HCAL production, QC and preparation for installation
Overview of the status report
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
The general status of module construction at IHEP
The status of optics assembly at CERN and quality check with 137Cs
The PMT+HV base assembly and test
Pre-installation pile-up test and survey experience in building 156
The module final assembly (cabling, CW+PMT)
Modules final test with the 137Cs source before installation
Conclusions
2
HCAL production, QC and preparation for installation
The general status of module construction at IHEP
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
ISTC start
Raw spacer delivery
delay
Supportreturn
21.09.04
#45+46Arrives
21.09.04
#47+48Leaves23.09.04
3
HCAL production, QC and preparation for installation
The status of optics assembly at CERN
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Module/week
Module/10days
50% = ½ HCAL
100% = 2/2 HCAL
21.09.04
#44 pass QC test
15.09.04
4
HCAL production, QC and preparation for installation
The on-line optics quality check with 137Cs
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Module #30, PMT #7
Tile light yield in the cell
Seen:minor under-compensationalong fiber
5
HCAL production, QC and preparation for installation
The module beam test @ X7 SPS
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
beam
6
HCAL production, QC and preparation for installation
The pulse shape study on the beam for layers
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
-600
-550
-500
-450
-400
-350
-300
-250
-200
-150
-100
-50
0
50
-250 -225 -200 -175 -150
Layer-1
Layer-2
Layer-3
Layer-4
Layer-5
Layer-6
Electron beam 30 GeVHCAL @ 90o
1-st layer
6-th layer
COMPENSATION
CORRECTION
for 25 ns
integrating time
L-1 1,000
L-2 0,998
L-3 0,989
L-4 0,982
L-5 0,959
L-6 0,941
25 ns
7
HCAL production, QC and preparation for installation
The status of optics quality check with 137Cs
26.05.04 Rustem DZHELYADIN (IHEP, Protvino)
44 modules HCAL test results
1304/1488 = 87.6%
Average = 4.7%
Tile to tile RMS within cell
8
HCAL production, QC and preparation for installation
The PMT+HV base assembly and test
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
CW all delivered
Solder/test in progress
Insertion
½ HCAL mid October
2/2 HCALwaiting for PMT’s delivery
9
HCAL production, QC and preparation for installation
The 137Cs, LED and HV control hardware
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
HYDRO system
2 Garage ready
2 Pump delivery 24.05.04 delivered
2 Hydro Box construction 30.09.04 in progress
2 set of control electronics
final design 1.07.04 completed
construction 1.11.04 1-st set under test @ CERN
LED/HV control
first board (160 ch.) 1.08.04 under test @ CERN
construction 1.03.05
LED drivers prototype 1.08.04 under test @ CERN
construction 1.03.05
Date of completion
10
HCAL production, QC and preparation for installation
Pre-installation pile-up test and survey experience
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Robert Kristic’s measurement:
Center Side
-1
0
1
2
3
4
5
6
7
TBTBTBTBTBTBTBTB
121115391687
Module
(mm
)
Position 1
Position 2
Position 3
Front Side
-5
-4
-3
-2
-1
0
1
2
TCBTBTBTCBTBTBTBTCB
121115391687
Module
(mm
)
Position 1
Position 2
Position 3
11
HCAL production, QC and preparation for installation
Modules final test with the 137Cs source
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Test zone in bldg.157137Cs run 4 modules
HV set for PMT
Check cable/connections
Light protection
Damage reparation
Start 10.10.04
50% 10.12.04
100% 10.03.05
12
HCAL production, QC and preparation for installation
Modules final test with the 137Cs source
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Test zone in bldg.157
Barrack available
Cables exist
PC computer required:
• 3.2 GHz P4 processor
• 1 Gb RAM memory
• ~120 Gb HDD
• 3-4 PCI slots
Tasks:
• HV/LED control
• HYDRO control
• 137CS data bank
• PMT’s data bank
13
HCAL production, QC and preparation for installation
Modules final test with the 137Cs source (2/2 HCAL)
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Test zone in bldg.156
Idea – not to move to b.157
• modules already on place
• exclude damage risk
• economy of manpower
14 working days truck+crane+crew
Required
• extend blue wall ~10m
• confirm space occupancy
• RP approval
14
HCAL production, QC and preparation for installation
The problems to be solved
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Manpower for optics assembly (Romanian, Ukrainian technicians)
October-
November’04
PC-computer for final test in b.156/157, later in the pit.
Cross calibration “25 ns” LFB and LeCroy QCD’s.
?? LFB counts per 1 GeV ??
Financing from RF-I unavailable since April !!!
could postpone modules construction => April’05
15
HCAL production, QC and preparation for installation
Conclusions
21.09.04 Rustem DZHELYADIN (IHEP, Protvino)
Provided problems would be solved
• Construction completion by November’04 looks straightforward
• Optics assembly completion by Christmas
• Final module check (cabling, PMT+CW, rad.source test)
50% in December’2004
100% in March’2005
• Installation can start within new schedule timetable