TABLE 7.4 : Existing Raw Sewage & Drain Water Quality YEAR : 2004Nambul River, Manipur
Sl. No. Parameters unit
RIVER DRAIN / OUTFALL OPEN SEWERS OF THE RIVERRemarksUpstream
NR - 3 Naoremthong
Mid Stream NR - 4
Hump Bridge
Downstream NR - 6
Keishamthong
D 2 Masjeed
RoadD 3
KakhulongD 6
Manipur Central Jail
D 10 Yumnam
LeikaiD 12
PishumD 14
Haobam Marak
A. Physical Aggregate Properties For Design purposes, average BOD is taken as 150 ppm and Faecal Coliform as 25000 per 100 ml
1 TSS mg / l 172.00 314.00 287.00 259.00 386.00 265.00 120.00 144.00 232.002 TDS mg / l 46.00 82.00 53.00 78.00 108.00 70.00 64.00 72.00 68.00B Determination of Metals 1 Potassium mg / l C Determination of Inorganic Non -Metallic Constituents 1 pH 7.20 6.10 6.80 6.21 6.32 6.50 7.10 6.23 6.432 Nitrogen * mg / l 3 Phosphorus * mg / l D Organic Constituent 1 DO mg / l 18.70 2.20 6.82 NIL NIL 2.00 18.00 16.50 8.402 BOD 5 mg / l 46.50 58.00 52.20 226.50 285.00 212.00 86.00 85.40 138.003 COD mg / l 48.00 55.70 50.00 167.00 314.50 158.00 42.00 47.00 42.00E Toxic Elements / Chemicals 1 Mercury * mg / l 2 Arsenic * mg / l 3 Pesticide * mg / l 4 Insecticide * mg / l F Biological Examination 1 Total Coliform FCU / 100 ml 12,000.00 24,000.00 18,000.00 40,800.00 41,200.00 36,800.00 32,400.00 32,400.00 32,000.00
2 Faecal Coliform FCU / 100 ml 3,200.00 8,000.00 5,000.00 23,200.00 28,800.00 26,400.00 22,000.00 22,000.00 24,000.00
Note : Detailed regular river water quality data is reproduced at Part 5 : Monitoring, Evaluation, Research & Development Scheme of the DPR* Data generation of these parameters will be started from 2006 January
/tt/file_convert/577cc3ea1a28aba711978f75/document.docSection 7 : DESIGN OF SYSTEM & COMPONENT OF MONITORING, EVALUATION, R & D , 7. 18
![Page 2: 2 Design Wide](https://reader035.vdocuments.site/reader035/viewer/2022081823/577cc3ea1a28aba711978f75/html5/thumbnails/2.jpg)
Govt. of Manipur Environment & Ecology Office
DPR (Detailed Project Report) on Conservation of Nambul River of Manipur
SECTION 3 : SWM SCHEME
Ward No. Location
Area
(sq.
km
.)
Tota
l Pop
ulat
ion
(200
1)
Projected Population (Design year : 2023 AD)
Wastes Generated
during 2001(in MT)
Wastes Generated during
2023 (in MT)
* Total Wastes targeted for collection
during 2023
**Total Estimated Bio-
degradable Wastes to be collected on
2023
***Expected Total
Compost Production annum on
2023
Remarks
2005 2008 2023 per day
per annum
per day
per annum
per day
per annum
6 Uripok 0.50 7,582 8,243 8,738 11,216 3.38 1,234.27 5.00 1,825.79 4.50 1,643.21 985.93 788.74
8 Sagolband – II (West) 0.38 6,449 6,752 6,980 8,117 2.88 1,049.83 3.62 1,321.32 3.26 1,189.19 713.51 570.81
9 Keishampat 1.06 7,836 8,401 8,824 10,942 3.49 1,275.62 4.88 1,781.18 4.39 1,603.06 961.84 769.47
11 Keishamthong 0.43 6,787 7,167 7,452 8,876 3.03 1,104.86 3.96 1,444.85 3.56 1,300.37 780.22 624.18
12 Khagempali 0.47 6,819 7,275 7,642 9,406 3.04 1,110.07 4.20 1,531.20 3.78 1,378.08 826.85 661.48
13 Kwakeithel Moirang Purel 0.66 9,376 10,184 10,790 13,819 4.18 1,526.32 6.16 2,249.65 5.55 2,024.69 1,214.81 971.85
14 Moirangkhom 0.50 7,242 7,619 7,902 9,315 3.23 1,178.93 4.15 1,516.38 3.74 1,364.74 818.85 655.08
15 Yumnam Leikai-Chingamathak 0.56 7,294 7,596 7,830 8,980 3.25 1,187.39 4.00 1,461.78 3.60 1,315.60 789.36 631.49
16 Chingamakha – I (North) 0.60 7,284 7,913 8,384 10,742 3.25 1,185.76 4.79 1,748.69 4.31 1,573.82 944.29 755.43
24 Paona Bazar 0.41 9,097 9,665 10,091 12,221 4.06 1,480.90 5.45 1,989.39 4.91 1,790.45 1,074.27 859.42
Total 5.57 75,766 80,815 84,632 103,632 33.79 12,333.95 41.22 15,044.43 37.10 13,539.99 8,123.99 6,499.20
Including 15% of non permanent Population 87,131 92,937 97,327 119,177 38.86 14,184.04 53.15 19,400.76 47.84 17,460.68 10,476.41 8,381.13
Note : * Taking 90 % of the total wastes generated
* * Taking 60% of the wastes generated
* * * Taking 80% and assuming 350 days on full day working for composting processes
Taking 0.446 kg of wastes generated by a person per day (CPHEEO Manual) and Source for the records of area & population from Imphal Municipality Council
TABLE 2. 5 : Required Infrastructure for Collection – Transportation – Disposal of the Solid Wastes Management Scheme
/tt/file_convert/577cc3ea1a28aba711978f75/document.docSection 7 : DESIGN OF SYSTEM & COMPONENT OF MONITORING, EVALUATION, R & D , 7. 19
3.8
![Page 3: 2 Design Wide](https://reader035.vdocuments.site/reader035/viewer/2022081823/577cc3ea1a28aba711978f75/html5/thumbnails/3.jpg)
Govt. of Manipur Environment & Ecology Office
DPR (Detailed Project Report) on Conservation of Nambul River of Manipur
SECTION 3 : SWM SCHEME
Ward No. Location
Total Projected
Population 2023
Total Projected Population including
non permanent population (+15%) 2023
Wastes generated per day in
MT
Wastes targeted for collection
per day in MT *
Required Domestic Wastes
Bin set **
Required Tricycle
***
Required Transferring
BinsRemarks
6 Uripok 11,216 12,898 5.75 5.18 2150 13 4 8 Sagolband – II (West) 8,117 9,335 4.16 3.75 1556 10 3 9 Keishampat 10,942 12,583 5.61 5.05 2097 13 4 11 Keishamthong 8,876 10,207 4.55 4.10 1701 11 3 12 Khagempali 9,406 10,817 4.82 4.34 1803 11 3 13 Kwakeithel Moirang Purel 13,819 15,892 7.09 6.38 2649 17 5 14 Moirangkhom 9,315 10,712 4.78 4.30 1785 11 3 15 Yumnam Leikai - Chingamathak 8,980 10,326 4.61 4.15 1721 11 3 16 Chingamakha – I (North) 10,742 12,353 5.51 4.96 2059 13 4 24 Paona Bazar 12,221 14,054 6.27 5.64 2342 15 4
Total 103,632 119,177 53.15 47.84 19863 124 37
Note :
* Taking 90 % * * Taking 60% of the wastes generated
* * * Taking 80% and assuming 350 days on full day working for composting processes Taking 0.446 kg of wastes generated by a person per day (CPHEEO Manual) and Source for the records of area & population from Imphal Municipality Council
/tt/file_convert/577cc3ea1a28aba711978f75/document.docSection 7 : DESIGN OF SYSTEM & COMPONENT OF MONITORING, EVALUATION, R & D , 7. 20