1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009 1

Upload: anna-hancock

Post on 19-Jan-2018

214 views

Category:

Documents


0 download

DESCRIPTION

3 Key Highlights Inyaka Water Treatment Works – Phase 1 Completed in 2008 and Phase 2 was commissioned in September Vaal River Eastern Sub-system Augmentation Project (VRESAP) : Industrial for Sasol and Eskom. It cost R2,7 Billion and will supply 160 million cubic meters per annum. Currently using a temporary abstraction works. Final testing of 3 pump sets running simultaneously still outstanding. Commissioning of all projects components to supply water, using the temporary abstraction works, successfully completed except the final testing of three pumps running together Berg River Water Project – commissioned in September 2008 at a cost of R1,55 Billion, and opened by President in March 2009; it supply 80 million cubic meters per annum to CCT Rehabilitation and Refurbishment of Dams – 29 Dams are completed, 20 dams are under construction and 9 dams are in the design stage. Total spent on Dam Safety and Rehabilitation Programme (DSRP) till 31 March 2009 is R468 million and an estimate R1,9 billion to be on the programme Adoption of a Social and Economic Development Charter for promoting BBBEE objectives 3

TRANSCRIPT

Page 1: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

1

2008/09 Annual Performance

Dr C RuitersDeputy-Director General:

National Water Resources InfrastructureDepartment: Water Affairs (DWA)

14 October 2009

1

Page 2: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

2

Presentation Outline

• Key Highlights• 2008/09 Performance against targets• Future Performance• Additional Project Information• Challenges facing the sector

2

Page 3: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

3

Key Highlights

•Inyaka Water Treatment Works – Phase 1 Completed in 2008 and Phase 2 was commissioned in September 2008. •Vaal River Eastern Sub-system Augmentation Project (VRESAP) : Industrial for Sasol and Eskom. It cost R2,7 Billion and will supply 160 million cubic meters per annum. Currently using a temporary abstraction works. Final testing of 3 pump sets running simultaneously still outstanding. Commissioning of all projects components to supply water, using the temporary abstraction works, successfully completed except the final testing of three pumps running together•Berg River Water Project – commissioned in September 2008 at a cost of R1,55 Billion, and opened by President in March 2009; it supply 80 million cubic meters per annum to CCT•Rehabilitation and Refurbishment of Dams – 29 Dams are completed, 20 dams are under construction and 9 dams are in the design stage. Total spent on Dam Safety and Rehabilitation Programme (DSRP) till 31 March 2009 is R468 million and an estimate R1,9 billion to be on the programme•Adoption of a Social and Economic Development Charter for promoting BBBEE objectives

3

Page 4: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

4

Strategic Objective

Output Performance against target for 2008/9Target Actual

Economic growth, social development and poverty eradication

Agency Establishment and Legislation in place

Bill tabled and debated in Parliament;Act Promulgated

Bill is in Parliament, but not tabled because of call for wider consultation

Implementation of the Infrastructure Programme

Nandoni Water Treatment Works – 96%

Target for design was 100%; 99% complete; construction target was 100%; actual 95%.

Vaal River Eastern Sub-system Augmentation Project (VRESAP)

Commissioning of all projects components to supply water, using the temporary abstraction works, successfully completed except the final testing of three pumps running together.

2008/09 Performance against targets (1)

4

Page 5: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

5

Strategic Objective

Output Performance against target for 2008/9Target Actual

Economic growth, social development and poverty eradication

Implementation of the Infrastructure Programme

De Hoop-construction of dam access progressed to 32% completion

Overall 12 days behind dam accelerated programme. Target for design 92% achieved 90% Outlet Works: 26% complete. Overall 36% complete

Inyaka Water Treatment Works – 54% complete

Phase 2 commissioned in September 2008.Phases 3 and 4: Design behind (Target 50% and actual 48%) Construction behind because of problems with designs (Target 18 % and actual 8 %). Phase 3 and 4: Construction experienced delays due to strike. Overall 54% completed

2008/09 Performance against targets (2)

5

Page 6: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

6

Strategic Objective Output

Performance against target for 2008/9

Target Actual

Economic growth, social development and poverty eradication

Implementation of the Infrastructure Programme

Hluhluwe Regional Water Scheme- 65 % completed

Phase 3: Water treatment plant reservoirs and pipelines (Target 98%, Actual 95%). Serious delays in material delivery due to non-payment of suppliers and non-conformance of pipe items from suppliers. Delays due to environmental go-ahead on pipelines. Hluhluwe Dam was at 36.5% and not recovering as expected, leading to water restrictions. Overall 62% Complete

Nandoni Bulk Distribution – 54% complete

Distribution Network: Pipelines, reservoirs and pump station (Design: Target 71% and Achieved 67%Construction: Target 82% and Achieved 64%). Lack of Professional Technical Human Resources; supplier payment problems because of implementation of SAP. Pipe line testing problematic because of pipe material supplied by external supplier and work on GRP pipes stopped

2008/09 Performance against targets (3)

6

Page 7: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

7

Strategic Objective Output

Performance against target for 2008/9

Target Actual

Economic growth, social development and poverty eradication

Operation and Maintenance of existing infrastructure

Bulk Water Supply Agreements in place

Final draft of agreements in place. Awaiting approval and signature. Draft O&M Agreements finalised.

2008/09 Performance against targets (4)

7

Page 8: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

8

Strategic Objective Output

Performance against target for 2008/9

Target Actual

Economic growth, social development and poverty eradication

Rehabilitation and Refurbishment of Dams

Improved dam safety – 10 dams

Improved dam safety – 12 dams

Maintenance of Infrastructure according to preventative and routine maintenance plans.

100%75%. Scheduled maintenance up to date. Shortage of suitable skilled supervisors staff.

Develop the mechanical and electrical infrastructure refurbishment programme

100%90% Planned refurbishment done. Lack of human resources and poor performance of contractors.

2008/09 Performance against targets (5)

8

Page 9: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

9

Strategic Objective Output

Performance against target for 2008/9

Target Actual

Economic growth, social development and poverty eradication

Implement the Dam Safety rehabilitation Programme (DSRP)

100% Rehabilitation programme on track.

Operate dams in accordance with emergency preparedness plans

100% Emergency plan implemented successfully in most dams.

2008/09 Performance against targets (6)

9

Page 10: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

10

ADDITIONAL PROJECT INFORMATION (1)

Strategic Objective Output Performance against target for 2008/9

Implementation of the Luvuvhu River GWW:Luvuvhu River GWW:Nandoni Bulk Distribution Works

82% 49% Overall progress Distribution Network: Pipelines, reservoirs and pump station (Design: Target 71% and Achieved 67%Construction: Target 82% and Achieved 64%).

Implementation of the Sabie River GWW: Inyaka Water Treatment works

Progress with implementation, expressed as 54% completion.

54% Complete

Hluhluwe Regional Water Scheme

Progress with implementation, expressed as 65% completion.

62% Complete

10

Page 11: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

11

Strategic Objective Output Performance against target for 2008/9

Komati Water Augmentation System

Preparatory work for implementation advanced and design in progress

Preparatory work for implementation complete. 1% complete.

Mooi-Mgeni Transfer Scheme

Spring-Grove Dam; preparatory work completed and design in progress

Preparatory work for implementation complete. 2% complete.

ADDITIONAL PROJECT INFORMATION (2)

11

Page 12: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

12

Strategic Objective Output Performance against target for 2008/9

Mdloti River Development

Raising of Hazelmere Dam; preparatory work for implementation completed and design in progress

No work done. 0% complete.

Betterment of Olifants-Doorn River Water Resources Project

Raising of Clanwilliam Dam: preparatory work for implementation completed and design in progress

No work done. 0% complete.

Nwamitwa Dam

Nwamitwa Dam: preparatory work for implementation completed and preliminary design in progress

Planning studies underway

ADDITIONAL PROJECT INFORMATION (3)

12

Page 13: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

13

Linkage of current targets with government overall aims The national water resources infrastructure targets fulfill objectives of government to priorities implementation of national infrastructure for economic growth and development; as well as ensuring that previously marginalised areas are the beneficiaries of basic services in order for those communities to prosper.

FUTURE PERFORMANCE (1)

13

Page 14: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

14

Output Performance Indicator

BaselineInfo

09/10Target and due date

Implementation of new bulk water infrastructure to meet social water needs, economic growth and development

Percentage completion as per project specification

19% De Hoop Dam (41%) Complete

89% Nandoni Water Treatment Works 99% complete

64% Nandoni Distribution 96% complete

50% Injaka Water Treatment Works 57% Complete

Percentage completion as per project specification

53% Hluhluwe Regional Water Scheme (73%) Complete

0% Mdloti River Development 42% complete 

1% Groot Letaba RWRP 7% complete

Percentage completion as per project specification

97% WSC *Vaal River East Sub-System Augmentation Project (VRESAP) 99,8% complete 

FUTURE PERFORMANCE (2)

14

Page 15: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

15

Performance Indicator

Baseline Info 09/10 Target and due date

Percentage completion as per project specification

0% WSC *Mooi-Mgeni Transfer Scheme 2 (Spring-Grove Dam) 5%

Percentage completion as per project specification

0% WSC *Komati Water Augmentation Scheme (KWAS) 5%

Percentage completion as per project specification

0% WSC *Mokolo Water Augmentation Project (5 % complete)

Percentage completion as per project plan and specification

0% WSC Olifants River Water ResourceDevelopment Project 2B-I :Bulk Distribution Scheme (5% complete)

FUTURE PERFORMANCE (3)

15

Page 16: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

16

Output Performance Indicator

Baseline Info 09/10 Target and due date

Operations of Water Infrastructure to ensure supply of Bulk Raw Water

Operate schemes as per system operating rules

100% compliance to system operating rules and existing Bulk Water supply agreements and license

100% Level of assurance of supply for different user group

Maintenance of Infrastructure as per Maintenance plan and procedures required to ensure infrastructure availability

Infrastructure availability 70% availability 80% availability

Development of Resource Management Plans (RMPs) to ensure controlled and sustainable development on state land

No uncontrolled development on/around DWAF dams

44 RMPs completed 2 RMPs

Rehabilitation and refurbishment of water resources infrastructure ( DSRP)

Fully functional and sustainable schemes (dams, canals, pump stations, etc)

50% condition of Infrastructure meet original design capacity/ performance requirements. Condition of Infrastructure rated “Poor (Level-D)” by SAICE report

70%

FUTURE PERFORMANCE (4)

16

Page 17: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

17

Output Performance Indicator

Baseline Info 09/10 Target and due date

Preparation for implementation of LHWP Phase 2

Protocol on LHWP Phase 2 approved by governments of RSA and Lesotho

Draft Heads of Agreement prepared

Protocol on LHWP Phase 2 drafted and submitted for approval by both parties by March 2010

Conversion of single to multiple-purpose dams

Strategy and plan (with budgets) for the conversion of single to multi purpose dams

Number of single purpose use dams converted to multi purpose use dams

3 dams converted to multi-purpose use dams

FUTURE PERFORMANCE (5)

17

Page 18: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

18

Challenges facing the sector• Ageing Infrastructure• Ageing workforce and problems with recruitment of Skilled

professionals (engineering, scientific and technical). Retention and recruitment of technical skills – leading to reliance on consultants

• Water Security and Availability• BBBEE issues –monopoly of adequate construction industry to support

SMMEs, • Construction costs increases, e.g. materials, SCM, professional staff

costs.• Financial resources for water resources infrastructure – “off budget”

projects, cost of materials thus regulation of water supply costs.

18

Page 19: 1 2008/09 Annual Performance Dr C Ruiters Deputy-Director General: National Water Resources Infrastructure Department: Water Affairs (DWA) 14 October 2009

19

Thank you