2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule Kris Dixit 1

Upload: kavindra-gaurhari

Post on 02-Jan-2016

19 views

Category:

Documents


0 download

DESCRIPTION

2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule. Kris Dixit. Goals. Discuss the merits of the 2% shift factor dispatchable rule and conceptually understand its impact on convergence - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

Kris Dixit

1

Page 2: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

Goals

• Discuss the merits of the 2% shift factor dispatchable rule and conceptually understand its impact on convergence

• Discuss 2% rule and possible options that will meet the original intent while maintaining convergence between the three markets

2

Page 3: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• With no CRR counter-flow bids, there is technically no generation on D in the auction. Within this model, Gen D is offline

• The fact that Gen D is offline, allows for line to congest and create a shadow price, thus causing a price difference between A and B in the CRR auction

Example – 1: CRR Market

A B

3

D

Gen D has a -10% SF on this constraint but there are no

counter flow offers on this node. This is the only generator with a –ve shift factor on the constraint

G

Bus B has a load that is being driven by its LDF due to Load

Zone (sink) bids

Line is overloading due to flow that is being driven by sink bids

on the load zone in the CRR auction.

Page 4: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• With no offers on bus D (TPO or energy), generator D is offline in the DAM. This generator may have no offers because it may intend to come online as merchant or has sold capacity bilaterally.

• The fact that Gen D is offline, allows for line to congest and create a shadow price, thus causing a price difference between A and B in the DAM

Issue 2 Example – 2: DAM Market

A B

4

D

Gen D has a -10% SF on this constraint but there are no energy offers on this node

G

Bus B has a load that is being driven by its LDF due to Load

Zone (sink) bids

Line is overloading due to flow that is being driven by sink bids on the load zone in the DAM.

Page 5: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• Generator D is offline. • Due to loads on B line A-B starts to congest• ERCOT operations would use the 2% rule to identify all generators with >

2% shift factor on the constraint that are dispatchable.• In this case there are no dispatchable generators with greater than 2%

shift factor and the constraint is deactivated

Example – 3: RT Market

A B

5

D

Gen D has a -10% SF on this constraint. Gen D is offline. This is the only generator with a -ve

shift factor on the constraint

X

Bus B has a load that is being driven by its demand

Line is overloading due to real time flow

Page 6: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• Identical situation occur in DAM, CRR and RT markets. However, congestion only occurs in DAM and CRR markets and not in RT

• Nearly impossible for ERCOT’s DAM and CRR Team to account for these constraints since they are being driven by information on dispatchable generators that is not available in advance

• The 2% dispatchable rule creates a fundamental disconnect between the CRR, DAM and RT markets, that cannot be accounted for in the CRR and DAM markets

• This leads to divergence between the three markets

Summary

6

Page 7: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

The 2% rule

• The 2% rule has been discussed in detail at CMWG and WMS• The intent of the 2% rule was to make sure that the market did not show

price signals for smaller lines that may have no locational benefit once generation is built

• However the 2% rule does not remain consistent through generation development cycles (see slides 10,11,12)

• The 2% rule cannot be seamlessly transitioned to the CRR and the DAM markets, since the minimum shift factor used is 0.0001 in those markets

7

Page 8: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

Our Proposal

• Eliminate 2% dispatchable rule. • Reapply the 2% rule differently by deactivating constraints on lines lower

than a specific MVA threshold• For example: if we deactivated all transmission lines with capacities less

than 50MVA• Such a rule can be seamlessly used across all three markets and could

remain consistent through development cycles• Creates certainty for market participants that are trying to understand

market exposures

8

Page 9: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

Appendix

9

Page 10: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• In this specific example the line A to B is overloading and there is no generator that has > 2% shift factor on this constraint.

• If there was a generator at bus C, it would have a +10% shift factor on the constraint

• If activated this constraint would create a negative price on bus C, consistent with the reliability state.

• Based on the 2% rule, this constraint is deactivated and SCED does not produce a price signal at bus C consistent with this state.

• Prices at all four points are identical, masking the underlying reliability issue

Issue 1 Example – 2% rule at timestamp T = 0

A B

50 MW line loaded to 102%

C

Bus C has a +10% SF on this constraint but does not see any

price signal. There is no generator on this node.

10

D

Bus D has a -10% SF on this constraint but does not see any

price signal. There is no generator on this node.

Page 11: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• Based on the historical price signals produced by SCED, bus C seems to have a good pricing profile and a developer decides to build a generator on bus C.

• Since there are no historical price signals, developer will never recognize reliability issues

• ERCOT and TDSP screening studies may catch this issue, only if they show up in typical base cases. If not, developer builds generation.

• When developer builds the intended generation, ERCOT would activate the constraint and the generator would become a discount to the rest of the system

• The only remedy would be a SPS, specifically at higher SF levels.• Point D would have been a better siting location

Issue 1 Example – 2% rule at timestamp T = 1

A B

50 MW line loaded to 102%

C

There is now a generator on this bus with a +10% SF on this constraint.

Now we see price signals since there are generators with shift factors

greater than 2%

11

D

Bus D has a -10% SF on this constraint. This bus will now see a price signal associated with the

reliability issue

Page 12: 2% Shift Factor dispatchable rule discussion and alternatives for the 2% rule

• The 2% rule is inconsistent through generation development cycles• The 2% rule masks potential reliability issues that are supposed to be

discovered through price signals• The 2% rule is a throwback to zonal congestion management and is no

longer relevant to the design intent of the nodal market

Issue 1 Summary

12