101 industrial engineering

49
www.gatescore.in GATE-ME Previous Years Solved Paper Industrial Engineering

Upload: sushil-kumar-singh

Post on 28-Jan-2016

224 views

Category:

Documents


0 download

DESCRIPTION

GATE

TRANSCRIPT

Page 1: 101 Industrial Engineering

www.gatescore.in

GATE-MEPrevious Years Solved Paper

Industrial Engineering

Page 2: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

YEAR 2013 OnE MARk

Q. 1 Customer arrive at a ticket counter at a rate of 50 per hr and tickets are issued in the order of their arrival. The average time taken for issuing a ticket is 1 .min Assuming that customer arrivals from a Poisson process and service times and exponentially distributed, the average waiting time is queue in min is(A) 3 (B) 4

(C) 5 (D) 6

Q. 2 Let X be a normal random variable with mean 1 and variance 4. The probability P X 0<" , is(A) .0 5

(B) greater than zero and less the .0 5

(C) greater than .0 5 and less than 1.0

(D) .1 0

Q. 3 In simple exponential smoothing forecasting, to give higher weightage to recent demand information, the smoothing constant must be close to(A) –1 (B) zero

(C) 0.5 (D) 1.0

YEAR 2013 TwO MARkS

Q. 4 A linear programming problem is shown below. Maximize x y3 7+ Subject to x y3 7 10#+ x y4 6 8#+ ,x y 0$It has(A) an unbounded objective function

(B) exactly one optimal solution.

(C) exactly two optimal solutions.

(D) infinitely many optimal solutions

YEAR 2012 OnE MARk

Q. 5 Which one of the following is NOT a decision taken during the aggregate production planning stage ?(A) Scheduling of machines

(B) Amount of labour to be committed

(C) Rate at which production should happen

(D) Inventory to be carried forward

YEAR 2012 TwO MARkS

�CooCon DaD Cor Q� 6 Dond Q7For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

Page 3: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Activity Predecessors Durations (days)

a - 3

b a 4

c a 5

d a 4

e b 2

f d 9

g c , e 6

h f , g 2

Q. 6 The critical path for the project is(A) a - b - e - g - h (B) a - c - g - h

(C) a - d - f - h (D) a - b - c - f - h

Q. 7 If the duration of activity f alone is changed from 9 to 10 days, then the(A) critical path remains the same and the total duration to complete the

project changes to 19 days.

(B) critical path and the total duration to complete the project remains the same.

(C) critical path changes but the total duration to complete the project remains the same.

(D) critical path changes and the total duration to complete the project changes to 17 days.

YEAR 2011 OnE MARk

Q. 8 Cars arrive at a service station according to Poisson’s distribution with a mean rate of 5 per hour. The service time per car is exponential with a mean of 10 minutes. At steady state, the average waiting time in the queue is(A) 10 minutes (B) 20 minutes

(C) 25 minutes (D) 50 minutes

Q. 9 The word ‘kanban’ is most appropriately associated with(A) economic order quantity

(B) just-in-time production

(C) capacity planning

(D) product design

YEAR 2011 TwO MARkS

�CooCon DaD Cor Q� 10 Dond 11One unit of product P1 requires 3 kg of resources R1 and 1 kg of resources R2

. One unit of product P2 requires 2 kg of resources R1 and 2 kg of resources R2

. The profits per unit by selling product P1 and P2 are . 2000Rs and . 3000Rs respectively. The manufacturer has 90 kg of resources R1 and 100 kg of resources

Page 4: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

R2.

Q. 10 The unit worth of resources R2, i.e., dual price of resources R2 in Rs. per kg is(A) 0 (B) 1350

(C) 1500 (D) 2000

Q. 11 The manufacturer can make a maximum profit of Rs.(A) 60000

(B) 135000

(C) 150000

(D) 200000

YEAR 2010 OnE MARk

Q. 12 The demand and forecast for February are 12000 and 10275, respectively. Using single exponential smoothening method (smoothening coefficient 0.25= ), forecast for the month of March is(A) 431

(B) 9587

(C) 10706

(D) 11000

Q. 13 Little’s law is a relationship between(A) stock level and lead time in an inventory system

(B) waiting time and length of the queue in a queuing system

(C) number of machines and job due dates in a scheduling problem

(D) uncertainty in the activity time and project completion time

Q. 14 Vehicle manufacturing assembly line is an example of(A) product layout

(B) process layout

(C) manual layout

(D) fixed layout

Q. 15 Simplex method of solving linear programming problem uses(A) all the points in the feasible region

(B) only the corner points of the feasible region

(C) intermediate points within the infeasible region

(D) only the interior points in the feasible region

YEAR 2010 TwO MARkS

Q. 16 Annual demand for window frames is 10000. Each frame cost . 200Rs and ordering cost is . 300Rs per order. Inventory holding cost is . 40Rs per frame per year. The supplier is willing of offer 2% discount if the order quantity is 1000 or more, and 4% if order quantity is 2000 or more. If the total cost is to be minimized, the retailer should(A) order 200 frames every time

Page 5: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

(B) accept 2% discount

(C) accept 4% discount

(D) order Economic Order Quantity

Q. 17 The project activities, precedence relationships and durations are described in the table. The critical path of the project is

Acaiviay Porecedeonce uorDaiCon (ion dDys)

P - 3

Q - 4

R P 5

S Q 5

T ,R S 7

U ,R S 5

V T 2

W U 10

(A) P -R-T -V

(B) Q -S -T -V

(C) P -R-U -W

(D) Q -S -U -W

�CooCon DaD Cor Q� 18 Dond 19Four jobs are to be processed on a machine as per data listed in the table.

JCb PorCcessiong aioe (ion dDys) ue dDae

1 4 6

2 7 9

3 2 19

4 8 17

Q. 18 If the Earliest Due Date (EDD) rule is used to sequence the jobs, the number of jobs delayed is(A) 1 (B) 2

(C) 3 (D) 4

Q. 19 Using the Shortest Processing Time (SPT) rule, total tardiness is(A) 0 (B) 2

(C) 6 (D) 8

YEAR 2009 OnE MARk

Q. 20 The expected time ( )te of a PERT activity in terms of optimistic time t0, pessimistic time ( )tp and most likely time ( )tl is given by

(A) tt t t

64

eo l p= + +

(B) tt t t

64

eo p l= + +

Page 6: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

(C) tt t t

34

eo l p= + +

(D) tt t t

34

eo p l= + +

Q. 21 Which of the following forecasting methods takes a fraction of forecast error into account for the next period forecast ?(A) simple average method

(B) moving average method

(C) weighted moving average method

(D) exponential smoothening method

YEAR 2009 TwO MARkS

Q. 22 Consider the following Linear Programming Problem (LPP):

Maximize Z = 3 2x x1 2+Subject to x1 4#

x2 6#

3 2x x1 2+ 18#

x1 0, 0x2$ $(A) The LPP has a unique optimal solution

(B) The LPP is infeasible.

(C) The LPP is unbounded.

(D) The LPP has multiple optimal solutions.

Q. 23 A company uses 2555 units of an item annually. Delivery lead time is 8 days. The reorder point (in number of units) to achieve optimum inventory is(A) 7 (B) 8

(C) 56 (D) 60

Q. 24 Six jobs arrived in a sequence as given below:

JCbs PorCcessiong Tioe (dDys)

I 4

II 9

III 5

IV 10

V 6

VI 8

Average flow time (in days) for the above jobs using Shortest Processing time rule is(A) 20.83 (B) 23.16

(C) 125.00 (D) 139.00

�CooCon DaD Cor Q� 25 Dond 26Consider the following PERT network:

Page 7: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

Acaiviay Opaioisaic aioe(dDys)

MCsa likely aioe (dDys)

Pessioisaic aioe (dDys)

1 - 2 1 2 3

1 - 3 5 6 7

1 - 4 3 5 7

2 - 5 5 7 9

3 - 5 2 4 6

5 - 6 4 5 6

4 - 7 4 6 8

6 - 7 2 3 4

Q. 25 The critical path duration of the network (in days) is(A) 11

(B) 14

(C) 17

(D) 18

Q. 26 The standard deviation of the critical path is(A) 0.33

(B) 0.55

(C) 0.77

(D) 1.66

YEAR 2008 OnE MARk

Q. 27 In an / /M M 1 queuing system, the number of arrivals in an interval of length T is a Poisson random variable (i.e. the probability of there being arrivals in an

interval of length T is !( )n

e TT nll-

). The probability density function ( )f t of the inter-arrival time is

(A) e t2 2

l l-^ h (B) e

t

2

2

l

l-

(C) e tl l- (D) et

ll-

Q. 28 A set of 5 jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. K per day.

Page 8: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

JCb PorCcessiong aioe

P 5

Q 2

R 3

S 2

T 1

A schedule that minimizes the total inventory cost is(A) T -S -Q -R-P (B) P -R-S -Q -T

(C) T -R-S -Q -P (D) P -Q -R-S -T

YEAR 2008 TwO MARkS

Q. 29 For the standard transportation linear programme with m source and n destinations and total supply equaling total demand, an optimal solution (lowest cost) with the smallest number of non-zero xij values (amounts from source i to destination j ) is desired. The best upper bound for this number is(A) mn (B) 2( )m n+(C) m n+ (D) 1m n+ −

Q. 30 A moving average system is used for forecasting weekly demand ( )F t1 and ( )F t2 are sequences of forecasts with parameters m1 and m2, respectively, where m1 and ( )m m m>2 1 2 denote the numbers of weeks over which the moving averages are

taken. The actual demand shows a step increase from d1 to d2 at a certain time. Subsequently,(A) neither ( )F t1 nor ( )F t2 will catch up with the value d2

(B) both sequences ( )F t1 and ( )F t2 will reach d2 in the same period

(C) ( )F t1 will attain the value d2 before ( )F t2(D) ( )F t2 will attain the value d2 before ( )F t1

Q. 31 For the network below, the objective is to find the length of the shortest path from node to nodeP G .Let dij be the length of directed arc from node i to node j .Let Sj be the length of the shortest path from P to node j . Which of the following equations can be used to find SG ?

(A) { , }MinS S SG Q R=

(B) { , }MinS S d S dG Q QG R RG= − −(C) { , }MinS S d S dG Q QG R RG= + +

(D) { , }MinS d dG QG RG=

Q. 32 The product structure of an assembly P is shown in the figure.

Page 9: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Estimated demand for end product P is as follows

Week 1 2 3 4 5 6

eoDond 1000 1000 1000 1000 1200 1200

ignore lead times for assembly and sub-assembly. Production capacity (per week) for component R is the bottleneck operation. Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is(A) 1000 (B) 1200

(C) 2200 (D) 2400

�CooCon DaD Cor Q� 33 Dond 34Consider the Linear Programme (LP)

Max 4 6x y+ Subject to 3 2x y+ 6#

2 3x y+ 6#

,x y 0$

Q. 33 After introducing slack variables s and t , the initial basic feasible solution is represented by the table below (basic variables are 6s = and 6t = , and the objective function value is 0)

4- 6- 0 0 0

s 3 2 1 0 6

t 2 3 0 1 6

x y s t RHS

After some simplex iterations, the following table is obtained

0 0 0 2 12

s 5/3 0 1 /1 3- 2

y 2/3 1 0 1/3 2

x y s t RHS

From this, one can conclude that(A) the LP has a unique optimal solution

(B) the LP has an optimal solution that is not unique

(C) the LP is infeasible

(D) the LP is unbounded

Q. 34 The dual for the LP in Q . 29 is(A) 6 6Min u v+ (B) 6 6Max u v+

Page 10: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

subject to subject to

3 2 4u v$+ 3 2 4u v#+ 2 3 6u v$+ 2 3 6u v#+ , 0u v$ , 0u v$

(C) 4 6Max u v+ (D) 4 6Min u v+ subject to subject to

3 2 6u v$+ 3 2 6u v#+ 2 3 6u v$+ 2 3 6u v#+ , 0u v$ , 0u v$

YEAR 2007 TwO MARkS

Q. 35 Capacities of production of an item over 3 consecutive months in regular time are 100, 100 and 80 and in overtime are 20, 20 and 40. The demands over those 3 months are 90, 130 and 110. The cost of production in regular time and overtime are respectively . 20Rs per item and . 24Rs per item. Inventory carrying cost is . 2Rs per item per month. The levels of starting and final inventory are nil. Backorder is not permitted. For minimum cost of plan, the level of planned production in overtime in the third month is(A) 40 (B) 30

(C) 20 (D) 0

Q. 36 The maximum level of inventory of an item is 100 and it is achieved with infinite replenishment rate. The inventory becomes zero over one and half month due to consumption at a uniform rate. This cycle continues throughout the year. Ordering cost is .100Rs per order and inventory carrying cost is .10Rs per item per month. Annual cost (in Rs.) of the plan, neglecting material cost, is(A) 800

(B) 2800

(C) 4800

(D) 6800

Q. 37 In a machine shop, pins of mm15 diameter are produced at a rate of 1000 per month and the same is consumed at a rate of 500 per month. The production and consumption continue simultaneously till the maximum inventory is reached. Then inventory is allowed to reduced to zero due to consumption . The lot size of production is 1000. If backlog is not allowed, the maximum inventory level is(A) 400 (B) 500

(C) 600 (D) 700

Q. 38 The net requirements of an item over 5 consecutive weeks are 50-0-15-20-20. The inventory carrying cost and ordering cost are .1Rs per item per week and .100Rs per order respectively. Starting inventory is zero. Use “ Least Unit Cost

Technique” for developing the plan. The cost of the plan (in Rs.) is(A) 200 (B) 250

(C) 225 (D) 260

Page 11: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

YEAR 2006 OnE MARk

Q. 39 The number of customers arriving at a railway reservation counter is Poisson distributed with an arrival rate of eight customers per hour. The reservation clerk at this counter takes six minutes per customer on an average with an exponentially distributed service time. The average number of the customers in the queue will be(A) 3

(B) 3.2

(C) 4

(D) 4.2

Q. 40 In an MRP system, component demand is(A) forecasted

(B) established by the master production schedule

(C) calculated by the MRP system from the master production schedule

(D) ignored

YEAR 2006 TwO MARkS

Q. 41 An manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is

MDchioneJCbs

P Q R S T U

M1 15 32 8 27 11 16

M2 6 19 13 20 14 7

The optimal make-span (in-hours) of the shop is(A) 120

(B) 115

(C) 109

(D) 79

Q. 42 Consider the following data for an item.Annual demand : 2500 units per year, Ordering cost : .100Rs per order, Inventory holding rate : 25% of unit pricePrice quoted by a supplier

Oordeor quDonaiay (uonias) Uonia porice (RsQ)500< 10

500$ 9

The optimum order quantity (in units) is(A) 447 (B) 471

(C) 500 (D) 600$

Page 12: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Q. 43 A firm is required to procure three items (P , Q , and R). The prices quoted for these items (in Rs.) by suppliers S1, S2 and S3 are given in table. The management policy requires that each item has to be supplied by only one supplier and one supplier supply only one item. The minimum total cost (in Rs.) of procurement to the firm is

Iaeo Supplieors

S1 S2 S3

P 110 120 130

Q 115 140 140

R 125 145 165

(A) 350 (B) 360

(C) 385 (D) 395

Q. 44 The table gives details of an assembly line.

WCork saDaiCon I II III IV V VI

TCaDl aDsk aioe Da ahe wCorksaDaiCon (ion oion) 7 9 7 10 9 6

What is the line efficiency of the assembly line ?(A) 70% (B) 75%

(C) 80% (D) 85%

Q. 45 A stockist wishes to optimize the number of perishable items he needs to stock in any month in his store. The demand distribution for this perishable item is

eoDond (ion uonias) 2 3 4 5

PorCbDbiliay 0.10 0.35 0.35 0.20

The stockist pays . 70Rs for each item and he sells each at . 90Rs . If the stock is left unsold in any month, he can sell the item at . 50Rs each. There is no penalty for unfulfilled demand. To maximize the expected profit, the optimal stock level is(A) 5 units (B) 4 units

(C) 3 units (D) 2 units

Q. 46 The expected completion time of the project is(A) 238 days (B) 224 days

(C) 171 days (D) 155 days

Q. 47 The standard deviation of the critical path of the project is(A) 151 days (B) 155 days

(C) 200 days (D) 238 days

YEAR 2005 OnE MARk

Q. 48 An assembly activity is represented on an Operation Process Chart by the symbol(A) 4 (B) A

(C) D (D) O

Page 13: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Q. 49 The sales of a product during the last four years were 860, 880, 870 and 890 units. The forecast for the fourth year was 876 units. If the forecast for the fifth year, using simple exponential smoothing, is equal to the forecast using a three period moving average, the value of the exponential smoothing constant a is

(A) 71 (B) 5

1

(C) 72 (D) 5

2

Q. 50 Consider a single server queuing model with Poisson arrivals ( )4/hourl = and exponential service ( 4/ )hourµ= . The number in the system is restricted to a maximum of 10. The probability that a person who comes in leaves without joining the queue is

(A) 111 (B) 10

1

(C) 91 (D) 2

1

YEAR 2005 TwO MARkS

Q. 51 A component can be produced by any of the four processes I, II, III and IV. Process I has a fixed cost of . 20Rs and variable cost of . 3Rs per piece. Process II has a fixed cost . 50Rs and variable cost of .1Rs per piece. Process III has a fixed cost of . 40Rs and variable cost of . 2Rs per piece. Process IV has a fixed cost of .10Rs and variable cost of . 4Rs per piece. If the company wishes to produce 100

pieces of the component, form economic point of view it should choose(A) Process I

(B) Process II

(C) Process III

(D) Process IV

Q. 52 A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are allowed for this operation. The expected standard production rate of the weld-joint (in units per 8 hour day) is(A) 45 (B) 50

(C) 55 (D) 60

Q. 53 The distribution of lead time demand for an item is as follows:

LeDd aioe deoDond PorCbDbiliay

80 0.20

100 0.25

120 0.30

140 0.25

The reorder level is 1.25 times the expected value of the lead time demand. The service level is(A) 25% (B) 50%

(C) 75% (D) 100%

Page 14: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Q. 54 A project has six activities ( toA F ) with respective activity duration 7, 5, 6, 6, 8, 4 days. The network has three paths A-B , C -D and E -F . All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is(A) 1 (B) 2

(C) 3 (D) 6

Q. 55 A company has two factories S1 , S2, and two warehouses 1D , D2. The supplies from S1 and S2 are 50 and 40 units respectively. Warehouse 1D requires a minimum of 20 units and a maximum of 40 units. Warehouse D2 requires a minimum of 20 units and, over and above, it can take as much as can be supplied. A balanced transportation problem is to be formulated for the above situation. The number of supply points, the number of demand points, and the total supply (or total demand) in the balanced transportation problem respectively are(A) 2, 4, 90

(B) 2, 4, 110

(C) 3, 4, 90

(D) 3, 4, 110

�CooCon DaD Cor Q� 56 Dond 57Consider a linear programming problem with two variables and two constraints. The objective function is : Maximize X X1 2+ . The corner points of the feasible region are (0, 0), (0, 2), (2, 0) and (4/3, 4/3)

Q. 56 If an additional constraint 5X X1 2#+ is added, the optimal solution is

(A) ,3535

b l (B) ,3434

b l

(C) ,2525

b l (D) (5, 0)

Q. 57 Let Y1 and Y2 be the decision variables of the dual and v1 and v2 be the slack variables of the dual of the given linear programming problem. The optimum dual variables are(A) Y1 and Y2 (B) Y1 and v1

(C) Y1 and v2 (D) v1 and v2

YEAR 2004 OnE MARk

Q. 58 In PERT analysis a critical activity has(A) maximum Float

(B) zero Float

(C) maximum Cost

(D) minimum Cost

Q. 59 For a product, the forecast and the actual sales for December 2002 were 25 and 20 respectively. If the exponential smoothing constant ( )a is taken as 0.2, then forecast sales for January 2003 would be(A) 21 (B) 23

(C) 24 (D) 27

Page 15: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Q. 60 There are two products P and Q with the following characteristics

PorCduca eoDond (Uonias) Oordeor cCsa (Rs/Cordeor)

HCldiong �Csa(RsQ/ uonia/ yeDor)

P 100 50 4

Q 400 50 1

The economic order quantity (EOQ) of products P and Q will be in the ratio(A) 1 : 1 (B) 1 : 2

(C) 1 : 4 (D) 1 : 8

YEAR 2004 TwO MARkS

Q. 61 A standard machine tool and an automatic machine tool are being compared for the production of a component. Following data refers to the two machines.

SaDondDordMDchione TCCl

AuaCoDaicMDchione TCCl

Seaup aioe 30 min 2 hours

MDchioniong aioe peor piece 22 min 5 min

MDchione orDae Rs. 200 per hour Rs. 800 per hour

The break even production batch size above which the automatic machine tool will be economical to use, will be(A) 4 (B) 5

(C) 24 (D) 225

Q. 62 A soldering operation was work-sampled over two days (16 hours) during which an employee soldered 108 joints. Actual working time was 90% of the total time and the performance rating was estimated to be 120 per cent. If the contract provides allowance of 20 percent of the time available, the standard time for the operation would be(A) 8 min (B) 8.9 min

(C) 10 min (D) 12 min

Q. 63 An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hours shift. This operation consist of three activities as below

Acaiviay SaDondDord aioe (oion)

M. Mechanical assembly 12

E. Electric wiring 16

T. Test 3

For line balancing the number of work stations required for the activities M, E and T would respectively be(A) 2, 3, 1 (B) 3, 2, 1

(C) 2, 4, 2 (D) 2, 1, 3

Page 16: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Q. 64 A maintenance service facility has Poisson arrival rates, negative exponential service time and operates on a ‘first come first served’ queue discipline. Breakdowns occur on an average of 3 per day with a range of zero to eight. The maintenance crew can service an average of 6 machines per day with a range of zero to seven. The mean waiting time for an item to be serviced would be

(A) 61 day (B) 3

1 day

(C) 1 day (D) 3 day

Q. 65 A company produces two types of toys : P and Q . Production time of Q is twice that of P and the company has a maximum of 2000 time units per day. The supply of raw material is just sufficient to produce 1500 toys (of any type) per day. Toy type Q requires an electric switch which is available @ 600 pieces per day only. The company makes a profit of . 3Rs and . 5Rs on type P and Q respectively. For maximization of profits, the daily production quantities of P and Q toys should respectively be(A) 1000, 500 (B) 500, 1000

(C) 800, 600 (D) 1000, 1000

Q. 66 A company has an annual demand of 1000 units, ordering cost of .100Rs / order and carrying cost of .100Rs / unit/year. If the stock-out cost are estimated to be nearly . 400Rs each time the company runs out-of-stock, then safety stock justified by the carrying cost will be(A) 4 (B) 20

(C) 40 (D) 100

YEAR 2003 OnE MARk

Q. 67 The symbol used for Transport in work study is(A) & (B) T

(C) > (D) 4

YEAR 2003 TwO MARkS

Q. 68 Two machines of the same production rate are available for use. On machine 1, the fixed cost is .Rs 100 and the variable cost is .Rs 2 per piece produced. The corresponding numbers for the machine 2 are .Rs 200 and .1Re respectively. For certain strategic reasons both the machines are to be used concurrently. The sales price of the first 800 units is . .Rs 3 50 per unit and subsequently it is only . .Rs 3 00. The breakeven production rate for each machine is(A) 75 (B) 100

(C) 150 (D) 600

Q. 69 A residential school stipulates the study hours as 8.00 pm to 10.30 pm. Warden makes random checks on a certain student 11 occasions a day during the study hours over a period of 10 days and observes that he is studying on 71 occasions. Using 95% confidence interval, the estimated minimum hours of his study during that 10 day period is(A) 8.5 hours (B) 13.9 hours

(C) 16.1 hours (D) 18.4 hours

Page 17: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Q. 70 The sale of cycles in a shop in four consecutive months are given as 70, 68, 82, 95. Exponentially smoothing average method with a smoothing factor of 0.4 is used in forecasting. The expected number of sales in the next month is(A) 59 (B) 72

(C) 86 (D) 136

Q. 71 Market demand for springs is 8,00,000 per annum. A company purchases these springs in lots and sells them. The cost of making a purchase order is .1200Rs. The cost of storage of springs is .120Rs per stored piece per annum. The economic order quantity is(A) 400

(B) 2,828

(C) 4,000

(D) 8,000

Q. 72 A manufacturer produces two types of products, 1 and 2, at production levels of x1 and x2 respectively. The profit is given is 2 5x x1 2+ . The production constraints are

3x x1 2+ 40#

3x x1 2+ 24#

x x1 2+ 10#

0x >1 , 0x >2The maximum profit which can meet the constraints is(A) 29 (B) 38

(C) 44 (D) 75

Q. 73 A project consists of activities A to M shown in the net in the following figure with the duration of the activities marked in days

The project can be completed(A) between 18, 19 days

(B) between 20, 22 days

(C) between 24, 26 days

(D) between 60, 70 days

Q. 74 The principles of motion economy are mostly used while conducting(A) a method study on an operation

(B) a time study on an operation

(C) a financial appraisal of an operation

(D) a feasibility study of the proposed manufacturing plant

Page 18: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

YEAR 2002 OnE MARk

Q. 75 The standard time of an operation while conducting a time study is(A) mean observed time + allowances

(B) normal time + allowances

(C) mean observed time # rating factor + allowances

(D) normal time # rating factor + allowances

Q. 76 In carrying out a work sampling study in a machine shop, it was found that a particular lathe was down for %20 of the time. What would be the %95 confidence interval of this estimate, if 100 observations were made ?(A) (0.16, . )0 24

(B) ( . , . )0 12 0 28

(C) ( . , . )0 08 0 32

(D) None of these

Q. 77 An item can be purchased for Rs. 100. The ordering cost is Rs. 200 and the inventory carrying cost is %10 of the item cost per annum. If the annual demand is 4000 unit, the economic order quantity (in unit) is(A) 50 (B) 100

(C) 200 (D) 400

YEAR 2002 TwO MARkS

Q. 78 Arrivals at a telephone booth are considered to be Poisson, with an average time of 10 minutes between successive arrivals. The length of a phone call is distributed exponentially with mean 3 nmi utes. The probability that an arrival does not have to wait before service is(A) 0.3

(B) 0.5

(C) 0.7

(D) 0.9

Q. 79 The supplies at three sources are 50, 40 and 60 unit respectively whilst the demands at the four destinations are 20, 30, 10 and 50 unit. In solving this transportation problem(A) a dummy source of capacity 40 unit is needed

(B) a dummy destination of capacity 40 unit is needed

(C) no solution exists as the problem is infeasible

(D) no solution exists as the problem is degenerate

Q. 80 A project consists of three parallel paths with mean durations and variances of ( , )10 4 , ( , )12 4 and ( , )12 9 respectively. According to the standard PERT assumptions, the distribution of the project duration is(A) beta with mean 10 and standard deviation 2

(B) beta with mean 12 and standard deviation 2

(C) normal with mean 10 and standard deviation 3

(D) normal with mean 12 and standard deviation 3

Page 19: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

YEAR 2001 OnE MARk

Q. 81 Production flow analysis (PFA) is a method of identifying part families that uses data from(A) engineering drawings

(B) production schedule

(C) bill of materials

(D) route sheets

Q. 82 When using a simple moving average to forecast demand, one would(A) give equal weight to all demand data

(B) assign more weight to the recent demand data

(C) include new demand data in the average without discarding the earlier data

(D) include new demand data in the average after discarding some of the earlier demand data

YEAR 2001 TwO MARkS

Q. 83 Fifty observations of a production operation revealed a mean cycle time of min10. The worker was evaluated to be performing at %90 efficiency. Assuming the allowances to be %10 of the normal time, the standard time (in second) for the job is(A) 0.198 (B) 7.3

(C) 9.0 (D) 9.9

********

Page 20: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

SOLuTIOn

Sol. 1 Option (C) is correct.Average waiting time of a customer (in a queue) is given by

E w^ h µ µ λλ=−^ h

Where l 50= customers per hour or .0 834 customer/min

µ 1= per min

Therefore E w^ h .

0.81 1 0 834

34#

=−^ h

5 min=

Sol. 2 Option (B) is correct.The normal random variable is X ,N µ σ= ^ hWhere 1µ= and 2s =

Here P X 0<^ h P x 20 1<σ

µ= − −c m

.P z 0 5<= −^ h

Where z = standard Normal Variable . .0 5 0 5f= − ^ h

Where value of zf^ h is always between .0 0 to .0 4999Hence the probability P X 0<" , = greater than zero and less than .0 5.

Sol. 3 Option (D) is correct.Higher weightage given to recent demand, therefore F Dt t= Ft ( )F D Ft t t1 1a= + −− −

or ( )F D1t t1 a= − +−

Thus from the given condition ( )F 1t 1 a-- 0=or a 1=The values of smoothing constant a^ h lie between 0 and 1. A low value of a gives more weightage to the past series and less weightage to the recent demand information. Hence, in simple exponential smoothing forecasting, higher value of a, i.e. 1, gives higher weightage to recent demand information and less weightage to the past series.

Sol. 4 Option (B) is correct.We haveMaximize x y3 7+Subject to x y3 7 10#+ x y4 6 8#+ ,x y 0$From these equation, we have

Page 21: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

The solution of the given problem must lie in the shaded area. One of the points ,O P and Q of shaded area must give the optimum solution of problem. So

At ,P 0 4 3^ h, Z .3 0 7 34

328 9 33# #= + = =

and at ,Q 2 0^ h, Z 3 2 7 0 6# #= + =Hence, there is only a single optimal solution of the problem which is at point ,P 0 4 3^ h.

Sol. 5 Option (A) is correct.Costs relevant to aggregate production planning is as given below.(i) Basic production cost : Material costs, direct labour costs, and overhead

cost.

(ii) Costs associated with changes in production rate : Costs involving in hiring, training and laying off personnel, as well as, overtime compensation.

(iii) Inventory related costs.

Hence, from above option (A) is not related to these costs. Therefore option (A) is not a decision taken during the APP.

Sol. 6 Option (C) is correct.

For path Duration

a - b - e - g - h 3 4 2 6 2 17 days= + + + + =

a - c - g - h 3 5 6 2 16 days= + + + =

a - d - f - h 3 4 9 2 18 days= + + + =

The critical path is one that takes longest path.Hence, path a - d - f - h 18 days= is critical path

Page 22: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 7 Option (A) is correct.From previous question, For critical patha -d - f -h 18 days= , the duration of activity f alone is changed from 9 to 10 days, then a - d - f - h 3 4 10 2 19 days= + + + =Hence critical path remains same and the total duration to complete the project changes to 19 days.

Sol. 8 Option (D) is correct.

Given : l 5 per hour= , µ 60 per hour101#= 6 per hour=

Average waiting time of an arrival

Wq ( )µ µ λλ= −

( )6 6 55= − hours6

5= min50=

Sol. 9 Option (B) is correct.Kanban Literally, a “Visual record”; a method of controlling materials flow through a Just-in-time manufacturing system by using cards to authorize a work station to transfer or produce materials.

Sol. 10 Option (A) is correct.Since, in Zj Row of final (second) obtimum table the value of slack variable S2 showns the unit worth or dual price of Resource R2 and the value of S2 in given below table is zero. Hence the dual Price of Resource R2 is zero.

Max Z P P2000 30001 2= +S.T. P P3 21 2+ 90# R1" – Resource

P P21 2+ 100# R2" – Resource

P1, P2 0$

Solution : Z . .P P S S2000 3000 0 01 2 1 2= + + +S.T. P P S3 21 2 1+ + 90= P P S21 2 2+ + 100= P 01$ , P 02$ , S 01$ , S 02$

First table :-

Cj 2000 3000 0 0

CB SB PB P1 P2 S1 S2

0 S1 90 3 2 " 1 0

0 S2 100 1 2 0 1

Zj 0 0 0 0

Z Cj j- 2000- 3000--

0 0

Second Table :-

Cj 2000 3000 0 0

CB SB PB P1 P2 S1 S2

3000 P2 45 3/2 1 1/2 0

0 S2 10 2- 0 1- 1

Zj 4500 3000 1500 0 " unit worth of R2

Z Cj j- 2500 0 1500 0

Page 23: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 11 Option (B) is correct.Since all 0Z Cj j $- , an optimal basic feasible solution has been attained. Thus, the optimum solution to the given LPP is

MaxZ 2000 0 3000 45# #= + .135000Rs= with P 01= and P 452 =

Sol. 12 Option (C) is correct.Given, forecast for February Ft 1- 10275=Demand for February Dt 1- 12000=Smoothing coefficient a .0 25=Which is The forecast for the next period is given by,

Ft ( ) ( )D F1t t1 1#a a= + −− −

. ( ) ( . ) ( )0 25 12000 1 0 25 10275# #= + − .10706 25= 10706-

Hence, forecast for the month of march is 10706.

Sol. 13 Option (B) is correct.Little’s law is a relationship between average waiting time and average length of the queue in a queuing system.The little law establish a relation between Queue length ( )Lq , Queue waiting time ( )Wq and the Mean arrival rate l.

So, Lq Wql=

Sol. 14 Option (A) is correct.Vehicle manufacturing assembly line is an example of product layout.A product-oriented layout is appropriate for producing one standardized product, usually in large volume. Each unit of output requires the same sequence of operations from beginning to end.

Sol. 15 Option (D) is correct.Simplex method provides an algorithm which consists in moving from one point of the region of feasible solutions to another in such a manner that the value of the objective function at the succeeding point is less (or more, as the case may be) than at the preceding point. This procedure of jumping from one point to another is then repeated. Since the number of points is finite, the method leads to an optimal point in a finite number of steps.Therefore simplex method only uses the interior points in the feasible region.

Sol. 16 Option (C) is correct.

Given : D 10000=Ordering cost Co .Rs 300= per order

Holding cost Ch .Rs 40= per frame per year

Unit cost, Cu .Rs 200=

EOQ CC D2

402 300 10000

h

o # #= = 387 units-

Total cost = Purchase cost + holding cost + ordering cost

For EOQ 387 units=

Total cost D C Q C QD C2u h o# # #= + +

Where Q 387 unitsEOQ= =

Page 24: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Total cost 1000 200 40 3000 2387

38710000

# # #= + +

2000000 7740 7752= + + .Rs 2015492=Now supplier offers %2 discount if the order quantity is 1000 or more.

For Q 1000 units=

Total cost 10000 (200 0.98) 40 30021000

100010000

## # #= + +

1960000 20000 3000= + + .Rs 1983000=Supplier also offers %4 discount if order quantity is 2000 or more.

For Q 2000 units=

Total cost 10000 (200 0.96) 40 30022000

200010000

# # # #= + +

1920000 40000 1500= + + .Rs 1961500=It is clearly see that the total cost is to be minimized, the retailer should accept %4 discount.

Sol. 17 Option (D) is correct.We have to draw a arrow diagram from the given data.

Here Four possible ways to complete the work.

PDah TCaDl duorDaiCon (dDys)

(i) P R T V- - - T 3 5 7 2 17= + + + =

(ii) Q S T V- - - T 4 5 7 2 18= + + + =

(iii) Q S U W- - - T 4 5 5 10 24= + + + =

(iv) P R U W- - - T 3 5 5 10 23= + + + =

The critical path is the chain of activities with the longest time durations.

So, Critical path Q S U W= − − −

Sol. 18 Option (C) is correct.In the Earliest due date (EDD) rule, the jobs will be in sequence according to their earliest due dates.Table shown below :

Job Processing time (in days)

Due date Operation start Operation end

1 4 6 0 0 4 4+ =

2 7 9 4 7 14 1+ =

4 8 17 11 1 8 11 9+ =

3 2 19 19 2 219 1+ =

Page 25: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

We see easily from the table that, job 2, 4, & 3 are delayed.Number of jobs delayed is 3.

Sol. 19 Option (D) is correct.By using the shortest processing time (SPT) rule & make the table

JCb PorCcessiong aioe(ion dDys)

lCw aioe ue dDae TorDdioness

SaDora Eond

3 2 0 2 19 0

1 4 2 2 4 6+ = 6 0

2 7 6 6 7 13+ = 9 4

4 8 13 13 8 21+ = 17 4

So, from the table

Total Tradiness 4 4 8= + =

Sol. 20 Option (A) is correct.

Under the conditions of uncertainty, the estimated time for each activity for

PERT network is represented by a probability distribution. This probability

distribution of activity time is based upon three different time estimates made

for each activity. These are as follows.to = the optimistic time, is the shortest possible time to complete the activity if

all goes well.

tp = the pessimistic time, is the longest time that an activity could take if every

thing goes wrong

tl = the most likely time, is the estimate of normal time an activity would take.

The expected time ( )te of the activity duration can be approximated as the arithmetic mean of ( )/t t 2o p+ and t2 l . Thus

( )te ( )

tt t

31 2 2l

o p= + +: D

t t t64o l p= + +

Sol. 21 Option (D) is correct.Exponential smoothing method of forecasting takes a fraction of forecast error into account for the next period forecast.The exponential smoothed average ut , which is the forecast for the next period ( )t 1+ is given by.

ut (1 ) .... (1 ) .....y y yt tnt n1 3a a a a a= + − + − +− −

(1 )[ (1 ) ... (1 ) ...]y y y y ( )t t tnt n1 2 1a a a a a a a= + − + − + + − +− − − −

( )u y ut t t1 1a= + −− −

u et t1 a= +−

where ( )e y ut t t 1= − − is called error and is the difference between the least observation, yt and its forecast a period earlier, ut 1- .The value of a lies between 0 to 1.

Page 26: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 22 Option (D) is correct.Given objective function Zmax x x3 21 2= + and constraints are

x1 4# ...(i)

x2 6# ...(ii)

x x3 21 2+ 18# ...(iii)

x1 0$

x2 0$Plot the graph from the given constraints and find the common area.

Now, we find the point of intersection &E F .

For E , x x3 21 2+ 18=E is the intersection point of equation. (ii) & (iii)

x2 6=So, x3 121+ 18= x1 2=For F , x x3 21 2+ 18= x1 4=So, x3 4 2 2# + 18= x2 3=Hence, ( , )E 2 6 or ( ,3)F 4

Now at point ( , )E 2 6 Z 3 2 2 6# #= + 18=At point ( , )F 4 3 Z 3 4 2 3# #= + 18=The objective function and the constraint (represent by equation (iii)) are equal.Hence, the objective function will have the multiple solutions as at point &E F , the value of objective function ( )Z x x3 21 2= + is same.

Sol. 23 Option (C) is correct.

In figure, ROP Re intorder po= LT Lead Time days8= = TT 365Total Time days= = q 2555stock level units= =Let the reorder quantity be x .Now from the similar triangles &ABC BDED D

TTq LT

x=

& 3652555 x

8=

Page 27: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

x 8 56 Units3652555

#= =

AlaeoronDae MeahCd Demand in a year D 2555 Units= Lead time T 8 days=Now, Number of orders to be placed in a year

N .Lead Time

Number of days in a year=

orders8365=

Now, quantity ordered each time or reorder point.

Q Number of ordersDemand in a years=

83652555= 56 Units=

Sol. 24 Option (A) is correct.In shortest processing time rule, we have to arrange the jobs in the increasing order of their processing time and find total flow time.So, job sequencing are I - III - V - VI - II - IV

JCbs PorCcessiong Tioe (dDys) lCw aioe (dDys)

I 4 4

III 5 4 5 9+ =

V 6 9 6 15+ =

VI 8 15 8 23+ =

II 9 23 9 32+ =

IV 10 32 10 42+ =

Now Total flow time T 4 9 15 23 32 42= + + + + + 125=

Average flow time Number of jobsTotal flow time=

Taverage 6125= 20.83 days=

Page 28: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 25 Option (D) is correct.Make the table and calculate the excepted time and variance for each activity

Acaiviay Opaioisaicaioe (dDys)to

MCsa likelyaioe (dDys)tm

Pessioisaicaioe (dDys)tp

Expecaed Tioe (dDys)

tt t t

64

eo m p= + +

VDoriDoncet t6

p o22

s = −b l

1 - 2 1 2 36

1 8 3 2+ + = 63 1

912− =b l

1 - 3 5 6 76

5 24 7 6+ + = 67 5

912− =b l

1 - 4 3 5 76

3 20 7 5+ + = 67 3

942− =b l

2 - 5 5 7 96

5 28 9 7+ + = 69 5

942− =b l

3 - 5 2 4 66

2 16 6 4+ + = 66 2

942− =b l

5 - 6 4 5 66

4 20 6 5+ + = 66 4

912− =b l

4 - 7 4 6 86

4 24 8 6+ + = 68 4

942− =b l

6 - 7 2 3 4 362 12 4+ + = 6

4 2912− =b l

Now, the paths of the network & their durations are given below in tables.

PDahs Expecaed Tioe duorDaiCon (ion dDys)

i Path 1-3-5-6-7 T 6 4 5 3 18= + + + =

ii Path 1-2-5-6-7 T 2 7 5 3 17= + + + =

iii Path 1-4-7 T 5 6 11= + =

Since path 1-3-5-6-7 has the longest duration, it is the critical path of the network and shown by dotted line.Hence,The expected duration of the critical path is 18 days.

Sol. 26 Option (C) is correct.The critical path is 1-3-5-6-7Variance along this critical path is,

2s 1 32

3 52

5 62

6 72s s s s= + + +− − − −

91949191= + + + 9

7=

Page 29: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

We know,

Standard deviation ( )Variance 2s=

.97 0 88= =

The most appropriate answer is 0.77.

Sol. 27 Option (C) is correct.The most common distribution found in queuing problems is poisson distribution. This is used in single-channel queuing problems for random arrivals where the service time is exponentially distributed.Probability of n arrivals in time t

P !( )

nT en T:l=

l−

where 0,1,2.......n =

So, Probability density function of inter arrival time (time interval between two consecutive arrivals)

( )f t e t:l= l−

Sol. 28 Option (A) is correct.Total inventory cost will be minimum, when the holding cost is minimum. Now, from the Johnson’s algorithm, holding cost will be minimum, when we process the least time consuming job first. From this next job can be started as soon as possible.Now, arrange the jobs in the manner of least processing time.T -S -Q -R-P or T -Q -S -R-P (because job Q and S have same processing time).

Sol. 29 Option (D) is correct.In a transportation problem with m origins and n destinations, if a basic feasible solution has less than m n 1+ − allocations (occupied cells), the problem is said to be a degenerate transportation problem.So, the basic condition for the solution to be optimal without degeneracy is.

Number of allocations m n 1= + −

Sol. 30 Option (D) is correct.

Here ( )F t1 & ( )F t2 = Forecastings

m1 & m2 = Number of weeksA higher value of m results in better smoothing. Since here m m> 21 the weightage of the latest demand would be more in ( )F t2 .Hence, ( )F t2 will attain the value of d2 before ( )F t1 .

Sol. 31 Option (C) is correct.There are two paths to reach from node to nodeP G .(i) Path P -Q -G (ii) Path P -R-G

For Path P -Q -G ,

Length of the path SG S dQ QG= +

For path P -R-G ,

Length of the path SG S dR RG= +

So, shortest path SG ,Min S d S dQ QG R RG= + +" ,

Page 30: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 32 Option (C) is correct.From the product structure we see that 2 piece of R is required in production of 1 piece P .So, demand of R is double of P

Week eoDond( )P

eoDond( )R

IonveonaCory levelProduction DemandI = −

1 1000 2000 R 2000-

2 1000 2000 R2 4000-

3 1000 2000 R3 6000-

4 1000 2000 R4 8000-

5 1200 2400 R5 10400-

6 1200 2400 R6 12800-

We know that for a production system with bottleneck the inventory level should be more than zero.So,

R6 12800- 0$For minimum inventory

R6 12800- 0= R6 12800= R 2133= 2200-

Hence, the smallest capacity that will ensure a feasible production plan up to week 6 is 2200.

Sol. 33 Option (B) is correct.The LP has an optimal solution that is not unique, because zero has appeared in the non-basic variable (x and y ) column, in optimal solution.

Sol. 34 Option (A) is correct.The general form of LP is

Max Z CX=Subject to AX B#And dual of above LP is represented by

Min Z B YT=Subject to A YT CT$

So, the dual is 6 6Min u v+Subject to 3 2u v+ 4$

Page 31: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

2 3u v+ 6$

,u v 0$

Sol. 35 Option (B) is correct.We have to make a table from the given data.

MConah PorCducaiCon (Pieces) eoDond Excess Cor shCora fCoro (pieces)

In regulartime

In over time

Regular Total

1 100 20 90 10 10 20 30+ =

2 100 20 130 30- 30 20 10− + =−

3 80 40 110 30- 30 40 10− + =

From the table,For 1st month there is no need to overtime, because demand is 90 units and regular time production is 100 units, therefore 10 units are excess in amount. For 2nd month the demand is 130 unit and production capacity with overtime is 100 20 120 units+ = , therefore 10 units (130 120 )10− = are short in amount, which is fulfilled by 10 units excess of 1st month. So at the end of 2nd month there is no inventory.Now for the 3rd month demand is 110 units and regular time production is 80 units. So remaining 110 80 30 units− = are produced in overtime to fulfill the demand for minimum cost of plan.

Sol. 36 Option (D) is correct.

Total annual cost cos cosAnnual holding t Annual ordering t= + Maximum level of inventory N 100=

So, Average inventory N2 50= =

Inventory carrying cost Ch .Rs per item per month10= .Rs per item per year10 12#= .Rs per item per year120=

So, Annual holding cost N C2 h#=

ChA 50 120#= .Rs item per year6000=And, Ordering cost Co per order100=

Number of orders in a year . order1 512=

8 order= So, Annual ordering cost

CoA .cosordering t per order no of orders#= 100 8#=

.Rs per order800=Hence, Total Annual cost 6000 800= +

.6800Rs=

Page 32: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 37 Option (B) is correct.Given :Number of items produced per moth

K 100 per month0=Number of items required per month

R 50 per month0= Lot size q0 1000=When backlog is not allowed, the maximum inventory level is given by,

Im KK R qo#= − 1000

1000 500 1000#= − 500=

Sol. 38 Option (B) is correct.Given :

Ch = Rs. 1 per item per week

Co = Rs. 100 per order

Requirements = 50 - 0 - 15 - 20 - 20Total cost is the cost of carrying inventory and cost of placing order.Case (I) Only one order of 105 units is placed at starting.

Weeks uDonaiay �Csa

IonveonaCory Used �Dororied fCorwDord Oordeor �Dororyiong TCaDl

1. 105 (ordered) 50 55 100 55 155

2. 55 0 55 0 55 55

3. 55 15 40 0 40 40

4. 40 20 20 0 20 20

5. 20 20 0 0 0 0

Total cost of plan 155 55 40 20= + + + 270 Rs= .Case (II) Now order is placed two times, 50 units at starting and 55 units after 2nd week.

Weeks uDonaiay �Csa

IonveonaCory Used �Dororied fCorwDord OordeoriongRsQ

�DororyiongRsQ

TCaDl RsQ

1. 50(ordered)

50 0 100 0 100

2. 0 0 0 0 0 0

3. 55(ordered)

15 40 100 40 140

4. 40 20 20 0 20 20

5. 20 20 0 0 0 0

Total cost of plan 100 140 20 260 .Rs= + + =Case (III) The order is placed two times, 65 units at starting and 40 units after 3rd week.

Page 33: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Weeks uDonaiay �Csa

IonveonaCory Used �DororiedfCorwDord

OordeoriongRsQ

�DororyiongRsQ

TCaDl RsQ

1. 65(ordered)

50 15 100 15 115

2. 15 0 15 0 15 15

3. 15 15 0 0 0 0

4. 40(ordered)

20 20 100 20 120

5. 20 20 0 0 0 0

Total cost of plan 115 15 120 250 .Rs= + + =Case (IV) Now again order is placed two times, 85 units at starting and 20 units after 4thweek.

Weeks uDonaiay �Csa

IonveonaCory Used �Dororied fCorwDord Oordeor �Dororyiong TCaDl

1. 85(ordered)

50 35 100 35 135

2. 35 0 35 0 35 35

3. 35 15 20 0 20 20

4. 20 20 0 0 0 0

5. 20(ordered)

20 0 100 0 100

Total cost of plan 135 35 20 100 290 .Rs= + + + =So, The cost of plan is least in case (III) & it is 250 .Rs

Sol. 39 Option (B) is correct.

Given : l 8 per hour= µ 6 minper customer=

/customer hours660= 10 /customer hour=

We know, for exponentially distributed service time.Average number of customers in the queue.

Lq ( )#µλ

µ λλ= −

( )108

10 88

#= − .3 2=

Sol. 40 Option (C) is correct.MRP (Material Requirement Planning) :MRP function is a computational technique with the help of which the master schedule for end products is converted into a detailed schedule for raw materials and components used in the end product.Input to MRP(i) Master production schedule.

(ii) The bill of material

(iii) Inventory records relating to raw materials.

Page 34: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 41 Option (B) is correct.First finding the sequence of jobs, which are entering in the machine. The solution procedure is described below :By examining the rows, the smallest machining time of 6 hours on machine M2. Then scheduled Job P last for machine M2

After entering this value, the next smallest time of 7 hours for job U on machine M2. Thus we schedule job U second last for machine M2 as shown below

After entering this value, the next smallest time of 8 hours for job R on machine M1. Thus we schedule job R first as shown below.

After entering this value the next smallest time of 11 hours for job T on machine M1. Thus we schedule job T after the job R .

After this the next smallest time of 19 hours for job Q on machine M2. Thus schedule job Q left to the U and remaining job in the blank block.Now the optimal sequence as :

Then calculating the elapsed time corresponding to the optimal sequence, using the individual processing time given in the problem.The detailed are shown in table.

JCbsM1 M2

Ion Oua Ion Oua

R 0 8 8 8 13 21+ =

T 8 8 11 19+ = 21 21 14 35+ =

S 19 19 27 46+ = 46 46 20 66+ =

Q 46 46 32 78+ = 78 78 19 97+ =

U 78 78 16 94+ = 97 97 7 104+ =

P 94 94 15 109+ = 109 109 6 115+ =

We can see from the table that all the operations (on machine 1st and machine 2nd) complete in 115 hours. So the optimal make-span of the shop is 115 hours.

Sol. 42 Option (C) is correct.

Given : D 2500= units per year

Co = Rs. 100 per order

Page 35: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Ch %25= of unit priceCase (I) : When order quantity is less than 500 units.

Then, Unit price 10 .Rs=and Ch %25= of 10 2.5 .Rs=

EOQ .CC D2

2 52 100 2500

h

0 # #= =

Q 447.21 447 units-=

Total cost cosunit tD Q c QD c2 h o# # #= + +

.2500 10 2447 2 5 447

2500 100# # #= + +

. .25000 558 75 559 75= + + 26118 .Rs=Case (II) : when order Quantity is 500 units. Then unit prize 9 .Rs= and ch 25% 9 2.25 .of Rs= = Q 500 units=

Total cost .2500 9 2500 2 25 500

2500 100# # #= + +

22500 562.5 500= + + 23562.5 .Rs=So, we may conclude from both cases that the optimum order quantity must be equal to 500 units.

Sol. 43 Option (C) is correct.Given, In figure

Step (I) : Reduce the matrix :In the effectiveness matrix, subtract the minimum element of each row from all the element of that row. The resulting matrix will have at least one zero element in each row.

Step (II) : Mark the column that do not have zero element. Now substract the minimum element of each such column for all the elements of that column.

Step (III) : Check whether an optimal assignment can be made in the reduced

Page 36: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

matrix or not.For this, Examine rows successively until a row with exactly one unmarked zero is obtained. Making square ( )4 around it, cross ( )# all other zeros in the same column as they will not be considered for making any more assignment in that column. Proceed in this way until all rows have been examined.

In this there is not one assignment in each row and in each column.Step (IV) : Find the minimum number of lines crossing all zeros. This consists of following substep(A) Right marked ( ) the rows that do not have assignment.

(B) Right marked ( ) the column that have zeros in marked column (not already marked).

(C) Draw straight lines through all unmarked rows and marked columns.

Step (V) : Now take smallest element & add, where two lines intersect.No change, where single line & subtract this where no lines in the block.

So, minimum cost is 120 140 125= + + 385=

Sol. 44 Option (C) is correct.

Total time used 7 9 7 10 9 6= + + + + + min48= Number of work stations 6= Maximum time per work station (cycle time) 10 min=We know,

Line efficiency Lh

Number of work stations cycle timeTotal time used

#=

Lh .6 1048 0 8#

= = %80=

Page 37: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 45 Option (A) is correct.

Profit per unit sold 90 70 20 .Rs= − = Loss per unit unsold item 70 50 20 .Rs= − =Now consider all the options :

�Dses Uonias ion saCck

Uonia sCld( eoDond)

PorCfia PorCbDbiliay TCaDl porCfia

OpaiCon( )

2 2 2 20 40# = 0.1 4

OpaiCon (�) 3 2 2 20 1 20 20# #− = 0.1 2

3 3 3 20 60# = 0.35 21

23

OpaiCon(B)

4 2 2 20 2 20 0# #− = 0 0

4 3 3 20 1 20 40# #− = 0.35 14

4 4 4 20 80# = 0.35 28

42

OpaiCon (A) 5 2 2 20 3 20 20# #− =− 0.10 2-

5 3 3 20 2 20 20# #− = 0.35 7

5 4 4 20 1 20 60# #− = 0.35 21

5 5 5 20 100# = 0.20 20

46

Thus, For stock level of 5 units, profit is maximum.

Sol. 46 Option (D) is correct.We have to make a network diagram from the given data.

For simple projects, the critical path can be determined quite quickly by enumerating all paths and evaluating the time required to complete each.There are three paths between anda f . The total time along each path is(i) For path a -b-d - f

Tabdf 30 40 25 20 115 days= + + + =(ii) For path a -c -e - f

Tacef 30 60 45 20 155 days= + + + =(iii) For path a -b-e - f

Tabef 30 40 45 20 135 days= + + + =Now, path a -c -e - f be the critical path time or maximum excepted completion time 155 daysT =

Page 38: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 47 Option (A) is correct.The critical path of the network is a -c -e - f .Now, for variance.

TDsk VDoriDonce (days2)

a 25

c 81

e 36

f 9

Total variance for the critical path

Vcritical 25 81 36 9= + + +

151 days2=We know the standard deviation of critical path is

s Vcritical= days151=

Sol. 48 Option (D) is correct.In operation process chart an assembly activity is represented by the symbol O

Sol. 49 Option (C) is correct.Gives :Sales of product during four years were 860, 880, 870 and 890 units.

Forecast for the fourth year u4 876=Forecast for the fifth year, using simple exponential smoothing, is equal to the forecast using a three period moving average.

So, u5 ( )31 880 870 890= + +

u5 880 unit=By the exponential smoothing method.

u5 ( )u x u4 4 4a= + − 880 ( )876 890 876a= + − 4 ( )14a=

a 144

72= =

Sol. 50 Option (A) is correct.Given : 4/hourl = , 4/hourµ=

The sum of probability Pnn

n

0

10

=

=

/ 1= n 10=

.....P P P P0 1 2 10+ + + 1=

In the term of traffic intensity r µλ= & 14

4r = =

So,

......P P P P P0 020

30

100r r r r+ + + + 1= , and so onP P P P1 0 2

20r r= =

( ........)P 1 1 10 + + + 1= P 110# 1=

P0 111=

Page 39: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Hence, the probability that a person who comes in leaves without joining the queue is,

P11 P110:r=

P1 1 11111

#= 111=

Sol. 51 Option (B) is correct.For economic point of view, we should calculate the total cost for all the four processes.

Total cost cos cosFixed t Variable t Number of piece#= +For process (I) :

Fixed cost 20 .Rs= Variable cost 3 .Rs per piece= Number of pieces 100= Total cost 0 3 1002 #= + 320 .Rs=For process (II) :

Total cost 50 1 100#= + 150 .Rs=For process (III) :

Total cost 40 2 100#= + 240 .Rs=For process (IV) :

Total cost 10 4 100#= + 410 .Rs=Now, we can see that total cost is minimum for process (II). So process (II) should choose for economic point of view.

Sol. 52 Option (A) is correct.

Given : Rating factor %120= Actual time Tactual min8= Normal time Tnormal actual time Rating factor#=

Tnormal 8 100120

#= . min9 6=

10% allowance is allowed for this operation.So, standard time,

T tans dard T

1 10010

normal=−

..0 99 6= 10.67min=

Hence, standard production rate of the weld joint

.10 678 60#= 45 units=

Sol. 53 Option (D) is correct.

The expected value of the lead time demand

. . . .80 0 20 100 0 25 120 0 30 140 0 25# # # #= + + + 112=Reorder level is 1.25 time the lead time demand.

So, reorder value .1 25 112#= 140=Here both the maximum demand or the reorder value are equal.

Hence, service level %100=

Page 40: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 54 Option (C) is correct.The 3 activity need to be crashed to reduce the project duration by 1 day.

Sol. 55 Option (C) is correct.First we have to make a transportation model from the given details.

We know,Basic condition for transportation model is balanced, if it contains no more than m n 1+ − non-negative allocations, where m is the number of rows and n is the number of columns of the transportation problem.

So, Number of supply point (allocations) m n 1= + − 2 2 1 3= + − = Number of demand points 4 ( . )No of blank blocks= Total supply or demand 50 40 90= + =

Sol. 56 Option (B) is correct.Given : Objective function Z X X1 2= +From the given corners we have to make a graph for andX X1 2

From the graph, the constraint X X 51 2#+ has no effect on optimal region.Now, checking for optimal solution

PCiona Z X X1 2= +

(i) ( , )O 0 0 Z 0=

(ii) (2,0)A Z 2 0 2= + =

(iii) ( , )B 0 2 Z 0 2 2= + =

(iv) ( / , / )C 4 3 4 3 / / /Z 4 3 4 3 8 3= + =

The optimal solution occurs at point ( / , / )C 4 3 4 3

Sol. 57 Option (D) is correct.We know,The inequality constraints are changed to equality constraints by adding or subtracting a non-negative variable from the left-hand sides of such constraints.

Page 41: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

These variable is called slack variables or simply slacks.They are added if the constraints are ( )# and subtracted if the constraints are ( ) .$ These variables can remain positive throughout the process of solution and their values in the optimal solution given useful information about the problem.Hence, Optimum dual variables are andv v1 2.

Sol. 58 Option (B) is correct.PERT (Programme Evaluation and Review Technique) uses even oriented network in which successive events are joined by arrows.Float is the difference between the maximum time available to perform the activity and the activity duration. In PERT analysis a critical activity has zero float.

Sol. 59 Option (C) is correct.Given :

Forecast sales for December ut 25= Actual sales for December Xt 20= Exponential smoothing constanta .0 2=We know that, Forecast sales for January is given by

ut 1+ [ ]u X ut t ta= + − . ( )25 0 2 20 25= + − . ( )25 0 2 5#= + − 25 1= − 24=Hence, Forecast sales for January 2003 would be 24.

Sol. 60 Option (C) is correct.For product P : 100 unitsD = , 50 ./Rs orderCo = , 4 ./ /Rs unit yearCh =Economic order quantity (EOQ) for product P ,

( )EOQ P CC D2h

o=

( )EOQ P 42 50 100# #= 2500 50= = ...(i)

For product Q : 400 UnitsD = 50 .Rs orderCo = , 1 . /Rs Unit yearCh =EOQ For Product Q ,

( )EOQ Q CC D2h

o=

12 50 400# #= 40000 200= = ...(ii)

From equation (i) & (ii),

( )( )EOQEOQ

Q

P 20050

41= =

( ) :( )EOQ EOQP Q :1 4=

Sol. 61 Option (D) is correct.Let, The standard machine tool produce x1 number of components.For standard machine tool,

cosTotal t

.cos cosFixed t Variable t Number of components#= +

( )TC SMT x6030

6022 2001# #= +: D

x6030 200 60

22 2001# # #= + x100 3220

1= + ...(i)

Page 42: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

If automatic machine tool produce x2 Number of components, then the total cost for automatic machine tool is

( )TC AMT 2 x605 8002= +b l

x1600 3200

2= + ....(ii)

Let, at the breakeven production batch size is x and at breakeven point.

( )TC SMT TCAMT

= ^ h

x100 3220+ 1600 00x

32= +

x x3220

3200- 1600 100= −

x320 1500=

x 201500 3#= 225=

So, breakeven production batch size is 225.

Sol. 62 Option (D) is correct.Given :

Total time T 16 hours= 16 60#= min960=Actual working time was 90% of total time

So, ,Actual time Tactual 90% 960of=

10090 960#= ,

864 minTactual =

Performance rating was 120 percent.

So, Normal time, Tnormal 120% of 864=

100120 864#= . min1036 8=

Allowance is 20% of the total available time.

So total standard time T tans dard T1normal

10020=

−^ h

..

..

1 0 21036 8

0 81036 8= − =

min1296= Number of joints soldered, N 108=Hence,

Standard time for operation 1081296= min12=

Sol. 63 Option (A) is correct.Given :

Number of units produced in a day 80 units= Working hours in a day 8 hours=Now, Time taken to produce one unit is,

T 60808#= min6=

Page 43: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Acaiviay SaDondDord aioe (oion) NCQ Cf wCork saDaiCons ( . / )S T T

M. Mechanical assembly 12 12/6 2=

E. Electric wiring 16 16/6 2.666 3= =

T. Test 3 3/6 0.5 1= =

Number of work stations are the whole numbers, not the fractions.So, number of work stations required for the activities , andM E T would be 2, 3 and 1, respectively.

Sol. 64 Option (A) is correct.Given :

Mean arrival rate l 3 per day= Mean service rate µ 6 per day=We know that, for first come first serve queue.Mean waiting time of an arrival,

t ( )µ µ λλ= −

( )6 6 33= − day6

1=

Sol. 65 Option (A) is correct.Solve this problem, by the linear programming model.We have to make the constraints from the given conditions.For production conditions

P Q2+ 2000# ...(i)For raw material

P Q+ 1500# ...(ii)For electric switch

Q 600# ...(iii)For maximization of profit, objective function

Z P Q3 5= + ...(iv)From the equations (i), (ii) & (iii), draw a graph for toy andP Q

Line (i) and line (ii) intersects at point A, we have to calculate the intersection point.

P Q2+ 2000= P Q+ 1500=

Page 44: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

After solving there equations, we get ( , )A 1000 500For point B ,

P Q2+ 2000= Q 600= P 2000 1200 800= − =So, ( , )B 800 600Here shaded area shows the area bounded by the three line equations (common area)This shaded area have five vertices.

Veoraices PorCfia Z P Q3 5= +

(i) 0(0, 0) Z 0=

(ii) (10 0, 500)A 0 Z 3000 2500 5500= + =

(iii) ( , )B 800 600 Z 2400 3000 5400= + =

(iv) ( , )C 0 600 Z 3000=

(v) ( , )D 1500 0 Z 4500=

So, for maximization of profit

P 1000= from point(ii)

Q 500=

Sol. 66 Option (C) is correct.Given : 1000 unitsD = , 100/orderCo = , 100 /unit yearCh =

400 .RsCs =We know that, optimum level of stock out will be,

.S O CDC

C CC2

h

o

h s

s#= +

.S O 1002 1000 100

100 400400

## #= +

44.72 0.895#= 40=

Sol. 67 Option (A) is correct.The symbol used for transport in work study is given by, &

Sol. 68 Option (A) is correct.Given : For machine M1 :

Fixed cost 100= Rs.

Variable cost 2= Rs. per pieceFor machine M 2 :

Fixed cost 200 .Rs= Variable cost 1 .Rs per piece=Let, n number of units are produced per machine, when both the machines are to be used concurrently.We know that,

Total cost

cos cosFixed t Variable t Number of units#= +For M1, Total cost of production n100 2#= +

Page 45: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

For M 2, Total cost of production n200= +Hence,Total cost of production on machine &M M1 2 is

n n100 2 200= + + + n300 3= +We know, Breakeven point is the point, where total cost of production is equal to the total sales price.Assuming that Number of units produced are less than 800 units and selling price is Rs. 3.50 per unit.So at breakeven point,

n300 3+ . ( )n n3 50= + n300 3+ . n3 50 2#= 300 n4=

n 4300= 75 units=

Sol. 69 Option (C) is correct.Warden checks the student 11 occasions a day during the study hours over a period of 10 days.So, Total number of observations in 10 days.

11 10 110 observations#= =Study hours as 8.00 pm to 10.30 pm.So, total study hours in 10 days

.2 5 10#= 25 .hours=Number of occasions when student studying 71=So, Probability of studying

P .Total observations

No of observations when student studying=

.11071 0 645= =

Hence,Minimum hours of his study during 10 day period is

T Total study hours in daysP 10#= .0 645 25#= 16.1 hours=

Sol. 70 Option (B) is correct.We know, from the exponential and smoothing average method, the exponential smoothed average u( )t 1+ which is the forecast for the next period ( )t 1+ is given by

u( )t 1+ (1 ) ....... (1 ) .......u u ut tnt n1 3a a a a a= + − + − +− −

Now, for sales of the fifth month put t 4= in the above equation,

So, u5 ( ) ( ) ( )u u u u1 1 14 322

31a a a a a a a= + − + − + −

where , , 70,68,82, 95and are and respectivelyu u u u1 2 3 4 and .0 4a =Hence u5 0.4 95 0.4(1 0.4)82 0.4(1 0.4) 682

# #= + − + − 0.4(1 0.4) 703

#+ − u5 . . .38 19 68 9 792 6 048= + + + .73 52=

Sol. 71 Option (C) is correct.Given :

D 800000= per annum

Page 46: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Co 1200 .Rs= Ch 120= per piece per annum

We know that,

Economic order quantity (EOQ ) N CC D2h

o= =

N 1202 1200 800000# #= 16 106#=

4 10 40003#= =

Sol. 72 Option (A) is correct.Given : Objective function, Z x x2 51 2= +and x x31 2+ 40#

x x3 1 2+ 24#

x x1 2+ 10#

x1 0> x2 0>First we have to make a graph from the given constraints. For draw the graph, substitute alternatively &x x1 2 equal to zero in each constraints to find the point on the &x x1 2 axis.Now shaded area shows the common area. Note that the constraint x x3 401 2#+ does not affect the solution space and it is the redundant constraint. Finding the coordinates of point G by the equations.

x x3 1 2+ 24= x x1 2+ 10=Subtract these equations,

(3 ) 0x x1 1− + 24 10= − x2 1 14= & 7x1= x2 x10 1= − 10 7= − 3=So, point ( , )G 7 3So, maximum profit which can meet the constraints at ( , )G 7 3 is

Zmax 2 7 5 3# #= +

14 15= + 29=

Sol. 73 Option (C) is correct.The various path and their duration are :-

Page 47: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

PDah uorDaiCon (dDys)

A-D -L 2 10 3 15+ + =

A-E -G -L 2 5 6 3 16+ + + =

A-E -H 2 5 10 17+ + =

B -H 8 10 18+ =

C -F -K -M 4 9 3 8 24+ + + =

C -F -H 4 9 10 23+ + =

A-E -K -M 2 5 3 8 18+ + + =

B -G -L 8 6 3 17+ + =

B -K -M 8 3 8 19+ + =

C -F -G -L 4 9 6 3 22+ + + =

Here maximum time along the path C -F -K -M . So, it is a critical path and project can be completed in 24 days.

Sol. 74 Option (A) is correct.The principal of motion economy are used while conduction a method study on an operation.Method study consist of the sequence of operation, which are performing on a machine. From the sequencing, the idle time of the machine reduced to a certain amount and the operation becomes faster and smooth. Also the productivity of the plant increases by the principle of motion economy.

Sol. 75 Option (B) is correct.

Standard Time Normal time Allowance= +

Sol. 76 Option (B) is correct.

Percentage Error E %20= or 0.20

Standard deviation S ( )n

E E1#= −

where n = No. of observation

S . ( . )100

0 20 1 0 20= − .0 04=

For %95 confidence level, 2!s =So, upper control limit UCL E S#s= + . . .0 20 2 0 04 0 28#= + = Lower control Limit LCL E S#s= − . . .0 20 2 0 04 0 12#= − =Hence %95 confidence interval of this estimate is (0.12, 0.28)

Sol. 77 Option (D) is correct.

Given : Co 200 Rs= D 4000 units= per annum

Ch %10= of 100 10 Rs= per annumThe Economic order quantity is,

EOQ CC D2h

o=

400 unit102 200 4000# #= =

Page 48: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

Sol. 78 Option (C) is correct.Given :

Average time between arrivals min10=Mean arrival rate (Number of arrivals per unit time) 6 per hourl = Average time between call min3=

Mean service rate µ 20 per hour360= =

So, the probability that an arrival does not have to wait before service is,

PO 1 µλ= − . .1 20

6 1 0 3 0 7= − = − =

Sol. 79 Option (B) is correct.

Total supply 50 40 60 150 units= + + = Total demand 20 30 10 50 110 units= + + + =In this question, the total availability (supply) may not be equal to the total demand, i.e.,

aii

m

1=/ bj

j

n

1

!=/

Such problems are called unbalanced transportation problems.Here total availability is more than the demand. So we add a dummy destination to take up the excess capacity and the costs of shipping to this destination are set equal to zero.So, a dummy destination of capacity 40 unit is needed.

Sol. 80 Option (B) is correct.In PERT analysis, a Beta distribution is assumed because it is unimodal, has non-negative end points, and is approximately symmetric.Here three parallel paths are given. But the critical path is one with the longest time durations.Two paths have same time duration of 12.

So, mean 12=The PERT analysis has a beta ( )b distribution and Standard deviation variance= 4 2= = .

Sol. 81 Option (D) is correct.Production flow analysis (PFA) is a comprehensive method for material analysis, Part family formation, design of manufacturing cells and facility layout design. These informations are taken from the route sheet.

Sol. 82 Option (D) is correct.The simple moving average method can be used if the underlying demand pattern is stationary. This method include new demand data in the average after discarding some of the earlier demand data.

Let mt = moving average at time t

yt = demand in time t and

n = moving average period

mt 1+ ny yt t n1 1= −+ − +

Sol. 83 Option (D) is correct.Given : Mean cycle time min10=The workers performing at %90 efficiency.

Page 49: 101 Industrial Engineering

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

GATE SOLVED PAPER - ME InDuSTRIAL EnGInEERInG

GATE Previous Year Papers Solved by Team GATESCORE

www.gatescore.in www.gatescore.in

So, Normal time min10 10090 9#= =

Allowance %10= Standard time = Normal time + Allowance

9 9 10010

#= + . . min9 0 9 9 9= + =

***********