03 progress update 21.08.2014 area04
TRANSCRIPT
-
8/11/2019 03 Progress Update 21.08.2014 Area04
1/4
1 Earthwork. 160 0.28% 160 0.28% 160 0.28% 0 0 0
2 Foundation. 3.87% 3.87% 3.87%
2.1 Blinding (Inclu. Anti-termite). 160 0.32% 160 0.32% 160 0.32% 0 0 0
2.2 Footing. 160 3.55% 160 3.55% 160 3.55% 0 0 0
3 Slab on Grade 6.52% 6.52% 6.52%
3.1 Stub Wall 160 3.99% 160 3.99% 160 3.99% 0 0 0
3.2 Backfilling (Inclu. Bitumen Membrane). 160 0.42% 160 0.42% 160 0.42% 0 0 0
3.3 Ground Slab 160 2.11% 160 2.11% 160 2.11% 0 0 0
4 G. Floor Tunnel 160 15.43% 160 15.43% 160 15.43% 0 0 0
5 F. Floor Tunnel 87 8.59% 87 8.59% 87 8.59% 0 0 0
6 Parapets and Staircase 4.23% 4.23% 4.23%
6.1 Parapets 160 3.76% 160 3.76% 160 3.76% 0 0 0
6.2 Staircase 87 0.47% 87 0.47% 87 0.47% 0 0 0
7 Block work 160 4.65% 160 4.65% 160 4.65% 0 0 0
8 Internal Plaster. 160 2.45% 160 2.45% 160 2.45% 0 0 0
9 WALL & FLOOR TILES 4.44% 4.44% 4.44%
9.1 Wall Tiles(Kitchen) 160 0.18% 160 0.18% 160 0.18% 0 0 0
9.2 Wall Tiles(Bathroom) 160 0.43% 160 0.43% 160 0.43% 0 0 0
9.3 Internal Main Floor Tiles 160 2.85% 160 2.85% 160 2.85% 0 0 0
9.4 Internal Bathroom Floor Tiles 160 0.04% 160 0.04% 160 0.04% 0 0 0
9.5 Marble Stairs 87 0.44% 87 0.44% 87 0.44% 0 0 0
9.6 External Floor Tiles 160 0.50% 160 0.50% 160 0.50% 0 0 0
10 JOINERY WORKS 4.57% 4.57% 4.23%
10.1 Int. Wooden Room Door Frames. 160 0.57% 160 0.57% 160 0.57% 0 0 0
10.2 Int. Wooden Room Door Shutters. 160 1.02% 160 1.02% 160 1.02% 0 0 0
10.3 External Wooden Door Frames. 160 0.16% 160 0.16% 160 0.16% 0 0 0
10.4 External Wooden Door Shutters. 160 0.27% 160 0.27% 160 0.27% 0 0 0
10.5 Wardrobes (Carcass) 160 0.51% 160 0.51% 160 0.51% 0 0 0
10.6 Wardrobes (Shutters) 160 0.34% 160 0.34% 0 0.00% (160) (160) (160)
10.7 Kitchen Cabinets (Carcass) 160 0.57% 160 0.57% 160 0.57% 0 0 0
10.8 Kitchen Cabinets (Shutters) 160 0.24% 160 0.24% 160 0.24% (43) (19) 0
10.9 Vanities (Metal Frames) 160 0.42% 160 0.42% 160 0.42% 0 0 0
NATIONAL HOUSING PROJECT - AL BARSHA SOUTH FIRST PHASE IIConstruction of 1240 Villas, Area - 04 (160 Villas)
Weekly Progress Update as on 21 August '14
Based on Revised Baseline Programme, Rev. 6.0, Dated 02.07.2013
StatusThisweek
Remarks
Sl.No.
Activity Description Total %
21 August 2014
Qty StatusPrevious
week
StatusLastweek
PlannedNo. ofVillas
Complete
Planned %Complete
Actual No.of Villas
Complete
Actual %Complete
Page 1 of 4 Area4U
-
8/11/2019 03 Progress Update 21.08.2014 Area04
2/4
StatusThisweek
Remarks
Sl.No.
Activity Description Total %
21 August 2014
Qty StatusPrevious
week
StatusLastweek
PlannedNo. ofVillas
Complete
Planned %Complete
Actual No.of Villas
Complete
Actual %Complete
10.11 Kitchen Exhaust Hood 160 0.04% 160 0.04% 160 0.04% 0 0 0
10.12 Kitchen Worktops 160 0.07% 160 0.07% 160 0.07% 0 0 0
10.13 Vanity Worktops 160 0.19% 160 0.19% 160 0.19% 0 0 0
10.14 Mirror Fixing. 160 0.18% 160 0.18% 160 0.18% 0 0 0
11 UPVC DOORS & WINDOWS. 2.02% 2.02% 2.02%
11.1 Upvc Doors. 160 0.69% 160 0.69% 160 0.69% 0 0 0
11.2 Windows Frames. 160 1.06% 160 1.06% 160 1.06% 0 0 0
11.3 Glass for Windows. 160 0.26% 160 0.26% 160 0.26% 0 0 0
12 FALSE CEILING WORKS 1.26% 1.26% 1.26%
12.1 Suspension system 160 0.24% 160 0.24% 160 0.24% 20 20 0
12.2 Gypsum Board 160 0.79% 160 0.79% 160 0.79% 0 0 0
12.3 False Ceiling Tiles 160 0.23% 160 0.23% 160 0.23% 0 0 0
13 HANDRAILS 0.91% 0.91% 0.91%
13.1 Balcony Handrails. 160 0.54% 160 0.54% 160 0.54% 0 0 0
13.2 Staircase Handrails. (Metal). 87 0.30% 87 0.30% 87 0.30% 0 0 0
13.3 Staircase Handrails. (Wooden). 87 0.08% 87 0.08% 87 0.08% 0 0 0
14 INTERNAL PAINTING WORKS 0.73% 0.73% 0.73%
14.1 Internal Paint Under coat 160 0.29% 160 0.29% 160 0.29% 0 0 0
14.2 Internal Paint First Coat 160 0.19% 160 0.19% 160 0.19% 0 0 0
14.2a Spray Plaster 160 0.04% 160 0.04% 160 0.04% 0 0 0
14.3 Internal Paint Final coat 160 0.20% 160 0.20% 160 0.20% (54) (42) 0
15 External Plaster. 160 2.59% 160 2.59% 160 2.59% 0 0 0
16 External Painting. 1.18% 1.18% 1.18%
16.1 Under coat (G + F Floor). 160 0.47% 160 0.47% 160 0.47% 0 0 0
16.2 Final coats (G + F Floor) 160 0.71% 160 0.71% 160 0.71% 0 0 0
17 ROOFING & WATER PROOFING 1.77% 1.77% 1.77%
17.1 Light Weight Concrete 160 0.41% 160 0.41% 160 0.41% 0 0 0
17.2 Waterproofing membrane 160 0.38% 160 0.38% 160 0.38% 0 0 0
17.3 Protection to waterproofing 160 0.73% 160 0.73% 160 0.73% 0 0 0
17.4 Roof Paving Tiles 160 0.05% 160 0.05% 160 0.05% 0 0 0
17.5 Timber Roof Structure. 69 0.14% 69 0.14% 69 0.14% 0 0 0
17.6 Roof Clay Tiles. 72 0.08% 72 0.08% 72 0.08% 0 0 0
18 EXTERNAL WORKS 7.24% 7.24% 7.24%
18.1 Installation of Water Tank 160 0.26% 160 0.26% 160 0.26% 0 0 0
18.2 Garages Structural Works 160 2.74% 160 2.74% 160 2.74% 0 0 0
Page 2 of 4 Area4U
-