10 16 2014 1030 charles cauchy direct insertion ground loop heat exchanger

Upload: meghan-woods

Post on 07-Jul-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    1/24

    Direct Insertion Ground Loop

    Heat Exchanger

    Charles Cauchy

    October 15 - 16, 2014

    Slide 1 of 24

    IGSHPA Technical Conference & Expo

    Baltimore, Maryland

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    2/24

    Outline

    1. Challenge – Solution

    2. US DOE Program Goals

    3. Technology

    4. Thermal Test Results

    5. Technology Review

    6. Areas of Use

    7. Example System Costing

    8. Method Comparisons

    9. Conclusions10.Acknowledgements

    11.Closing

    Slide 2 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    3/24

    The Challenge

    • Biggest barrier to

    greater geothermal

    heat pump use

    Slide 3 of 24

    • High cost• Large area

    • Large & expensive

    equipment

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    4/24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    5/24

    Development Overview

    Awarded US Dept. of Energy Grant - 2013

    GOAL of Program:

    To develop a ground loop heat exchanger that can be:

    • Expediently inserted into the earth• Via the use of man-portable equipment• Resulting in low cost, space efficient ground loops for

    ground source heat pumps• Thermally testing the heat exchanger  

    Slide 5 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    6/24

    The Direct Insertion Ground Loop Heat Exchangeraddresses key barriers to wider GSHP adoption by:

    • Significantly reducing high installation costs for ground loops

    • Reducing space requirements for ground coupling (slinky

    field or large drilling equipment in densely built areas)

    • Greatly reducing ground cover disruption and providing a

    flexible grid structure for placement around obstacles

    •  Allows for angular ground loop placement enhancing under-

    structure installation or radial center point headering

    Potential Benefits

    Slide 6 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    7/24

    The Technology

    EarthSpar ™ 

    Core Concept – Part A

    Water Jets/Metal Driving Tip

    • Loosening soil

    • Lubricating insertion

    • Dislodging rocks

    • Displacement

    • Hard soil erosion

    • Deflection

    Slide 7 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    8/24

    The Technology

    Core Concept – Part B

    Concentric Tube DesignUp Pipe Flow

    Down Pipe Flow

    • Single Tube Heat Exchanger

    • With same flow rate achieve

    laminar flow in down-flow

    • Turbulent flow in up-flow

    • Improved thermal performance

    Slide 8 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    9/24

    The Technology

    Pressure Drop in 20ft. EarthSpar ™ 

    Coaxial Heat Exchanger

    Same cross-sectional area

    Slide 9 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    10/24

    The Technology

    Pressure Drop in 20ft. EarthSpar ™ 

    Coaxial Heat Exchanger

    Slide 10 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    11/24

    The Technology

    Slide 11 of 24

    Core Concept – Part C

    Insertion Platform

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    12/24

    The Technology

    Heat Exchanger Insertion

    • Insertion into varying soil types

    • Sand, sandy loam

    • Gravel, cobble

    • Clay

    • Subsurface boulder field (Insertion halted)

    • Insertion speed ~ 2 – 4 ft/min

    • Insertion for 24, 30ft heat exchangers ~ 6 hours at 2 ft/min

    [700 ft] 3 hours at 4 ft/min

    (total insertion time, including equipment placement ontargets, will be increased)

    • Extraction of heat exchanger – straightforward and rapid

    Slide 12 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    13/24

    Thermal Testing

    •  ASHRAE 1118-TRP

    • Inline water heating device

    • Precision Watt meter – energy-in

    • Input power control

    • Thermocouples – in-flow &

    out-flow temperatures

    • Flow meter – in-line

    • ~ 10°F ΔT• Wireless data acquisition

    20’ EarthSpar ™ Testing 

    Slide 13 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    14/24

    y = 2.2366ln(x) + 80.241

    Slope of Ave. Temp.

    0

    20

    40

    60

    80

    100

    120

       3  :   3   0  :   5   9   P   M

       4  :   0   6  :   0   0   P   M

       4  :   4   1  :   0   0   P   M

       5  :   1   6  :   0   1   P   M

       6  :   3   7  :   2   3   P   M

       7  :   1   2  :   2   4   P   M

       8  :   0   2  :   3   6   P   M

       8  :   3   7  :   3   7   P   M

       9  :   1   2  :   3   7   P   M

       9  :   0   8  :   5   7   A   M

       9  :   4   3  :   5   8   A   M

       1   0  :   1   8  :   5   8   A   M

       1   0  :   5   3  :   5   9   A   M

       1   1  :   2   8  :   5   9   A   M

       1   2  :   0   4  :   0   0   P   M

       1   2  :   3   9  :   0   0   P   M

       1  :   2   5  :   1   1   P   M

       2  :   0   0  :   1   2   P   M

       2  :   3   5  :   1   2   P   M

       3  :   1   0  :   1   3   P   M

       3  :   4   5  :   1   3   P   M

       4  :   2   0  :   1   4   P   M

       5  :   0   1  :   0   0   P   M

       5  :   3   6  :   0   1   P   M

       6  :   1   1  :   0   1   P   M

       8  :   4   7  :   1   2   P   M

       8  :   0   6  :   2   2   A   M

       8  :   4   4  :   4   1   A   M

       T   e   m   p   e   r   a   t   u   r   e

    Time ~ 41.5 Hours

    After 5 Hours Stabilization

    IN

    OUT

    Ave. Δ T

    Ambient

    Linear (IN)

    Linear (OUT)

    Log. (Ave. Δ T)

    Linear (Ambient)

    Thermal Testing

    Test Data

    Slide 14 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    15/24

    Thermal Testing

    Thermal conductivity: Line Source Method

    = 3.412 ×

    4 ×  

    = 3.412 ×56

    7.8 ×.66  = 2.249 Btu/hr-ft-°F 

    • 20W/ft heat rate

    • 17.8 ft of tested length – heat exchanger

    •  ~ 10°F ΔT (heated IN – earth cooled OUT)• Thermal insulation between down-flow & up-flow

    concentric tubes for 67% of length

    Slide 15 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    16/24

    0.96

    1.44

    2.00

    2.24 EarthSpar

    y = 850.06x-0.473 

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    0 0.5 1 1.5 2 2.5 3 3.5

       L   o   o   p   L   e   n   g   t    h    f   t

    Thermal k Btu/hr-ft-F

    Effect of Ground Loop Heat Exchanger Thermal

    Conductivity on Loop Length

    Performance Benefit

    Slide 16 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    17/24

    System Flexibility

    •  Angular insertions

    • Under structures

    • Radial loop field• Extraction - straightforward

    • Shallow water wells

    • Under structure races for

    utilities, communicationslines, water lines

    Slide 17of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    18/24

    • Water-jet technology

    • Soil displacement/insertion

    • Tangential obstruction dodging• One-step process

    • Concentric - High thermal performance

    •  Agile insertion platform – tight areas

    •  Angular insertion• Easily extract heat exchanger

    Technology Review

    Slide 18 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    19/24

     Areas of Use

    Where Drilling or Trenching May Be Superior

    • Where bedrock is close to the surface

    •  Areas/soils with closely spaced large rocks

    • Large commercial/industrial/institutional systems

    • Single source ground loop/non-distributed• Excavation already planned (i.e.. Parking lot)

    • Capital equipment (i.e.. Drilling rigs) on-site and can be

    amortized over many borings

    • Limited space (tons/ft2) – drilling excels

    EarthSpar ™ will not replace existing ground loop methodologies 

    EarthSpar ™ will be strong adjunct methodology in many applications

    Slide 19 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    20/24

    Cost Advantage

    Estimated Ground Loop Cost Comparison

    Standard Ground Loop $ vs. DIGLHE $4 ton example (700’ Vertical) 

    Boreholes DIGLHE 

    Drilling w/grout $9,100 $1,400 Insertion labor  

    Pipe $1,252 $2,240 

    Connection Pipe, Fittings $ 400 $1,000 

    Completion labor, etc. $1,100 $1,400 

    Total $11,852 $6,040 

    Slide 20 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    21/24

    Method Comparisons

    Low Cost

    LandscapePreservation

    Limited

     Access

    High

    Performance

    Drilling OtherEarth Moving

    Existing Loop

    Paradigms

    EarthSpar ™ 

    Slide21 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    22/24

    1. The EarthSpar ™ concept is a viable technology2. Core concepts were proven to work to drive pipe, displace soils

    and function even with obstructions (rocks)3. Insertion times (> 2 ft/min) allow for rapid placement of GSHP

    ground loops

    4. High thermal performance may lead to shorter lengths of heatsink in the ground than with conventional designs

    5. Small, mobile insertion equipment allows for ground loops to beplaced in space restrained areas

    6. Capital costs associated with ground loops (bore drilling andlarge horizontal field processes) are greatly reduced

    7. Project goals were met (rapid insertion & thermal testing)8. Can reduce ground loop installation cost by 50%9. Will expand GSHP market in residential & small commercial

    Conclusions

    Slide 22 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    23/24

    Special thanksto the U.S. Department of Energy and Bahman

    Hebibzadeh (DOE Program Manager) 

    for supporting the development of the EarthSpar ™Direct Insertion Ground Loop Heat Exchanger

    &

    Rex Ambs – Geofurnace LLC

    &

    IGSHPA

     Acknowledgements

    Slide 23 of 24

  • 8/18/2019 10 16 2014 1030 Charles Cauchy Direct Insertion Ground Loop Heat Exchanger

    24/24

    Charles Cauchy

    [email protected] 

    231-633-1702

    www.promethientgeo.com

    Slid 24 f 24

    mailto:[email protected]:[email protected]