10 Points of Lift Plan Development

Host: Mike Parnell

President/CEO, ITI

ASME B30 Vice Chair (Cranes & Rigging)

ASME P30 Chair (Lift Planning)

Page 2: 10 Points of Lift Plan Development

A world leader in crane and rigging training and consulting.

WHO WE ARE

We Rig It Right!

2

Page 3: 10 Points of Lift Plan Development

Serving a Variety of Industries

•Aerospace

•Chemicals

•Construction

•DOD

•DOE

•Electric Utility

•Hydro

•Manufacturing

WHO WE ARE

• Maritime

• Mining

• Nuclear

• Oil & Gas

• Pulp & Paper

• Railroad

• Shipbuilding

• Wind Energy

3

Page 4: 10 Points of Lift Plan Development

The World's Greatest

Organizations Trust their

Crane & Rigging

Operations

to ITI's Expertise

OUR CUSTOMERS

4

Page 5: 10 Points of Lift Plan Development

SHOWCASE WEBINAR SERIES

Past Presentations:

Cranes, Rigging & Your Organization

Effective Crane & Rigging Training Methods for Your Employees

10 Audit Points for Your Crane & Rigging Operations: An HSE Perspective

Tackling the Challenges of Training Site Supervisors, Lift Directors, and other Leaders

4 Major Lifting Considerations in Power Gen Environments

Rigging & Sling Failures: Case Studies & Solutions

Today's Presentation: 10 Points of Lift Plan Development

WEBINAR TRAINING COURSES

• Lift Director & Site Supervisor

• Critical Lift Planning

• Rigging Gear Inspection for

Supervisors

• Advanced Rigging:

Load Distribution & Center of

Gravity

• Advanced Rigging:

Multi-Crane Lifts & Load Turns

5

Page 6: 10 Points of Lift Plan Development

Mr. Parnell has a wealth of knowledge regarding cranes, rigging, and lifting activities throughout a variety of industries.

•30+ years learning about wire rope, rigging, load handling, and lifting activities.

•Vice Chair of the ASME B30 Main Committee which sets the standards in the US for cranes and rigging

•Chair of the ASME P30 Main Committee which sets the standards for lift planning.

ASME standards are also adopted by many countries around the world.

MIKE PARNELL – ABOUT YOUR HOST

The views expressed in this presentation are that of ITI and are not necessarily the views of the ASME or any of its committees.

6

Page 7: 10 Points of Lift Plan Development

The Lift Plan

7

Page 8: 10 Points of Lift Plan Development

Weight, CG, dimensions and source

Shifting components?

Evaluate / verify the attachment points are suitable for load handling, while maintaining load integrity

THE LOAD

8

Page 9: 10 Points of Lift Plan Development

Identify LHE capacity and

configuration

Dynamics, environmental,

load eccentricities

LHE meets manufacturers',

regulatory and site

requirements

Proper set-up, erection, installation and

dismantle procedures

LOAD HANDLING EQUIPMENT

9

Page 10: 10 Points of Lift Plan Development

Method

Capacity

Dynamic, environmental, CG-to-pick point

Equipment meets regulations/ site requirements

Procedure to install and remove

Rigging protection; consider temperature, chemical, D/d, edges, abrasion, load turning

THE RIGGING

10

Page 11: 10 Points of Lift Plan Development

Load movement and travel paths

Free from inadvertent contact

Dynamics, environmental eccentricities

Personnel positions; spotters, signalers, tag liners, blocking, cribbing or connecting crew

LHE and LOAD MOVEMENT

11

Page 12: 10 Points of Lift Plan Development

Lift Director

Site Supervisor

LHE Owner

LHE User

Lift Engineer

Lift Planner

Soils Analyst

LHE Operator

Qualified Rigger

Qualified Signaler

Regulatory Representative

Load Manufacturer Representative

Rigging Equipment Representative

Site Safety Officer

LHE Spotters

Load Spotters

PERSONNEL TRAINING & QUALIFICATION

12

Page 13: 10 Points of Lift Plan Development

Scope of work

Access, travel path, egress for LHE and load

Foundation; compaction tests, soils analysis, structures, vaults, voids, backfill

Load landing point

SITE

13

Page 14: 10 Points of Lift Plan Development

Suitable communication; hand / voice / video / horns / lights

Backup plan

COMMUNICATION

14

Page 15: 10 Points of Lift Plan Development

Vehicular traffic

Potential interference from other activities

Barricades, guards or physical measures to restrict interference

SITE CONTROL

15

Page 16: 10 Points of Lift Plan Development

Response teams

I.D. type of hazard

Recommended action

Contact and communication

CONTINGENCY PLANS

16

Page 17: 10 Points of Lift Plan Development

Site Plan

Responders

Ensure the rigging team understands

EMERGENCY ACTION PLAN

17

Page 18: 10 Points of Lift Plan Development

Review activity

Handling sequence

Personnel assignments

Questions/solutions

Review

Sign-off

PRE-LIFT MEETING

18

Page 19: 10 Points of Lift Plan Development

LHE inspected

Load inspected

Rigging inspected

Personnel ready

Site inspected

EXECUTING CLP

19

Page 20: 10 Points of Lift Plan Development

Initiate the lift

During the lift proceed as planned or stop and adjust according to contingency or acceptable methods

If impossible to proceed, “all-stop” and secure load & LHE.

THE LIFT

20

Page 21: 10 Points of Lift Plan Development

After the lift review, inspect and update

POST LIFT REVIEW

21

Page 22: 10 Points of Lift Plan Development

Q&A