone Safety Hazards)

Page 16: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Statewide Traffic Barrier Inventory

Page 17: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

230 Transition

Page 18: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

High Priority Barrier Features1 - Un-connected Transitions2 - Pre 230 Terminals3 - Pre 230 Transitions4 - Tongue & Groove Concrete Barrier5 - Pre 230 Type 1 and 1A Guardrail6 - Pre 230 Type 2 Guardrail7 - Pre 230 Impact Attenuators8 - Rebar Pin & Loop Concrete Barrier9 - 4 Loop Pin & Loop Concrete Barrier10 - 230 Transitions11 - 230 Impact Attenuators

Page 19: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Cost to Upgrade High Priority Features

HIGH PRIORITY FEATURE NUMBER COST

UN-CONNECTED TRANSITIONS Included in Pre-230 Terminals

PRE-230 TERMINALS 11,100 units $45,000,000

PRE-230 TRANSITIONS 1,000 units $ 6,000,000

T&G CONCRETE BARRIER 7 miles $ 3,000,000

PRE-230 Type 1 GUARDRAIL 140 miles $19,000,000

PRE-230 Type 2 GUARDRAIL Included in Pre-230 Type 1

PRE-230 IMPACT ATTENUATORS 60 units $ 3,000,000

TOTAL $76,000,000

Page 20: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Required 1R Items

Replacement of striping and delineation Gravel shoulders matched to paved

surface elevation Replacement of signal loops if impacted Replacement of rumble strips Adjust existing features as needed Vertical clearance policy followed Traffic mobility standards followed

Page 21: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Benefits of a 1R Program

Provides opportunity to plan and deliver projects strategically.

Allows more timely development of single lift preservation projects.

Simplifies project delivery – only impacted features are addressed.

Page 22: 2009 ACEC/ODOT CONFERENCE ODOT’S 1R PROGRAM Liz Hunt, P.E. ODOT Pavement Services Engineer

Questions?