  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    1/34

    New York State Pavilion

    Flushing Meadows Corona Park

    Pre-Scoping Study

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    2/34

    New York State Pavilion

    Pre-Scoping Study For

    Goals

    Determine overall condition of

    the observation towers

    Sample foundation conditions

    beneath the Towers and Tent

    Structures

    Provide schematic

    recommendations and cost

    estimates for stabilization and

    restoration of the Pavilion

    Towers

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    3/34

    New York State Pavilion

    Pre-Scoping Study For

    Site Plan

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    4/34

    New York State Pavilion

    Pre-Scoping Study For

    Roof Structure

    Overall in Good Condition

    Missing Roof

    Lead Based Paint and EpoxyFloor Coating is Hazardous

    PCB Material

    Peeling Paint, Surface Rust

    with Pitting of Steel

    Adequate Structural Capacity

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    5/34

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    6/34

    New York State Pavilion

    Pre-Scoping Study For

    Metal Deck

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    7/34

    New York State Pavilion

    Pre-Scoping Study For

    Concrete Towers

    Isolated Cracks and Spalls

    Areas where reinforcing is too

    close to exterior

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    8/34

    New York State Pavilion

    Pre-Scoping Study For

    Typical Tower Wall

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    9/34

    New York State Pavilion

    Pre-Scoping Study For

    Tower Steel Piles

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    10/34

    New York State Pavilion

    Pre-Scoping Study For

    Tower Stairs

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    11/34

    New York State Pavilion

    Pre-Scoping Study For

    Basement

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    12/34

    New York State Pavilion

    Pre-Scoping Study For

    Stabilization Plan

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    13/34

    New York State Pavilion

    Pre-Scoping Study For

    Abate, Clean and Paint Steel

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    14/34

    New York State Pavilion

    Pre-Scoping Study For

    Add Roof to Each Tower

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    15/34

    New York State Pavilion

    Pre-Scoping Study For

    Structural Repairs

    Reinforce perimeter floor

    channel

    Inspect, restore or replace

    cable hangers

    Replace corroded bolts

    Reattach Elevator Rails

    Seal cracks and patch spalls

    in tower walls and plaza piers

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    16/34

    New York State Pavilion

    Pre-Scoping Study For

    Replace Stairs

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    17/34

    New York State Pavilion

    Pre-Scoping Study For

    Waterproof all Observation Levels

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    18/34

    New York State Pavilion

    Pre-Scoping Study For

    Restore Drainage System in Basement

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    19/34

    New York State Pavilion

    Pre-Scoping Study For

    Safe & Code Compliant Electric Service

    New Panelboards

    Facility Grounding

    Permanent FAA Service Lightening Protection

    Back-up Power

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    20/34

    New York State Pavilion

    Pre-Scoping Study For

    Basic Utility Upgrades

    Landscape & Special Lighting

    Security Lighting Intrusion Alarm Control

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    21/34

    New York State Pavilion

    Pre-Scoping Study For

    Cost EstimateStabilization

    Priced as prevailing wage / project labor

    Based on normal working hours

    Markups include: Design Contingency, General

    Conditions, Overhead & Profit and Design Fee

    Escalation is not included.

    TOTAL COST: $11,434,803

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    22/34

    New York State Pavilion

    Pre-Scoping Study For

    Restoration Plan

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    23/34

    New York State Pavilion

    Pre-Scoping Study For

    Architectural

    Replace Level 1 partitions including storefront type walls

    around perimeter and around elevator shafts.

    Replace plaster soffit under observation levels

    Restore and replace 2 elevator sky cabs including elevator

    equipment.

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    24/34

    New York State Pavilion

    Pre-Scoping Study For

    Utilities

    Replace domestic water piping heating and fixtures serving

    Level 1 and including underground lines.

    Replace sanitary piping including underground piping.

    Heating and AC at Level 1

    Sprinkler and fire alarm system

    Electrical conduit, wires and misc. wiring devices

    General lighting, exit lighting and emergency lighting

    Telephone system

    Public address system

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    25/34

    New York State Pavilion

    Pre-Scoping Study For

    Cost EstimateRestoration

    Priced as prevailing wage / project labor

    Based on normal working hours

    Markups include: Design Contingency, General

    Conditions, Overhead & Profit and Design Fee

    Escalation is not included.

    TOTAL COST: $20,538,130

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    26/34

    New York State Pavilion

    Pre-Scoping Study For

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    27/34

    New York State Pavilion

    Pre-Scoping Study For

    Tent of Tomorrow Timber Piles

    1996 Pile

    ProbeDepth

    2012 Pile

    ProbeDepth

    1

    2

    3

    2

    2

    4

    5

    ~ 1 loss per 10 years

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    28/34

    New York State Pavilion

    Pre-Scoping Study For

    Silman Cost Estimate

    Stabilize Column Foundations (Timber Piles)

    Promenade Restoration: Roof, walls, stairs, escalator

    and railings

    Repair Concrete Columns

    Replace Cables in Suspension Roof System

    Clean and Paint Steel

    Replace Translucent Roof Panels

    TOTAL COST: $31,578,950

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    29/34

    New York State Pavilion

    Pre-Scoping Study For

    Adaptive Reuse

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    30/34

    New York State Pavilion

    Pre-Scoping Study For

    Adaptive Reuse

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    31/34

    New York State Pavilion

    Pre-Scoping Study For

    Adaptive Reuse

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    32/34

    New York State Pavilion

    Pre-Scoping Study For

    Adaptive Reuse

  • 8/13/2019 11-18-13 NYS Pavilion Borough Board Presentation

    33/34

    New York State Pavilion

    Pre-Scoping Study For

    Options - Cost Summary