    08 Project Monitoring and Control

    Malte Foegen

    - 2 - 2007 wibas IT Maturity Services GmbHFor student use only

    1 Project Monitoring and Control Overview

  • 8/12/2019 08 - Project Monitoring and Control

    2/20

    22

    - 3 - 2007 wibas IT Maturity Services GmbHFor student use only

    Provide understanding of the projects progress

    so that appropriate corrective actions can be taken when theprojects performance deviates significantly from the plan.

    Monitor Projectagainst the Plan

    (SG 1)

    Manage CorrectiveActions to Closure

    (SG 2)

    Project-PlansProject Planning

    - 4 - 2007 wibas IT Maturity Services GmbHFor student use only

    Actual performance and progress of the project aremonitored against the project plan.

    Monitor Project against the Plan(SG 1)

    Monitor Project

    Planning

    Parameters(SP 1.1)

    Monitor

    Project Risks

    (SP 1.3)

    Monitor

    Commitments

    (SP 1.2)

    Monitor Data

    Management

    (SP 1.4)

    Monitor

    StakeholderInvolvement

    (SP 1.5)

    Conduct

    MilestonesReviews

    (SP 1.7)

    Conduct

    ProgressReviews

    (SP 1.6)

    Project-PlansProject Planning

  • 8/12/2019 08 - Project Monitoring and Control

    3/20

    33

    - 5 - 2007 wibas IT Maturity Services GmbHFor student use only

    Typical WP for Monitoring the Project against the Plan

    Monitor Project against the Plan (SG 1)

    SP 1.1 MonitorProject Planning

    Parameters

    1. Records of project

    performance

    2. Records ofsignificant deviations

    SP 1.3 MonitorProject Risks

    1. Records of projectrisk monitoring

    SP 1.2 MonitorCommitments

    1. Recordscommitment reviews

    SP 1.4 Monitor DataManagement

    1. Records of DataManagement

    SP 1.5 MonitorStakeholder

    Involvement

    1. Records of

    stakeholderinvolvement

    SP 1.7 ConductMilestones Reviews

    1. Documented

    milestone reviews

    results

    SP 1.6 ConductProgress Reviews

    1. Documented project

    reviews results

    Project-PlansProject Planning

    - 6 - 2007 wibas IT Maturity Services GmbHFor student use only

    Manage Corrective Actions to Closure

    (SG 2)

    Corrective actions are managed to closure when theprojects performance or results deviate significantly fromthe plan.

    Analyse Issues

    (SP 2.1)

    TakeCorrective

    Actions

    (SP 2.2)

    ManageCorrective

    Actions

    (SP 2.3)

    Project-Plans

  • 8/12/2019 08 - Project Monitoring and Control

    4/20

    44

    - 7 - 2007 wibas IT Maturity Services GmbHFor student use only

    Manage Corrective Actions to Closure

    (SG 2)

    Typical WP for Managing Corrective Actions to Closure

    SP 2.1 AnalyseIssues

    1. List of issues

    needing Correctiveactions

    SP 2.2 Take

    Corrective Actions

    1. Corrective actions

    plan

    SP 2.3 Manage

    Corrective Actions

    1. Corrective actions

    results

    Project-Plans

    - 8 - 2007 wibas IT Maturity Services GmbHFor student use only

    Relationships between Project Planning (PP) andProject Monitoring and Control (PMC)

    Project Planning (PP) Project Monitoring and Control (PMC)

    Plan & Track

    SP 2.7 Establish the Project Plan

    SP 1.1 Monitor Project Planning

    ParametersTime Plan (PP SP 2.1) -

    Costs, Effort (PP SP 1.4) -Attributes of the work results and

    Duties (PP SP 1.2) -

    Resources (PP SP 2.4)

    Knowledge and Skills (PP SP 2.5)

    Commitment Management SG 3 / SP 3.3 Obtain Plan Commitment SP 1.2 Monitor Commitments

    Data Management SP 2.3 Plan for Data Management SP 1.4 Monitor Data Management

    SP 2.1 Establish the Budget andSchedule

    SP 1.4 Determine Estimates of Effort and

    Cost

    SP 1.2 Establish Estimates of WorkProduct and Task

    SP 2.5 Plan for Needed Knowledge andSkills

    Stakeholder Involvement SP 2.6 Plan Stakeholder Involvement SP 1.5 Monitor Stakeholder Involvement

    Risk Management SP 2 .2 Ident ify Pro ject Risks SP 1 .3 Monitor Project Risiks

    SP 2.4 Plan for Project Resources

    Issue ManagementSG 2 Manage Corrective Action to

    Closure

  • 8/12/2019 08 - Project Monitoring and Control

    5/20

    55

    - 9 - 2007 wibas IT Maturity Services GmbHFor student use only

    Project Monitoring and Control is necessary to identify

    actions such that the project stays on track.

    Why do we do it?

    Provide an understanding of theproject's progress

    Take appropriatecorrective actions

    Provide status information for allstakeholders

    Advice and Guidance

    Use defined measurements fromMeasurement and Analysis to monitor

    the projects progress

    Determine major deviations and record the deviations and decisions

    Add all gathered issues to the Issue List

    When re-planning is needed revise estimates and plans

    For closed issues think about lessons learned for the related corrective actionsand take those into account for planning and risk management processes

    - 1 0 - 2007 wibas IT Maturity Services GmbHFor student use only

    The project manager is responsible for tracking the project constantly.

    Who makes it?

    RUP: Project Manager

    The Project Manager plans, manages and allocates resources, shapes priorities,coordinates interactions with customers and users, and keeps the project teamfocused

    Team Members

    Must support the project manager in estimations, risk analysis, stakeholderidentification, and the team must commit to the plan

    When will we do it?

    permanent

  • 8/12/2019 08 - Project Monitoring and Control

    6/20

    66

    - 1 1 - 2007 wibas IT Maturity Services GmbHFor student use only

    Project Monitoring and Control is done throughout the life

    cycle. Measurements can help understand the progress.

    Project Planning

    Measurementand Analysis

    Project Monitoring and Control

    - 1 2 - 2007 wibas IT Maturity Services GmbHFor student use only

    Project Monitoring and Control is a key element of the Plan-Do-Check-Act control circuit

    Do

    Check

    Act

    PMC SG 1

    PMC SG 2

    Plan

    PP

    REQM, RD, TS, PI

    MA

  • 8/12/2019 08 - Project Monitoring and Control

    7/20

    77

    - 1 3 - 2007 wibas IT Maturity Services GmbHFor student use only

    2 Tracking of Cost and Schedule Performance

    - 1 4 - 2007 wibas IT Maturity Services GmbHFor student use only

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan 03 Feb 03 Mrz 03 Apr 03 Mai 03 Jun 03 Jul 03 Aug 03 Sep 03 Okt 03 Nov 03 Dez 03

    Projected

    Actual

    How is this project doing?

  • 8/12/2019 08 - Project Monitoring and Control

    8/20

    88

    - 1 5 - 2007 wibas IT Maturity Services GmbHFor student use only

    Lets Take A Look Under The Hood

    - 1 6 - 2007 wibas IT Maturity Services GmbHFor student use only

    The %-complete approaches to answer the question Havewe done what we said wed do? are subjective, incompleteand draw false conclusions

    The classic approach:

    % complete estimating

    % of Budget spent

    % of work done

    % of time elapsed

  • 8/12/2019 08 - Project Monitoring and Control

    9/20

    99

    - 1 7 - 2007 wibas IT Maturity Services GmbHFor student use only

    Earned Value Analysis is an industry standard to monitor

    and control schedule and budget.

    Earned Value Analysis is an industry standard way to:

    measure a projects progress,

    forecast its completion date and final cost

    provide schedule and budget variances along the way

    By integrating three measurements, Earned Value provides consistent,numerical indicators with which you can evaluate and compare projects.

    - 1 8 - 2007 wibas IT Maturity Services GmbHFor student use only

    Earned Value Analysis answers all three questions:schedule performance, budget performance and completionperformance.

    It compares the

    PLANNED amount of work with

    what has actually been COMPLETED

    to determine if

    COST

    SCHEDULE

    WORK ACCOMPLISHED

    are progressing as planned.

    Work is Earned or credited as it is completed.

  • 8/12/2019 08 - Project Monitoring and Control

    10/20

    1010

    - 1 9 - 2007 wibas IT Maturity Services GmbHFor student use only

    Earned Value provides an Early Warning signal for prompt

    corrective action

    Bad news does not age well.

    Still time to recover

    Timely request for additional funds

    - 2 0 - 2007 wibas IT Maturity Services GmbHFor student use only

    Some New Terms

    BCWS - Budgeted Cost of Work Scheduled

    Planned cost of the total amount of work scheduled to be performed by themilestone date.

    ACWP - Actual Cost of Work Performed

    Cost incurred to accomplish the work that has been done to date.

    BCWP - Budgeted Cost of Work Performed

    The planned (not actual) cost to complete the work that has been done.

  • 8/12/2019 08 - Project Monitoring and Control

    11/20

    1111

    - 2 1 - 2007 wibas IT Maturity Services GmbHFor student use only

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan

    03

    Feb

    03

    Mrz

    03

    Apr

    03

    Mai

    03

    Jun

    03

    Jul

    03

    Aug

    03

    Sep

    03

    Okt

    03

    Nov

    03

    Dez

    03

    BCWS

    BCWS - Budgeted Cost of Work Scheduled

    - 2 2 - 2007 wibas IT Maturity Services GmbHFor student use only

    49000

    56000

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWPACWP

    ACWP and BCWP - Actual Cost of Work Performed andBudgeted Cost of Work Performed

  • 8/12/2019 08 - Project Monitoring and Control

    12/20

    1212

    - 2 3 - 2007 wibas IT Maturity Services GmbHFor student use only

    55000

    49000

    56000

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWS

    BCWP

    ACWP

    The Whole Story

    - 2 4 - 2007 wibas IT Maturity Services GmbHFor student use only

    Some Derived Metrics

    SV: Schedule Variance (BCWP-BCWS)

    A comparison of amount of work performed during a given period of time towhat was scheduled to be performed.

    A negative variance means the project is behind schedule

    CV: Cost Variance (BCWP-ACWP)

    A comparison of the budgeted cost of work performed with actual cost.

    A negative variance means the project is over budget.

  • 8/12/2019 08 - Project Monitoring and Control

    13/20

    1313

    - 2 5 - 2007 wibas IT Maturity Services GmbHFor student use only

    All indicators at a glance

    - 2 6 - 2007 wibas IT Maturity Services GmbHFor student use only

    More Derived Metrics

    SPI: Schedule Performance Index

    SPI=BCWP/BCWS

    SPI

  • 8/12/2019 08 - Project Monitoring and Control

    14/20

    1414

    - 2 7 - 2007 wibas IT Maturity Services GmbHFor student use only

    Performance Metrics

    SPI: BCWP/BCWS

    49,000/55,000 = 0.891

    CPI: BCWP/ACWP

    49,000/56000 = 0.875

    CSI: SPI x CPI

    .891 x .875 = 0.780

    - 2 8 - 2007 wibas IT Maturity Services GmbHFor student use only

    The cost performance index can be used to makeprojections

    EAC: Estimate at Completion

    EAC = BAC / CPI

    The EAC gives an idea of the final cost of aproject.

    Example:

    EAC= 102,000 / 0.875= 116,571

  • 8/12/2019 08 - Project Monitoring and Control

    15/20

    1515

    - 2 9 - 2007 wibas IT Maturity Services GmbHFor student use only

    102000

    90882

    103865

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWS

    BCWP

    ACWP

    Today

    Making Projections

    - 3 0 - 2007 wibas IT Maturity Services GmbHFor student use only

    102000

    116,571

    0

    20000

    40000

    60000

    80000

    100000

    120000

    140000

    Jan-03

    Mar

    -03

    May

    -03

    Jul-0

    3

    Sep-03

    Nov-0

    3

    Jan-04

    Mar

    -04

    BCWS

    BCWP

    ACWP

    Today

    Estimate to Complete

  • 8/12/2019 08 - Project Monitoring and Control

    16/20

    1616

    - 3 1 - 2007 wibas IT Maturity Services GmbHFor student use only

    At the end

    The project will be 14% over budget

    The project will be 3 months late (25% time overrun)

    - 3 2 - 2007 wibas IT Maturity Services GmbHFor student use only

    Requirements of Earned Value

    Proper WBS Design

    Work Items must be small

    Work measurement

    work-hours, dollars, units, etc.

    Good Project Management Practices

  • 8/12/2019 08 - Project Monitoring and Control

    17/20

    1717

    - 3 3 - 2007 wibas IT Maturity Services GmbHFor student use only

    Evaluate Scrum against CMMI PP and PMC.

    Step 1: Estimate tasks and efforts. (15 min)

    Overall result of the next series of exercises:

    Evaluate Scrum against CMMI PP and PMC practices.

    Deliver a spreadsheet with the following structure:

    Break up in your teams.

    Task and Results:

    (7 min) Establish the tasks to do the exercise above

    (7 min) Use planning poker to estimate the effort for your tasks

    Goal:

    Understand exercise and practice planning and estimating Ex

    rcis

    CMMI Text - What Scrum - How OK?

    Suggestion how todo with Scrum

    PP SP

    1.1

    Establish a WBS to

    estimate the scope of theproject

    Yes/

    No

    - 3 4 - 2007 wibas IT Maturity Services GmbHFor student use only

    Evaluate Scrum against CMMI PP and PMC.Step 2: Set up a spreadsheet to calculate Earned Value.(15 min).

    Break up in your teams.

    Task and Results:

    (12 min) Develop a spreadsheet that allows to handle the Earned Value

    (3 min) Test your sheet to ensure that i t works

    Goal:

    Understand how to use and implement Earned Value

    Be prepared to use Earned Value to track your exercise

    Ex

    rcis

  • 8/12/2019 08 - Project Monitoring and Control

    18/20

    1818

    - 3 5 - 2007 wibas IT Maturity Services GmbHFor student use only

    Evaluate Scrum against CMMI PP and PMC.

    Step 3: Do the evaluation.( min)

    Break up in your teams.

    Task and Results:

    Do your tasks and track the efforts

    After 30 min, provide an estimate at completion (EAC)

    Goal:

    Understand Scrum

    Understand PP and PMC

    Practice an evaluation

    Apply Earned Value

    Ex

    rcis

    - 3 6 - 2007 wibas IT Maturity Services GmbHFor student use only

    All formulas

    BCWS - Budgeted Cost of Work Scheduled

    ACWP - Actual Cost of Work Performed

    BCWP - Budgeted Cost of Work Performed

    SV: Schedule Variance (BCWP-BCWS)

    CV: Cost Variance (BCWP-ACWP)

    SPI: Schedule Performance Index (BCWP/BCWS)

    CPI: Cost Performance Index (BCWP/ACWP)

    CSI: Cost Schedule Index (CSI=CPI x SPI)

    BAC = Budget at completion (=BCWS until project completion)

    EAC = BAC / CPI

    Ex

    rcis

  • 8/12/2019 08 - Project Monitoring and Control

    19/20

    1919

    - 3 7 - 2007 wibas IT Maturity Services GmbHFor student use only

    Trademarks and Service Marks

    Capability Maturity Model; Capability Maturity Modeling; Carnegie Mellon , CMM; and CMMI are registered in the U. S.Patent and Trademark Office by Carnegie Mellon University.

    IDEAL; Personal Software Process; PSP; SCAMPI; SCAMPI Lead Assessor; SCAMPI Lead Appraiser ; SEI; SEPG;Team Software Process; and TSP are service marks of Carnegie Mellon University.

    iNTACS is a registered trademark by the International Assessor Certification Scheme

    Special permission to use CMMI for Development, Version 1.2 (CMU/SEI-2006-TR-008 ESC-TR-2006-008), copyright2006 by Carnegie Mellon University, in the combination of CMMI and ITIL is granted by the Software EngineeringInstitute. The SEI and CMU do not directly or indi rectly endorse wibas IT Maturity Services GmbHs work.

    IT Maturity Services is a registered trademark by wibas IT Maturity Services GmbH

    wibas IT Maturity Services is official SEI Partner of the Software Engineering Institute of the Carnegie Mellon Universityfor SCAMPI appraisals and CMMI training. For inquiri es, call:

    wibas IT Maturity Services GmbHYvonne Fischer

    Customer Relations ManagerOtto-Hesse-Str. 19 B64293 DarmstadtGermanyTel: 0049 - 6151 - 50 33 49 - 21Fax: 0049 - 6151 - 50 33 49 - [email protected]

    - 3 8 - 2007 wibas IT Maturity Services GmbHFor student use only

    Revision History

    Rev.no.

    State Date Comments Responsible

    1.0 Finished 15.10.2004 Initial version Malte Foegen

    1.1 Finished 22.01.2006 Updated layout Malte Foegen

    1.2 Finished 23.12.2007 Updated layout Malte Foegen

    1.3 Finished 19.01.2008 Added formula overview for Earned Value Malte Foegen

    1.4 Finished 07.02.2009 Updated exercises Malte Foegen

    Target status: finishedTemplate-Version: 2.11

  • 8/12/2019 08 - Project Monitoring and Control

    20/20

    - 3 9 - 2007 wibas IT Maturity Services GmbHFor student use only