1483633458077566

Upload: rizal-b

Post on 03-Jun-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 1483633458077566

    1/6

    6/10/201

    CHAPTER 16

    MANAGEMENT CONTROLS OFPROJECT

    Zuni Barokah, Ph.D.Magister Manajemen

    Fakultas Ekonomika dan Bisnis UGM2014

    NATURE OF PROJECTS

    Definition: set of activities intended to accomplish a specified end result of

    sufficient importance to be of interest to management

    Begins when management has approved the general natureof project and approximate amount of resources spent in thefirst phase of the work

    Ends when objective has been accompl ished or when it hasbeen canceled

    Varies greatly.

    PROJECTS, IN CONTRAST WITHONGOING OPERATIONS

    Single Objective

    Ongoing operations: multiple objections

    Organization Structure

    Superimposed on an ongoing organizations.

    Focus on the Project

    PROJECTS, IN CONTRAST WITHONGOING OPERATIONS

    Need for Trade-Offs

    Between scope, schedule, and costs.

    Not typical in ongoing organizations

    Less-Reliable Standards

    Project design is used only once.

    Repetitive projects tend to have more developed standard.

    Frequent Changes in Plans

    Lead by unforeseen environmental conditions

    PROJECTS, IN CONTRAST WITHONGOING OPERATIONS

    Different Rhythm

    Greater Environmental Influence

    Exceptions

    THE CONTROL ENVIRONMENT:PROJECT ORGANIZATION STRUCTURE

    Temporary organization (disbanded after the project hasbeen completed or canceled)

    Matrix Organization

    Members of the project team are employees of the sponsoring

    organization.

    Project manager and manager of the functional department are

    members bosses that permanently assigned. (Their basic loyaltyis to their functional department)

  • 8/12/2019 1483633458077566

    2/6

    6/10/201

    THE CONTROL ENVIRONMENT:PROJECT ORGANIZATION STRUCTURE

    Evolution of Organization Structure

    Architects, engineer, schedulers, and cost analysts are

    predominate in the planning phase of a construction project

    The managers are production managers in the execution ofproject

    In the final stages, the work tapers off, and principal task may

    obtain the sponsors acceptance with marketing skills being aprincipal requirement

    THE CONTROL ENVIRONMENT:CONTRACTUAL RELATIONSHIP

    Appears when project is conducted by an outside contractor.

    Two general types of contract : Fixed Price Contracts

    Contractor agrees to complete the specified work by a specified date atspecified price.

    There will be penalty if contractor fails to complete the work at specifieddate.

    Sponsor is responsible for auditing the quality and quantity of the work toensure that it is done as specified

    Cost-Reimbursement Contracts

    Sponsor agrees to pay reasonable costs plus a profit.

    Sponsor has considerable responsibility for the control of costs.

    Comparable system and personnel used by contractor needed.

    THE CONTROL ENVIRONMENT:CONTRACTUAL RELATIONSHIP

    Contrast in Contract Types

    Fixed-price contract is appropriate to be used when the scope of

    the project can be closely specified in advance and whenuncertainties are low

    Profit component or fee in cost-reimbursement usually should be

    fixed monetary amount. Fixed fee normally is adjusted if the scope

    or schedule of the project is significantly changed

    THE CONTROL ENVIRONMENT:CONTRACTUAL RELATIONSHIP

    Variations

    For both type of contract, in an incentive contract, completion

    dates or cost targets are defined in advance and contractorrewarded for completing the project earlier than target date or for

    incurring less than the target cost

    Different contract types may be used for different activities on the

    project

    INFORMATION STRUCTURE

    Work Packages Smallest element of Information in project control system.

    An aggregated work package is called the work breakdown

    structure

    Indirect Cost Accounts

    Established for administrative and support activities in addition to

    work packages for direct project work

    PROJECT PLANNING

    Starting point:

    rough estimations that was used as the basis of the decision to take

    the project

    Refining the estimations into detailed spesifications.

    Developing a management control system, underlying task

    control system, and organization chart.

    Plan for planning

    For a project with moderate complexity

  • 8/12/2019 1483633458077566

    3/6

    6/10/201

    PROJECT PLANNING:NATURE OF THE PROJECT PLAN

    Three related parts of final plan:

    Scope

    Specifications of each work package and the name of the person orunit responsible

    Schedule

    Estimated time required to complete each work package

    Cost

    Stated in project budget, usually under control budget

    PROJECT PLANNING:NETWORK ANALYSIS

    Two commonly used techniques to construct the time

    schedule:

    PERT (program evaluation and review technique) CPM (critical path method)

    Three basic steps:

    Estimating the time required for each work package

    Indentifying the interdependencies among work packages

    Calculating the critical path

    PROJECT PLANNING:NETWORK ANALYSIS

    Two commonly used techniques to construct the time

    schedule:

    PERT (program evaluation and review technique)

    CPM (critical path method)

    Three basic steps:

    Estimating the time required for each work package

    Indentifying the interdependencies among work packages

    Calculating the critical path

    PROJECT PLANNING:NETWORK ANALYSIS

    Probabilistic PERT

    Estimated times arrived on a probabilistic basis:

    A most likely time

    An optimistic time

    An pessimistic time

    PROJECT PLANNING:ESTIMATING COSTS

    Made at a level of aggregation that incorporates severalwork packages.

    At individual work package level, resources are controlled in

    terms of physical quantities.

    Less standardized, less accurate.

    Types of unknown (have to be taken into account)

    Known unknowns

    Unknown unknowns

    PROJECT PLANNING:PREPARING THE CONTROL BUDGET

    Prepared close to the inception of the work.

    Delaying preparation of the control budget ensures that

    the control budget incorporates current information.

    Control budget is an important link between planning and

    the control of performance

  • 8/12/2019 1483633458077566

    4/6

    6/10/201

    PROJECT PLANNING:OTHER PLANNING ACTIVITIES

    Other activities are performed during the planning phase

    Ex: ordering materials, obtaining permits, selecting personals, etc.

    These activities must be controlled and integrated into

    the overall effort

    PROJECT EXECUTION

    Both the sponsor and the project management are

    concerned with:

    Project time schedule realization

    Projects output specifications realization

    Projects input realization (costs)

    PROJECT EXECUTION:NATURE OF REPORTS

    Types of reports managers need:

    Trouble reports

    Report happened troubles and future troubles.

    Progress reports

    Compare actual schedule and costs with planned schedule and costs

    for the work done (including indirectly related overheads)

    Financial reports

    Less important.

    The process takes time.

    PROJECT EXECUTION:NATURE OF REPORTS

    Quantity of reports Paperwork problem/information overload (reports with too many

    details) could cause some problem. But not necessarily serious.

    A review of the set of reports is needed.

    Percent complete In cases where work packages are partially completed at reporting

    date, percentage of completion measurement is necessary

    If accomplishment measured in physical terms: percentage of completion can be measured easily

    If no quantitative measure is available: percentage of completion is subjective

    PROJECT EXECUTION:NATURE OF REPORTS

    Summarizing progress Aggregating individual work packages, thus providing an overallmeasure of accomplishment

    Punch list

    A list of items yet to be accomplished (including defects that need

    to be corrected)

    PROJECT EXECUTION:USE OF REPORTS

    Trouble reports Managers tasks: decide which troubles have the highest priority

    Progress reports

    Managers tasks: carefully analyze progress report, identify

    problems that might be not apparent in the trouble report, and

    plan on how to solve them.

  • 8/12/2019 1483633458077566

    5/6

    6/10/201

    PROJECT EXECUTION:USE OF REPORTS

    Cost to complete

    Type of comparison

    Actual cost to date VS budgeted cost of the work done to date

    Current estimate of total costs for the project VS budgeted cost for the

    project

    Current estimate = actual cost to date + estimated cost to complete

    A useful way (if calculated properly) to show how the project is expected to

    come out.

    PROJECT EXECUTION:INFORMAL SOURCES OF INFORMATION

    Practically, these written reports usually are less

    important than information manager gathers from talking

    with people

    A formal report should contain no surprises, but still is

    essential

    PROJECT EXECUTION:REVISIONS

    Lengthy or complex project is more likely to have its plan

    revised.

    Usually because of the actual cost exceeds the budgeted cost.

    Regarding comparison with future progress:

    Revised plan VS Original plan

    Solution: compare to both plan

    PROJECT EXECUTION:PROJECT AUDITING

    Quality audit must be held as a work is progressing.

    The defects could be hidden otherwise

    Generally, auditing as the work progresses is preferable

    Operational auditing: examining costs incurred, paying

    attention to management actions

    PROJECT EVALUATION:ASPECTS

    1. An evaluation of performance in executing the project1. Carried out shortly after the project completed

    2. An evaluation of the results obtained from the project

    1. Not feasible until several years later

    PROJECT EVALUATION:EVALUATION OF PERFORMANCE

    evaluation of the project management To assist in decisions regarding project managers

    evaluation of the process of managing the project

    Discover better ways of conducting future projects

    Evaluating a project tends to be subjective.

  • 8/12/2019 1483633458077566

    6/6

    6/10/201

    EVALUATION OF PERFORMANCECOST OVERRUNS

    actual costs exceed budgeted costs

    Possibilities:

    Budgeted costs are too low

    Excessive actual costs

    Budget does not represent what the costs should have

    been.

    EVALUATION OF PERFORMANCEHINDSIGHT

    Even though a decision seems unreasonable when it is

    being evaluated, the decision might be entirely

    reasonable at the time of decision making.

    Indications like personal use of projects assets and

    poor control system can still be used.

    Evaluations may lead to changes of rules or

    procedures.

    PROJECT EVALUATION:EVALUATION OF RESULTS

    There is no point in attempting to evaluate a project

    unless some action can be taken based on the

    evaluation.

    In many projects, expected benefits are not stated in

    objective, measurable terms, making evaluation of

    results complicated.

    In these cases, benefit-cost analysis is not feasible

    Must rely on judgment

    Comparison should be a part of evaluation