04 integration - pmp study notes

Upload: ashrafkhimani

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 04 Integration - PMP Study Notes

    1/4

    Page 1 of 4 Last Updated

    12/5/07

    Integration Management

    Includes the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and

    project management activities within the Project Management Process Groups

    1. Develop Project Charter (Initiating): developing the project charter that formally authorizes a project or a projectphase.

    2. Develop Preliminary Project Scope Statement (Initiating): developing the preliminary project scope statement thatprovides a high-level scope narrative.

    3. Develop Project Management Plan (Planning): documenting the actions necessary to define, prepare, integrate, andcoordinate all subsidiary plans into a project management plan.

    4. Direct and Manage Project Execution (Executing): executing the work defined in the project management plan toachieve the projects requirements defined in the project scope statement.

    5. Monitor and Control Project Work (Controlling): monitoring and controlling the processes used to initiate, plan,execute, and close a project to meet the performance objectives defined in the project management plan.

    6. Integrated Change Control (Controlling): reviewing all change requests, approving changes, and controllingchanges to the deliverables and organizational process assets.

    7. Close Project(Closing): finalizing all activities across all of the Project Management Process Groups to formally closethe project or a project phase.

    SOW: a narrative description of products or services to be supplied by the project, indicates: business need, product scope,

    strategic plan

    Feasibility study: A preliminary study that examines the profitability of the project, the soundness or feasibility of the

    product of the project, the marketability of the product or service, alternative solutions, and the business demands that

    generate the request

    Enterprise environmental factors: External or Internal enterprise factors that may influence the projects success, Company

    Culture & Structure, Government or industry standards, infrastructure, existing human resources, personal administration

    (Hire, Fire, and performance), work authorization, Market place condition, Stake holder risk tolerance, Commercial database,

    PMIS

    Organizational Process Assets: Any process related assets that can be used to influence the projects success: Standards,

    Policies, Standard Product and Project Life Cycles, Quality policies & procedure, performance measurement criteria,

    Templates, Communication requirements, Project Closure Guidelines, Risk Control procedure, Issue and Defect Management

    Procedure, Change Control Procedure, Procedure for Approving & issuing work authorization. It also include Process

    Measurement database, project files, Historical information & Lessons learned, Configuration management database,

    financial database containing labor hours, costs & budgets.

    Project Selection Methods

    1. Benefit Measurement Methods (Comparative Approach)1. Cost-benefit analysis2. Weighted scoring model3. Cash flow analysis techniques (Payback period, Internal Rates of return, Preset Value (PV) and net present

    value (NPV), Opportunity Cost, Discounted Cash Flow)

    2. Constrained Optimization Methods (Mathematical Models)1. Linear 2. Nonlinear 3. Dynamic 4. Integer 5. Multiple Objective Programming

    PMIS: Tools & Techniques to gather integrate and disseminate the outputs of project management processes. Aids in all

    aspect of PM from initiation to closeout. It incorporates the configuration management system and the change controlsystem. Can include manual & automated systems

    Project management methodology: PLC, phases, deliverables, templates, checklists, guidelines, roles& responsibilities. Can

    be either a formal mature process or an informal technique that aids a project management team in effectively developing the

    project artifacts

    Expert judgment: Individual/ Groups with specialized knowledge or training

    Project Charter: formal document

    1. Issued by initiator or sponsor external to project organization with higher level and authority who has the authority tofund

    2. Authorize project (the project has begun)

  • 7/28/2019 04 Integration - PMP Study Notes

    2/4

    Page 2 of 4 Last Updated

    12/5/07

    3. Gives Project Manager Authority4. It is broad enough that it does not have to change as the project changes 5. why (Market demand, Business needs, Customer request, Technological advanced, Legal requirements, Social need)Project Charter components:

    1. Requirements that specify Customer/Sponsor Needs, wants and expectations 2.Business Needs 3.Project purpose or

    justification 4. Assigned PM authority 5.Stakeholder influence 6.Functional organization participation 7.Assumptions &

    Constraints 8.Business case and return on investment 9.Summary BudgetConstraints: An applicable restriction or limitation, either internal or external to the project, that will affect the performance

    of the project or a process

    Assumptions: for planning purposes, are considered to be true, real, or certain without proof or demonstration. Assumptions

    generally involve a degree of risk

    Preliminary Project Scope Statement: More details than the charter, Less details than Project Scope Statement, way of

    proving the understanding of the project

    Project Management Plan: It defines how project is executed, monitored and controlled and closed, can be either summary

    or detailed and can be composed of one or more subsidiary plans and other components, created by the project manager with

    the help of the project team having input from the stakeholders and approved by the stakeholders. Approved, Realistic,

    Formal and buy-in

    Management (subsidiary) plans: Specify how you will define, plan, manage and control each knowledge area. Includes:

    project scope management plan, Schedule management plan, Cost management plan, Quality management plan, Staffing

    management plan, Communication management plan, Risk management plan, Procurement management plan, Contract

    management plan

    PMP component: PM processes selected, how work will be executed, how changes will be monitored and controlled, how

    configuration management will be performed, how integrity of the performance measurement baselines will be maintained

    and used, the need and techniques for communication among stakeholders, the selected PLC and, for multi-phase projects,

    the associated project phases, key management reviews for content, extent, and timing to facilitate addressing open

    issues and pending decisions, work authorization system,

    Configuration Management: It is a sub system of overall project management information system. Documentations control,

    change control and version control.

    Change Control System: It is a collection of formal documented procedures that define how project deliverables and

    documentation are controlled, changed and approved. Subsystem of configuration management. It must also includeprocedures to handle changes that may be approved without prior review

    Work authorization system: a subsystem of the overall project management system , a collection of formal documented

    procedures that defines how project work will be authorized (committed) to ensure that the work is done by the

    identified organization, at the right time, and in the proper sequence, Includes the steps, documents, tracking

    system, and defined approval levels needed to issue work authorizations

    Direct and Manage Project Execution: the process requires the project manager and plan to accomplish the work defined in

    the project scope statement. The project manager, along with the project management team, directs the performance of the

    planned project activities, and manages the various technical and organizational interfaces that exist within the project and

    keep the stakeholders well-informed

    Work Performance Information: Schedule progress, status information, completed /no completed deliverables, schedule

    activities that have started and those that have been finished, Extent to which quality standards are being met, Costsauthorized and incurred, Estimates to complete the schedule activities that have started, Percent physically complete of the in-

    progress schedule activities, documented lessons learned posted to the lessons learned knowledge base, resource utilization

    detail

    Deliverable: Any unique measurable, tangible, verifiable outcome, product, result, capability to perform a service or item that

    must be produced to complete a process, phase, project or part of a project, subject to approval by the project sponsor or

    customer.

    Monitor and Control Project Work: monitoring includes collecting, measuring, and disseminating performance

    information, and assessing measurements and trends to effect process improvements. Performed to monitor project processes

    associated with initiating, planning, executing, and closing

  • 7/28/2019 04 Integration - PMP Study Notes

    3/4

    Page 3 of 4 Last Updated

    12/5/07

    Earned Value Technique: measures performance (scope, schedule, cost) from initiation through closure. Means to forecast

    future performance based upon past performance.

    Forecasts: estimates or predictions of conditions and events in the projects future, based on information and knowledge

    available at the time of the forecast, using EVM

    Integrated Change Control: It is performed from project inception thru completion, it includes

    1. Identifying that a change needs to occur or has occurred2. Make sure only approved changes are implemented3. Reviewing and approving requested changes4. Managing approved changes as and when they occur and regulating them5. Maintain integrity of baseline6. Review and approve all recommended corrective and preventive actions7. Controlling and updating scope, cost, budget, schedule and quality requirements8. Documenting impact of requested changes9. Validating defect repair10. Controlling project quality to standards based on quality reports.

    Change control board: Responsible for approving and rejecting the requested changes, the roles and responsibilities of these

    boards are clearly defined within the configuration control and change control procedures (PMP), and are agreed to by the

    sponsor, customer, and other stakeholders

    Changes request: Changes requested to project objectives (scope, time, cost and quality), are often identified while project

    work is being performed. Requests for a change can be direct or indirect, externally or internally initiated, and can be

    optional or legally/contractually mandated, may approved or rejected in the CCB process and implemented during the direct

    project execution process

    Corrective Action: reactive documented recommendations required to bring expected future project performance into

    conformance with the project management plan, projects must meet their performance measurement baseline, implementing

    actions to deal with actual deviation from the performance baseline, may approved or rejected in the CCB process and

    implemented during the direct project execution process

    Preventive Action: proactive documented recommendations that reduce the probability of negative consequences associated

    with project risks, deal with anticipated or possible deviation from the performance baseline, may approved or rejected in the

    CCB process and implemented during the direct project execution process

    Defect repair: request to correct product defects found in the quality inspection or the audit process, validated Defect Repair:notification that re-inspected repaired items have either been accepted or rejected, may approved or rejected in the ICC

    process and implemented during the direct project execution process

    Historical Information can include:

    Tasks, WBS, Reports, Estimates, Project Plans, Lessons learned, Benchmarks, Risks, Resources needed, Correspondence

    Administrative Closure Procedure: The procedures to transfer the project products or services to production and/or

    operations, step- by-step methodology for administrative the closure, Actions and activities to define the stakeholder approval

    requirements for changes and all levels of deliverables, Actions and activities that are necessary to confirm that the project

    has met all sponsor, customer, and other stakeholders requirements, verify that all deliverables have been provided and

    accepted, and validate that completion and exit criteria have been met, Actions and activities necessary to satisfy completion

    or exit criteria for the project.

    Contract Closure Procedure: Step-by-step methodology that addresses the terms and conditions of the contracts and any

    required completion or exit criteria for contract closure. It contains all activities and related responsibilities of the project

    team members, customers, and other stakeholders involved in the contract closure process. The actions performedformally close all contacts associated with the completed project.

    Final Product, Service, or Result: Formal acceptance and handover. Receipt of a formal statement that the terms of the

    contract have been met.

    Organizational process assets updates: Formal Acceptance Documentation, Project Files, Project Closure Documents,

    historical information, lessons learned, knowledge base.

    Managing Change, PM must be concerned with:

    Influencing the factors that affect change Ensuring that change is beneficial Determining that a change has occurred Determining if a change is needed

  • 7/28/2019 04 Integration - PMP Study Notes

    4/4

    Page 4 of 4 Last Updated

    12/5/07

    Looking for alternatives to changes Minimizing the negative impact of changes Notifying stakeholders affected by the changes Managing changes as they occurSteps to make changes:

    Evaluate (assess) the impact of the change Create (compute) alternatives, including cutting other tasks, crashing, fast tracking, etc. Meet with mgmt, sponsor, & internal Stakeholders Meet with the customer as necessary