1.1 project information
TRANSCRIPT
120-17 Emanuel County Institute
HVAC Replacement
ADDENDUM # 3 00 9113 - 1
DOCUMENT 00 9113
ADDENDUM No. 3
1.1 PROJECT INFORMATION
A. Project Name:
Emanuel County Institute- HVAC Replacement
Swainsboro Georgia
B. Owner:
Emanuel County Board of Education
201 North Main Street
Swainsboro, Georgia 30401
C. Architect:
James W. Buckley & Associates, Inc.
114 North Green Street
Swainsboro, Georgia 30401
1.2 Date of Addendum: September 24, 2018
1.3 NOTICE TO BIDDERS
A. This Addendum is issued to all registered plan holders pursuant to the Instructions to Bidders
and Conditions of the Contract. This Addendum serves to clarify, revise, and supersede
information in the Project Manual, Drawings, and previously issued Addenda. Portions of the
Addendum affecting the Contract Documents will be incorporated into the Contract by
enumeration of the Addendum in the Owner/Contractor Agreement.
B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid
Form.
C. The date for receipt of bids is changed by this Addendum, at same time and location.
1. Bid Date: September 12, 2018, September 26, 2018 Revised October 3,2018
2. Bid Time; 2:00 p.m. Local time
3. Location: Offices of the owner 201 north Main Street Swainsboro GA
120-17 Emanuel County Institute
HVAC Replacement
ADDENDUM # 3 00 9113 - 2
1.4 REVISIONS TO PROJECT MANUAL
A. Invitation to Bid
1. Revise Bid Date, the revised bid date is October 03 2018 the time 2:00 pm
and location remain unchanged
B. Proposal Form
1. Delete Proposal form add revised Document Proposal form, copy enclosed this
addendum
C. 01 2300 ALTERNATES
1. Delete Section 01 2300 Alternates, Add, revised section 01 2300 Alternates, copy
enclosed this addendum.
D. 237210 AIR TO AIR ENERGY RECOVERY EQUIPMENT (Alternate)
1. Add Section 23 7210 Air to Air Energy Recovery Equipment, surfacing in its entirety,
copy enclosed this addendum
E. 23 8216.14 ELECTRIC AIR COILS
1. Add Section 23 8216.14 Electric Air Coils, surfacing in its entirety, copy enclosed this
addendum
1.5 REVISIONS TO DRAWINGS
A. Drawing M1.4
1. Revise drawing 2/M1.4 as shown on attached sketch SK-M3.
2. Add drawing 3/M1.4 as shown on attached sketch SK-M4.
B. Drawing M3.0
1. Delete Drawing Add Revised Drawing M3.0, copy enclosed this addendum
C. Drawing M3.1
1. Delete Drawing Add Revised Drawing M3.1, copy enclosed this addendum
D. Sheet E1.0
1. 1. Under General Note #8 - Change warranty period to Two (2) years.
2. 2. Add General Note #16 reading as follows: Contractor shall provide new engraved
identification labels for all new HVAC units. Identification labels shall be per
specifications and shall denote Unit designation and Panel and circuit number serving the
unit.
3. Label shall be attached to disconnect switch serving the unit. If no disconnect switch is
provided, install such label on the HVAC unit.
E. Drawing E2.0
1. 1. Delete Sheet E2.0 in its entirety. Add attached revised sheet E2.0R
F. Drawing E3.0
1. 1. Add the following to keyed note #10: "Existing Panel serving IHP-A7 is panel "HMC"
120-17 Emanuel County Institute
HVAC Replacement
ADDENDUM # 3 00 9113 - 3
2. 2. Add the following to keyed note #15: "Change breaker serving ERU-A1 to a 50A/3P
breaker"
G. Drawing E3.2
1. 1. Delete Sheet E3.2 in its entirety. Add attached revised sheet E3.2R
H. Drawing E3.3
1. 1. Delete Sheet E3.3 in its entirety. Add attached revised sheet E3.3R
I. Drawing E3.4
1. 1. Delete Sheet E3.4 in its entirety. Add attached revised sheet E3.4R
1.6 ATTACHMENTS
A. This Addendum includes the following attached Documents
1. Project Manual
a. Proposal Form
b. 01 2300 Alternates
c. 23 7210 Air to Air Energy Recovery
Equipment
d. 23 8216.14 Electric Air Coils
2. Sketches SK-M3, SK-M4
3. Drawings:
a. M1.5, M3.0, M3.1
b. E2.0, E3.2, E3.3, E3.4,
END OF DOCUMENT 00 9113
120-17 Emanuel County Institute
HVAC Replacement
Addendum # 3
PROPOSAL FORM B-1
SECTION B
PROPOSAL FORM
Date:
To: Emanuel County Board of Education 201 North Main Street Swainsboro, GA 30401 Re: Emanuel County Institute HVAC Replacement
Emanuel County, Georgia
Gentlemen:
BASE BID – Emanuel County Institute HVAC Replacement
A. Having carefully examined the plans and specifications entitled, Emanuel County Institute HVAC
Replacement, Emanuel County Middle County, Georgia, and the drawings similarly entitled, enumerated on
Index of Drawings, dated May and Addendum No.(s) as well as the premises and conditions
affecting the work, the undersigned proposes to furnish all services, labor, and materials called for by them for
the entire work, where accordance with said documents for the sum of:
Dollars ($ )
Sum is herein after called the "Base Bid."
B-02 CONTRACT AWARD
A. The undersigned understands and agrees to, if a contract is awarded, it will be awarded based on Base Bid and
accepted alternates chosen in any order, financial stability, and proof of ability to fully complete the project and
complete the project on schedule. Upon Owner's request all information needed to prove contractor's ability to
complete the project and complete it on schedule will be provided immediately.
B-03 ALLOWANCES
A. The base bid amount provided above to include certain allowances. The type and quantity of the allowances to
be included in the Contractor’s base bid are defined in Section 01 2100 – Allowances.
B. The Contractor to complete the form below by inserting quantities and costs as follows:
1. Insert the material quantities indicated in Section 01 2100 and as modified by addenda.
2. Insert unit costs as from Unit costs listed in bid proposal form.
3. Calculate total value of allowance.
C. Value of allowance(s) included in this form shall be utilized to establish a value against which change orders
will be charged.
D. Failure to complete this form and provide a reasonable dollar value shall be, at the Owner’s options, grounds
for rejection of bid.
120-17 Emanuel County Institute
HVAC Replacement
Proposal Form
B-2
E. Allowances:
Include Owner’s Cash Allowance within Base Bid, $40,000.00 US
B-04 ALTERNATES
A. The undersigned further proposes that should any of the following alternates be accepted and incorporated in
the contract, the Base Bid will be altered in each case as follows:
ALTERNATE NO. 1: (ADD) Thermostats
ADD the Sum of:
Dollars ($ )
ALTERNATE NO. 2: (ADD) HVAC Controls
ADD the Sum of:
Dollars ($ )
ALTERNATE NO. 3: (ADD) HVAC Controls- Select
ADD the Sum of:
Dollars ($ )
ALTERNATE NO. 4: (ADD) Mini Split Heat Pumps
ADD the Sum of:
Dollars ($ )
ALTERNATE NO. 5: (ADD) Heat Pumps
ADD the Sum of:
Dollars ($ )
ALTERNATE NO. 6: (ADD) ERV Units
ADD the Sum of:
Dollars ($ )
120-17 Emanuel County Institute
HVAC Replacement
Proposal Form
B-3
ALTERNATE NO. 7: (ADD) Media Center
ADD the Sum of:
Dollars ($ )
B-05 CONTRACT AND BONDS
A. In case he is notified in writing by mail, telegraph, or delivery of the acceptance of this proposal within thirty-
five (35) days after the time set for the opening of bids, the undersigned agrees to execute within ten (10) days
a contract (Form of Agreement between Contractor and Owner, Refer to General Conditions) for the work for
the above stated compensation and at the same time to furnish and deliver to the Owner a Performance Bond
and a Payment Bond both in an amount equal to 100% of the contract sum.
B. Contractor to require documentation from following Sub-Contractors used to develop base bid that they can
in fact provide a payment and performance bond, Attach documents to this proposal form. Bonds are not
required. At the discretion of owner, post bid, the owner may request bonds where they will be add to contract
sum.
B-06 COMMENCEMENT OF WORK
A. Undersigned agrees to commence actual physical work on the site with an adequate work force and equipment
within 5 days of written Owner’s notice to proceed to be issued about xxxx,2018 Start work on site
xxxxx,2018 and agrees to complete all work including deficiencies on or before xxxx2018.
B-07 BID BOND
Enclosed herewith is a bid bond (**) in the amount of _______________________________________ ____
Dollars ($ ) (being not less than 5% of the Base Bid). The undersigned
agrees that the above stated amount is the proper measure of liquidated damages, which the Owner will sustain
by the failure of the undersigned to execute the Contract and to furnish the Performance and Payment Bond in
case this proposal is accepted, and further agrees to the following:
1. If this proposal is accepted within thirty-five (35) days after the date set for the opening of bids and the
undersigned fails to execute the contract within ten (10) days after written notice of such acceptance or
if he fails to furnish both Performance and Payment Bond, the obligation of the bid bond will remain
in full force and effect and the money payable thereon shall be paid into the funds of the Owner as
liquidated damages for such failure; otherwise the obligation of the bond will be null and void.
2. The surety company shall have an A.M. Best rating of “A” with a financial size of “&” or better.
Surety Company must be licensed to do business in the State of Georgia as listed in the Debt of
Treasury Circular 570, latest edition, at time of bid.
120-17 Emanuel County Institute
HVAC Replacement
Proposal Form
B-4
B-08 ACCEPTANCE
A. For and in consideration of the sum of $1.00, the receipt of which is hereby acknowledged, the undersigned
agrees that this proposal may not be revoked or withdrawn after the time set for opening of bids, but shall
remain open for acceptance for a period of thirty-five (35) days following such time.
B-09 Statement of Bidder’s Qualifications
To accompany bids submitted for the Project
Name of Bidder
Business Address
Phone Number _ ________________Fax Number _____________E-Mail
Where Incorporated ______________________________When Organized _______________
Type of Business: General Contractor __ Subcontractor, Other
Federal identification number or social security number
Credit Available for this Contract $
Contracts now in Hand $
*Within ten calendar days after bid date and prior to award of the construction contract the contractor must furnish
Program manager/Owner a current audited financial statement.
Plan of Organization (Proprietorship, Partnership, Corporation)
Full name of person who holds Georgia Contractors license, Attach copy
The Bidder has never refused to sign a contract at the original bid. (True _____ ) (False ______)
The Bidder has never been declared in default on a contract. (True _____ ) (False ______)
The bidders OSHA safety modification index number (________) a number greater than one my disqualify bidder
The bidders EEV number (__________) Georgia immigration act law.
By signing this document, I (the bidder) certify that construction, under this company’s name, is my primary means of
business and employment.
Past Experience: ______________________________________________________
List of last two (2) projects K-12 schools completed within the past five (5) years of this project’s scope or larger
by dollar value and square footage. Do not list post secondary or other commercial structures completed by the
prosper under bidder’s name
1. _____________________________________ __________________________________________
Project Address
120-17 Emanuel County Institute
HVAC Replacement
Proposal Form
B-5
___________________________________________________________________________________________
_______________________
Owner’s Contact Name/Phone Number
__________________________________________________
____________________________________
Size in Square Feet Contract Amount
2. _____________________________________ __________________________________________
Project Address
___________________________________________________________________________________________
_______________________
Owner’s Contact Name/Phone Number
__________________________________________________
____________________________________
Size in Square Feet Contract Amount
Remarks:
______________________________________________________________________________
(The above statements must be subscribed and sworn to before a Notary Public)
Date:
Firm Name:
By:
Title:
_______________________________________________
(Notary Public)
The foregoing statement of qualifications is submitted under oath.
Respectfully submitted,
Name:
Address:
By:
120-17 Emanuel County Institute
HVAC Replacement
Proposal Form
B-6
Title:
A. The full name and addresses of persons and firms interested in the foregoing bids as principals are as follows:
B. The legal name of the bidder is:
120-17 Emanuel County Institute
HVAC Replacement
Proposal Form
B-7
Contractor Affidavit under O.C.G.A. § 13-10-91(b)(1)
By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10-91,
stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of
services on behalf of (name of public employer) has registered with, is authorized to use and uses the federal
work authorization program commonly known as E-Verify, or any subsequent replacement program, in
accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the
undersigned contractor will continue to use the federal work authorization program throughout the contract
period and the undersigned contractor will contract for the physical performance of services in satisfaction of
such contract only with subcontractors who present an affidavit to the contractor with the information required by
O.C.G.A. § 13-10-91(b). Contractor hereby attests that its federal work authorization user identification number
and date of authorization are as follows:
_________________________________
Federal Work Authorization User Identification Number
_________________________________
Date of Authorization
_________________________________
Name of Contractor
_________________________________
Name of Project
_________________________________
Name of Public Employer
I hereby declare under penalty of perjury that the foregoing is true and correct.
Executed on ______, ___, 201__ in _____(city), ______(state).
_________________________________
Signature of Authorized Officer or Agent
_______________________________
Printed Name and Title of Authorized Officer or Agent
SUBSCRIBED AND SWORN BEFORE ME
ON THIS THE ______ DAY OF ______________, 201__.
_________________________________
NOTARY PUBLIC
My Commission Expires:
_________________________________
END OF SECTION B
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
106-18 Burke County Middle School
HVAC Replacement
SECTION 01 2300
ALTERNATES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.3 DEFINITIONS
A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined
in the bidding requirements that may be added to or deducted from the base bid amount if
Owner decides to accept a corresponding change either in the amount of construction to be
completed or in the products, materials, equipment, systems, or installation methods described
in the Contract Documents.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work
of the alternate into Project.
1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar
items incidental to or required for a complete installation whether or not indicated as part
of alternate.
B. Notification: Immediately following award of the Contract, notify each party involved, in
writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or
deferred for later consideration. Include a complete description of negotiated revisions to
alternates.
C. Execute accepted alternates under the same conditions as other work of the Contract.
D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections
referenced in schedule contain requirements for materials necessary to achieve the work
described under each alternate.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
106-18 Burke County Middle School
HVAC Replacement
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
PART 4 - SCHEDULE OF ALTERNATES:
A. ALTERNATE NO. 1 THERMOSTATS
1. Under Base bid: Replace furnish 7-day programmable thermostats for all HVAC
equipment (existing and new).
2. Under This alternate furnish Wi-Fi programmable thermostats for all HVAC equipment
(existing and new).
B. ALTERNATE NO.2 HVAC CONTROLS
1. Under base bid, provide furnish 7-day programmable thermostats for all HVAC
equipment (existing and new).
2. Under this alternate provide furnish Direct Digital Controls as specified in this Section 23
0900 instrumentation and controls for HVAC by one of the vendors listed. Provide for all
HVAC equipment (existing and new).
C. ALTERNATE NO.3 HVAC CONTROLS select
1. Under base bid, provide furnish 7-day programmable thermostats for all HVAC
equipment (existing and new).
2. Under this alternate provide furnish Direct Digital Controls as specified in this Section 23
0900 instrumentation and controls for HVAC by “Automated Logic Corporation”.
Provide for all HVAC equipment (existing and new).
D. ALTERNATE NO.4 MINI-SPLIT HEAT PUMPS
1. Under base bid, provide Mini-Split Heat Pumps from one of the listed manufactures
2. Under this alternate provide Mini-Split Heat Pumps as Manufactured by Mitsubishi
E. ALTERNATE NO.5 HEAT PUMPS
1. Under base bid, provide Heat Pumps from one of the listed manufactures
2. Under this alternate provide Heat Pumps as Manufactured by Trane or Carrier
F. ALTERNATE NO. 6 ERV UNITS
1. Under Base bid: Replace only part of ERV as specified. Use Section 23 7200 Air to Air
Energy Recovery Equipment
a. Under This alternate Replace completely with all new ERV’s, Use section 23 7210
Air to Air Energy Recovery Equipment
G. ALTERNATE NO.7 MEDIA CENTER
1. Under base bid, the HVAC unit servicing the Media Center the existing unit shall reman
2. Under this alternate Remove and replace the HVAC unit servicing the Media Center.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
106-18 Burke County Middle School
HVAC Replacement
END OF SECTION 01 2300
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 1
SECTION 23 7210
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Packaged energy recovery units. (Alternate)
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product indicated. Include rated capacities, operating
characteristics, furnished specialties, and accessories.
1. Complete fan performance curves for both Supply Air and Exhaust Air, with system
operating conditions indicated, as tested in an AMCA Certified Chamber.
2. Sound performance data for both Supply Air and Exhaust Air, as tested in an AMCA
Certified chamber.
3. Motor ratings, electrical characteristics and motor and fan accessories.
4. Performance ratings for all DX coils.
5. Microprocessor Controller (DDC) specifications to include available options and
operating protocols. Include complete data on all factory-supplied input devices.
6. AHRI Certified coil performance ratings with system operating conditions indicated.
Ratings shall be in accordance with Standard 410.
7. Energy wheel performance data for both summer and winter operation.
8. Electric consumption data and construction specifications for electric heater, to include
heat output, warranty and safety certifications.
B. Shop Drawings: For air-to-air energy recovery equipment. Include plans, elevations, sections,
details, and attachments to other work.
1. Detail equipment assemblies and indicate dimensions, weights, loads, required
clearances, method of field assembly, components, and location and size of each field
connection.
2. Wiring Diagrams: For power, signal, and control wiring.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 2
1.4 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Plans, elevations, and other details, drawn to scale, on which the
following items are shown and coordinated with each other, using input from Installers of the
items involved:
1. Suspended ceiling components.
2. Structural members to which equipment or suspension systems will be attached.
B. CLOSEOUT SUBMITTALS
C. Operation and Maintenance Data: For air-to-air energy recovery equipment to include in
maintenance manuals.
1.5 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged with protective
covering for storage and identified with labels describing contents.
1. Filters: Filter’s shall be MERV 8 disposable. Furnish Supply Air, Exhaust Air, and final
filters for each unit. 2. Fan Belts: One set(s) of belts for each belt-driven fan in energy recovery units.
3. Wheel Belts: One set(s) of belts for each heat wheel.
1.6 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by
a qualified testing agency, and marked for intended location and application.
B. ARI Compliance:
1. Capacity ratings for air-to-air energy recovery equipment shall comply with ARI 1060,
"Performance Rating of Air-to-Air Heat Exchangers for Energy Recovery Ventilation
Equipment."
2. Capacity ratings for air coils shall comply with ARI 410, "Forced-Circulation Air-
Cooling and Air-Heating Coils."
C. ASHRAE Compliance:
1. Applicable requirements in ASHRAE 62.1, Section 5 - "Systems and Equipment" and
Section 7 - "Construction and Startup."
2. Capacity ratings for air-to-air energy recovery equipment shall comply with
ASHRAE 84, "Method of Testing Air-to-Air Heat Exchangers."
D. NRCA Compliance: Roof curbs for roof-mounted equipment shall be constructed according to
recommendations of NRCA.
E. UL Compliance: Entire unit shall be ETL Certified per U.L. 1995 and bear an ETL sticker.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 3
F. Blowers shall be AMCA Certified for air flow.
1.7 COORDINATION
A. Coordinate layout and installation of air-to-air energy recovery equipment and suspension
system with other construction that penetrates ceilings or is supported by them, including light
fixtures, HVAC equipment, fire-suppression system, and partition assemblies.
B. Coordinate sizes and locations of concrete bases with actual equipment provided.
C. Coordinate sizes and locations of roof curbs, equipment supports, and roof penetrations with
actual equipment provided.
1.8 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or
replace components of air-to-air energy recovery equipment that fail in materials or
workmanship within specified warranty period.
1. Warranty Period for Packaged Energy Recovery Units: Two (2) years.
2. Warranty Period for dx compressors: Five (5) years.
PART 2 - PRODUCTS
2.1 PACKAGED ENERGY RECOVERY UNITS
A. Manufacturers: Subject to compliance with requirements, provide products by the following:
1. Aaon
2. Annexaire
3. Greenheck
4. Munters Cargocaire.
5. SEMCO Inc.
6. Seasons 4
7. Trane
8. Temtrol
9. Valent
10. Venmar Ventilation Inc.
B. Unit shall be fully assembled at the factory and consist of an insulated metal cabinet, exhaust air
blower, evaporator coil, energy wheel, packaged DX system, phase and brownout protection,
motorized dampers, motorized recirculating damper, curb assembly, filter assembly intake air,
supply air blower assembly, exhaust/relief blower assembly, filter assembly for exhaust air, and
an electrical control center. All specified components and internal accessories factory installed
are tested and prepared for single-point high voltage connection except with electric post heat
which has dual point power.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 4
C. Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1.
D. Housing: Manufacturer's standard construction with corrosion-protection coating and exterior
finish, hinged access doors with neoprene gaskets for inspection and access to internal parts,
minimum 2-inch- thick thermal insulation, knockouts for electrical and piping connections,
exterior drain connection, and lifting lugs.
1. Inlet: Weatherproof hood, with damper for exhaust and supply.
a. Exhaust: Spring-return, two-position, motor-operated damper.
b. Supply: Spring-return, two-position, motor-operated damper.
2. Roof Curb: Refer to Section "Roof Accessories" for roof curbs and equipment supports.
E. Heat Recovery Device: Energy wheel shall be of total enthalpy, rotary air-to-air type and shall
be an element of a removable energy wheel cassette. The cassette shall consist of a galvanized
steel framework (designed to produce laminar air flow through the wheel), an energy wheel as
specified and a motor and drive assembly. The cassette shall incorporate a pre-tensioned
urethane drive belt with a five year warranty. The wheel media shall be a polymer film matrix in
a stainless steel framework and be comprised of individual segments that are removable for
servicing. Non-segmented energy wheels are not acceptable. Silica gel desiccant shall be
permanently bonded to the polymer film and is designed and constructed to permit cleaning and
servicing. The energy wheel is to have a five year warranty. Performance criteria are to be as
specified in AHRI Standard 1060, complying with the Combined Efficiency data in the
submittal.
F. Supply and Exhaust Fans: Airfoil plenum fan with isolators and insulated flexible duct
connections.
1. Motor and Drive: Direct driven. Assembly shall be mounted on heavy gauge galvanized
steel rails and further mounted on 1.125 inch thick neoprene vibration isolators. Blower
motor shall be capable of continuous speed modulation and controlled by a VFD.
2. Comply with NEMA designation, temperature rating, service factor, enclosure type, and
efficiency requirements for motors specified in Section "Common Motor Requirements
for HVAC Equipment."
3. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load
will not require motor to operate in service factor range above 1.0.
G. Filters: Unit shall have permanent metal filters located in the outdoor air intake and shall be
accessible from the exterior of the unit. MERV 8 disposable pleated filters shall be provided in
the supply air stream. MERV 8 disposable pleated filters shall be provided in the supply final
air stream and MERV 8 filters in the exhaust air stream.
1. Comply with NFPA 90A.
2. Filter Holding Frames: Arranged for flat or angular orientation, with access doors on both
sides of unit. Filters shall be removable from one side or lift out from access plenum.
3. Factory-fabricated, viscous-coated, flat-panel type.
4. Thickness: 1 inch.
5. MERV: 8, according to ASHRAE 52.2.
6. Media: Interlaced glass fibers sprayed with nonflammable adhesive.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 5
7. Frame: Galvanized steel with metal grid on outlet side, steel rod grid on inlet side,
hinged, and with pull and retaining handles.
H. Reheat Coil with factory installed modulating hot gas reheat valve.
I. Cooling Coils: Rated according to ARI 410 and ASHRAE 33, and bearing the ARI label.
1. Access: Fabricate coil section to allow removal and replacement of coil and to allow in-
place access for service and maintenance of coil(s).
2. Casing: Manufacturer's standard material.
3. Tubes: Copper.
4. Tube Headers: Manufacturer's standard material.
5. Fins: Aluminum.
6. Fin and Tube Joint: Mechanical bond.
7. Leak Test: Coils shall be leak tested with air under water.
8. Refrigerant Coils:
a. Capacity Reduction: Circuit coils for interlaced control permitting independent
operation of either compressor without conflict with the other compressor.
b. Suction and Distributor: Seamless copper tube with brazed joints.
J. Cooling-Coil Condensate Drain Pans:
1. Fabricated from stainless-steel sheet and sloped in multiple planes to collect and drain
condensate from cooling coils, coil piping connections, coil headers, and return bends.
2. Complying with requirements in ASHRAE 62.1.
3. Drain Connections: At low point of pan.
4. Units with stacked coils shall have an intermediate drain pan to collect and drain
condensate from top coil.
K. Packaged DX System: Unit shall have an integral compressor(s) and evaporator coil located
within the weather-tight unit housing. Condenser coils and appurtenant condenser fan
assemblies shall be factory installed as integral subassemblies of the unit and mounted on the
exterior of the unit. Condenser fan motors shall be three phase, type 56 frame, Open Air Over
and Shaft Up. Each condenser fan motor shall have a vented frame, rated for continuous duty
and be equipped with an automatic reset thermal protector. Motors shall be UL Recognized and
CSA Certified. The refrigerant compressor(s) shall be hermetic scroll-type and shall be
equipped with liquid line filter drier, thermostatic expansion valves (TXV)(s), manual reset
high pressure and low pressure cutouts and all appurtenant sensors, service ports and safety
devices. Compressed refrigerant system shall be fully charged with R-410A refrigerant. Each
compressor shall be factory-equipped with an electric crankcase heater to boil off liquid
refrigerant from the oil.
L. Packaged DX Control and Diagnostics: The Packaged DX system shall be controlled by an
onboard digital controller (DDC) that indicates both owner-supplied settings and fault
conditions that may occur. The DDC shall be programmed to indicate the following faults:
1. Global alarm condition (active when there is at least one alarm)
2. Supply Air Proving alarm
3. Dirty Filter Alarm
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 6
4. Compressor Trip alarm
5. Compressor Locked Out alarm
6. Supply Air Temperature Low Limit alarm
a. Sensor #1 Out of Range (outside air temperature)
b. Sensor #2 Out of Range (supply air temperature)
c. Sensor #3 Out of Range (cold coil leaving air temperature)
M. Indirect-Fired Gas Furnaces:
1. Description: Factory assembled, piped, and wired; complying with NFPA 54, "National
Fuel Gas Code," and ANSI Z21.47, "Gas-Fired Central Furnaces."
a. AGA Approval: Furnace shall bear label of AGA.
2. Burners: Stainless steel.
a. Ignition: Electronically controlled electric spark with flame sensor.
3. Heat-Exchanger Drain Pan: Stainless steel.
4. Power Vent: Integral, motorized centrifugal fan interlocked with gas valve.
5. Gas Control Valve: Electronic modulating with 12-1 turndown.
6. Gas Train: Single-body, regulated, redundant, 24-V ac gas valve assembly containing
pilot solenoid valve, pilot filter, pressure regulator, pilot shutoff, and manual shutoff.
Control devices and control sequence shall comply with requirements of FMG.
7. Access: Fabricate section to allow removal and replacement of furnace and to allow in-
place access for service.
N. Piping and Wiring: Fabricate units with space within housing for piping and electrical conduits.
Wire motors and controls so only external connections are required during installation.
1. Indoor Enclosure: NEMA 250, Type 12 enclosure contains relays, starters, and terminal
strip.
2. Outdoor Enclosure: NEMA 250, Type 3R enclosure contains relays, starters, and terminal
strip.
3. Include disconnect switches.
4. Variable-speed controller to vary fan capacity from 100 to approximately 50 percent.
O. Motorized dampers: Intake Air, Exhaust Air, Motorized dampers of low leakage type shall be
factory installed.
P. Accessories:
1. Roof Curb: Galvanized steel with gasketing, and factory-installed wood nailer;
complying with NRCA standards; minimum height of 14 inches.
2. Intake weather hood with 2-inch- thick filters.
3. Exhaust weather hood with birdscreen.
4. Hail Guards: Protects the condensing unit from damage due to extreme weather
conditions such as hail and flying debris. 5. Recirculation air Dampers.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 7
6. Duct flanges.
7. Hinged access doors with quarter-turn latches.
2.2 CONTROLS
A. The unit shall be constructed so that it can be operated as a heating and cooling system
controlled by a Building Management System (BMS).
B. Unit supply fan shall be configured for Constant Volume (ON/OFF).
C. Unit exhaust fan shall be configured for Constant Volume (ON/OFF).
D. Outside Air / Return Air damper control shall be field adjustable two-position.
E. Dirty filter sensor shall be factory installed.
F. Operating protocol: The DDC shall be factory-programmed for BACNetMSTP.
G. Variable Frequency Drive (VFD): unit shall have factory installed variable frequency drive for
modulation of the supply and exhaust air blower assemblies. The VFD shall be factory-
programmed for unit-specific requirements and shall not require additional field programming
to operate.
H. Airflow monitoring.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of the Work.
B. Examine casing insulation materials and filter media before air-to-air energy recovery
equipment installation. Reject insulation materials and filter media that are wet, moisture
damaged, or mold damaged.
C. Examine roughing-in for electrical services to verify actual locations of connections before
installation.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install heat wheels so supply and exhaust airstreams flow in opposite directions and rotation is
away from exhaust side to purge section to supply side.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 8
1. Install access doors in both supply and exhaust ducts, both upstream and downstream, for
access to wheel surfaces, drive motor, and seals.
2. Install removable panels or access doors between supply and exhaust ducts on building
side for bypass during startup.
3. Access doors and panels are specified in Section "Air Duct Accessories."
B. Roof Curb: Install on roof structure or concrete base, level and secure, according to The NRCA
"Roofing and Waterproofing Manual - Volume 4: Construction Details - Low-Slope Roofing,"
Illustration "Raised Curb Detail for Rooftop Air Handling Units and Ducts." Install air-to-air
energy recovery equipment on curbs and coordinate roof penetrations and flashing with roof
construction specified in Section "Roof Accessories." Secure air-to-air energy recovery
equipment to upper curb rail, and secure curb base to roof framing or concrete base with anchor
bolts.
C. Unit Support: Install unit level on structural curbs. Coordinate wall penetrations and flashing
with wall construction. Secure air-to-air energy recovery equipment to structural support with
anchor bolts.
D. Install gas-fired furnaces according to NFPA 54, "National Fuel Gas Code."
E. Install units with clearances for service and maintenance.
F. Install new filters at completion of equipment installation and before testing, adjusting, and
balancing.
G. Pipe drains from drain pans to nearest roof drain or gutter; use ASTM B 88, Type L, drawn-
temper copper water tubing with soldered joints, same size as condensate drain connection.
3.3 CONNECTIONS
A. Comply with requirements for piping specified in Section "Natural Gas Piping". Drawings
indicate general arrangement of piping, fittings, and specialties.
B. Install piping adjacent to unit to allow service and maintenance.
C. Connect piping to units mounted on vibration isolators with flexible connectors.
D. Connect cooling condensate drain pans with air seal trap at connection to drain pan and install
cleanouts at changes in pipe direction.
E. Refrigerant Piping: Comply with applicable requirements in Section "Refrigerant Piping."
F. Comply with requirements for ductwork specified in Section "Metal Ducts."
G. Install electrical devices furnished with units but not factory mounted.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
AIR-TO-AIR ENERGY RECOVERY EQUIPMENT (Alternate) 23 7210- 9
3.4 FIELD QUALITY CONTROL
A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test,
and adjust components, assemblies, and equipment installations, including connections.
B. Tests and Inspections:
1. Engage a factory authorized service representative to perform startup service.
a. Clean entire unit.
b. Comb coil fins as necessary.
c. Install clean filters.
d. Operational Test: After electrical circuitry has been energized, start units to
confirm proper motor rotation and unit operation.
e. Adjust seals and purge.
f. Test and adjust controls and safeties. Replace damaged and malfunctioning
controls and equipment.
g. Set initial temperature and humidity set points.
h. Set field-adjustable switches and circuit-breaker trip ranges as indicated.
2. Air-to-air energy recovery equipment will be considered defective if it does not pass tests
and inspections.
3. Prepare test and inspection reports.
3.5 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance personnel to
adjust, operate, and maintain air-to-air energy recovery units.
END OF SECTION 23 7210
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
ELECTRIC AIR COILS 23 8216.14 - 1
SECTION 23 8216.14
ELECTRIC AIR COILS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions, apply to this Section.
1.2 SUMMARY
A. Section includes electric resistance air coils.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components
and profiles, and finishes for each air coil.
2. Include rated capacities, operating characteristics, and pressure drops for each air coil.
B. Shop Drawings: Include diagrams for power, signal, and control wiring.
1.4 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Reflected ceiling plans, drawn to scale, on which coil location and
ceiling-mounted access panels are shown and coordinated with each other.
1.5 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For air coils to include in operation and maintenance
manuals.
1.6 FIELD CONDITIONS
A. Altitude above Mean Sea Level: Zero feet.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
ELECTRIC AIR COILS 23 8216.14 - 2
PART 2 - PRODUCTS
2.1 DESCRIPTION
A. ASHRAE Compliance: Comply with applicable requirements in ASHRAE 62.1, Section 5 -
"Systems and Equipment" and Section 7 - "Construction and Startup."
2.2 COILS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the
following:
1. Brasch Manufacturing Co., Inc.
2. Chromalox.
3. Dunham-Bush, Inc.
4. INDEECO.
5. Lennox Industries, Inc.
6. Markel Products Co.
7. Trane.
B. Testing Agency Listing and Labeling: Listed and labeled as defined in NFPA 70, by a qualified
testing agency, and marked for intended location and application.
C. Coil Assembly: Comply with UL 1995.
D. Heating Elements: Coiled resistance wire of 80 percent nickel and 20 percent chromium;
surrounded by compacted magnesium-oxide powder in tubular-steel sheath; with spiral-wound,
copper-plated, steel fins continuously brazed to sheath.
E. Heating Elements: Open-coil resistance wire of 80 percent nickel and 20 percent chromium,
supported and insulated by floating ceramic bushings recessed into casing openings, and
fastened to supporting brackets.
F. High-Temperature Coil Protection: Disk-type, automatically reset, thermal-cutout, safety
device; serviceable through terminal box without removing heater from duct or casing.
1. Secondary Protection: Load-carrying, manually reset or manually replaceable, thermal
cutouts; factory wired in series with each heater stage.
G. Frames: Galvanized-steel channel frame, for slip-in mounting.
H. Control Panel: Unit mounted with disconnecting means and overcurrent protection. Include the
following controls:
1. SCR Controls
2. Magnetic contactor.
3. Time-delay relay.
4. Airflow proving switch.
120-17 Emanuel County Institute
Addendum #3 HVAC Replacement
ELECTRIC AIR COILS 23 8216.14 - 3
I. See Section "Instrumentation and Control for HVAC" for thermostat.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine ducts, plenums, and casings to receive air coils for compliance with requirements for
installation tolerances and other conditions affecting coil performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install coils level and plumb.
B. Install coils in metal ducts and casings constructed according to SMACNA's "HVAC Duct
Construction Standards, Metal and Flexible."
C. Clean coils using materials and methods recommended in writing by manufacturers, and clean
inside of casings and enclosures to remove dust and debris.
3.3 CONNECTIONS
A. Ground equipment according to Section "Grounding and Bonding for Electrical Systems."
B. Connect wiring according to Section "Low-Voltage Electrical Power Conductors and Cables."
3.4 FIELD QUALITY CONTROL
A. Perform the following tests and inspections:
1. Operational Test: After electrical circuitry has been energized, operate electric coils to
confirm proper unit operation.
2. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and
equipment.
B. Prepare test and inspection reports.
END OF SECTION 23 8216.14
c105
c280
c280
c280
c280
c280
c280
230
c240
c80
c80
c185
c240
c105
c185
c2940
OHP-1B
OHP-1A
IHP-1
MEDIA CENTER
CONFERENCE
BOYS OFFICE
GIRLSMECHANICALMEDIA DISTRIBUTION
N/E
C
36X36
REPLACE EXISTING WALL MOUNTED
RETURN GRILLE. VERIFY SIZE PRIOR TO
ORDERING NEW GRILLE. PROVIDE NEW
FIRE DAMPER LABEL.
EXISTING 10 TON INDOOR
UNIT TO REMAIN UNDER
BASE BID. SEE PART PLAN IF
ALTERNATE TO REPLACE IS
ACCEPTED.
T
PPD-1
INSTALL PPD-1 IN EXISTING
RETURN AIR PLENUM OF UNIT.
12
S
H
12
NOTE: CLEAN ALL EXISTING SUPPLY AND RETURN AIR DEVICES
(WHICH ARE TO REMAIN) OF DIRT AND DUST WITH A
NON-ABRASIVE CLEANING DETERGENT.
REMOVE EXISTING LINED
40X20 SUPPLY DUCT AND
REPLACE WITH NEW 40X20
UNLINED SUPPLY DUCT AS
SHOWN.
6"Ø
N/E
REMOVE EXIST. 6"Ø SUPPLY DUCT AND
OFFSET SUPPLY DUCT AS SHOWN.
40
X2
0
N/E
EDH-1
N/E
NOTE: EDH-1 SHALL BE REPLACED UNDER
BASE BID AND ALTERNATE. IHP-1 & OHP-1 TO
BE REPLACED IF ALTERNATE IS ACCEPTED.
EXISTING 5 TON OUTDOOR
UNITS TO REMAIN UNDER BASE
BID. SEE PART PLAN IF
ALTERNATE TO REPLACE IS
ACCEPTED.
2
DATE
DRAWING NO.
SEAL
PROJECT NO. APPROVED BY:
JAMES W. BUCKLEY & ASSOCIATES INC. -- ARCHITECTS
SWAINSBORO, ALBANY, ROME, SAVANNAH AND ATHENS
EMANUEL COUNTY INSTITUTE HVAC REPLACEMENT
SWAINSBORO EMANUEL COUNTY BOARD OF EDUCATION GEORGIA
SCHOOL CODE: 653-0196
MEDIA CENTER - BASE BID
9/17/18
CABNO 13015 M1.4 / SK-M3
HVAC NEW WORK PLAN - MEDIA CENTER
SCALE: 3/32" = 1' - 0"
2
M1.4
OHP-1
IHP-1
SL
SL
CONCRETE
PAD
RACK PIPING ON
WALL. SEE DETAIL.
IF ALTERNATE IS ACCEPTED,
REMOVE EXISTING 10 TON
SPLIT HEAT PUMP SYSTEM AND
REPLACE WITH NEW 10 TON
SYSTEM AS SHOWN.
40
X2
0
EX
IS
T.
N/E
CONNECT TO EXISTING SUPPLY,
RETURN AND OUTSIDE AIR
DUCTS.
MECH
ANIC
ALGIRLS
BOYS
CONFERENCE
OFFICE
2
DATE
DRAWING NO.
SEAL
PROJECT NO. APPROVED BY:
JAMES W. BUCKLEY & ASSOCIATES INC. -- ARCHITECTS
SWAINSBORO, ALBANY, ROME, SAVANNAH AND ATHENS
EMANUEL COUNTY INSTITUTE HVAC REPLACEMENT
SWAINSBORO EMANUEL COUNTY BOARD OF EDUCATION GEORGIA
SCHOOL CODE: 653-0196
MEDIA CENTER - ALTERNATE
9/17/18
CABNO 13015 M1.4 / SK-M4
HVAC ALTERNATE - PART PLAN MEDIA CENTER
SCALE: 3/32" = 1' - 0"
3
M1.4
WHP-C9
3013
3010BOYS
3012GIRLS
3011JANITOR
3014CONF. ROOM
3015WORK ROOM
5
EX
IS
T. 2
0X
12
EX
IS
T. 1
6X
12
EXIST. 24X12
EFD
ERU-C1
8
c225
c825
c825
c290
c60
T
T
S
H
A
B
BASE BID - EXISTING ENERGY RECOVERY UNIT TO REMAIN.
REPLACE WHEEL AS NOTED ON BASE BID SCHEDULE.
PPD-12
11
F-C5
16
N/E
N/E
N/E
ALTERNATE BID - REMOVE EXISTING ROOF MOUNTED
ENERGY RECOVERY UNIT (ERU), ROOF CURB AND
ASSOCIATED SUPPLY AND RETURN DUCTWORK AS
REQUIRED. INSTALL NEW ERU AND RECONNECT TO EXISTING
DUCTWORK. PROVIDE NEW DUCTWORK WHERE REQUIRED.
VERIFY EXISTING DUCT SIZES AND ARRANGEMENT PRIOR TO
ORDERING AND INSTALLING NEW ERU.
ON ROOF
G
BASE BID - GAS PIPING SHALL
REMAIN AS SHOWN, AND NOTED
ON ORIGINAL DESIGN,
ALTERNATE - PIPING SHALL BE
LOCATED AS SHOWN, BUT FINAL
CONNECTION POINTS MUST BE
COORDINATED PRIOR TO
INSTALLATION OF ERU-C1.
1
2
"
GRAPHIC SCALE IN FEET
8' 0' 16' 24' 32'8'
NORTHKEY PLAN
c200
c350
c350 c350
c350 c350
c125
9049VESTIBULE
9050
9054JANITOR
9046
HOME MANAGEMENTCLASSROOM
EX
IS
T. 1
4"Ø
EX
IS
T. 1
6X
16
EXIST. 26X16
ES/FD
ERU-B1
EXIST. 10X10
EXIST. 12X12
EFD
ERU-A1
c260
c260
c260
EX
IS
T. 1
6X
6
EFD
c160
T
S
H
T S H
c50
N/E
c
D
10
300
c1200
1
1
1
1
1
1
EFD
T
D
SL
ON ROOF
BASE BID - EXISTING ENERGY RECOVERY UNIT TO REMAIN.
REPLACE WHEEL AS NOTED ON BASE BID SCHEDULE.
ALTERNATE BID - REMOVE EXISTING ROOF MOUNTED
ENERGY RECOVERY UNIT (ERU), ROOF CURB AND
ASSOCIATED SUPPLY AND RETURN DUCTWORK AS
REQUIRED. INSTALL NEW ERU AND RECONNECT TO EXISTING
DUCTWORK. PROVIDE NEW DUCTWORK WHERE REQUIRED.
VERIFY EXISTING DUCT SIZES AND ARRANGEMENT PRIOR TO
ORDERING AND INSTALLING NEW ERU.
N/E
N/E
ON ROOF
18X16
N/E
N/E
EXIST. 8X10
EXIST. 12X10
c125
EXIST. 10X10
10X10
N/E
18X16
1
2
"
BASE BID - GAS PIPING SHALL
REMAIN AS SHOWN, AND NOTED
ON ORIGINAL DESIGN,
ALTERNATE - PIPING SHALL BE
LOCATED AS SHOWN, BUT FINAL
CONNECTION POINTS MUST BE
COORDINATED PRIOR TO
INSTALLATION OF ERU-A1 & ERU B1.
1
2
"
G
5018CORRIDOR
5020CLASSROOM
5027CLOSET
5024CLASSROOM
5 5
EXIST. 20X14
EFD
ERU-D1
EXIST. 22X12
EFD
8 8
EFD
EFD
c175
c175
c175
c175
T S
H
TT
T
B
A
B
A
B
1
1
1
1
1
D
c685
PROVIDE NEW MVD IF
EXIST. MVD NOT
PRESENT.
18X10
22X
12
FD
EXIST.
22X12
N/E
F-D1
16
N/E
EXIST. 20X14
EXIST. 16X14
N/E
BASE BID - EXISTING ENERGY RECOVERY UNIT TO REMAIN.
REPLACE WHEEL AS NOTED ON BASE BID SCHEDULE.
ALTERNATE BID - REMOVE EXISTING ROOF MOUNTED
ENERGY RECOVERY UNIT (ERU), ROOF CURB AND
ASSOCIATED SUPPLY AND RETURN DUCTWORK AS
REQUIRED. INSTALL NEW ERU AND RECONNECT TO EXISTING
DUCTWORK. PROVIDE NEW DUCTWORK WHERE REQUIRED.
VERIFY EXISTING DUCT SIZES AND ARRANGEMENT PRIOR TO
ORDERING AND INSTALLING NEW ERU.
ON ROOF
1
G
BASE BID - GAS PIPING SHALL
REMAIN AS SHOWN, AND NOTED
ON ORIGINAL DESIGN,
ALTERNATE - PIPING SHALL BE
LOCATED AS SHOWN, BUT FINAL
CONNECTION POINTS MUST BE
COORDINATED PRIOR TO
INSTALLATION OF ERU-D1.
1
2
"
DELTA ENGINEERING GROUP, LLC
204 PITCARIN WAY SUITE A
AUGUSTA, GEORGIA 30909
706-364-1770
PROJECT NUMBER
PROJECT DATE
APPROVED BY
CHECKED BY
DRAWN BY
Copyright (c) 2008All Rights Reserved.
ISSUED FOR:NOT VALID UNLESS SIGNED
JA
ME
S W
. B
UC
KL
EY
&
A
SS
OC
IA
TE
S IN
C. -- A
RC
HIT
EC
TS
SW
AIN
SB
OR
O, A
LB
AN
Y, R
OM
E, S
AV
AN
NA
H A
ND
A
TH
EN
SG
EO
RG
IA
SHEET
NUMBER:
05/21/2018
NO 13015
CAB
CAB
BID
WA
RN
IN
G: C
on
tra
cto
rs, su
bco
ntra
cto
rs, v
en
do
rs a
nd
su
pp
lie
rs a
re
a
dv
ise
d th
at th
e co
ntra
ct d
ocu
me
nts co
nsist o
f
Arch
ite
ct-re
pro
du
ce
d p
rin
te
d, b
ou
nd
a
nd
n
um
be
re
d sp
ecifica
tio
ns, A
rch
ite
ct-re
pro
du
ce
d p
rin
te
d, b
ou
nd
a
nd
nu
mb
ere
d b
lu
e- o
r b
la
ck
-lin
e p
rin
ts, a
dd
en
da
, p
ost-b
id
a
dd
en
da
, a
nd
ch
an
ge
o
rd
ers o
nly
. D
ocu
me
nts re
pro
du
ce
d b
y
pa
rtie
s o
th
er th
an
th
e A
rch
ite
ct, w
he
th
er in
h
ard
co
py
o
r in
e
le
ctro
nic fo
rm
at, sh
all n
ot b
e co
nsid
ere
d p
art o
f th
e
co
ntra
ct d
ocu
me
nts a
nd
d
o n
ot su
pe
rse
de
th
e p
ro
visio
ns o
f th
e co
ntra
ct d
ocu
me
nts. T
he
co
ntra
cto
r, su
bco
ntra
cto
rs,
ve
nd
ors a
nd
su
pp
lie
rs a
re
so
le
ly
re
sp
on
sib
le
fo
r v
erifica
tio
n th
at in
fo
rm
atio
n u
tiliz
ed
in
b
id
din
g, d
ev
elo
pm
en
t o
f sh
op
dra
win
gs, a
nd
co
nstru
ctio
n o
f th
e fa
cility
a
re
id
en
tica
l to
th
e co
ntra
ct d
ocu
me
nts.
EM
AN
UE
L C
OU
NT
Y IN
ST
IT
UT
E H
VA
C R
EP
LA
CE
ME
NT
SW
AIN
SB
OR
OE
MA
NU
EL
C
OU
NT
Y B
OA
RD
O
F E
DU
CA
TIO
N
GE
OR
GIA
SC
HO
OL
C
OD
E: 65
3-0
19
6
M1.5
MHW
HVAC
ALT
ERNA
TES
HVAC PART PLAN - ALTERNATE FOR ERU-C1
SCALE: 1/8" = 1' - 0"
2
M1.5
A B
C
D
N.I.C.
OLDGYM
N.I.C.
N.I.C.
HVAC PART PLAN - ALTERNATE FOR ERU-A1 AND ERU-B1
SCALE: 1/8" = 1' - 0"
1
M1.5
HVAC PART PLAN -ALTERNATE FOR ERU-C1
SCALE: 1/8" = 1' - 0"
3
M1.5
OUTDOOR HEAT PUMP SCHEDULE
ITEM
OHP-1
HEATING CAP. M.B.H.
HI
(1)
HILO LO
INDOOR HEAT PUMP SCHEDULE
ITEMNOTES
DRIVE
COOLING CAP. BTUH
SENSIBLETOTAL
AUX. HEAT (2)
K.W.STGS.
(1)
ITEM
REFRIGERATION PIPE SCHEDULE
IHP/OHP-1
IHP-A3
IHP-A4
IHP-A5
IHP-A6
IHP-A7
IHP-A8
IHP-A9
OHP-A3
OHP-A4
OHP-A5
OHP-A6
OHP-A7
OHP-A8
OHP-B2
OHP-B3
OHP-B4A
3.6 2.6 TWA 120 E (3)(5)13.0119,000 88.3122.5 (2) 1 1/8"
IHP-A1 OHP-A1
OHP-B1
IHP-A2
OHP-A10
(1) REFRIGERANT PIPE SIZES INDICATED ARE FOR ESTIMATING PURPOSES ONLY.
EXACT SIZES AND ACCESSORIES REQUIRED SHALL BE DETERMINED BY EQUIPMENT
MANUFACTURER FROM FIELD OBTAINED DIMENSIONS.
(1) RATINGS IN ACCORDANCE WITH A.R.I. STANDARD 240.
(2) HEATER SIZED AT 208 VOLT. COORDINATE WITH ELECTRICAL PLANS.
(3) ELECTRICAL DATA PROVIDED IS BASED ON EQUIPMENT SELECTED AS BASIS OF DESIGN. VERIFY ELECTRICAL REQUIREMENTS WITH ELECTRICAL PLANS AND/OR CONTRACTOR BEFORE ORDERING EQUIPMENT.
NOTIFY ENGINEER IMMEDIATELY IF ANY DISCREPANCIES ARE FOUND. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF ELECTRICAL DATA IF OTHER MANUFACTURERS ARE FURNISHED.
(4) FURNISH DUAL CIRCUIT SPLIT FACE COIL.
(5) FURNISH WITH BLUE DIAMOND CONDENSATE PUMP.
(6) FURNISH PLASMA PURIFICATION DEVICE. REFER TO PLASMA PURIFICATION SCHEDULE.
(7) BALANCE ALL AIR DEVICES TO AIRFLOWS INDICATED ON PLANS.
(8) UNIT SHALL REMAIN UNDER BASE BID. REPLACE UNIT WITH MODEL INDICATED IF ALTERNATE IS ACCEPTED.
(1) RATINGS IN ACCORDANCE WITH A.R.I. STANDARD 240.
(2) ELECTRICAL DATA PROVIDED IS BASED ON EQUIPMENT SELECTED AS BASIS OF DESIGN. VERIFY ELECTRICAL REQUIREMENTS WITH ELECTRICAL PLANS
AND/OR CONTRACTOR BEFORE ORDERING EQUIPMENT. NOTIFY ENGINEER IMMEDIATELY IF ANY DISCREPANCIES ARE FOUND. CONTRACTOR SHALL BE
RESPONSIBLE FOR COORDINATION OF ELECTRICAL DATA IF OTHER MANUFACTURERS ARE PROVIDED.
(3) FURNISH UNIT WITH 2 COMPRESSORS.
(4) COOLING AND HEATING CAPACITY IS TOTAL NET CAPACITY FOR 2 UNITS.
(5) UNIT SHALL REMAIN UNDER BASE BID. REPLACE UNIT WITH MODEL INDICATED IF ALTERNATE IS ACCEPTED.
SUPPLY
C.F.M.
EXT. S.P.
(IN. W.C.)
O.A.
C.F.M.
FAN
HP.
TRANE MODEL
NO.
COOLING
CAPACITY
(1) BTUH
SEER.
MIN.
C.O.P. (1)
TRANE
MODEL NO.
SUCTION
LINE O.D. (1)
LIQUID LINE
O.D.(1)
(2) 1/2"
ELECTRICAL DATA (3)
VOLTAGE PHASE M.C.A. M.O.C.P.
ELECTRICAL DATA (2)
VOLTAGE PHASE M.C.A. M.O.C.P.
200/230 3 41 50
SIZE E.E.R.
TW-A1
AMANA MODEL NO.ITEM
THRU WALL HEAT PUMP SCHEDULE
09 9,000 12.0 8,100 360 2.5
PTH 09 (1)
COOLING
CAPACITY
BTUH
ELEC.
HEAT (KW)
(2)
FAN
C.F.M.
HEATING
CAPACITY
BTUH
PACKAGED WALL MOUNT HEAT PUMP SCHEDULE
HEATING CAP.
EXT. S.P.
ITEM
SUPPLY
C.F.M. W.C. C.F.M.
O.A.
BTUH (1)
COOLING CAP.
MIN.
E.E.R.
HI STAGESLOLO
(1)
HI
C.O.P.
K.W.
AUX. HEAT(1)
BARD
MODEL NO.
0.3600 60 10.217,100
4
W18H (3)(4)3.110.216.5 1.9 1
(1) RATINGS IN ACCORDANCE WITH A.R.I. STANDARD 240.
(2) ELECTRICAL DATA PROVIDED IS BASED ON EQUIPMENT SELECTED AS BASIS OF DESIGN. VERIFY ELECTRICAL REQUIREMENTS WITH ELECTRICAL PLANS AND/OR CONTRACTOR BEFORE ORDERING
EQUIPMENT. NOTIFY ENGINEER IMMEDIATELY IF ANY DISCREPANCIES ARE FOUND. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF ELECTRICAL DATA IF OTHER MANUFACTURERS ARE
PROVIDED.
(3) UNITS SHALL HAVE INTEGRAL DISCONNECTS AND HOT GAS REHEAT DEHUMIDIFICATION SYSTEM. PROVIDE GASKETS FOR UNIT TO WALL SEAL SHIPPED
LOOSE FOR FIELD INSTALLATION.
(4) FURNISH MOTORIZED FRESH AIR DAMPER.
IHP-A10
IHP-B3
IHP-B4
IHP-B1
IHP-B2
MODEL NUMBER
TITUS
TYPE FINISH NOTESMARK
AIR DEVICE SCHEDULE
SIZE (1)
NECK
DAMPER
OPPOSED BLADE
(1) DUCT RUNOUT SHALL BE SAME SIZE AS NECK SIZE UNLESS NOTED OTHERWISE.
(2) BLADES 14 GAUGE, FRAME 16 GAUGE HEAVY STEEL.
(3) VERIFY EXISTING CEILING TYPE. PROVIDE LAY-IN TYPE GRILLE FOR T-BAR AND SURFACE TYPE GRILLE FOR ALL OTHER CEILINGS.
IHP-1 (4)(6)(7)(8)4000 23000.5 124,00087,600BELT - - TWE 120 E 208 3 9 15
ELECT. DATA (2)
VOLTS PHASE
208/230 1
6000 8000.5
--3000 7000.5
(7)1400 -2000.5 --DIRECT - - EXISTING TO REMAIN- - - -
(6)(7)1600 -1950.5 --DIRECT - - EXISTING TO REMAIN- - - -
(6)(7)3000 -1950.5 --BELT - - EXISTING TO REMAIN- - - -
(4)3000 1 1/23200.5 93,00072,900BELT 11.24 1 TWE 090E208 3 45.7 50
--1000 1350.5 DIRECT
0.5
-- DIRECT
(7)1400 --0.5 --DIRECT - - EXISTING TO REMAIN- - - -
(7)2000 -1000.5 --DIRECT - - EXISTING TO REMAIN- - - -
(7)4000 -2400.5 --DIRECT - - EXISTING TO REMAIN- - - -
- - EXISTING TO REMAIN-- --
- - - -
- - EXISTING TO REMAIN-- --
- - - -
- - EXISTING TO REMAIN-- --
- - - -
3.3 2.3
TWA090E
11.0 EER93,000 49.082.0
208/230 3 34.4 45
- - EXISTING TO REMAIN-- --
- - - -
- - EXISTING TO REMAIN-- --
- - - -
- - EXISTING TO REMAIN-- --
- - - -
IHP-A1/OHP-A1
IHP-A2/OHP-A2A & A2B - -
IHP-A3/OHP-A3 1 3/8" 5/8"
IHP-A4/OHP-A4 - -
IHP-A5/OHP-A5 - -
IHP-A6/OHP-A6 - -
IHP-A7/OHP-A7 1 3/8" 5/8"
IHP-A8/OHP-A8 3/4" 3/8"
IHP-A9/OHP-A9A & A9B
IHP-A10/OHP-A10
IHP-B1/OHP-B1 - -
IHP-B2/OHP-B2 3/4" 3/8"
IHP-B3/OHP-B3 - -
IHP-B4/OHP-B4 - -
TW-D1
09 9,000 12.0 8,100 360 2.5
PTH 09 (1)
0.3 0
9
W30H (3)1
WHP-C1 THRU
WHP-C9 & C11
208/230 3
WHP-A1
0.31100 100 10.034,600
9
W36H (3)(4)3.019.632.0 2.0 1208/230 3
WHP-A2 0.41000 100 10.030,000
9
W30H (3)(4)3.118.929.8 2.18 1208/230 3
WHP-A3
IHP-B5
IHP-C1
OHP-B5 IHP-B5/OHP-B5 1/2" 1/4"
OHP-C1 IHP-C1/OHP-C1 1/2" 1/4"
0.3 0
9
W30H (3)1
WHP-D1 THRU
WHP-D8
208/230 3
0.31100 0 10.234,600
9
W36H (3)3.019.632.0 2.0 1WHP-D9 & D10
208/230 3
0.3 0
9
W30H (3)1
WHP-D11 THRU
WHP-D17
208/230 3
ENERGY RECOVERY UNIT SCHEDULE - BASE BID
ITEM
5 1,300
NOMINAL
TONS
SUPPLY
ERU-A1 1,200
ERU
CFM CFM
1,300
SEMCO MODEL
NUMBER
7.5 2,000ERU-B1 1,9002,000
7.5 2,250ERU-C1 2,0002,250
7.5 3,050ERU-D1 2,5003,050
A
SIDE WALL
SUPPLY REGISTERSTANDARD WHITE
MANUFACTURERS
YES
SEE PLANS
WITH 3/4" BLADE SPACING
300RS - DOUBLE DEFLECTION
B
SIDE WALL
RETURN GRILLE
SEE PLANS
STANDARD WHITE
MANUFACTURERS
NO
WITH 1/2" BLADE SPACING
355RL - 35° DEFLECTION
C
HEAVY DUTY
RETURN GRILLE
SEE PLANS
STANDARD WHITE
MANUFACTURERS
NO
WITH 1/2" BLADE SPACING
33RL - 38° DEFLECTION
(2)
--1601600 0.5 1/2 DIRECT 34,100 48,000 7.2 1 TAM4AO 48208 1 47 50 4TWA304848,000 13.0 46.5 31.8 3.4 2.4
208/230 3 21 35
7/8" 3/8"
(7)
EXISTING TO REMAIN- -- BELT -- -- -- -- --
- - - - - - EXISTING TO REMAIN
- - - -
OHP-A2A
& A2B
11.24 1 TWE090E72,900 93,0001 1/2 BELT (4)208 3 45.7 50
TWA090E
3.3 2.349.082.011.0 EER93,000
208/230 3 34.4 45
13.630,00021,6001/3 TAM4AO 30208 1 24 25 2.33.216.528.813.030,000
4TWA3030208/230 3 11 15
3800
TWE120E
BELT2 124,00087,600 218.72(4)200 208 3 73.0 80
OHP-A9A
& A9B
13.0
4TWA3060 (4)119,000 122.5 88.3
3.6 2.6
208/230 3 20 35
7/8" 3/8"
MSZ GL09NA
15
MITSUBISHI
----9,0007,300DIRECT
0.76
--170
FLA
11208/230
MITSUBISHI
MUZ-GL09NA
3.34.446.710.924.69,000
208/230 1 9 15
3/8" 1/4"
--7.2 131,5001/2 DIRECT 41,5002000.51400 TAM4AO 42208 1 47 50 4TWA304241,500 13.0 40.5 26.6 2.43.4
200/230 3 18 30
PKA-A18
(5)
MITSUBISHI
----18,00012,240DIRECT
0.33
----425
FLA
208/230 1 1 15
PKA-A18
--
MITSUBISHI
----18,00012,240DIRECT
0.33
----425
FLA
208/230 1 1 15
18,000 15.3 19.0 13.0 2.83 9.5 HSPF
MITSUBISHI
PUZ-A18
208/230 1 13 15
18,000 15.3 19.0 13.0 2.83 9.5 HSPF
MITSUBISHI
PUZ-A18
208/230 1 13 15
& B4B
(1) SET OUTSIDE AIR TO 15 CFM.
(2) HEATER SIZED AT 208 VOLTS.
(1) VERIFY VOLTAGE REQUIREMENT WITH IHP/WHP ELECTRICAL REQUIREMENTS.
(2) IHP-C10 SHALL BE 1240 CFM.
ITEM
PLASMA PURIFICATION DEVICE SCHEDULE
GLOBAL PLASMA SOLUTIONS
MODEL NO.
PPD-2 IHP-A5
1600
UNIT
SERVED
TREATED
AIRFLOW
(CFM)
GPS-FC-3-BAS12
POWER
(VA)
INPUT
VOLTAGE (1)
24 VAC
PPD-3 IHP-A6
3000
GPS-FC-3-BAS1224 VAC
PPD-1 IHP-1
4000
GPS-FC48-AC10 WATTS24 VAC
WHP-C1 THRU
WHP-C11
WHP-D1 THRU
WHP-D8
WHP-D9 & D10
WHP-D11 THRU
WHP-D17
PPD-4 THRU
PPD-14
PPD-15 THRU
PPD-22
PPD-23 & PPD-24
PPD-25 THRU
PPD-31
1100 (2)
1100
1100
1100
6
D
8
D
SQUARE
CEILING DIFFUSER
MANUFACTURERS
STANDARD WHITE
YES TMS / 24"X24" FACE (3)
(3)
6"Ø
SQUARE
CEILING DIFFUSER
MANUFACTURERS
STANDARD WHITE
YES8"Ø
TMS / 24"X24" FACE
SERVES
RTU-A1
RTU-B1
RTU-C1
RTU-D1
RTU CFM
RETURN
1,200
(1) EXISTING RTU AND ERU UNITS TO REMAIN. BALANCE AIRFLOWS TO CFM'S AS LISTED. FURNISH REPLACEMENT WHEEL IN EXISTING ERU'S.
(2) WHEEL ENTERING AIR CONDITIONS TO BE 95 °F DB/78°F WB IN SUMMER AND 23 °F DB/17 °F WB WINTER.
RETURN AIR TEMPS SHALL BE 75 °F DB/62 °F WB SUMMER AND 72°F DB/57°F WB WINTER.
FVTS200H-4RN4AB (1)
SP2200T-4RN4AA (1)
SP2200T-4RN4AA (1)
FV-3000
1,900
2,000
10
D
(3)
SQUARE
CEILING DIFFUSER
MANUFACTURERS
STANDARD WHITE
YES10"Ø TMS / 24"X24" FACE
ERU LVG AIR TEMPS
DB/WB °F (2)
SUMMER
81.5/67.8
WINTER
56.1/46.6
MAX PD. MAX PD.
--
80.9/67.3 57.6/48.2--
IHP-D1
PKA-A18
--
MITSUBISHI
----18,00012,240DIRECT
0.33
----425
FLA
208/230 1 1 15
OHP-C2 18,000 24.6 19.0 11.0 4.28 2.47
MITSUBISHI
PUZ-A18
208/230 1 11 28
IHP-D1/OHP-D1 1/2" 1/4"
EXIST. TO REMAIN
EXIST. TO REMAIN
EXIST. TO REMAIN
2,500 81.8/68.1 55.4/46.1.50 .25
HP
OUTSIDE AIR EXHAUST AIR
HP
3 1.5
1100 10.030,000 3.118.929.8 2.18
1100 10.030,000 3.118.029.8 2.18
1100 10.030,000 3.118.029.8 2.18
-- - -
- -
- -
82.0/68.2 54.9/45.7
GPS-FC-3-BAS
GPS-FC-3-BAS
GPS-FC-3-BAS
GPS-FC-3-BAS
1224 VAC
1224 VAC
1224 VAC
1224 VAC
(1) FURNISH BACKDRAFT DAMPER, ROOF CURB ADAPTER (IF REQUIRED), INSECT SCREEN, AND DISCONNECT MEANS.
(2) SWITCH WITH ROOM LIGHTS. FURNISH AUXILIARY CONTACTS AS REQUIRED.
(3) CONTROL WITH THERMOSTAT. SET AT 85°F (ADJUSTABLE).
(4) CONTROL WITH WALL SWITCH.
(5) SHALL BE NSF LISTED. CONNECT TO JAMB MOUNTED DOOR SWITCH. LOCATE ON HINGE SIDE OF EXTERIOR DOOR.
(6) COORDINATE ELECTRICAL REQUIREMENTS WITH ELECTRICAL PLANS & CONTRACTOR BEFORE ORDERING EQUIPMENT. NOTIFY
ENGINEER IMMEDIATELY IF DISCREPANCIES FOUND.
F-A6 RECEIVING 9028 (5)1440 - 1750 - MARS 48 STD
1/2
SONESLOCATION R.P.M.H.P. NOTESC.F.M.ITEM
FAN SCHEDULE
ELECTRICAL DATA (6)
VOLTS PHASE
115 1Ø
S.P.
(IN. WC)
GREENHECK
MODEL NO.
F-A1 TOILET 9011 (1)(2)90 .25 1550 3.6 G-060-D
1/60
115 1Ø
F-A2 TOILET 9015 (1)(2)90 .25 1550 3.6 G-060-D
1/60
115 1Ø
F-A3 TOILET 9020 (1)(2)90 .25 1550 3.6 G-060-D
1/60
115 1Ø
F-A4 BATHROOM 9033 (1)(2)90 .25 1550 3.6 G-060-D
1/60
115 1Ø
F-A5 DISHWASH 9029 (1)(4)1300 .25 1140 9.3 G-133-B
1/6
115 1Ø
F-A7 9042
EXISTING
1550 - - - CARMON
-
- -
F-A8 HOME EC. 9045 (1)(4)1300 .25 1140 9.3 G-133-B
1/6
115 1Ø
F-B1 KILN 9070 (1)(3)500 .25 1300 6.4 G-095-G
1/12
115 1Ø
F-B2 ART 9067 (1)(4)1300 .25 1140 9.3 G-133-B
1/6
115 1Ø
F-C1 STAFF TOILET 3009 (1)(2)115 .25 1300 2.8 G-070-G
1/60
115 1Ø
F-C2 DARK ROOM 3022 (1)(4)115 .25 1300 2.8 G-070-G
1/60
115 1Ø
F-C3 SCIENCE 3006 (1)(4)785 .25 1550 8.7 G-095-D
1/8
115 1Ø
F-C4 SCIENCE 3005 (1)(4)1215 .25 1140 9.2 G-133-B
1/6
115 1Ø
F-C5 SCIENCE (1)(4)1215 .25 1140 9.2 G-133-B
1/6
115 1Ø
F-D1 CLASSROOM 5020 (1)(4)1030 .25 1140 8.3 G-123-B
1/6
115 1Ø
F-D2 SCIENCE 5026 (1)(4)1030 .25 1140 8.3 G-123-B
1/6
115 1Ø
F-D3 SCIENCE 5028 (1)(4)1030 .25 1140 8.3 G-123-B
1/6
115 1Ø
6
E SQUARE
CEILING DIFFUSER
MANUFACTURERS
STANDARD WHITE
YES TMS / 12"X12" FACE (3)6"Ø
IHP-C2
PLA-A18
--
MITSUBISHI
----18,00015,300DIRECT
.51
----570
FLA
208/230 1 1 15
1
OHP-D1 18,000 15.3 19.0 13.0 2.83 9.5 HSPF
MITSUBISHI
PUZ-A18
208/230
1/4"
13 15
IHP-C2/OHP-C2 1/2"
IHP-G1 0.57600
TWE240E
BELT5 255,000181,400 222.44 (4)0 208 3 97.0 100 10.0 EER
TWA240E (3)255,100 236.0 134.0
3.2 2.0
208/230 3 86.0 100
OHP-G1
IHP-G1/OHP-G1 2 - 1 3/8" 2 - 5/8"
TO REMAIN
F
EGG CRATE
RETURN / EXHAUST
22"X22"
STANDARD WHITE
MANUFACTURERS
NO
(2)
WITH BORDER FRAME
50 / 24X24 PANEL
IHP-B6 -- DIRECT
SLZ-KA15
15
MITSUBISHI
----15,00010,050DIRECT
0.28
--390
FLA
11208/230 OHP-B6
MITSUBISHI
SUZ-KA15
1.992.7110.218.016.015,000
208/230 1 12 15(5)
IHP-B6/OHP-B6 1/2" 1/4"
0.51240 0 10.240,500
9
W42H (3)3.1022.2638.5 2.03 1208/230 3WHP-C10
ENERGY RECOVERY UNIT SCHEDULE - ALTERNATE
ITEM
1300 1.0
C.F.M.
TO
SPACE
EXT. S.P.
(IN W.C.)
ERU-A1 1
FAN HP
SUPPLY
1200 1.0
C.F.M.
FROM
SPACE
EXT. S.P.
(IN W.C.)
1
FAN HP
EXHAUST
100 RVE-40-30P-30H
GREENHECK
MODEL NO. (1)
GAS HEAT
INPUT
(MBH)
65.7
COOLING COIL
TOTAL
CAPACITY
MBTU/HR
78.0
WB
95.0
DB
46.357.119.023.068.481.2
ENTHALPY WHEEL (2)
WBDB DB WB DB WB
SUMMER
ENT. AIR
SUMMER
LVG. AIR
WINTER
ENT. AIR
WINTER
LVG. AIR
(1) ENERGY RECOVERY UNITS TO BE PACKAGED SYSTEM WITH INTEGRAL CONTROL SYSTEM. FURNISH CONTROLS COMPATIBLE WITH BUILDING MANAGEMENT SYSTEM OR STAND ALONE CONTROLS AS REQUIRED
PER ALTERNATE.
(2) BASED ON 75°F DB/50%RH RETURN AIR (SUMMER) AND 72°F RETURN AIR (WINTER)
EX
HA
US
T A
IR
OUTDOOR AIR
RELIEF/RETURN AIR
SUPPLY AIR
GAS HEAT
SUPPLY FAN
ENTHALPY WHEEL
EXHAUST FAN
FILTERS
FILTERS
ERU-B1
ERU-C1
ERU-D1
41.5
SENS
CAPACITY
MBTU/HR
40.3
HG REHEAT
CAPACITY
MBTU/HR
CONTROL SECTION
CONDENSING
SECTION
HOT GAS
REHEAT COIL
DX COOLING
COIL
2000 1.0 1 1/2 1900 1.0 1 1/2100 RVE-40-36P-15H
102.1 78.095.0 46.157.319.023.068.681.263.4 88.9
2250 1.0 2 2000 1.0 1 1/2
150 RVE-40-36P-30H
104.4 78.095.0 45.155.419.023.068.981.967.7 61.9
3050 1.0 3 2500 1.0 3200 RVE-40-36P-30H
131.6 78.095.0 42.451.419.023.070.183.586.2 73.1
(1) PROVIDE WITH PROVING SWITCH. REFER TO SPECIFICATIONS FOR SEQUENCE OF OPERATION.
EDH-1 40X20 INDEECO
25
SIZE KWITEM
ELECTRIC DUCT HEATER SCHEDULE
MANUFURER &
MODEL NO.
SCR
STAGES
2
2 2
2
2
2
2
DELTA ENGINEERING GROUP, LLC
204 PITCARIN WAY SUITE A
AUGUSTA, GEORGIA 30909
706-364-1770
PROJECT NUMBER
PROJECT DATE
APPROVED BY
CHECKED BY
DRAWN BY
Copyright (c) 2008All Rights Reserved.
ISSUED FOR:NOT VALID UNLESS SIGNED
JA
ME
S W
. B
UC
KL
EY
&
A
SS
OC
IA
TE
S IN
C. -- A
RC
HIT
EC
TS
SW
AIN
SB
OR
O, A
LB
AN
Y, R
OM
E, S
AV
AN
NA
H A
ND
A
TH
EN
SG
EO
RG
IA
SHEET
NUMBER:
05/21/2018
NO 13015
CAB
CAB
BID
WA
RN
IN
G: C
on
tra
cto
rs, su
bco
ntra
cto
rs, v
en
do
rs a
nd
su
pp
lie
rs a
re
a
dv
ise
d th
at th
e co
ntra
ct d
ocu
me
nts co
nsist o
f
Arch
ite
ct-re
pro
du
ce
d p
rin
te
d, b
ou
nd
a
nd
n
um
be
re
d sp
ecifica
tio
ns, A
rch
ite
ct-re
pro
du
ce
d p
rin
te
d, b
ou
nd
a
nd
nu
mb
ere
d b
lu
e- o
r b
la
ck
-lin
e p
rin
ts, a
dd
en
da
, p
ost-b
id
a
dd
en
da
, a
nd
ch
an
ge
o
rd
ers o
nly
. D
ocu
me
nts re
pro
du
ce
d b
y
pa
rtie
s o
th
er th
an
th
e A
rch
ite
ct, w
he
th
er in
h
ard
co
py
o
r in
e
le
ctro
nic fo
rm
at, sh
all n
ot b
e co
nsid
ere
d p
art o
f th
e
co
ntra
ct d
ocu
me
nts a
nd
d
o n
ot su
pe
rse
de
th
e p
ro
visio
ns o
f th
e co
ntra
ct d
ocu
me
nts. T
he
co
ntra
cto
r, su
bco
ntra
cto
rs,
ve
nd
ors a
nd
su
pp
lie
rs a
re
so
le
ly
re
sp
on
sib
le
fo
r v
erifica
tio
n th
at in
fo
rm
atio
n u
tiliz
ed
in
b
id
din
g, d
ev
elo
pm
en
t o
f sh
op
dra
win
gs, a
nd
co
nstru
ctio
n o
f th
e fa
cility
a
re
id
en
tica
l to
th
e co
ntra
ct d
ocu
me
nts.
EM
AN
UE
L C
OU
NT
Y IN
ST
IT
UT
E H
VA
C R
EP
LA
CE
ME
NT
SW
AIN
SB
OR
OE
MA
NU
EL
C
OU
NT
Y B
OA
RD
O
F E
DU
CA
TIO
N
GE
OR
GIA
SC
HO
OL
C
OD
E: 65
3-0
19
6
M3.0
MHW
HVAC
SCH
EDUL
ES
POINT NAME
DDC SYSTEM POINTS LIST - WALL MOUNTED HEAT PUMP
HARDWARE POINTS
ANALOG
INPUT
SHOWN ON
GRAPHIC
SOFTWARE POINTS
PID
LOOP
SCHEDULE TREND ALARM
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
XXROOM TEMP
ROOM OFFSET
X
XX
ROOM HUMIDITYXX
COMPRESSORX
REVERSING VALVE (HEAT/COOL)X
XAUXILIARY HEAT
XSUPPLY FAN
X
POINT NAME
DDC SYSTEM POINTS LIST - SPLIT SYSTEM HEAT PUMPS
HARDWARE POINTS
X
SHOWN ON
GRAPHIC
SOFTWARE POINTS
SCHEDULE
X
TREND ALARM
ZONE TEMP
XXZONE SETPOINT ADJUST
XXZONE OVERRIDE
X
XXSMOKE DETECTOR (1)
X X
XXFAN STATUS
X
XXFAN START/STOP
X
XXREVERSING VALVE
X
XXCOMPRESSOR STAGE 1
X
SCHEDULEX
HEATING SETPOINTXX
COOLING SETPOINTXX
HIGH ZONE TEMPX
LOW ZONE TEMPX
COMPRESSOR RUNTIME EXCEEDX
FAN FAILUREX
FAN IN HANDX
FAN RUNTIME EXCEEDEDX
(1) WHERE REQUIRED
XXCOMPRESSOR STAGE 2 (1)
X
ELECTRIC HEATX XX
OA/ RETURN AIR DAMPERS (1)X X X
ANALOG
INPUT
PID
LOOP
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
X
POINT NAME
DDC SYSTEM POINTS LIST - MISC POINTS
HARDWARE POINTS
X
SHOWN ON
GRAPHIC
SOFTWARE POINTS
SCHEDULE
X
TREND ALARM
OUTSIDE AIR TEMPERATURE
XXOUTSIDE AIR HUMIDITY
X
ANALOG
INPUT
PID
LOOP
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
X
POINT NAME
DDC SYSTEM POINTS LIST - DUCTLESS SPLIT SYSTEMS
HARDWARE POINTS
X
SHOWN ON
GRAPHIC
SOFTWARE POINTS
SCHEDULE TREND ALARM
SPACE TEMP (1)
HIGH SPACE TEMPX
(1) TEMPERATURE IS FOR INFORMATION ONLY. CONTROL OF UNIT SHALL BE THRU UNIT FURNISHED CONTROLS.
ANALOG
INPUT
PID
LOOP
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
X
POINT NAME
DDC SYSTEM POINTS LIST - THRU THE WALL UNITS
HARDWARE POINTS
X
SHOWN ON
GRAPHIC
SOFTWARE POINTS
SCHEDULE TREND ALARM
SPACE TEMP (1)
HIGH SPACE TEMPX
(1) TEMPERATURE IS FOR INFORMATION ONLY. CONTROL OF UNIT SHALL BE THRU UNIT FURNISHED CONTROLS.
ANALOG
INPUT
PID
LOOP
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
POINT NAME
DDC SYSTEM POINTS LIST - ENERGY RECOVERY UNIT
HARDWARE POINTS
ANALOG
INPUT
SHOWN ON
GRAPHIC
SOFTWARE POINTS
PID
LOOP
SCHEDULE TREND ALARM
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
OA INTAKE DAMPERSX X
X
OA INTAKE FILTERX X
X
SUPPLY TEMP BEFORE WHEELX
X
ENTHALPY WHEELX
X
X
SUPPLY TEMP AFTER WHEELX
X
XXCOMPRESSOR (EACH STAGE)
XXSUPPLY FAN
XX X
SUPPLY TEMPX
X
X
RELIEF FILTERX X
X
RELIEF TEMP BEFORE WHEELX
X
XXRELIEF FAN
XX X
RELIEF DAMPERSX X
X
RECIRCULATION DAMPERSX X
X
SPACE HUMIDITY MONITORX X
SPACE TEMPERATURE MONITORX X
XXSMOKE DETECTOR
X X
X
SCHEDULE X X
HEATING SETPOINTXX
COOLING SETPOINTXX
HIGH ZONE TEMPX
LOW ZONE TEMPX
COMPRESSOR RUNTIME EXCEEDX
FAN FAILUREX
FAN IN HANDX
FAN RUNTIME EXCEEDEDX
HIGH MIXED AIR TEMPX
LOW MIXED AIR TEMPX
XXGAS HEATING
ENERGY RECOVERY UNIT AIRFLOW SCHEMATIC
SCALE: NONEM3.1
1
O.A. DAMPER
SMOKE DETECTOR.
SM
SUPPLY FAN
O.A.
INTAKE
SUPPLY
AIR
AIR-COOLED
CONDENSER
GAS PREHEAT
COIL
SPACE TEMP,
HUMIDITY
MONITORING
FILTER GAGE AND
D.P. SWITCH
RELIEF
DAMPER
EXHAUST
RELIEF
EXHAUST
AIR
EXHAUST PREFILTER
WITH FILTER GAGE AND
D.P. SENSOR
MD
MD
TEMP. SENSOR
(TYP.)
M
EXHAUST
FAN
ENTHALPY
WHEEL
EVAPORATOR
COIL
HOT GAS
REHEAT
COIL
PRE
FILTER
MD
RECIRCULATION
DAMPER
POINT NAME
DDC SYSTEM POINTS LIST - ENERGY RECOVERY UNIT
HARDWARE POINTS
ANALOG
INPUT
SHOWN ON
GRAPHIC
SOFTWARE POINTS
PID
LOOP
SCHEDULE TREND ALARM
ANALOG
OUTPUT
BINARY
INPUT
BINARY
OUTPUT
ANALOG
VALUE
BINARY
VALUE
OA INTAKE DAMPERSX X
X
OA INTAKE FILTERX X
X
SUPPLY TEMP BEFORE WHEELX
X
ENTHALPY WHEELX
X
X
SUPPLY TEMP AFTER WHEELX
X
XXCONDENSER (EACH STAGE)
SUPPLY TEMP AFTER COILSX
X
GAS HEATX
X
XXSUPPLY FAN
XX X
SUPPLY TEMPX
X
X
RELIEF FILTERX X
X
RELIEF TEMP BEFORE WHEELX
X
XXRELIEF FAN
XX X
RELIEF DAMPERSX X
X
RECIRCULATION DAMPERSX X
X
SPACE HUMIDITY MONITORX X
SPACE TEMPERATURE MONITORX X
XXSMOKE DETECTOR
X X
X
X
SCHEDULE X X
NOTE: IF DDC CONTROLS ALTERNATE IS ACCEPTED AND ENERGY
RECOVERY UNIT ALTERNATE IS ACCEPTED FURNISH CONTROLS PER THIS
POINTS LIST AND AIRFLOW SCHEMATIC
X
1
X
1
XZONE HUMIDITY (2)
(2) MEDIA CENTER
1
X
2
DELTA ENGINEERING GROUP, LLC
204 PITCARIN WAY SUITE A
AUGUSTA, GEORGIA 30909
706-364-1770
PROJECT NUMBER
PROJECT DATE
APPROVED BY
CHECKED BY
DRAWN BY
Copyright (c) 2008All Rights Reserved.
ISSUED FOR:NOT VALID UNLESS SIGNED
JA
ME
S W
. B
UC
KL
EY
&
A
SS
OC
IA
TE
S IN
C. -- A
RC
HIT
EC
TS
SW
AIN
SB
OR
O, A
LB
AN
Y, R
OM
E, S
AV
AN
NA
H A
ND
A
TH
EN
SG
EO
RG
IA
SHEET
NUMBER:
05/21/2018
NO 13015
CAB
CAB
BID
WA
RN
IN
G: C
on
tra
cto
rs, su
bco
ntra
cto
rs, v
en
do
rs a
nd
su
pp
lie
rs a
re
a
dv
ise
d th
at th
e co
ntra
ct d
ocu
me
nts co
nsist o
f
Arch
ite
ct-re
pro
du
ce
d p
rin
te
d, b
ou
nd
a
nd
n
um
be
re
d sp
ecifica
tio
ns, A
rch
ite
ct-re
pro
du
ce
d p
rin
te
d, b
ou
nd
a
nd
nu
mb
ere
d b
lu
e- o
r b
la
ck
-lin
e p
rin
ts, a
dd
en
da
, p
ost-b
id
a
dd
en
da
, a
nd
ch
an
ge
o
rd
ers o
nly
. D
ocu
me
nts re
pro
du
ce
d b
y
pa
rtie
s o
th
er th
an
th
e A
rch
ite
ct, w
he
th
er in
h
ard
co
py
o
r in
e
le
ctro
nic fo
rm
at, sh
all n
ot b
e co
nsid
ere
d p
art o
f th
e
co
ntra
ct d
ocu
me
nts a
nd
d
o n
ot su
pe
rse
de
th
e p
ro
visio
ns o
f th
e co
ntra
ct d
ocu
me
nts. T
he
co
ntra
cto
r, su
bco
ntra
cto
rs,
ve
nd
ors a
nd
su
pp
lie
rs a
re
so
le
ly
re
sp
on
sib
le
fo
r v
erifica
tio
n th
at in
fo
rm
atio
n u
tiliz
ed
in
b
id
din
g, d
ev
elo
pm
en
t o
f sh
op
dra
win
gs, a
nd
co
nstru
ctio
n o
f th
e fa
cility
a
re
id
en
tica
l to
th
e co
ntra
ct d
ocu
me
nts.
EM
AN
UE
L C
OU
NT
Y IN
ST
IT
UT
E H
VA
C R
EP
LA
CE
ME
NT
SW
AIN
SB
OR
OE
MA
NU
EL
C
OU
NT
Y B
OA
RD
O
F E
DU
CA
TIO
N
GE
OR
GIA
SC
HO
OL
C
OD
E: 65
3-0
19
6
M3.1
MHW
HVAC
POI
NTS
LISTS