1 status of hydrogen system development mice collaboration meeting, frascati, june 26-29, 2005 yury...

29
1 Status of Hydrogen System Development Status of Hydrogen System Development MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov, Tom Bradshaw, Elwyn Baynham, Mike Courthold, Matthew Hills, Tony Jones Applied Science Division, Engineering and Instrumentation Department RAL

Post on 19-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

1

Status of Hydrogen System DevelopmentStatus of Hydrogen System Development

MICE Collaboration Meeting, Frascati, June 26-29, 2005

Yury Ivanyushenkov, Tom Bradshaw, Elwyn Baynham, Mike Courthold, Matthew Hills, Tony Jones

Applied Science Division,Engineering and Instrumentation Department

RAL

2

• Hydrogen system:

- principal points

- process and instrumentation diagram (PID)

- layout

• Hydrogen R&D:

- motivation and scope

- work packages

- components

- layout

• Plans

Scope

3

• Individual hydrogen system for each of 3 absorbers.

• Use of a metal hydride bed for hydrogen storage.

• Compact location of the components under hydrogen extraction hood close to the absorber.

Conceptual points

4

MICE hydrogen system layout: Principle

Hood

MICE

Cabinet for hydride bed and pipework

H2sensorArgon Jacketing

Safety area

1m3

• Argon jacketing of pipework is proposed in outside the hood. Basic philosophy is shown below:

5Pressuregauge

Non-return valve

P P VP Vacuum pumpBursting diskPressure relief valve

ValvePressureregulator

Pre-coolingOut In

Metal Hydride storage unit

(20m3 capacity)

Purge valve

0.5 bar

0.9 bar

H2 Detector

P

P

VP1

VP2

Purge valve

Chiller/Heater

Unit

1 bar

PP

0.5 bar

0.9 bar Helium supply

Hydrogen supply

High level vent

Buffer vessel

Vent outsideflame arrester

Extract hoodH2Detector

PP

Nitrogen supply

PP

PP

1 m3

Hydrogen zone 2

Vent manifold Vent manifold

P1

PV1

PV7

PV8

PV2

PV3

PV4

HV1

Fill valve

Tbed

HV2

HV3

P3

P

P2

PV6

High level vent

Non return valve

0.1 bar

MICE hydrogen system (familiar sketch)

Liquid level gauge

Internal Window

LH2 absorber

Safety windows

Vacuum

Vacuum vessel

6

MICE hydrogen system PID

7

MICE hydrogen system layout

8

MICE hydrogen system layout (2)

9

•To construct a prototype hydrogen handling system at RAL which will become the first full system of MICE

•This will consist of 2 main parts

•The external system – which will be in the final form

•to deliver H2 to the absorber and store the H2 in the hydride beds

•The safety system to vent H2 in failure modes- to include relief valves and buffer volume

•The dummy absorber

•The absorber will be simulated by a simple cryostat with a containment vessel to contain 20 litres of H2 – operated from a condensing pot with a cryocooler

Hydrogen system development: Scope

10

The development programme will address the following issues:

•Confirm the working parameters of a hydride bed in the regimes of storage, absorption and desorption of hydrogen ?

•Purity of hydrogen and effects of impurities.

•Hydride bed heating/ cooling power requirements.

•Instrumentation and control required for the operation of the system

•Safety aspects including - safety relief valves, sensors and interlocks and safety documentation

•The R&D programme will enable the final design for the MICE hydrogen system to be confirmed and the HAZOP to be completed.

Hydrogen system development: Scope (2)

11

• WP1 Initial design -> Internal safety review

• WP2 Detailed design and procurement

• WP3 Installation and commissioning

• WP4 Test Programme

Hydrogen system R&D: Work packages

12

Initial Design

H2 handling system

• Confirmation of

• components on H2 circuit diagram

• pipe sizes, mass flows, pressure drops, relief valve specifications, venting, manifolding

• vacuum and purging systems

• layouts in hall

• H2 zones

• basic specifications for purchased items

Hydrogen system R&D: WP1

13

Initial Design

Dummy absorber

• Cryostat design

• H2 containment vessel, condensing pot, internal pipework components

• Pre - cooling – heat exchanger etc

• Heater for load simulation and H2 boil off

• Instrumentation

• Data acquisition

• Outline definition of test programme and proposals for fault condition simulation

Hydrogen system R&D: WP1 (2)

14

Conclusion of WP1

• Update cost estimates for main components

• Internal Engineering and Safety Review

- Aim will be confirm the scope of the R&D programme and release the stage of WP2 – detailed design and procurement

Hydrogen system R&D: WP1

15

Tchill

Pressuregauge

Non-return valveP P VP Vacuum pumpBursting diskPressure

relief valveValvePressure

regulator

CoolantOut In

Test absorber assembly

Metal Hydride storage unit

(20m3 capacity)

Purge valve

0.5 bar

0.9 bar

H2 Detector

P

P

VP1

VP2

Purge valve

Chiller/Heater

Unit

1 bar

PP

0.5 bar

0.9 bar Helium supply

Hydrogen supply

High level vent

Buffer vessel

Vent outsideflame arrester

Extract hoodH2Detector

PP

Nitrogen supply

PP

PP

1 m3

Hydrogen zone 2

Vent manifold Vent manifold

P1

PV1

PV7

PV8

PV2

PV3

PV4

HV1

Fill valve

Tbed

HV2

HV3

P3

P

P2

PV6

High level vent

Non return valve

0.1 bar

Hydrogen system test rig

Mass spectrometer

M. F.M.

Mass flow meter

16

Hydrogen test cryostat: Concept

T H

T H

• Instrumentation mimics what we will need on the absorber for the control system and interlocks

• Heater will regulate temperature of cryocooler – need redundancy and interlock with compressor

• Dia.Reservoir =height=290mm

17

Hydrogen Test Cryostat Outline

1120

Ø 580

18

Hydrogen test cryostat

Condenser

LH2 dummy absorber

Level sensors

Cryocooler SRDK-4151.5 W @4.2K35/45 W @50K

Radiation shield

Hydrogen inlet and outlet

He inlet and outlet

Cu bottom plate with heat exchanger

19

Hydrogen test cryostat (2)

Cu bottom plate with heat exchanger

Cartridge heaters

Finned top plateof condenser

20

Instrumentation

- Capacitance-based level sensors (2 or even 3)(communicating with a supplier concerning choice of a sensor)

- Temperature sensors (PRTs)(standard components of any cryogenic system)

- Cartridge heaters(standard components)

21

Control system

- Initial control sequence diagrams have been developed (example)

- Will be revised and completed

- Talking to ISIS and DL experts on hardware implementation

22

Chiller onSet Tchill = Tchill_initial

Start PV1,2,3,4 closed

VP1 on, PV6 Open

Cooling system OnStart Pressure Control Loop

Start Vac MonitorOpen Pv1,Pv2

Tbed<Tbed1And

P3<1.e-5

P1Pset1

Close PV1,PV2Stop Pressure Control Loop

Set Tchill = Tchill_lowOpen PV3

Hlevel>Hlevel1

H2 System Ready

Increment/DecrementTchill

EmptySequence

P3<1.e-5

Vac monitor

Pressure Control

Yes

No

Yes

No Yes

No

Provisional Hydrogen System Control Sequence

Control logic – Fill Sequence

23

(1600)φ216.3

140

(1810)

2-Rc3/4Relief valve

Filter

Valve

Metal hydride tank

Table 1 The specification of the MH tank for RAL 

Hydrogen Storage Capacity 20 Nm3

Tank Description:

Heat Transfer Medium Water

MH Weight 155kg

Tank Total Weight 220 Kg

Operating Condition:

Charging Gas Component Hydrogen of 99.99% purity

Charging Gas Pressure 1.2 barA

Hydrogen Charging Rate 70NL/min

(up to 90% of Storage Capacity)

Discharging Gas Pressure 1.2 barA

Hydrogen Discharging Rate 70NL/min

(up to 90% of Storage Capacity)

Utility Requirements:

Cooling Medium Water

Below -10 ℃ ( At 20L/min )

Heating Medium Above 20 ℃ ( At 20L/min )

Status:-Waiting for a new quotation from the supplier

24

Hydrogen R&D: Layout

25

Hydrogen R&D: Phase I initial

26

Hydrogen R&D: Phase I initial (2)

27

Hydrogen R&D: Phase I final

28

Hydrogen R&D: Phase I final (2)

29

Outline Schedule

•WP1 Initial design: May – August 05

with Review in September 05

•WP2 Detailed design and procurement: Aug 05 – Feb 06

•WP3 Installation and commissioning: Jan – April 06

•WP4 Test Programme: June – Oct 06

Hydrogen system R&D – Schedule