090925 tfsh fareham study

Upload: bilalfalcon

Post on 06-Apr-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 090925 Tfsh Fareham Study

    1/57

    Fareham SDA

    Access Study

    Fareham Borough Council

    Civic Offices

    Civic WayFareham

    Hampshire

    PO16 7AZ

    Fareham SDA

    Access Study

    February 2009

    Stoneham Place

    Stoneham Lane

    Southampton

    Hampshire

    SO50 9NW

    Environment Department

    Hampshire County Council

    The Castle

    Winchester

    SO23 8UD

  • 8/2/2019 090925 Tfsh Fareham Study

    2/57

    Fareham SDA

    Access Study

    Fareham SDA

    Access Study

    Issue and Revision Record

    Rev Date Originator Checker Approver Description

    A 31.10.2008 A Palmer A Thompson G. Maclean 1st

    DRAFT

    B 12.12.2008 S Almond A Thompson G. Maclean

    Amendments made in

    light of Highways Agency

    meeting

    C 6.1.2009

    S Almond A Thompson G Maclean

    Final Issue

    D 6.2.2009S Almond A Thompson G Maclean

    2nd

    Final Issue

  • 8/2/2019 090925 Tfsh Fareham Study

    3/57

    Fareham SDA

    Access Study

    List of Contents Page

    EXECUTIVE SUMMARY 1

    1 INTRODUCTION...................................................................................................................... 3

    2 ACCESS STUDY DATA SOURCES AND ASSUMPTIONS ................................................. 5

    2.1 Solent Strategic Transport Model.................................................................................. 52.2 New Transport Model.................................................................................................... 6

    2.3 Development Traffic...................................................................................................... 6

    2.4 Past Reports ................................................................................................................... 7

    2.5 Other Supporting Documents or Studies ..................................................................... 11

    3 TRAFFIC ASSESSMENT METHODOLOGY ....................................................................... 13

    3.1 Assessment Year.......................................................................................................... 13

    3.2 Assessment Period....................................................................................................... 13

    3.3 Study Area ................................................................................................................... 13

    3.4 Assignment of Traffic.................................................................................................. 13

    3.5 Design flows for lane requirements............................................................................. 14

    4 ASSESSMENT OF ACCESS OPTIONS................................................................................. 15

    4.1 General......................................................................................................................... 15

    4.2 Description of Options................................................................................................. 15

    4.3 Option Cost Review..................................................................................................... 16

    4.4 Assessment Criteria ..................................................................................................... 17

    4.5 Option Evaluations ...................................................................................................... 184.6 Merge and Diverge analysis ........................................................................................ 30

    4.7 Summary of the Initial Option Assessment ................................................................. 34

    5 TRAFFIC MODELLING......................................................................................................... 35

  • 8/2/2019 090925 Tfsh Fareham Study

    4/57

    Fareham SDA

    Access Study

    Figure 4.4 Option 4 M27 J10 all traffic movements with A32 realigned.............................................. 26Figure 4.5 Option 5 M27 J10 with A32 realigned and BRT ................................................................. 28

    Figure 4.1: Taper merge ........................................................................................................................ 30Figure 4.2: Parallel merge ..................................................................................................................... 31Figure 4.3: Merge with lane gain .......................................................................................................... 31Figure 4.4: Lane gain with Ghost Island option 1................................................................................. 31Figure 4.5: Lane gain with Ghost Island merge option 2...................................................................... 32Figure 4.6: 2Two lane gain with Ghost Island ...................................................................................... 32Figure 4.7: Taper diverge ...................................................................................................................... 32Figure 4.8: Lane drop at taper diverge .................................................................................................. 33

    Figure 4.9: Ghost Island diverge for lane drop...................................................................................... 33Figure 4.10: 2 lane drop ........................................................................................................................ 33

    List of Tables

    Table 4-1 Option Matrix....................................................................................................................... 15Table 4-3 Summary of the Interchange Parameters ............................................................................. 30Table 5-1: M27 Junction 11 Signalised Junction Modelling Results .................................................... 35

  • 8/2/2019 090925 Tfsh Fareham Study

    5/57

  • 8/2/2019 090925 Tfsh Fareham Study

    6/57

    Fareham SDA

    Access Study

    The Policy criterion in the evaluation process is deemed as the primary operator in terms of whether

    the proposed access strategy would be a suitable option. Therefore if an option fails to satisfy current

    transport policy then it would not go through for further traffic analysis. For example, where an optionis considered to be a new junction onto the M27 this would contravene Department for Transport

    Policy set out in DfT Circular 02/07, which states that no new junctions would be permitted on the

    SRN to facilitate new development, except for motorway service areas.

    The traffic element of the study bases its traffic assessment on a simple reassignment of a traffic

    network model. The model is based on an AM Peak period only and is not all coded is simulation.

    That is, not all the junctions and links in the model include the geometric data that would influence the

    assignment of the trip within the network. Therefore further work will be required to upgrade the

    network in the locality of the proposed SDA and a PM peak period. This will provide confidence that

    the preferred option is still a valid with the return trip. Nevertheless, in the absence of a fully

    simulated model covering the Fareham area including the county roads, the existing SSTM represents

    the best traffic data source available for this project, a view shared by the Highways Agency.

    A sort summary of why each option was dismissed or considered suitable is provided for reference

    below:

    Option 1 The exiting junctions on the M27 do not have sufficient capacity to

    accommodate the proposed SDA traffic.

    Option 2 New M27 J10 all traffic movements would contravene policy set out DfT

    Circular 02/07.

    Option 3 The option would be viewed as a new M27 J10 and would therefore contravenepolicy set out DfT Circular 02/07.

    Option 4 Provide west facing slip roads which would provide little benefit to the whole

    scheme and does not easily prioritise BRT movements to Fareham Town Centre; and

    Option 5 is viewed as the most suitable option and is therefore taken forward for more

    detailed traffic modelling analysis.

    The traffic levels likely to be generated by the proposed SDA will not be accommodated by any of the

    options proposed. Therefore the solution for access to the proposed SDA will requiring a significant

    proportion of the forecast car demand to be accommodated in an alternative way, eg containment or

    mode shift.

  • 8/2/2019 090925 Tfsh Fareham Study

    7/57

    Fareham SDA

    Access Study

    1 INTRODUCTION

    The South East Plan proposes that a Strategic Development Area (SDA) is built on land to the north of

    Fareham. The proposed SDA is to consist of up to 10,000 dwellings and 121,000 square metres of

    employment development, delivered between 2016 and 2026. It is recognised that this scale of

    development will have a significant impact on the local transport infrastructure. The location of the

    proposed SDA site is to the north of the M27 at Fareham, Figure 1.1.

    Figure 1.1 Proposed Fareham SDA Site Location

    J10

    J11

    A32SDA

    M27

    N

    A32

    Fareham

    A27

  • 8/2/2019 090925 Tfsh Fareham Study

    8/57

    Fareham SDA

    Access Study

    Setting Strategic Direction, Fareham SDA Mott Gifford/MVA February 2008.

    The study is to review options for providing access to the proposed SDA from the SRN. We haveapplied a two stage approach to the assessment. The first stage of this assessment considers all options

    available and assesses the proposals against criteria such as; conformity with relevant policy or/and

    compliance with the standards. The more feasible options are then taken forward to detailed traffic

    modelling and junction analysis.

    The scope of this assessment does not consider proposals for the internal network of the proposed

    SDA.

    The remainder of this report is structured as follows:

    Chapter 2 states the data sources used for this study

    Chapter 3 - describes the methodology for the assessment of the junctions

    Chapter 4 provides an initial assessment of the options;

    Chapter 5 - presents the results of the traffic modelling of each of the feasible options;

    Chapter 6 - highlights the cost implications for each of the feasible options;

    Chapter 7 - sets out summary of the report findings; and

    Chapter 8 - highlights the conclusions and recommendations.

  • 8/2/2019 090925 Tfsh Fareham Study

    9/57

    Fareham SDA

    Access Study

    2 ACCESS STUDY DATA SOURCES AND ASSUMPTIONS

    2.1 Solent Strategic Transport Model

    Background traffic flow data for the study has been sourced from the Solent Strategic Traffic Model

    (SSTM) developed by Atkins for Hampshire County Council to represent travel demand in the Solent

    area. The SSTM represents an average hour within the morning peak period (0700-1000) and an

    average hour within the inter peak period (1000-1600) in 2004. The evening peak period has not been

    modelled within SSTM and has not been considered as part of this study. Assessment of the PM peak

    will be important at some stage as a valid option for the AM peak may not be suitable for the PM peak

    and additional refinement may potentially be needed.

    The highway network has been modelled using the SATURN suite of programs. It was based on an

    existing model developed by WSP for the Highways Agency, which was in turn based on based on the

    M27 ITS study carried out by MVA.

    The network density is shown in Figure 2.1. The model includes all the Motorways, A roads, B roads

    and other roads that are considered to carry high volumes of traffic.

    Figure 2.1: Highway Network Density

    N

    Southampton

  • 8/2/2019 090925 Tfsh Fareham Study

    10/57

    Fareham SDA

    Access Study

    The network has a mixture of buffer and simulation coding (simulation coding takes account of delays

    due to junctions). The motorway network and associated junctions have been coded in simulation and

    the Portsmouth area has also been coded in simulation; the rest of the network has been coded asbuffer using speed-flow curves to take account of delays. This type of coding is only suitable for areas

    that are not congested.

    Within the study area for this project, both M27 Junction 10 and 11 are simulated in the model,

    although junctions on the A32 north and south of the motorway are coded in buffer making the

    predicted reassignment of traffic on the wider network in response to any proposed changes at M27

    Junctions 10 and 11 (e.g. realigned A32) potentially open to question. However, in the absence of a

    fully simulated model covering the Fareham area including the county roads, the existing SSTM

    represents the best traffic data source available for this project, a view shared by the Highways

    Agency (Appendix A).

    2.2 New Transport Model

    The limitations of the existing SSTM to provide an accurate representation of the traffic implications

    associated with new highway infrastructure are recognised by the two relevant highway authorities,

    Hampshire County Council and the Highways Agency. A new more detailed model of the local area is

    in preparation, with data collection currently ongoing. The new transport model will capture the

    current network issues, such as queuing on the M27 mainline in the peak periods.

    Any preliminary conclusions set out in this report will need to be reassessed once the new improved

    modelling tool is available.

    2.3 Development Traffic

    Traffic forecasts for development proposals in the local area as set out in the draft core strategies

    including the SDA, are taken from Peter Brett Associates (PBA) Transport Assessment titled

    Assessing the Impact of Harbour Authorities LDF Proposals on the Strategic Highway Network and

    produced in July 2008.

    The PBA work provides a very detailed quantification and distribution analysis of traffic associated

    with all development sites included within the draft core strategies for Fareham, Gosport, Havant and

    Portsmouth. This study has taken the PBA figures at face value as scrutiny of the PBA report is not

    part of this project scope. We understand from PBA that the following approach was applied to the

    derivation of traffic forecasts associated with the SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    11/57

    Fareham SDA

    Access Study

    PBA provided traffic turning movements for the study area network extracted from SSTM in the

    with and without SDA development scenarios set out below. Where Bus Rapid Transit (BRT) is

    included in Scenario 3, a reduction in traffic demand as a result of mode switch to BRT by car usershas been allowed for in the PBA figures:

    Scenario 1 Base (No Development SDA)

    Scenario 2 Base + Development SDA existing highway network; and

    Scenario 3 Base + Development SDA + BRT +A32 realigned to M27 J11.

    Initial observations of the data show a considerable increase in traffic travelling eastwards towards

    Fareham and Portsmouth. It is not possible with the data selected for this study from the PBA model to

    determine the likely increase in traffic north of the proposed SDA.

    2.4 Past Reports

    As described above, three studies have been carried out over the past year to consider the transportimplications of the SDA. These previous reports are listed below and a short description of each report

    follows:

    BRT Alignment and Operation Assessment WSP August 2008;

    Assessing the Impact of the Harbour Authorities Local Development Framework Proposals on

    the Strategic Highways Network Peter Brett Associates July 2008; and

    Setting Strategic Direction, Fareham SDA Mott Gifford/MVA February 2008.

    2.4.1 BRT Alignment and Operation Assessment WSP (August 2008)

    WSP Development and Transportation was commissioned by PRUPIM, a stakeholder in the

    development for the proposed Fareham SDA, to assess the BRT alignment options between Fareham

    Town Centre and the SDA.

    The alignments investigated by the study were put forward by both PRUPIM and Hampshire County

    Council as part of previous related studies.

    The principle focus of the assessment was to identify a route that would best serve the SDA in terms

  • 8/2/2019 090925 Tfsh Fareham Study

    12/57

    Fareham SDA

    Access Study

    The study provided policy context for the development of a comprehensive BRT network in South

    Hampshire. The BRT proposal developed from a light rail transit (LRT) which HCC was forced to

    abandon by central government in 2005 on the grounds of cost. The LRT project proposed to linkFareham, Gosport and Portsmouth and was also known as the South Hampshire Rapid Transit

    (SHRT).

    Despite the abandonment of the LRT scheme, development of a new transit system continued. During

    the development of LRT two alternative schemes were considered, with BRT seen as the next best

    option to deliver some of the strategic benefits of the LRT for the area. This is supported in both the

    Hampshire County Councils Local Transport Plan 2 (2006-2011) and Fareham Borough Council

    transport strategies for the proposed SDA.

    The WSP report therefore explored four BRT options, three of which had sub-options for routes

    through Fareham. The options considered were as follows:

    Option 1 Access via disused rail line route;

    Option 2 Access Via Kiln Lane;

    Option 3 Access via Funtley Hill; and

    Option 4 Access via the A32 (M27 Junction 10).

    The report tested the options in terms of operational requirements, assessing whether the options

    provided an efficient network with high levels of accessibility. The assessment examined the potential

    journey times, locations of bus stops and vehicle requirements to operate the route option and provided

    an engineering assessment of each route.

    The report ranked the options using a scoring matrix against the following Criteria:

    Integration with the wider BRT system;

    Ensuring Journey Time Reliability;

    Provide access to central Fareham;

    An efficient and accessible route throughout the SDA sectors;

    Cost; and

  • 8/2/2019 090925 Tfsh Fareham Study

    13/57

    Fareham SDA

    Access Study

    The report did not select an option but provided data to inform debate on the options available to serve

    the proposed SDA with BRT. This assessment cannot, and does not, determine the preferred BRT

    routing. However, of the two highest scoring options, Option 4 provides a scheme that requiresconsiderably less traffic management measures to be implemented, as the route for BRT would follow

    the A32 for the majority of its journey. Whereas, Option 3 would require considerable investment in

    junction improvements to accommodate bus priority systems and permanent changes to the

    management of residential traffic flows in the north Fareham area.

    For the SDA Access Study it is assumed that Option 4 is used as the basis for BRT provision between

    the SDA and Fareham Town Centre. However, it should be stressed that this selection is for the

    assessment of SDA Access options to the M27 only and does not conclude the selection process

    required for BRT routing. Indeed the final access strategy for the proposed SDA will need to consider

    the wider impact of BRT options which is outside the scope of this study.

    2.4.2 Assessing the Impact of the Harbour Authorities Local Development FrameworkProposals on the Strategic Highways Network Peter Brett Associates (July 2008)

    The Peter Brett Associates (PBA) study focused on updating the Solent Strategic Transport Model and

    calculating a detailed forecast of growth and distribution patterns related to the development proposals

    set out in the Core Strategies of the Harbour Authorities. The model was for an AM peak period only.

    PBA supplied Mott MacDonald with the model results for the M27 Junctions 10 and 11. Three

    scenarios were provided which were the with and without the proposed SDA development.

    The PBA assessment was not required to investigate mitigation measures for the traffic issues

    identified in their model. Mott MacDonald therefore continues on from PBAs initial assessment andinvestigates suitable access options for the proposed SDA.

    It was noted that the projected traffic flows at the M27 J10 and J11 showed that demand to and from

    the east was considerably higher than those to and from the west.

    2.4.3 Setting Strategic Direction, Fareham SDA Mott Gifford/MVA (February 2008)

    The report considered the transport implications of the proposed large development area included in

    the South East Plan known as North Fareham Strategic Development Area (SDA). The Summary of

    the report provides a concise review of the report main findings and is provided in Appendix B for

    reference. A distilled version of the summary is provided below, focusing on the main transportation

    issues pertinent to this Access Study.

  • 8/2/2019 090925 Tfsh Fareham Study

    14/57

    Fareham SDA

    Access Study

    A containment factor of 40% was assumed for the purposes of the study, i.e. 40% of the economically

    active population will live and work in the SDA. If the containment factor were lower, the movements

    to and from the SDA during the peaks could be very significantly higher. The robustness of the 40%figure should be considered in detail before any clear conclusions are drawn regarding transport

    measures required to deliver the SDA;

    The distribution of trips associated with the SDA during the peak periods is orientated strongly

    towards Portsmouth as the main employment and retail centre;

    Public transport connectivity to key destinations is critical and Bus Rapid Transit is the centrepiece of

    the public transport strategy for the SDA, with a route proposed to penetrate the site through M27 J10.

    Consideration of highway access from the Strategic Road Network (SRN) involved the M27 J10 and

    M27 J11, as well as a combination of the two. Any solution will need to complement the SDAs public

    transport package rather than compete against it and any option which allows movement for all traffic

    through M27 J10 will dilute the attractiveness of the BRT by limiting its journey time advantage over

    the car for trips between the SDA and Fareham;

    With a 40% containment factor applied and a progressive approach to the impact of smarter choices,

    the preferred option for highway access from the SRN is to realign the A32 just south of Albany Farm

    to tie in the M27 J11. The link will need to be a dual carriageway with two lanes both north and

    southbound. M27 J11 would be improved through the introduction of a single lane free-flow

    eastbound on-slip.

    The existing A32 through M27 J10 and its existing east-facing slip roads would operate as bus/High

    Occupancy Vehicle only, thus accommodating the buses on a north/south alignment whilst providingquick access from the SDA to/from the M27 and the proposed bus/HOV lane using the M27 hard

    shoulder. Careful consideration would be needed regarding the enforcement of this proposal, as with

    any HOV scheme and the time periods in which the restrictions would apply;

    Only a small percentage of trips associated with the SDA would be distributed to the north towards

    Alton. The A32 north of the SDA would carry significant traffic levels with or without the SDA going

    ahead, as background traffic using this route is forecast to increase in 2026; and

    Although a transport strategy has been identified which will provide multi-modal access between the

    SDA and its key destinations, the strategy has not been considered in the context of demand

    management measures such as city centre parking controls. The aspirations for sustainable

    development are only likely to be realised in terms of transport if area wide demand management of

    t i i l t d t i t th t 20

  • 8/2/2019 090925 Tfsh Fareham Study

    15/57

    Fareham SDA

    Access Study

    2.5 Other Supporting Documents or Studies

    2.5.1 Circular 2/07: Planning and the Strategic Road Network - Department for Transport

    Circular 2/07 provides an explanation of how the Highways Agency (HA) is to participate in all stages

    of the planning process. The document sets out a framework for collaborative working coordinating a

    number of organisations including Government Offices, regional and local planning authorities, local

    highway authorities, public transport providers and developers. The aim of this working alliance is to

    ensure national and regional objectives are aligned with a common objective in terms of the strategic

    road network and standards.

    In summary the circular details how:

    The HA will have an active involvement in the development of Regional Spatial Strategies,

    Local Development Frameworks;

    Working together and in partnership will establish mutual goals and assist in the production of

    a sustainable development policy; and

    Sets out how the HA will deal with planning applications.

    The circular emphasises the importance of consultation in securing delivery of sustainable and

    effective outcomes for the road network, which will not burden other road users should a development

    go ahead.

    With regard to this assessment, an access study, 'The Capacity enhancements and access to the

    network' section is the most pertinent in determining the appropriate access strategy for the SDA ontothe SRN.

    In section 41 of the DfT document it states that:

    There is a general presumption that there will be no additional accesses to motorways and other

    routes of strategic national importance, other than the provision of service areas, facilities for the

    travelling public, maintenance compounds and, exceptionally, other major transport interchanges.

    Access from other types of development to motorways and other routes of strategic national

    importance will be limited to existing junctions with all-purpose roads. Modifications to existing

    junctions will be carried out only where traffic flows and safety will not be adversely affected.

    Connections to slip roads and/or connector roads will not be permitted.

    Therefore based on the above statement if an option for access to the SDA requires a new junction on

  • 8/2/2019 090925 Tfsh Fareham Study

    16/57

    Fareham SDA

    Access Study

    For the Fareham SDA the Companion Document states:

    At Fareham: careful balance between maintaining settlement identity and maximising opportunitiesfor sustainable movement between the SDA and the existing urban area; quality of public transport

    connections with Portsmouth, including the development of an attractive bus based service linking

    Portsmouth and Fareham via Gosport; sensitive treatment of the relationship with Portsdown Hill to

    the east of the SDA location, and of the setting of the neighbouring settlements

    This statement therefore confirms regional planning policy support for providing options that improve

    transport links eastwards, towards Portsmouth.

    2.5.3 A32 Access Study - Mott Gifford (December 2008)

    Although not part of this assessment the realignment of the A32, as identified in the Mott Gifford/

    MVA report above plays a significant role in the development of any access improvements for the

    proposed Fareham SDA. A high level assessment of the route options for the A32 realignment has

    been undertaken for the A32 Realignment Study carried out by Mott Gifford. The realignment study

    assesses seven potential routes between the existing A32 and M27 Junction 11.

    The implication of the A32 realignment has also been considered in the WSP and PBA reports. Indeed

    the PBA model provided a projection of likely reassignment of trips between M27 J10 and J11, should

    the link be provided. For this assessment the exact line of the route is not important, however the

    likely reassignment of trips between M27 J10 and J11 with improved infrastructure in place is a key

    issue.

    2.5.4 High Occupancy Vehicle Lanes Fact Sheet 2002 and ICARO 1999 (Leeds City Council)

    The use of an High Occupancy Vehicle lanes is considered in this study. To determine the likely

    reassignment of traffic movements the High Occupancy Vehicle Lanes Fact Sheet 2002 and ICARO

    1999 has been referenced. The link to the online document is provided below.

    (www.konsult.leeds.ac.uk/private/level2/instruments029/12_029c.htm accessed on 29/10/2008

    The study investigated HOV lanes and provides case studies. In essence an HOV lane is designed to

    discourage single or low occupancy car use by providing priority to vehicles with more than a

    minimum number of people (usually 2 or 3). In turn, possible congestion will be reduced as there will

    be fewer vehicles on the road. In order to gain public support for HOV lanes, it is crucial to police the

    appropriate use of this lane. Enforcement, according top the case study at the above link, can be either

    http://www.konsult.leeds.ac.uk/private/level2/instruments029/12_029c.htm%20accessed%20on%2029/10/2008http://www.konsult.leeds.ac.uk/private/level2/instruments029/12_029c.htm%20accessed%20on%2029/10/2008http://www.konsult.leeds.ac.uk/private/level2/instruments029/12_029c.htm%20accessed%20on%2029/10/2008
  • 8/2/2019 090925 Tfsh Fareham Study

    17/57

    Fareham SDA

    Access Study

    3 TRAFFIC ASSESSMENT METHODOLOGY

    3.1 Assessment Year

    The year of assessment is 2026 when it assumed that the SDA will be completed.

    3.2 Assessment Period

    In the absence of a PM peak model, and with confirmation that an AM peak assessment using SSTM

    is acceptable to the Highways Agency for the purposes of assessing impact of Farehams core strategy

    on the Strategic Highway Network, the SSTM 2026 AM peak hour period is the assessment period.

    3.3 Study Area

    The study area includes M27 Junctions 10 and 11 including motorway slip roads. Non-motorwayjunctions are not considered within this study.

    3.4 Assignment of Traffic

    The short study programme does not allow for an iterative approach to testing and developing all the

    potential access strategy options. Ideally, proposed modifications to the network would be coded into

    the SATURN model with assignments run to understand the resultant redistribution of traffic betweenthe two junctions (including background traffic), prior to more detailed analysis. The approach to

    reassignment in this study is therefore mainly a first principles manual approach based upon a number

    of assumptions. The one exception is the option to realign the A32 to tie in to M27 Junction 11, which

    PBA had assumed in their study and the reassignment of traffic from the wider area in response this

    scheme has been allowed for in the flows extracted from SSTM. Assumptions applied to the manual

    assignment of traffic are : -

    If a new all moves junction is provided at J10 then traffic to and from the A27 will be shared

    between J11 and J10 70%/30% respectively. The distribution of these trips east and west is in

    the same proportion to the base data;

    Where BRT priority is proposed at the M27 Junction 10, only BRT vehicles are permitted on

  • 8/2/2019 090925 Tfsh Fareham Study

    18/57

    Fareham SDA

    Access Study

    Figure 3.1: Illustration of Trip Reassignment Assumptions

    J10

    J11

    N

    M27

    SDA35%

    SDA

    65%

    SDA

    A32

    30%

    A32

    70%

    A27Fareham

    3.5 Design flows for lane requirements

    The design flows for the traffic lanes requirements are based on the Highways Agency Design Manual

    for Roads Bridges standards TD22/06 Layout of Grade Separated Junctions. It is assumed that the

    design flow per lane is 1,600 vehicles per hour (vph) for all-purpose roads, and 1,800vph per lane for

    motorways Although these figures do not represent the maximum throughput per lane greater traffic

  • 8/2/2019 090925 Tfsh Fareham Study

    19/57

    Fareham SDA

    Access Study

    4 ASSESSMENT OF ACCESS OPTIONS

    4.1 General

    This section reviews the highway options proposed for access to the Fareham SDA from the M27. For

    reference an indicative highway layout is presented with each option. For this first stage the internal

    layout of the proposed SDA and details of lane layouts at the junctions is not considered.

    4.2 Description of Options

    Five broad options have been proposed which provide access to the proposed SDA from the M27.

    Three of the options have previously been considered in the Setting Strategic Direction, Fareham

    SDA report produced by Mott Gifford/MVA Consultancy.

    The options which are considered in this study are:

    Option 1 Do Minimum Only minor changes to the highway network are made in this

    scenario.

    Option 2 New all traffic movements junction is provided west of the existing M27 J10

    with the Bus Rapid Transit route using the existing M27 J10.

    Option 3 West facing slip roads are provided to the west of M27 J10 with the A32

    realigned to M27 J11. A BRT route is provided through the existing M27 J10;

    Option 4 Existing M27 J10 is upgraded to accommodate all traffic movements and the

    A32 is realigned to join M27 J11; and

    Option 5 M27 J10 remains unchanged with a dedicated BRT route in peak periods and the

    A32 is realigned to join M27 J11.

    A matrix of which features are included in each option is presented in Table 4.1 below. A description

    of the elements is also provided for reference.

    Table 4-1 Option Matrix

  • 8/2/2019 090925 Tfsh Fareham Study

    20/57

    Fareham SDA

    Access Study

    Additional West facing slip roads at J10 The option proposes to provide west facing slip roads

    at M27 Junction 10 but as a separate junction.

    New All moves junction at M27 J10 - A new junction is constructed to the west of M27 J10. This

    would be an all moves junction allowing traffic from the north and south of the M27 to access the

    M27 east and westbound mainlines.

    A32 Realigned to tie into M27 J11 - Assumes a link between the existing A32 and the M27 J11.

    For this study the alignment of the link is not significant and therefore the reassignment of traffic

    between the junctions is the same for each option that includes this element.

    The realignment of the A32 at M27 J11 assumes the provision of a segregated left turn lane from A32

    to the M27 eastbound slip road. The type of segregated lane is illustrated in the Highways Agency

    Design Manual for Roads and Bridges TD51/03 at Figure 2/6. This shows a segregated lane feeding

    directly into the offside lane of the slip road. This arrangement takes advantage of the current M27 J11

    layout where two lanes are provided on the slip road to M27 eastbound mainline

    BRT & HOV Lane Assumes that access at the existing M27 is restricted to Bus Rapid Transit

    (BRT) and High Occupancy Vehicles (HOV). This restriction is assumed to be applied across the

    whole peak assessment, ie the AM peak period. BRT and HOV could be phased in at stages of

    development, with the HOV element of the proposal coming in much later. Once the development

    matures, an HOV policy could be initiated, furthering the cumulative impact of modal shift to ease

    possible congestion. As per the Leeds case study, the restrictions on access through the junctions

    would most probably be for peak periods only.

    As highlighted in the WSP report, reducing congestion on the Fareham/Gosport peninsula is a priorityfor Hampshire County Council. This will be achieved in part by the provision of a dedicated route for

    high speed bus travel between Gosport and Fareham. The proposed BRT link between the proposed

    SDA and Fareham Town Centre is seen as a key element of that scheme.

    All traffic on M27 J10 Slip roads Some options assume that certain turning moves would be

    banned for all motorists as a result of HOV or BRT at M27 J10. Therefore if no restrictions are

    implemented then an all moves/ all traffic junction is possible.

    4.3 Option Cost Review

    An order of magnitude cost for each option has been estimated which allows comparison between

    each option. However, the estimates were based upon basic information with a high level of risk.

  • 8/2/2019 090925 Tfsh Fareham Study

    21/57

    Fareham SDA

    Access Study

    Statutory undertakings

    Major road land drainage

    Design

    4.4 Assessment Criteria

    The options will be assessed against the following criteria:

    Policy

    o Whether the proposal meets the aspiration of providing a suitable BRT link betweenSDA, Fareham and towards Portsmouth;

    o In line with Regional Spatial Strategy for the South East that the option prioritises

    improvements to eastern facing transport links between the SDA and the Portsmouth

    area; and

    o The access strategy conforms to Department for Transport Circular 02/07.

    Design Standards - Compliance with HA DMRB;

    Traffic Capacity - Suitability in terms of providing appropriate level of traffic capacity;

    Cost/ Benefit Whether the scheme is Value for money considering the likely traffic flows

    using the proposed facility; and

    Deliverability Issues Assesses likely land take and construction issues such as likely impact

    on existing structures, road infrastructure (outline design level only) or communities.

    As this is a high level assessment the identification of deliverability issues for each option is in broad

    terms only. This study does not investigate detailed issues such as; geotechnical constraints, structural

    suitability, construction phasing issues, exact land take and associated works. The deliverability

    assessment is to determine whether the option has any fundamental risks that would result in the

    option being wholly undeliverable. Therefore there may still be some construction challenges/ riskseven if the scheme is viewed in this assessment as a suitable option.

    The assessment may not provide commentary on every aspect identified above as analysis may reveal

    that a single criterion is sufficiently detrimental for the option to be discounted eg if the scheme

    contravenes policy set out in DfT Circular 02/07.

  • 8/2/2019 090925 Tfsh Fareham Study

    22/57

    Fareham SDA

    Access Study

    4.5 Option Evaluations

    4.5.1 Option 1 Do Minimum

    (i) Description of Option

    This option assumes that there would be no improvements made to the existing road network. Access

    to the proposed development would therefore be achieved via J10 where east facing only slip roads arecurrently provided. Trips arriving from the west on the M27 would be required to u-turn at J11 then

    travel west to J10 to access the development. All egress from the proposed development onto the M27

    is achieved at J10 through the east facing slip road. Therefore vehicles from the development wishing

    to travel west would need to undertake a u-turn at J11.

    This option is identified as the Do Minimum scenario and is illustrated in Figure 4.1 below.

    Figure 4.1 Option 1 Do Minimum

    N

    A32

    SDA

    J10

    M27

    J11A32

    FarehamA27

  • 8/2/2019 090925 Tfsh Fareham Study

    23/57

    Fareham SDA

    Access Study

    In addition the alternative BRT alignments through North Fareham west of the A32 are likely to be

    challenging to deliver as they could require substantial traffic management measures and bus priority

    junction improvements to be made. Such an option would reduce journey time advantages for the BRTand could result in additional land take requirements.

    The option does not provide an improved access for east facing slip roads and therefore could be seen

    as contravening Regional Spatial Strategy aspirations.

    The option does not provide any improvements to accommodate the additional traffic demand. The

    Highways Agency, in accordance with DfT Circular 02/07, would not endorse this option as this could

    compromise the level of service on the M27 by placing addition traffic pressure on slip roads andjunctions that are currently over capacity.

    Conclusion

    To dismiss any improvements would exacerbate existing queuing problems, due to the additional

    development traffic demand.

    This scheme has been discounted as a viable access option as it does not satisfy current transportpolicy.

  • 8/2/2019 090925 Tfsh Fareham Study

    24/57

    Fareham SDA

    Access Study

    4.5.2 Option 2 New M27 J10 all traffic movements

    (i) Description of Option

    Option 2 proposes to provide a new all moves junction, located to the west of the existing J10. For

    Option 2 a BRT route is provided through the existing M27 J10 and therefore southbound access for

    traffic travelling to Fareham is restricted. Access north bound for local traffic is still permitted. A

    sketch of Option 2 is shown at Figure 4.2 (schematic layout only).

    Figure 4.2 Option 2 new M27 J10 with BRT

    A32

    N SDA

    J10

    M27

    J11

    A32Fareham

    A27

    (ii) Option Appraisal

    Policy

    This option would allow a high speed bus link to be provided between the SDA and Fareham through

    the existing M27 J10. Therefore this option is considered a suitable option in policy terms. Priorities

  • 8/2/2019 090925 Tfsh Fareham Study

    25/57

    Fareham SDA

    Access Study

    Design Standards

    Notwithstanding the above policy failure of such an access proposal, a major risk for the suitability ofproviding a new all moves M27 J10 is achieving the weaving length specified in the Highways

    Agency Design Manual for Roads and Bridges (DMRB). The minimum distance specified for the

    weaving length is 2km between junctions (DMRB Vol. 6 TD22/06).

    An alternative solution would be to reduce the weaving distance required by lowering the existing

    speed limit on this section of the M27. It is questionable whether the Highways Agency (HA) would

    find such a strategy an acceptable solution.

    Traffic Capacity

    The PBA traffic model for the AM peak scenario indicates that the A32 would need to be upgraded to

    a dual carriageway with three lanes southbound and two lanes northbound. To reduce the A32

    southbound carriageway to a two lane carriageway the development traffic would need to be reduced

    by between 10% and 20% in the AM Peak. Beyond the SDA development the number of lanes

    required is likely to be less.

    Having such a major road travelling through the site on a north-south axis would result in a major

    severance issue within the proposed SDA development compromising the east/ west permeability of

    the site.

    Cost/ Benefit

    The order of magnitude cost for Option 2 has been estimated to be in the region of 11,535,000

    The PBA model flows indicate that westbound demand is considerably lower than eastbound demand.

    Such low levels of demand could make it difficult to justify a large expenditure on infrastructure and

    land purchase when investment in the A32 link and associated M27 J11 improvements could provide

    similar benefits to this westbound traffic, as well as improve eastbound access capacity.

    Deliverability Issues

    The provision of a new major grade separated junction on the M27 will require considerable land take.

    As well as land take for the junction itself, consideration will need to be made on how such a junction

    could be linked to the existing highway network. It is likely that any connector roads could result in

    moderate severance issues for both the proposed SDA and considerable traffic impact on the

    residential area north of Fareham Town Centre.

  • 8/2/2019 090925 Tfsh Fareham Study

    26/57

    Fareham SDA

    Access Study

    To satisfy DMRB standards the new junction would be located and aligned in such a manner

    that the connector roads would result in considerable traffic impact on the residential area

    north of Fareham Town Centre. The connector roads would also impact on the aspirations ofthe SDA master plan layouts by splitting the site into two parts.

    This option will therefore not be considered for further assessment.

    F h SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    27/57

    Fareham SDA

    Access Study

    4.5.3 Option 3 Split M27 J10 all traffic movements

    (i) Description of Option

    Option 3 proposes to upgrade M27 J10 to an all moves junction for access to the SDA only. The

    junction improvement would essentially be a mirror of the existing junction providing the missing

    west facing slip roads. Option 3 would therefore have the following improvements or features:

    New west facing slip roads for all traffic moves at M27 J10.

    Realigned A32 to M27 J11;

    Southbound access to Fareham through J10 would be restricted to BRT only;

    Slip roads at J10 would be restricted to HOV and BRT access only.

    A sketch of Option 3 is presented in Figure 4.3 below (schematic layout only see Mott Giffordreport A32 Realignment, Options Identification)

    Figure 4.3 Option 3 split M27 J10 with A32 realigned

    J10

    J11

    M27

    A32

    A32

    SDAN

    F h SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    28/57

    Fareham SDA

    Access Study

    In terms of the Regional Spatial Strategy this proposal does provide improvements for east facing

    transport links via the realigned A32 to the M27 J11. However, the Highways Agency, in accordance

    with DfT Circular 02/07, would not endorse this option as the new slip roads would be viewed as anew junction onto the M27.

    Design Standards

    For the west facing slip roads it is assumed that any new junction designed at this site will be designed

    in accordance with HA DMRB standards.

    To satisfy DMRB standards the new slip road could be located and aligned in such a manner that theconnector roads could result in considerable traffic impact on the aspirations of the SDA master plan

    layouts by splitting the site into two parts.

    This study does not consider issues associated with the potential alignment of the new A32 link road.

    A separate Mott Gifford study provides an assessment of potential link alignments called Fareham

    Strategic Development Area, A32 Realignment Options Identification.

    It is assumed that the M27 J11 segregated left turn lane from the new A32 link to the eastbound M27mainline will be designed in accordance to TD51/03.

    Traffic Capacity

    With these probable changes in flows it is envisaged that no alterations would be required for the

    existing A32. However, the new A32 realignment would need to be a dual carriageway with three

    lanes eastbound to M27 J11 and two lanes westbound from the junction. To reduce the realigned A32

    to a dual carriageway with two lanes in both directions the eastbound development traffic would need

    to be reduced by up to 10%.

    Based on the reassignment of PBA flows the new connector roads at the split J10 could be single

    carriageway.

    It should be noted that the proposed junction improvements at J11 might not have sufficient capacity

    to accommodate the eastbound flows derived from the PBA model. Therefore it is assumed that any

    demand over and above the capacity of the segregated left turn lane will be dealt with by reducing

    trips from the SDA. The likely reduction of trips required from the site may be in the order of between

    50-60% of east bound trips after the BRT and HOV reassignment.

    Cost/ Benefit

    Fareham SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    29/57

    Fareham SDA

    Access Study

    As discussed above in the option descriptions the A32 will connect to M27 J11. For eastbound traffic

    from the SDA a segregated left turn lane will be provided. There is a risk that the additional traffic on

    this slip road could require the merging section of the slip road to be extended beyond the bridge forDownend Road. This could result in the span of the bridge needing to be increased.

    Conclusion

    The Option is considered unsuitable for the following reasons:

    The option does not conform to policy set out in DfT Circular 02/07 as this is considered to be

    a new junction onto the SRN.

    The likely cost to benefit ratio may be disproportionate for a new west facing slip roads as the

    flows to and from the west that the junction would facilitate are low.

    To satisfy DMRB standards the new junction may be located and aligned in such a manner

    that the connector roads compromise the aspirations of the SDA master plan layouts by

    severing the site into two parts.

    This option is therefore not considered further due to the cost and severance issues identified above.

    Fareham SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    30/57

    Fareham SDA

    Access Study

    4.5.4 Option 4 Existing M27 J10 all traffic movements

    (i) Description of Option

    Option 4 proposes to provide a dumbbell type junction. Option 4 would therefore have the following

    improvements or features:

    Two new roundabout junctions located on the existing A32 either side of the M27

    New west facing slip roads for all traffic moves at M27 J10.

    Realigned A32 to M27 J11;

    A sketch of the layout is presented in Figure 4.4 below (schematic layout only see Mott Gifford

    report A32 Realignment, Options Identification). The assessment of this proposal assumes that the

    new A32 link would be provided to M27 J11.

    Figure 4.4 Option 4 M27 J10 all traffic movements with A32 realigned

    J10

    N

    M27

    A32

    SDA

    J11A32

    FarehamA27

    Fareham SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    31/57

    Access Study

    (ii) Option Appraisal

    Policy

    This option requires access to the southern section of the junction to be open to all traffic for the west

    facing slip roads. This option would therefore not be able to provide a priority route for BRT through

    M27 J10. The proposed A32 Link Road prioritises eastbound movement by providing a second link

    to/from the SDA site.

    Although an alternative BRT route could be provided, as discussed above in Section 2, BRT

    alignments through North Fareham west of the A32 are likely to be challenging to deliver as theycould require substantial traffic management measures and bus priority junction improvements to be

    constructed. Such measures could result in additional land take requirements.

    Providing west facing slips at M27 J10 may have considerable impact on the residential area in North

    Fareham as additional trips could reassign from M27 J9 and J11 to this junction.

    With regard to DfT Circular 02/07, this option is viewed as a junction improvement, so is acceptable.

    Cost/ Benefit

    The order of magnitude cost for Option 4 has been estimated to be in the region of 79,096,000.

    The PBA model flows indicate that westbound demand is considerably lower than eastbound demand.

    Such low levels of demand might make it difficult to justify a large expenditure on infrastructure and

    land purchase when investment in M27 J11 improvements could provide similar benefits to this

    westbound traffic, as well as improve the junctions performance for eastbound access.

    Conclusion

    This scheme has been discounted as the access option does not provide a priority route for BRT from

    the proposed site to Fareham. An alternative BRT route could be used instead, however such a scheme

    could be complex to deliver compared to a direct route along the A32 through J10 which would have

    better journey time savings.

    There is a considerable risk of trips currently using M27 J9 and J11 reassigning to use this junction to

    travel west. This could greatly increase congestion in this area of north Fareham.

    In cost benefit terms the infrastructure investment for the west bound slip roads may be

    Fareham SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    32/57

    Access Study

    4.5.5 Option 5 Existing M27 J10 BRT/HOV only with A32 link to J11

    (i) Description of Option

    Option 5 would have the following improvements or features:

    No major infrastructure changes to M27 J10;

    Realigned A32 to M27 J11;

    Segregated left turn lane at J11 to allow direct access to M27 eastbound mainline;

    Southbound access to Fareham through J10 would be restricted to BRT only; and

    Slip roads at J10 would be restricted to BRT access only.

    Option 5 is illustrated in Figure 4.5 below (schematic layout only see Mott Gifford report A32

    Realignment, Options Identification).

    Figure 4.5 Option 5 M27 J10 with A32 realigned and BRT

    J10

    N

    M27

    SDAA32

    J11A32

    Fareham SDA

  • 8/2/2019 090925 Tfsh Fareham Study

    33/57

    Access Study

    In terms of the Regional Spatial Strategy this proposal does provide improvements for east facing

    transport links via the realigned A32 to the M27 J11.

    With regard to DfT Circular 02/07, this option is viewed as a junction improvement.

    Traffic Capacity

    It is assumed that there would be no need for any improvements to the existing A32 southbound. The

    new A32 realignment to M27 J11 would need to be a dual carriageway with two lanes to and from the

    M27 J11. It is recognised that the proposed segregated left turn lane at J11 would not have sufficient

    capacity for the eastbound demand. Therefore the eastbound trips generated by the development in theAM peak would need to reduce by between 50% and 60%.

    Cost/ Benefit

    The order of magnitude cost for Option 5 has been estimated to be in the region of 46,035,000.

    This option is focused on providing improvements to the M27 J11 and the realignment of the A32.

    The changes proposed at J10 could be minimal such as additional road markings and road signsbacked up by suitable enforcement measures.

    Deliverability Issues

    The connector road to J10 may still have substantial traffic flows as it is assumed that 35% of the trips

    generated by the site may be HOV. This could still result in moderate severance issues for the

    proposed SDA if the site was spilt east and west of the current A32.

    Conclusion

    The Option will be taken forward for further analysis for the following reasons:

    It facilitates BRT access from the SDA to Fareham;

    Provides improved east facing transport links;

    Conforms with DfT Circular 02/07; and

    The option provides additional junction capacity.

    This option is therefore taken forward for further analysis in the next section

    Fareham SDA

    A S d

  • 8/2/2019 090925 Tfsh Fareham Study

    34/57

    Access Study

    4.6 Merge and Diverge analysis

    All options have been assessed to determine the number of lanes required to meet merge and diverge

    standards as set out in HA DMRB guidance. The required merging and diverging parameters have

    been extracted from the DMRB standards TD22/06 Layout of Grade Separated Junctions. The

    assessment is presented in Table 4.2 below. Option 2 has not been analysed as it is assumed that the

    junction will be designed to HA DMRB standards, whereas the other options are improvements to

    existing junction layouts and therefore require analysis.

    Table 4-2 Summary of the Interchange Parameters

    Existing Option 1 Option 3 Option 4 Option 5

    M27 EB J10 Diverge (New) n/a n/a A A n/a

    J10 Merge A F A B E

    J11 Merge (New) n/a n/a F F F

    M27 WB J10 Diverge A A A A A

    J10 Merge (New) n/a n/a A G n/a

    A32 SB J10 Diverge C D A C A

    J10 Merge E E E E E

    Merge Diverge

    A - Taper merge A - Taper diverge

    B - Parallel merge C - Lane drop at Taper diverge

    E - Lane gain D - Ghost Island diverge for lane drop

    F - Lane gain with Ghost Island E - 2 Lane drop

    G - 2 Lane gain with Ghost Island

    For reference some broad descriptions and the illustration from DMRB for the merge and diverge

    layouts are provided below:

    o Taper Merge Is where a slip road from a junction joins the mainline carriageway through anarea forming a funnel to the mainline carriageway (Figure 4.1).

    Fareham SDA

    Access St d

  • 8/2/2019 090925 Tfsh Fareham Study

    35/57

    Access Study

    Figure 4.2: Parallel merge

    o Lane Gain The slip road from the junction does not taper but forms a new lane on the

    mainline carriageway (Figure 4.3).

    Figure 4.3: Merge with lane gain

    o Lane gain with ghost island This is where a two lane slip road is provided from the junction .

    The off side lane of the slip road merges with the mainline carriageway and the inside lanecontinues on to form a new lane on the mainline. The two slip road lanes are separated by a

    ghost island (Figure 4.4 and Figure 4.5).

    Figure 4.4: Lane gain with Ghost Island option 1

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    36/57

    Access Study

    Figure 4.5: Lane gain with Ghost Island merge option 2

    o 2 Lane gain with ghost island A two lane slip road from a junction form two new lanes on

    the mainline carriageway. The slip road lanes are separated by a ghost island (Figure 4.6).

    Figure 4.6: 2Two lane gain with Ghost Island

    o Taper Diverge - Where the slip road from the junction leaves the mainline carriageway

    through an area forming a funnel from the mainline carriageway (Figure 4.7).

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    37/57

    Access Study

    Figure 4.8: Lane drop at taper diverge

    o Ghost island diverge for lane drop Where a two lane off slip road is provided by diverting

    the nearside lane to form the first lane of the slip road and an additional taper diverge type slip

    for lane two of the mainline carriageway. The diverging lanes are separated with a ghost

    island (Figure 4.9).

    Figure 4.9: Ghost Island diverge for lane drop

    o 2 lane drop Two lanes on the mainline carriageway divert to form the off slip roads ( Figure4.10).

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    38/57

    y

    The results indicate that for the M27 eastbound merge at J10 only Option 3 satisfies the standards for a

    taper merge. All the other options could require the merging to be upgraded. Option 5, the preferred

    access option, will require a review of mainline flows to determine the actual design of the merge.

    Based on the PBA data indicates that the diverge movement for all the options satisfy the standards

    and therefore no changes would be required for options that include westbound diverge movements at

    M27 J10.

    4.7 Summary of the Initial Option Assessment

    The initial review of options reveals that OPTION 5 is the best option to satisfy the brief to provide

    access for the proposed SDA from the Strategic Road Network.

    The merge and diverge analysis revealed that Option 5 might require additional slip road capacity at

    J11 for eastbound trips. This can be achieved by increasing the slip road length and alignment.

    However, any such improvements could require the span of Downend Road bridge to be lengthened toaccommodate any additional lanes on the M27. In this study such infrastructure improvements are not

    considered.

    The assessment of the option is therefore not a predict and provide based assessment but uses a

    reverse engineering approach where analysis is made only on improvements that can be constructed

    within the limitations of the existing highway infrastructure. The traffic that cannot be accommodated

    within the improvements is then highlighted as the amount of demand that needs to be dealt with in

    some other manner, eg containment or mode switch. In the case of Option 5, based on thereassignment of PBA traffic forecasts, the eastbound SDA traffic could need to be reduced by between

    50% and 60% in the AM peak.

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    39/57

    y

    5 TRAFFIC MODELLING

    This chapter presents the results of the traffic modelling (Stage 2) for Option 5, which is the only

    option to be assessed.

    Option 5 requires the M27 Junction 11 to be modelled. The junction is fully signalised in Option 5 and

    therefore the TRANSYT computer program has been used for the capacity assessment. TRANSYT is

    the industry standard program, developed by Transport Research Laboratories to analyse fully-

    signalised or partially-signalised roundabouts. The junctions can be modelled, and their delay

    minimised, by calculating timings which reduce blocking-back by keeping the circulating carriagewayfree flowing.

    The base traffic model has been provided by WSP. The year of assessment for the proposed SDA is

    2026 when it is assumed that the site will be fully developed. The assessment was carried out for the

    morning peak period (AM) as per the PBA traffic data.

    It is assumed that improvements to M27 J11 will be required to accommodate the SDA development

    Flows and proposed A32 realignment. The model therefore includes the following alterations to the

    existing layout:

    Eastbound traffic from the A32 does not enter the roundabout but uses the segregated left turnlane; and

    A third lane on the M27 Mainline West Off Slip at the stop line.

    This is for an AM peak period only and additional changes or improvements may be required for a PM

    peak period to accommodate the return trip.

    A summary table of the results is provided below:

    Table 5-1: M27 Junction 11 Signalised Junction Modelling Results

    2026 Base Case No Development 2026 With Development andimprovements

    ArmMax Degree Of

    Saturation(%)

    Max QMax Degree Of

    Saturation(%)

    Max Q

    Proposed A32Link

    37 0 70 9

    M27 MainlineEast Off slip

    83 26 83 26

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    40/57

    It should be noted that this assessment assumes that the majority of demand for M27 Junction 11

    channelled into a segregated left turn lane between the realigned A32 and the M27 east mainline.

    Further assessment of the mainline flows and the merge arranges is required to confirm that this option

    is suitable.

    It should also be noted that the provision of the segregated left turn lane requires a significant

    reduction in vehicle trips generated by the proposed SDA development.

    Further refinement of the strategic model and the junction layouts should be undertaken to confirm

    that M27 J11 is suitable for the propose Fareham SDA.

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    41/57

    6 CONCLUSIONS AND RECOMMENDATIONS

    6.1 Conclusions

    This study approached the selection of the options for access to the SDA from the M27 in two parts.

    The first part assessed each proposal against broad evaluation criteria to narrow down the number of

    access options to be taken forward to detailed traffic assessment. The second section of the report

    provided a more detailed traffic assessment of the preferred option.

    This study reviewed five access options for the proposed Fareham SDA from/to the M27. The option

    appraisal section provided outline designs to illustrate the proposed access options. The five options

    were:

    Option 1 Do Minimum Only minor changes to the highway network are made in this

    scenario.

    Option 2 New all traffic movements junction is provided west of the existing M27 J10with the Bus Rapid Transit route using the existing M27 J10.

    Option 3 West facing slip roads are provided to the west of M27 J10 with the A32

    realigned to M27 J11. A BRT route is provided through the existing M27 J10;

    Option 4 Existing M27 J10 is upgraded to accommodate all traffic movements and the

    A32 is realigned to join M27 J11; and

    Option 5 M27 J10 remains unchanged with a dedicated BRT route in peak periods and the

    A32 is realigned to join M27 J11.

    The option evaluation section assessed each access proposal against five criteria which were:

    Policy;

    Design Standards;

    Traffic Capacity;

    Cost/ Benefit; and

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    42/57

    The traffic review element of the study based its traffic assessment on the reassignment of PBA

    SATURN traffic model data. The model used was for an AM peak period only and therefore there is

    an element of risk when considering the traffic implications of each option. The return trip in the PM

    peak could reveal that a valid option for the AM peak is not suitable for the PM peak and therefore

    require additional refinement or an alternative option, previously dismissed on other grounds, be

    considered.

    It is important to note that all the options which were considered beneficial in traffic terms included

    the A32 realignment.

    After the first stage of the assessment only Option 5 was taken forward for further analysis. The trafficdata was input into a TRANSYT Model, a programme used to model linked traffic signals. This

    revealed that Option 5 in the AM peak period worked satisfactorily.

    It was concluded that OPTION 5 is the most suitable access option for the proposed Fareham SDA,

    based on an AM peak period traffic assessment.

    6.2 Recommendations

    The traffic assessment of each option was based on the manual reassignment of an AM peak period

    model only. It would be advisable that the preferred option, Option 5, is coded into the new traffic

    model currently being developed. As well as providing more robust reassignment, this will reveal

    whether Option 5 is suitable, in traffic terms, for a PM peak period.

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    43/57

    Appendix A HA Letter

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    44/57

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    45/57

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    46/57

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    47/57

  • 8/2/2019 090925 Tfsh Fareham Study

    48/57

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    49/57

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    50/57

    Fareham SDA

    Access Study

  • 8/2/2019 090925 Tfsh Fareham Study

    51/57

    Appendix C TRANSYT Results

  • 8/2/2019 090925 Tfsh Fareham Study

    52/57

    Fareham SDA

    Access Study

    M M U if R d M M A

  • 8/2/2019 090925 Tfsh Fareham Study

    53/57

    C-2227552/01/C - 6 February 2009/C-2 of 6P:\Southampton\HCC\Projects\227552\JD Fareham SDA Access\02 Documents\Out\MG-Fareham SDA Access Study Report-01D.doc/AP

    Link NodeActualFlow

    (PCU/H)

    Sat.Flow

    (PCU/H)

    Degree OfSaturation

    (%)

    MeanCruise Time

    Per PCU(sec)

    MeanDelay TimePer PCU

    (sec)

    UniformDelay(PCU-H/H)

    Rand +OverSatDelay

    (PCU-H/H)

    Cost OfDelay(/H)

    MeanStops Per

    PCU(%)

    Cost OfStops(/H)

    MeanMax

    Queue(PCU)

    AverageExcessQueue(PCU)

    P.I.(/H)

    Green1Start

    Green1End

    Green2Start

    Green2End

    101 1 1702 3856 83 11 17 5.5 2.4 112.2 82 79.6 26 0.0 191.8 39 10

    102 1 763 1978 72 11 17 2.3 1.3 50.4 77 33.6 11 0.0 84.0 39 10

    103 1 218 2015 70 8 28 1.1 0.6 24.1 99 12.3 8 0.0 85.7 17 34

    104 1 207 2015 70 8 24 0.8 0.6 19.4 111 13.2 8 0.0 32.5 17 34

    105 1 278 1978 61 8 25 1.4 0.6 27.9 92 14.6 6 0.0 100.9 17 34

    106 1 84 1978 61 8 21 0.3 0.2 6.9 106 5.1 6 0.0 11.9 17 34

    107 1 2127 6000 35 11 1 0.0 0.3 3.9 1 0.9 0 0.0 4.8

    201 2 873 1908 83 18 21 2.7 2.4 72.8 89 17.3 14 0.0 90.1 5 37

    202 2 1000 1965 93 18 32 3.4 5.5 126.3 111 24.7 20 0.0 150.9 5 37

    203 2 978 2105 84 18 21 3.1 2.6 81.3 89 19.5 16 0.0 100.8 5 37

    204 2 284 1965 51 5 27 1.6 0.5 29.8 110 17.9 5 0.0 47.7 44 0

    206 2 363 2061 76 5 24 1.2 1.2 34.5 69 14.4 7 0.1 110.1 44 0

    207 2 78 2061 76 5 32 0.4 0.3 9.9 119 5.3 7 0.1 18.8 44 0

    208 2 400 1917 74 5 24 1.3 1.4 37.4 62 14.2 5 0.0 108.2 44 0

    210 2 1235 4000 31 11 1 0.0 0.2 3.2 1 0.8 0 0.0 3.9

    301 3 527 1864 85 11 37 2.7 2.6 76.2 113 34.1 11 0.0 110.3 44 3

    302 3 541 1915 85 11 36 2.8 2.6 77.1 113 34.8 11 0.0 111.9 44 3

    303 3 450 1980 82 8 16 0.8 1.2 28.7 68 17.4 13 0.0 115.5 10 39

    304 3 363 1980 82 8 28 1.8 1.0 39.4 115 23.9 13 0.0 63.3 10 39

    305 3 394 1908 83 8 18 0.8 1.2 27.6 73 16.6 14 0.0 110.5 10 39

    Fareham SDA

    Access Study

    306 3 761 1908 80 8 12 0 6 1 9 36 4 26 11 4 4 0 0 47 8 10 39

  • 8/2/2019 090925 Tfsh Fareham Study

    54/57

    C-3227552/01/C - 6 February 2009/C-3 of 6P:\Southampton\HCC\Projects\227552\JD Fareham SDA Access\02 Documents\Out\MG-Fareham SDA Access Study Report-01D.doc/AP

    306 3 761 1908 80 8 12 0.6 1.9 36.4 26 11.4 4 0.0 47.8 10 39

    307 3 1607 4000 60 11 1 0.0 0.5 7.1 2 1.7 1 0.0 8.7

    308 3 400 1908 83 8 30 2.1 1.2 46.5 117 26.7 14 0.0 73.2 10 39

    309 3 777 4000 60 11 1 0.0 0.2 3.4 2 0.8 1 0.0 4.2

    401 4 496 1852 37 18 2 0.0 0.3 4.2 0 0.0 0 0.0 4.2

    402 4 291 4000 26 9 1 0.0 0.0 0.7 1 0.2 0 0.0 0.9

    403 4 761 4000 26 9 1 0.0 0.1 1.8 1 0.4 0 0.0 2.3

    404 4 761 2400 32 11 1 0.0 0.2 3.3 2 0.8 0 0.0 4.1

  • 8/2/2019 090925 Tfsh Fareham Study

    55/57

    Fareham SDA

    Access Study

    2026 AM

  • 8/2/2019 090925 Tfsh Fareham Study

    56/57

    C-5227552/01/C - 6 February 2009/C-5 of 6P:\Southampton\HCC\Projects\227552\JD Fareham SDA Access\02 Documents\Out\MG-Fareham SDA Access Study Report-01D.doc/AP

    2026 AM

    Link NodeActualFlow

    (PCU/H)

    Sat.Flow

    (PCU/H)

    Degree OfSaturation

    (%)

    MeanCruise Time

    Per PCU(sec)

    MeanDelay Time

    Per PCU(sec)

    UniformDelay

    (PCU-H/H)

    Rand +OverSat

    Delay(PCU-H/H)

    Cost OfDelay

    (/H)

    MeanStops Per

    PCU(%)

    Cost OfStops

    (/H)

    MeanMax

    Queue(PCU)

    AverageExcess

    Queue(PCU)

    P.I.

    (/H)

    Green1

    Start

    Green1

    End

    Green2

    Start

    Green2

    End

    101 1 1702 3856 83 11 17 5.5 2.4 112.2 82 79.6 26 0.0 191.8 40 11

    102 1 763 1978 72 11 17 2.3 1.3 50.4 77 33.6 11 0.0 84.0 40 11

    103 1 218 2015 70 8 12 0.1 0.6 10.0 22 2.8 5 0.0 23.8 18 35

    104 1 207 2015 70 8 22 0.7 0.6 17.9 106 12.5 5 0.0 30.4 18 35

    105 1 278 1978 61 8 9 0.1 0.6 10.2 17 2.6 2 0.0 23.3 18 35

    106 1 84 1978 61 8 18 0.2 0.2 5.9 94 4.5 2 0.0 10.5 18 35

    107 1 2127 6000 35 11 1 0.0 0.3 3.9 1 0.9 0 0.0 4.8

    201 2 873 1908 83 18 21 2.7 2.4 72.8 89 17.3 14 0.0 90.1 7 39

    202 2 1000 1965 93 18 32 3.4 5.5 126.3 111 24.7 20 0.0 150.9 7 39

    203 2 978 2105 84 18 21 3.1 2.6 81.3 89 19.5 16 0.0 100.8 7 39

    204 2 284 1965 51 5 26 1.5 0.5 28.8 110 17.9 5 0.0 46.7 46 2

    206 2 363 2061 76 5 23 1.1 1.2 33.4 71 14.7 7 0.1 110.6 46 2

    207 2 78 2061 76 5 28 0.3 0.3 8.7 118 5.2 7 0.1 17.9 46 2

    208 2 400 1917 74 5 23 1.2 1.4 36.0 63 14.4 5 0.0 107.8 46 2

    210 2 1235 4000 31 11 1 0.0 0.2 3.2 1 0.8 0 0.0 3.9

    301 3 527 1864 85 11 37 2.7 2.6 76.2 113 34.1 11 0.0 110.3 46 5

    302 3 541 1915 85 11 36 2.8 2.6 77.1 113 34.8 11 0.0 111.9 46 5

    303 3 450 1980 82 8 16 0.8 1.2 28.7 68 17.4 13 0.0 115.5 12 41

    304 3 363 1980 82 8 28 1.8 1.0 39.4 115 23.9 13 0.0 63.3 12 41

    Fareham SDA

    Access Study

    305 3 394 1908 83 8 18 0 8 1 2 27 6 74 16 6 14 0 0 110 5 12 41

  • 8/2/2019 090925 Tfsh Fareham Study

    57/57

    C-6227552/01/C - 6 February 2009/C-6 of 6P:\Southampton\HCC\Projects\227552\JD Fareham SDA Access\02 Documents\Out\MG-Fareham SDA Access Study Report-01D.doc/AP

    305 3 394 1908 83 8 18 0.8 1.2 27.6 74 16.6 14 0.0 110.5 12 41

    306 3 761 1908 80 8 12 0.6 1.9 36.4 26 11.4 4 0.0 47.8 12 41

    307 3 1607 4000 60 11 1 0.0 0.5 7.1 2 1.7 1 0.0 8.7

    308 3 400 1908 83 8 30 2.1 1.2 46.7 117 26.7 14 0.0 73.4 12 41

    309 3 777 4000 60 11 1 0.0 0.2 3.4 2 0.8 1 0.0 4.2

    401 4 496 3856 70 18 31 3.2 1.2 61.5 101 11.2 9 0.0 72.7 17 27

    402 4 291 5632 29 9 2 0.1 0.1 2.2 8 1.3 9 0.0 3.5 34 12

    403 4 761 5632 29 9 6 1.1 0.1 17.6 56 24.1 9 0.0 41.7 34 12404 4 761 2400 32 11 3 0.4 0.2 8.9 45 19.7 11 0.0 28.6