05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

Upload: sorley

Post on 11-Jan-2016

26 views

Category:

Documents


1 download

DESCRIPTION

05/07/12 – 5/13/12. Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started. 05/07/12 – 5/13/12. Demolition at 1927 wing nearing completion. 05/07/12 – 5/13/12. Phase 1 Air Handler Units removed. 05/07/12 – 5/13/12. Field Measured Phase 3 Rotunda - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: 05/07/12 – 5/13/12

05/07/12 – 5/13/12

Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

Page 2: 05/07/12 – 5/13/12

05/07/12 – 5/13/12

Demolition at 1927 wing nearing completion

Page 3: 05/07/12 – 5/13/12

05/07/12 – 5/13/12

Phase 1 Air Handler Units removed

Page 4: 05/07/12 – 5/13/12

•Field Measured Phase 3 Rotunda

•Completed Electrical Shutdown to relocate Main Electrical Panel

Exterior

•Complete drilled piers•Form and Pour Footings at South Side

Interior

•Continue with MEP in 1927 Wing•Prep for floor cut at main electrical room

•Wall off existing area at Spartan Grille to facilitate Taco Bell/C-Store Relocation

During the break…

NEXT WEEK LOOK AHEAD

Phase 3 Rotunda Field Measurement and Verification