  • Introduction to Rotary Equipment in Refinery March,2014

    [email protected]

  • Rotary Equipment in Refinery

  • Large population of Rotating equipment Heart of Refinery Total : 2075

    Compressors: Centrifugal compressor : Integrally geared compressor Reciprocating compressors Diaphragm compressors. Screw compressors

    Turbines: Steam turbines. Gas Turbines Expansion Turbine

    Blowers

    Fin fan

    Centrifugal Pumps

    Dozing pumps Centrifuges, Extruder.

  • Area wise fin fan

    DHDT 44 SRU 54 VGO 44

    MS Block 52 DCU 66

    HGU 10

    CDU 38 FCCU 20

    328

    Reciprocating compressor

    DHDT 2 VGO 4 MS Block 14

    HGU 4 CPP 1

    25

    Centrifugal compressors

    DHDT 1 SRU 3 VGO 1

    MS Block 2 DCU 1

    IAC 5

    FCCU 2 CPP 5

    ETP 1 PPU 2

    23

    Screw compressor

    PPU 3 MS Block- 3

    6

    Integrally geared centrifugal compressors : 11

  • HMEL Criticality Matrix

    Area Super critical Critical Semi critical Essential Total CDU 46 58 48 152

    DCU 1 53 65 44 163 SRU 48 76 28 152

    CT and IAC 1 8 15 22 46

    DHDT 1 32 52 24 109

    ETP 47 80 53 180

    FCCU 2 58 62 28 150 CPP 4 29 43 75 151 HGU 5 19 20 18 62

    LPG Treater 9 22 10 41 RODM 29 66 44 139

    RWTP 16 35 33 84 VGO 1 31 66 26 124

    Offsite 52 98 45 195 MS Block 3 74 74 66 217 PPU 1 109 0 0 110

    Total 19 660 832 564 2075

  • Rotating Equipment Organization

    AGM Rotating equipment

    Managers -Rotating equipment Regular maintenance

    AM Workshop Rotary equipment, Mechanical seal refurbishing, Oil Analysis, Balancing

    AM-Condition monitoring

    Manager- Reliability Rotary

    AM- Spares & Services

  • Why Rotating Equipment are most critical & heart of Refinery ?

    Has big population and varies type. Had complicated instrumentation and control ( microprocessor based) Logics , PLC based with lot of safety integrated , Turbomachines have speed governing with integrated compressor control. Handles Hydrocarbon, Hydrogen.. Has single line major turbomachines Has dual mechanical seals ( API seals) Hot pumps : ( temp. 360 degrees C, congealing fluid, needs proper warm up).

    Slurry pump in FCCU, Column bottom pumps Fractionator bottom pumps in VGO. DCU coke charge pumps. VR pumps in CDU.

    Needs high reliability and availability What went wrong- RCA of failures . What can go wrong - FMEA Low MTTR High MTBF

    Has dual Dry gas seals in centrifugal compressors.

    Some special features :

  • Maintenance Philosophy

    Minimize unplanned / breakdown jobs/ repeated failures, move with improvements & maximize the life of

    components & system.

    Preventive maintenance

    Predictive maintenance

    Emergency maintenance

    Corrective maintenance

  • June 4, 2014

    Copyright HPCL-Mittal Energy Ltd.

    Predictive / Preventive Maintenance

    Preventive maintenance: preventive maintence , based on: OEM recommendations, Behavior pattern of similar machines at other sites. Mainly for equipments having stand-by. Reciprocating machines have time based maintenance.

    Other single stream machines in planned turnaround: Minor or major overhauls.

    SAP has PM module, generate the work notifications and maintenance orders, capture histories , maintenance planning, work scheduling, .

    Predictive maintenance:

    Predictive maintenance, attempts to evaluate the condition of equipment by performing periodic or continuous (online) monitoring of equipment.

    Utilizes technologies such as vibration analysis, sound level measurements, ultrasound, oil analysis, Motor Current Analysis and other specific online tests.

  • June 4, 2014

    Copyright HPCL-Mittal Energy Ltd.

    ONLINE CONDITION MONITORING (GE SYSTEM-1)

    Machine Data Monitoring & Management System (MMS): To continuously monitor and display parameters like vibrations, bearing temperature, winding temperatures etc. for 37 critical rotary machines across the GGSR Refinery.

    Alarms are generated when conditions exceed preconfigured alarm limits and these alarms are used to automatically shut down the machine thru ESD/PLC.

    The System 1 software in combination with the System 1 Rulepaks provide output for diagnosis or analysis of all the 37 critical machineries connected to this network.

    Online monitoring equipments DHDT 5 SRU 3

    VGO 9 MS Block 9 DCU 3

    PPU 6 FCCU 2

    37

  • June 4, 2014

    Copyright HPCL-Mittal Energy Ltd.

    OFFLINE CONDITION MONITORING ( EMERSON)

    782 equipments which are not covered under the on-line condition monitoring system shall be monitored using portable analyser Emerson CSI-2130.

    Condition monitoring frequency shall be fixed for each equipment based on the criticality of the equipment, safety and environmental aspect. (as per guide line of OISD 124); Functional criticality analyses (FCA)

    Equipments covered under offline condition monitoring are regularly trended using the RBM ware software.

    Vibration Analysis and Recommendation (VAR) Reports shall be generated for the equipments which exceed the alarm limits configured in the RBMware software as per ISO 10816. Both on line and off line vibrations shall be monitored in Condition monitoring lab in workshop on large display.

    Oil Analysis shall be done as per schedule for equipment defined in Oil analysis in reference to OISD standard. We shall be on line with OEM of extruder ( M/s Coperion) in PPU for condition monitoring of lubrication oil of gearbox (having 64 bearings).

  • Refinery Rotating Equipment Engineer - Challenges SAFETY:

    HSEF and Fire fighting:

    JOB SAFETY ANALYSIS & RISK ASSESSMENT Scaffolding Safety , Ladder Safety for Contractor Supervisors, WP Issuers &

    Acceptors INCIDENT INVESTIGATION

    Codes & Standards (API 617, 611, 612, 610, 682, 670, 686) Bearings & Lubrication Centrifugal Pumps Positive displacement Pumps Centrifugal compressors Reciprocating compressors Screw Compressors Steam Turbines Gas Turbines Alignment Balancing Turbines Governing system & electronic governors On line Vibration monitoring system Vibration Analysis Pneumatic tools Mechanical seals

  • Instrumentation : Fire & gas detection system, Process optimization, Overview of DCS & PLC, Electrical : Hazardous area classifications, Motors ELECT. SAFETY- Electrical Insulations/Static Electricity Hazard/safety measures

    All rounder: SAP PM Module

    What Went Wrong?, Learning From Incident / Case studies Metallurgy Process RCA Economist Should be able to work under pressure Good team player Industrial Engineering (scheduling , planning & Control) Inventory Management Innovative (jugads). Extracting best work from technicians/ contractors

    Dry Gas seals Couplings Fans, Blowers & Extruders Jet Pumps Condition Monitoring, Vibrations analysis, Lube

    oil analysis Anti surge system

  • 14

    PM Philosophy Rotary Equipment

    Equipment Type Preventive Maintenance Frequency Centrifugal Pump 6 month Sundyne (Pumps & Compressor) 6 month Booster Pump 6 month Vacuum Pumps 6 month Vertical Pump (VS1 & VS4) 6 month Gear Box Clubbed with Parent Equipment Dosing pumps 9 month Agitator (ETP) 3 months Agitator (PPU Reactor) Opportunity based Agitator (Dosing Skid) 6 months Agitator (Tank Farm) 6 months Fans and Blower 6 month Air fin cooler 3 month Turbines (Pump Drive) 1 year / opportunity based Turbine (centrifugal compressor drive) Stroke check only on yearly basis, detail inspection plan will be OEM specific Reciprocating Compressor Based running in Hours as per OEM specific Integral Geared compressor Annual Inspection as specified by OEM Screw Compressor Annual Inspection as specified by OEM Centrifugal Compressor OEM specific work schedule Single line machine Included in Predictive Maintenance, Overhaul in Opportunity Shut down

  • Proprietary & Confidential

    Predictive / Condition Monitoring Schedule

    Criticality Frequency of Vibration capturing Frequency of Signature analysis No of equipments

    Super critical 7 Days weekly 18

    Critical 7 Days only for those equipments which run

    above threshold limit 551

    Semi critical 15 Days only for those equipments which run

    above threshold limit 832

    Essential 30 Days only for those equipments which run

    above threshold limit 564

  • Proprietary & Confidential

    1. Revised frequencies for Preventive maintenance based on

    equipment performance/ experience from 3 months to 6 months for

    pumps. Advantage:- prevents over maintenance & related costs

    .Moving towards condition based maintenance

    2. Clocking for recip machines (PM based on running hours)

    3. Internal Audit for quality SAP order closure history

    4. LLFS

    Action on

    Preventive Maint. schedule for critical machines

  • Proprietary & Confidential

    Best Practices Adopted In Maintenance:

    Selection of Proactive maintenance strategy for plant and equipment's. E-SPIR for spare part interchangeability across tags and review for spares inventory optimization.

    Hydraulic torqueing and tensioning for the critical & hydrocarbon joints thus avoiding hydrocarbon leakages.

    Fully functional state of art Workshop providing continuous support for maintenance, machining, repairs, testing, assemblies, fabrications, Mechanical seal refurbishing for

    API seals, making new parts by reverse engineering, with attempt to carry out all

    repairs in house, reclaim damaged parts. Soft footing correction of electrical motors by blue matching thus avoiding vibration related problems in motors. (28 LT motors, 8 HT motors, resulting smooth operations of machines without vibrations) In house Mechanical seal refurbishment shop, thus ensuring equipment availability and safety. Mechanical run test of compressors / Water trials of Pumps done before taking in line with Hydrocarbon thus avoiding any leakage of hydrocarbon. In-house capability of attending problems in major rotating equipment. Engineers trained by OEMs and on job thus capable of resolving maintenance

    problems in critical areas. Boroscopic inspection of suction pipe line and inlet nozzles before commissioning. Hot alignment of Hot pumps is very essential.

  • Proprietary & Confidential

    Baroscopic inspection of Pump suction

    (DHDT)

  • It was originally planned to run delayed coker unit fro 10 days and then

    shutdown it fro 12 days to make other units ready.

    We overhauled the turbine in this opportunity and replaced the turbine rotor

    with spare rotor. Complete overhauling of steam turbine done sucessfully

  • Demonstration of

    turbine rotor barring

    done manually

  • Skilled persons, spares , dedication, tireless working is key to success in

    rotary equipment. Passions towards

    rotary machines

    Temporary innovative repair resolutions in

    Turbomachinery can save a significant

    amount of downtime. Permanent resolution

    can implemented at a later opportunity like

    a planned turnarounds etc.

    Some Leanings