1 dart orange line project update and development opportunities timothy h. mckay, p.e. senior vice...
TRANSCRIPT
![Page 1: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/1.jpg)
1
DART Orange LineProject Update and
Development Opportunities
Timothy H. McKay, P.E.Senior Vice President
Rail Program Development
July 25, 2011
![Page 2: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/2.jpg)
2
Orange Line Expansion
![Page 3: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/3.jpg)
3
Irving-1 & 2(2012)
Orange Line Expansion
![Page 4: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/4.jpg)
4
Irving-3(2014)
Orange Line Expansion
![Page 5: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/5.jpg)
5
• Awarded in December 2008
• KSWRP, a Joint Venture
• Kiewit
• Stacy & Witbeck
• Reyes
• Parsons
• Contract Value $430M
I-1/I-2 Design-Build Project
![Page 6: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/6.jpg)
6
• 2 Line Sections (I-1/I-2)• 9.29 miles Total Length• Connects to Green Line at
Bachman Station• Ends on DFW Property at Belt
Line Station• Revenue Service
• I-1 August 2012• I-2 December 2012
Project Description
![Page 7: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/7.jpg)
7
Project Map
![Page 8: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/8.jpg)
8
Transit-Oriented Development (TOD) is moderate to higher density development, located within an easy walk of a major transit stop, generally with a mix of residential, employment, and shopping opportunities designed for pedestrians without excluding the auto.
What is Transit Oriented Development?
![Page 9: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/9.jpg)
9
• Core Up to 600 ft Greatest intensity
• Center600-1500 ft Intermediate intensity
• Edge 1500-2600 ft Greater than community average intensity
General Limits for TOD
![Page 10: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/10.jpg)
10
Examples of TOD
Baylor Station
![Page 11: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/11.jpg)
11
Examples of TOD
Mockingbird Station
![Page 12: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/12.jpg)
12
Examples of TOD
Downtown Plano Station
![Page 13: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/13.jpg)
13
Identified Opportunities
Texas Stadium
Area
![Page 14: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/14.jpg)
14
Texas Stadium Area
DART Light Rail
![Page 15: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/15.jpg)
15
North of UD Station
Identified Opportunities
![Page 16: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/16.jpg)
16
North of University of Dallas Station
UD Station Platform
UD Bus Transfer
![Page 17: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/17.jpg)
17
Las Colinas Urban Center
Identified Opportunities
![Page 18: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/18.jpg)
18
Las Colinas Urban Center
DART Light Rail
![Page 19: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/19.jpg)
19
Irving Convention
Center
Identified Opportunities
![Page 20: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/20.jpg)
20
Convention Center
![Page 21: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/21.jpg)
21
DFW Airport
Identified Opportunities
![Page 22: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/22.jpg)
22
DFW Airport
![Page 23: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/23.jpg)
23
Property Classification and Evaluation ProcessProperty Classification and Evaluation Process
![Page 24: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/24.jpg)
* TOD Catalyst Facilities* TOD Catalyst Facilities
1 Mockingbird Station2 Park Lane Station3 Pearl Station4 Spring Valley Station5 Deep Ellum Station
6Downtown Plano Station
7Cedars Station- Powhatten
8Lake Highlands Station
9 South Irving Station
10Arapaho Center Station
11 Parker Road Station
12Addison Transit Center
13 Westmoreland Station14 LBJ-Skillman Station15 Galatyn Park Station16 Trinity Mills Station17 Forest Lane Station18 Illinois Station19 Kiest Station20 Forest-Jupiter Station
![Page 25: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/25.jpg)
TOD Process and ProceduresTOD Process and ProceduresTOD Investment Package Checklists
Station Area Property DataPlanning Documents (as available) Due Diligence
Title Reports ○ Projected Ridership ○ Market Assessment ○
Survey
○Zoning and Land use Plan ○ Financial Feasibility ○
Phase 1 Environmental ○ Member City Plan ○ Property and Sales Tax Rates ○
Phase 1 Appraisal ○
Floodplain Maps ○
Assessment Economic ImpactOutcome
+,-, neutral Recommendations
-Stakeholder Discussions -Due Diligence -Planning Documentation -Financial Feasibility
DART potential income-Sale-Land Lease-Other
Proceed to Solicitation Process
Selection
Impact on DART Services-Ridership-Operations-Maintenance
Explore Joint Venture/
Partnerships
Do Nothing
![Page 26: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/26.jpg)
TOD Process andTOD Process andProceduresProcedures
26
DART Board
TOD Project Team
President/ExecutiveDirector
Director Economic Development and Planning
Executive TODReview Committee
DART CFO
Senior VP Rail Project Development
TBD/As NeededAppropriate City Representative
(as needed)
DART Departments(various)
Special Consultants(real estate, economic development)
![Page 27: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/27.jpg)
27
![Page 28: 1 DART Orange Line Project Update and Development Opportunities Timothy H. McKay, P.E. Senior Vice President Rail Program Development July 25, 2011](https://reader033.vdocuments.site/reader033/viewer/2022061306/5514708e550346494e8b602c/html5/thumbnails/28.jpg)
28
Questions?