APWA 2016 PWX 8/18/2016 1 “Next” Practices in Project Delivery Drives Roadway Success Jake Smithwick Assistant Professor University of North Carolina at Charlotte Des Mryglod Director Public Works & Engineering Leduc County Colin Roggeveen Principal RPM Consulting Services Just because something is written in a contract does not make it so

Upload: others

Post on 05-Jan-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

APWA 2016 PWX 8/18/2016

1

“Next” Practices in Project Delivery Drives Roadway Success

Jake SmithwickAssistant Professor

University of North Carolina  at Charlotte

Des MryglodDirector

Public Works & EngineeringLeduc County

Colin RoggeveenPrincipal

RPM Consulting Services

Just because something is written in a contract does not make it so

APWA 2016 PWX 8/18/2016

2

Project Performance

• Only 2.5% of projects defined as successful (scope, cost, schedule, & business)– PricewaterhouseCoopers, 2009

• Only 30% of projects completed within 10% of planned cost & schedule – Construction Industry Institute Performance

Assessment Committee, 2015 edition

• 31% of projects cancelled before completed, 53%cost twice as much– Standish Group Chaos Report, 2010

APWA 2016 PWX 8/18/2016

3

Vendor 1

Vendor 2

Vendor 3

Vendor 4

High

Low High

Low High

Low High

Low

Impact of Minimum Requirements

Vendor 1Vendor 2Vendor 3Vendor 4

It Is More Important For The Vendor To Know What To Do Than It Is For Client To Know What The Vendor Should Do

APWA 2016 PWX 8/18/2016

4

The Process

3 Written SubmittalsBlind Evaluations: standard templates, no modifications, and no names.

Risk Assessment

= risks you don’t control

2 pages each, 6 pages in total

APWA 2016 PWX 8/18/2016

5

Project Capability

Project Capability Template

APWA 2016 PWX 8/18/2016

6

• Plan 1– We will use our 20 years of experience in working with mechanical

systems to minimize the risk of the heating and cooling system design.

• Plan 2– We have identified the design of the heat/cooling system as a risk. It has

not been used before in the area. Will ensure that the system performance and installation is verified in the pre-award period.

– We have bid using best rated mechanical contractor in the area (rated at 9.8 out of 10.0, next best rated 9.1)

– Mechanical contractor identified modifications to the design to improve output and sustainability of the system with the following impacts (mechanical system cost minimized by 15% - see VA#1)

– Mechanical system will be provided by one manufacturer, and will be commissioned by the manufacturer, contractor, and general contractor, who will take full responsibility of commissioning the system

Example of SolutionsRisk: Design of Heating/Cooling SystemType: Project Capability

• Plan 1– We will work with the user to minimize the impact of noise from

demolition.

• Plan 2– We have planned to demolition during off hours and weekends. This

will have a slight impact on our cost (less than 1%), but the impact to customer satisfaction justifies this.

– We will also install rubber sheets on the floors to diminish noise and vibrations.

– Both solutions can be performed within your budget. – Both solutions have been used on multiple previous projects w/ high

levels of customer satisfaction (9.4/10).

Example of SolutionsRisk: Noise from Demolition

Type: Project Capability

APWA 2016 PWX 8/18/2016

7

Risk Assessment

Risk Assessment

= risks you don’t control

Risk Assessment TemplateTypical Risk Assessment Template

APWA 2016 PWX 8/18/2016

8

Example of Solutions Risk: Loss of Radio Flagship in Major MarketType: Risk Assessment• Plan 1

– We will work very hard to maintain excellent affiliate relationships. If we lose a radio station (e.g. it changes its format) we will move quickly to replace the lost station. If we cannot quickly replace a flagship station, we can be very creative and could even consider purchasing all local inventory from a new flagship station.

• Plan 2– In the past 10 yrs, on over 50 accounts, 7 radio stations format changes

have occurred. The following solution is optimal.– We own and will maintain two radio contracts covering the area, where

signals can be switched if required. The flagship station will be the station with the stronger signal and greater coverage.

– If a station is lost we will have a equal replacement within 2 months. If within two months a replacement is not contracted we will purchase inventory from another station or discount the cost of an inventory purchase and add it to our payments to the client.

Example of Solutions

• Solution 1– By optimizing the building location, using a hybrid design and exploring

strong fundamental architectural design process with will provide an optimum solution. As design progresses, continuous verification of the budget will be utilized to ensure success

• Solution 2

• The owner can be assured that the budget is not a risk. Our world class team has connections to a wide range of high performing suppliers to ensure that you always get the best prices and ensure the budget is met.

Risk: Owner’s Budget (DB Residence Hall)Type: Risk Assessment

Generic Marketing InformationNOT a Plan

Will say whatever they think the client wants to hear in order to get the job

APWA 2016 PWX 8/18/2016

9

• Solution 3– The Owner’s budget cannot accommodate the building program per the

requirements.

– We have identified multiple Value Added options that enable us to meet the budget and still deliver the required number of beds (in order to maximize owner revenue streams):

• Removal of underground parkade – $2,054,717 savings• Reduction in certain finishes (wall panels vs. dry wall) – $67,000

savings• Design efficiency opportunities: Adjust net-to-gross ratios in

targeted areas of building program (hallways, common spaces). Reduction in building footprint results in significant material savings – net savings $1,686,149

Example of SolutionsRisk: Owner’s Budget (DB Residence Hall)Type: Risk Assessment

• Plan 1– Coordination with [water company] is critical. We will

coordinate and plan with [water company] as soon as the award is made to make sure that we get water to the site to irrigate the fields.

• Plan 2– We will coordinate and schedule the water with [water

company]. However, based on past experience there is a high risk they will not meet the schedule (the water company does not meet schedule over 90% of the time).

– We will have temporary waterlines setup and ready to connect to the nearby fire hydrant to irrigate until [water company] is ready.

– We will also have water trucks on-site if there is problems with connecting the lines.

Example of Solutions Risk: Getting water to the site

Type: Risk Assessment

APWA 2016 PWX 8/18/2016

10

Value Added

Value Added TemplateTypical Value Added Template

APWA 2016 PWX 8/18/2016

11

Example: Value Added Items

• Reroofing this building will not stop all water leaks. The majority of the leaks are caused by cracks in the parapet walls, broken/missing glass, and poor caulking. For an additional $10K and 3 weeks in schedule we can replace and repair all of these items.

The Process

APWA 2016 PWX 8/18/2016

12

Clarification / Preplanning Period

The Process

APWA 2016 PWX 8/18/2016

13

Measured Environment• Must be simple and dominant

• Must be for the purposes of positive accountability

• Transparency and openness

• Measuring against a plan (or expectation created by the individual/team doing the work)

Project Background• Budget: $27M | 3.3KM

– Single largest project County has ever undertaken

• 4-lane Highway + Water Main– 300,000m3 Earthwork– 46,000T Asphalt– 91,000T Aggregate– 110,000m2 Subgrade

• Best value contractor:– $1M in proposed cost-saving initiatives– Awarded 30% below budget

APWA 2016 PWX 8/18/2016

14

Location

Proactive Risk Management• Utility Relocation: We contacted local utility

companies 8 months ahead of the project start date and were assured of a May 4 start. Previous experience has 5+ weeks delay without pre-approval.

• Public Access on Highway 510: Construct full length temporary detour. Creates unimpeded access, giving more access for our work.

• Tree Clearing: Environment Canada mandates trees cannot be cleared if birds have nested after April 15. Potential schedule delays up through August 1 if trees not removed ahead of time.

APWA 2016 PWX 8/18/2016

15

Value of “Thinking Ahead”Interview Comments

“I’ve visited the site numerous times. I personally prepared our proposal, and have reviewed all of the

details. We are having one subcontractor perform all of the major electrical, water, and other underground work.

This process has helped us coordinate our work to a much higher level.”

-Risk Plan Score: 7.0 / 10

VS...

“I reviewed our proposal in the past few days. I’ve spent a several hours reviewing it – I check all of our

estimators’ and business development staff work before submission. Our staff visited the site once.”

- Risk Plan Score: 3.4 / 10

Contract Management• Less time managing Contractor • More time required managing Utility Co.’s

• Team Environment– Shared Construction Site Office– Less time in meetings– Proactive vs Reactive

• Risk Management– Bi-weekly review and update of Risk Plan– New issues came with options & costs for solutions

APWA 2016 PWX 8/18/2016

16

Final Results

Schedule

• Utility Companies 12 weeks behind schedule• 18 days certified weather delays

Substantial Completion Nov 5, 2015 (4 days behind schedule)

Final ResultsBudget

• Original Contract $14,755,894.21

• Approx $42k Contractor initiated change orders – 0.26%• $1.5M Work added to contract• $300k Design related changes• $465k Quantity overrun on Topsoil

• Final Contract $16,177,613.17

• Variance $1,421,718.96 (8.79%)

APWA 2016 PWX 8/18/2016

17

Thoughts for owners• Simplifies the selection process

– saves staff review time– publically defendable / transparent– return for the taxpayers – Best Value

• Emphasis on project risk at the outset

• But… it requires a change in thinking– Apprehension of a new process from the client– Concern from the contractors “it’s not how we normally do

things”

• Changing the process from an adversarial process to a cooperative process

Award of Excellence

APWA 2016 PWX 8/18/2016

18

Comments / Questions

[email protected]

[email protected]

[email protected]