1expect the bestwww.vita.virginia.gov
Briefing to the IT Project Review Committee
January 19, 2005
ITIB Recommended Technology Investment Projects (RTIP) Report for 2005
January Workshop – Reporting Categories
www.vita.virginia.gov 2expect the best
Workshop Objectives (Agenda)
• Confirm Workshop goals & objectives/outcomes
• Establish basic assumptions & definitions
• Review IT investment portfolio management (level set)
• Review RTIP 2004 (level set)
• Establish desired outcomes for RTIP 2005
– Business Queries
• Identify RTIP 2005 reporting categories & requirements
– Project categories
– Format & structure
• Develop RTIP 2005 prioritization criteria
– Planning Approval
– Development Approval
• Define/establish IT Portfolio evaluation criteria & selection process
www.vita.virginia.gov 3expect the best
Reporting Categories – Major IT Projects
• Active – Do not rank?
• Planning – Rank/prioritize
• Development – Rank/prioritize
• Not Recommended– Rationale
www.vita.virginia.gov 4expect the best
RTIP 2005 Reporting CategoryActive Category
• Projects approved for development by the ITIB• Under oversight by the CIO and ITIB• Reported on the Commonwealth Major IT
Projects Dashboard• Not included in the ranking process as funds
have already been allocated?• Recommend funding be maintained through the
budgeting process• Protect the investment through continued
periodic review and approval by the CIO & ITIB
www.vita.virginia.gov 5expect the best
RTIP 2005 Definitions Projects Approved for Planning
• Planning Approval – approval granted by the CIO to proceed with project planning (Revised definition)
• Project Planning – activities to conduct effective initial analyses of business needs and potentially useful technologies required for development of a detailed business case, with sufficient level of detail, definition of scope, business justification, and the agencies’ own confidence in the presented data as per CIO/ITIB guidance (New definition – RTIP 2004 Transmittal Letter)
www.vita.virginia.gov 6expect the best
RTIP 2005 Reporting CategoryProjects Approved for Planning
• Recommended for funding – Enterprise/Collaboration Opportunities– Secretariat – Agency
• Funded – maintain funding– Enterprise/Collaboration Opportunities– Secretariat– Agency
www.vita.virginia.gov 7expect the best
Project Life Cycle Processes Matrixed with
SDLC, Waterfall MethodPM Life Cycle Code of Virginia
(§2.2-2018 and 2019)
Systems Development Lifecycle (SDLC)
PSG Phase Deliverables
Selection IT Strategic Planning
Initiation Project PlanningBPR Study,
Feasibility Study, Requirements Definition, Systems Analysis
Project Initiation
BPR, Business Rqts., Systems Rqts., Technical Rqts., Detailed Project Proposal, Detailed Business Case, Develop Project Charter
Planning
Project Development
Systems Design, BPR Project Planning
Approved Project Charter, Detailed Project Plan
Execution and Control Project Development Programming, Testing
Implementation, Post-Implementation Analysis, BPR
Project Execution and Control
Closeout Project Development Project Closeout
Operations and Support Asset Ops. & Management
Milestone: CIO Approval for Planning
Milestone: ITIB/CIO Approval for Development
www.vita.virginia.gov 8expect the best
Project Life Cycle Processes Matrixed with
SDLC, RAD MethodPM Life Cycle Code of Virginia
(§2.2-2018 and 2019)
Systems Development Lifecycle (SDLC)
PSG Phase Deliverables
Selection IT Strategic Planning
Initiation
Project PlanningBPR Study, Feasibility Study, Requirements Definition, Systems Analysis, Systems Design, Build Prototype, Programming, Testing, Implementation, Post Implementation Analysis
Project Initiation
BPR, Business Rqts., Systems Rqts., Technical Rqts., Detailed Project Proposal, Detailed Business Case, Develop Project Charter, Prototype
Planning
Project Development
Project Planning
Approved Project Charter, Detailed Project Plan
Execution and Control Project Development Feasibility Study, Requirements Definition, Systems Analysis, Systems Design, Build Prototype, Programming, Testing, Implementation, Post Implementation Analysis
Project Execution and Control
Closeout Project Development Project Closeout
Operations and Support Asset Operation and Management
Milestone: CIO Approval for Planning
Milestone: ITIB/CIO Approval for Development
www.vita.virginia.gov 9expect the best
RTIP 2005 DefinitionsProjects Approved for Development
• Development Approval – approval by the ITIB to proceed with detailed project planning, project execution and control, project closeout, and asset operation and management (New definition)
• Detailed Project Planning – activities required to complete a detailed project plan for project execution and control as specified in the Commonwealth Project Management Standard and Guideline (New definition)
www.vita.virginia.gov 10expect the best
• Recommended for Development Approval –Unfunded – Enterprise/Collaboration Opportunities– Secretariat – Agency
• Funded – maintain funding– Enterprise/Collaboration Opportunities– Secretariat– Agency
RTIP 2005 Reporting CategoryProjects Approved for Development
www.vita.virginia.gov 11expect the best
Project Life Cycle Processes Matrixed with SDLC, Waterfall Method
PM Life Cycle Code of Virginia
(§2.2-2018 and 2019)
Systems Development Lifecycle (SDLC)
PSG Phase Deliverables
Selection IT Strategic Planning
Initiation
Project Planning
BPR Study,
Feasibility Study, Requirements Definition, Systems Analysis
Project Initiation
BPR, Business Rqts., Systems Rqts., Technical Rqts., Detailed Project Proposal, Detailed Business Case, Develop Project Charter
Planning
Project Development
Systems Design, BPR Project Planning
Approved Project Charter, Detailed Project Plan
Execution and Control Project Development Programming, Testing
Implementation, Post-Implementation Analysis, BPR
Project Execution and Control
Closeout Project Development Project Closeout
Operations and Support
Asset Operation and Management
Milestone: CIO Approval for Planning
Milestone: ITIB/CIO Approval for Development
www.vita.virginia.gov 12expect the best
Project Life Cycle Processes Matrixed with
SDLC, RAD MethodPM Life Cycle Code of Virginia
(§2.2-2018 and 2019)
Systems Development Lifecycle (SDLC)
PSG Phase Deliverables
Selection IT Strategic Planning
InitiationProject Planning
BPR Study, Feasibility Study, Requirements Definition, Systems Analysis, Systems Design, Build Prototype, Programming, Testing, Implementation, Post Implementation Analysis
Project Initiation
BPR, Business Rqts., Systems Rqts., Technical Rqts., Detailed Project Proposal, Detailed Business Case, Develop Project Charter, Prototype
Planning
Project Development
Project Planning
Approved Project Charter, Detailed Project Plan
Execution and Control Project Development Feasibility Study, Requirements Definition, Systems Analysis, Systems Design, Build Prototype, Programming, Testing, Implementation, Post Implementation Analysis
Project Execution and Control
Closeout Project Development Project Closeout
Operations and Support Asset Operation and Management
Milestone: CIO Approval for Planning
Milestone: ITIB/CIO Approval for Development
www.vita.virginia.gov 13expect the best
RTIP 2005 DefinitionsNot Recommended for Funding
• Identified for Preliminary Planning - projects which address an agency business need but which requires further review by the CIO and ITIB before authorizing the expenditure of additional planning funds (Revised definition)
• Collaboration Opportunity – a common business need identified by more than one agency that creates the possibility for agencies to work together towards a common solution (New definition)
www.vita.virginia.gov 14expect the best
RTIP Reporting CategoryNot Recommended for Funding Category
• Not recommended for funding– Identified for Preliminary Planning – Collaboration Opportunities– Secretariat– Agency
www.vita.virginia.gov 15expect the best
RTIP Report Structure - Format
• Format– Break into two sections
• RTIP Report – Reflects Priority Technology Investment Projects– Submit 9/1/2005
• RTIP Report Supplement – Includes updates based on budget submissions– Reflects entire project portfolio and detailed project
report appendices– Submit 11/1/2005 to coincide with budget process
www.vita.virginia.gov 16expect the best
RTIP Report Structure - Content
• Content– Keep the ‘Top 26’ concept?– Lobby for a select 5 or 6?– Report only projects that meet certain thresholds
(ROI, Risks, Strategic Alignment, Benefits)?– Report only enterprise/collaboration opportunities?– Include only those projects in need of funding?